Professional Documents
Culture Documents
Canal Pow
Canal Pow
Province of Palawan
Municipality of Rizal
OFFICE OF THE MUNICIPAL ENGINEER
PROGRAM OF WORK
Name of Project : Relocation of Water System Intake Structure
Location : Punta Baja
Brief Description
:
Source of fund/Amount : 20% DF-2022
Implementation : By Contract
Desirable Starting Date : W/in 7 Cal. Days Upon Receipt of NTP
Date : September 2022
Site Prep. And other Prelim. Activities 1.00 lumpsum 3,500.00 1000.00
Construction of temporary Facilities 1.00 lumpsum 5,000.00 1500.00
Project layout/Stake out 1.00 lumpsum 4,000.00 500.00
Materials:
8'x8' Tarpaulin(Billboard/Sign Board) 64.00 sq.ft. P 30.00 P 1920.00
Ordinary Plywood 1/4'' thk. 1.00 pcs 650.00 650.00
Good sawn Lumber 40.00 bd.ft. 60.00 2400.00
Assorted Common Nails 1.00 kgs 100.00 100.00
Materials Cost 5070.00
Manpower :
1 Construction Foreman 1.00 days P 650.00 P 650.00
1 Skilled Labor 1.00 days 500.00 500.00
2 Unskilled Labor 1.00 days 350.00 700.00
Labor Cost 1,850.00
Equipment :
Minor Tools ( 10% of Labor Cost ) P 185.00
Equipment Cost 185.00
Materials:
Safety Shoes 30.00 man-day 20.00 600.00
Working Gloves 30.00 man-day 25.00 750.00
Rain Coat 30.00 man-day 20.00 600.00
Rubber Boots 30.00 man-day 20.00 600.00
First aid Medicine 1.00 set 2,380.00 2,380.00
Materials Cost 4,930.00
Manpower :
1 Safety Practitioner/ Officer ( Part time @4 hrs / week ) 6.00 days 650.00 P 3,900.00
1 Health Personnel ( @ 3 days / week ) 14.00 days 500.00 7,000.00
Labor Cost 10,900.00
PART II Earthwork
Manpower :
1 Construction Foreman 1.00 days P 650.00 P 650.00
1 Skilled Labor 1.00 days 500.00 500.00
2 Unskilled Labor 1.00 days 350.00 700.00
Labor Cost 1,850.00
Equipment :
1 backhoe ( 0.5 cu.m.) 1.00 day 16,000.00 16,000.00
Equipment Cost 16,000.00
803(1)a Structure Excavation, Gravel 24.75 cu.m
Manpower :
1 Construction Foreman 2.00 days P 650.00 P 1,300.00
1 Skilled Labor 2.00 days 500.00 1,000.00
2 Unskilled Labor 2.00 days 350.00 1,400.00
Labor Cost 3,700.00
Equipment :
Page 1 of 9
1 backhoe ( 0.5 cu.m.) 2.00 day 16,000.00 32,000.00
Equipment Cost 32,000.00
Manpower :
1 Construction Foreman 1.00 days P 650.00 P 650.00
1 Skilled Labor 1.00 days 500.00 500.00
2 Unskilled Labor 1.00 days 350.00 700.00
Labor Cost 1,850.00
Equipment :
1 backhoe backhoe ( 0.5 cu.m.) 1.00 day 16,000.00 16,000.00
Equipment Cost 16,000.00
Manpower :
1 Construction Foreman 2.00 days P 650.00 P 1,300.00
1 Skilled Labor 2.00 days 500.00 1,000.00
2 Unskilled Labor 2.00 days 350.00 1,400.00
Labor Cost 3,700.00
Equipment :
1 backhoe backhoe ( 0.5 cu.m.) 2.00 day 16,000.00 32,000.00
Equipment Cost 32,000.00
Materials:
Portland Cement 21.00 bags. P 370.00 P 7,770.00
Screened Sand 1.50 cu.m. 1,200.00 1,800.00
Gravel, G1 3.00 cu.m. 1,100.00 3,300.00
# 16 G.I. Tie Wires 1.00 kl. 120.00 120.00
Materials Cost 12,990.00
Manpower :
1 Construction Foreman 1.00 day 650.00 P 650.00
2 Skilled Labor 1.00 day 500.00 1,000.00
6 Unskilled Labor 1.00 day 350.00 2,100.00
Labor Cost 3,750.00
Equipment :
1 bagger mixer 1.00 day 1,376.00 1,376.00
Equipment Cost 1,376.00
Materials:
Portland Cement 63.00 bags. P 370.00 P 23,310.00
Screened Sand 4.00 cu.m. 1,200.00 4,800.00
Gravel, 3/8 7.00 cu.m. 1,200.00 8,400.00
# 16 G.I. Tie Wires 3.00 kl. 120.00 360.00
Materials Cost 36,870.00
Manpower :
1 Construction Foreman 3.00 days 650.00 P 1,950.00
2 Skilled Labor 3.00 days 500.00 3,000.00
6 Unskilled Labor 3.00 days 350.00 6,300.00
Labor Cost 11,250.00
Equipment :
1 bagger mixer 3.00 days 1,376.00 4,128.00
1 concrete vibrator 3.00 days 730.00 2,190.00
Equipment Cost 6,318.00
Materials: 24.30
Portland Cement 25.00 bags. P 370.00 P 9,250.00
Screened Sand 13.00 cu.m. 1,200.00 15,600.00
Gravel, 3/8 25.00 cu.m. 1,200.00 30,000.00
# 16 G.I. Tie Wires 2.00 kls. 120.00 240.00
Materials Cost 55,090.00
Manpower :
1 Construction Foreman 1.00 days 650.00 P 650.00
2 Skilled Labor 1.00 days 500.00 1,000.00
6 Unskilled Labor 1.00 days 350.00 2,100.00
Labor Cost 3,750.00
Equipment :
1 bagger mixer 1.00 days 1,376.00 1,376.00
1 concrete vibrator 1.00 days 730.00 730.00
Page 2 of 9
Equipment Cost 2,106.00
900(1)c2 Tie Beam 0.90 cu.m.
Materials:
Portland Cement 9.00 bags. P 370.00 P 3,330.00
Screened Sand 0.50 cu.m. 1,200.00 600.00
Gravel, 3/8 1.00 cu.m. 1,200.00 1,200.00
# 16 G.I. Tie Wires 2.00 kls. 120.00 240.00
Materials Cost 5,370.00
Manpower :
1 Construction Foreman 1.00 days 650.00 P 650.00
2 Skilled Labor 1.00 days 500.00 1,000.00
6 Unskilled Labor 1.00 days 350.00 2,100.00
Labor Cost 3,750.00
Equipment :
1 bagger mixer 1.00 days 1,376.00 1,376.00
1 concrete vibrator 1.00 days 730.00 730.00
Equipment Cost 2,106.00
Materials:
16mm dia. X 6.0m RSB 16 pcs. 620.00 9,920.00
Materials Cost 9,920.00
Manpower :
1 Construction Foreman 1.00 day 650.00 P 650.00
2 Skilled Labor 1.00 day 500.00 1,000.00
6 Unskilled Labor 1.00 day 350.00 2,100.00
Labor Cost 3,750.00
Equipment :
1 Bar Cutter 1.00 day 1,758.00 P 1,758.00
1 Bar Bender 1.00 day 2,800.00 2,800.00
Equipment Cost 4,558.00
Materials:
12mm dia. X 6.0m RSB 50.00 pcs. 420.00 21,000.00
Materials Cost 21,000.00
Manpower :
1 Construction Foreman 2.00 days 650.00 P 1,300.00
2 Skilled Labor 2.00 days 500.00 2,000.00
6 Unskilled Labor 2.00 days 350.00 4,200.00
Labor Cost 7,500.00
Equipment :
1 Bar Cutter 2.00 days 1,758.00 P 3,516.00
1 Bar Bender 2.00 days 2,800.00 5,600.00
Equipment Cost 9,116.00
Materials:
12mm dia. X 6.0m RSB 22.00 pcs. 420.00 9,240.00
Materials Cost 9,240.00
Manpower :
1 Construction Foreman 1.00 days 650.00 P 650.00
1 Skilled Labor 1.00 days 500.00 500.00
6 Unskilled Labor 1.00 days 350.00 2,100.00
Labor Cost 3,250.00
Equipment :
1 Bar Cutter 1.00 days 1,758.00 P 1,758.00
1 Bar Bender 1.00 days 2,800.00 2,800.00
Equipment Cost 4,558.00
Page 3 of 9
902(1)a4 Tie Beam 19.00 pcs.
Materials:
12mm dia. X 6.0m RSB 19.00 pcs. 420.00 7,980.00
Materials Cost 7,980.00
Manpower :
1 Construction Foreman 1.00 days 650.00 P 650.00
1 Skilled Labor 1.00 days 500.00 500.00
6 Unskilled Labor 1.00 days 350.00 2,100.00
Labor Cost 3,250.00
Equipment :
1 Bar Cutter 1.00 days 1,758.00 P 1,758.00
1 Bar Bender 1.00 days 2,800.00 2,800.00
Equipment Cost 4,558.00
BREAKDOWN OF INDIRECT COST: ( BASED ON DAO NO. 197, DATED OCT. 07 2016 OF DPWH)
1.) Contractor's :10%
2.) OCM :5%
3.) Mob./Demob. :1%
4.) EVAT :7%
Approved By:
Page 4 of 9
Republic of the Philippines
Province of Palawan
Municipality of Rizal
OFFICE OF THE MUNICIPAL ENGINEER
PROGRAM OF WORK
Name of Project : Relocation of Water System Intake Structure
Location : Punta Baja
Brief Description
:
Source of fund/Amount : 20% DF-2022
Implementation : By Contract
Desirable Starting Date : W/in 7 Cal. Days Upon Receipt of NTP
Date : September 2022
Site Prep. And other Prelim. Activities 1.00 lumpsum 3,500.00 1000.00
Construction of temporary Facilities 1.00 lumpsum 5,000.00 1500.00
Project layout/Stake out 1.00 lumpsum 4,000.00 500.00
Materials:
8'x8' Tarpaulin(Billboard/Sign Board) 64.00 sq.ft. P 30.00 P 1920.00
Ordinary Plywood 1/4'' thk. 1.00 pcs 650.00 650.00
Good sawn Lumber 40.00 bd.ft. 60.00 2400.00
Assorted Common Nails 1.00 kgs 100.00 100.00
Materials Cost 5070.00
Manpower :
1 Construction Foreman 1.00 days P 650.00 P 650.00
1 Skilled Labor 1.00 days 500.00 500.00
2 Unskilled Labor 1.00 days 350.00 700.00
Labor Cost 1,850.00
Equipment :
Minor Tools ( 10% of Labor Cost ) P 185.00
Equipment Cost 185.00
Materials:
Safety Shoes 30.00 man-day 20.00 600.00
Working Gloves 30.00 man-day 25.00 750.00
Rain Coat 30.00 man-day 20.00 600.00
Rubber Boots 30.00 man-day 20.00 600.00
First aid Medicine 1.00 set 2,380.00 2,380.00
Materials Cost 4,930.00
Manpower :
1 Safety Practitioner/ Officer ( Part time @4 hrs / week ) 6.00 days 650.00 P 3,900.00
1 Health Personnel ( @ 3 days / week ) 14.00 days 500.00 7,000.00
Labor Cost 10,900.00
PART II Earthwork
Manpower :
1 Construction Foreman 1.00 days P 650.00 P 650.00
1 Skilled Labor 1.00 days 500.00 500.00
2 Unskilled Labor 1.00 days 350.00 700.00
Labor Cost 1,850.00
Equipment :
1 backhoe ( 0.5 cu.m.) 1.00 day 16,000.00 16,000.00
Equipment Cost 16,000.00
803(1)a Structure Excavation, Gravel 24.75 cu.m
Manpower :
1 Construction Foreman 2.00 days P 650.00 P 1,300.00
1 Skilled Labor 2.00 days 500.00 1,000.00
2 Unskilled Labor 2.00 days 350.00 1,400.00
Labor Cost 3,700.00
Equipment :
Page 5 of 9
1 backhoe ( 0.5 cu.m.) 2.00 day 16,000.00 32,000.00
Equipment Cost 32,000.00
Manpower :
1 Construction Foreman 1.00 days P 650.00 P 650.00
1 Skilled Labor 1.00 days 500.00 500.00
2 Unskilled Labor 1.00 days 350.00 700.00
Labor Cost 1,850.00
Equipment :
1 backhoe backhoe ( 0.5 cu.m.) 1.00 day 16,000.00 16,000.00
Equipment Cost 16,000.00
Manpower :
1 Construction Foreman 2.00 days P 650.00 P 1,300.00
1 Skilled Labor 2.00 days 500.00 1,000.00
2 Unskilled Labor 2.00 days 350.00 1,400.00
Labor Cost 3,700.00
Equipment :
1 backhoe backhoe ( 0.5 cu.m.) 2.00 day 16,000.00 32,000.00
Equipment Cost 32,000.00
Materials:
Portland Cement 21.00 bags. P 370.00 P 7,770.00
Screened Sand 1.50 cu.m. 1,200.00 1,800.00
Gravel, G1 3.00 cu.m. 1,100.00 3,300.00
# 16 G.I. Tie Wires 1.00 kl. 120.00 120.00
Materials Cost 12,990.00
Manpower :
1 Construction Foreman 1.00 day 650.00 P 650.00
2 Skilled Labor 1.00 day 500.00 1,000.00
6 Unskilled Labor 1.00 day 350.00 2,100.00
Labor Cost 3,750.00
Equipment :
1 bagger mixer 1.00 day 1,376.00 1,376.00
Equipment Cost 1,376.00
Materials:
Portland Cement 63.00 bags. P 370.00 P 23,310.00
Screened Sand 4.00 cu.m. 1,200.00 4,800.00
Gravel, 3/8 7.00 cu.m. 1,200.00 8,400.00
# 16 G.I. Tie Wires 3.00 kl. 120.00 360.00
Materials Cost 36,870.00
Manpower :
1 Construction Foreman 3.00 days 650.00 P 1,950.00
2 Skilled Labor 3.00 days 500.00 3,000.00
6 Unskilled Labor 3.00 days 350.00 6,300.00
Labor Cost 11,250.00
Equipment :
1 bagger mixer 3.00 days 1,376.00 4,128.00
1 concrete vibrator 3.00 days 730.00 2,190.00
Equipment Cost 6,318.00
Materials:
Portland Cement 8.00 bags. P 370.00 P 2,960.00
Screened Sand 0.50 cu.m. 1,200.00 600.00
Gravel, 3/8 1.00 cu.m. 1,200.00 1,200.00
# 16 G.I. Tie Wires 1.00 kl. 120.00 120.00
Materials Cost 4,880.00
Manpower :
1 Construction Foreman 1.00 day 650.00 P 650.00
2 Skilled Labor 1.00 day 500.00 1,000.00
6 Unskilled Labor 1.00 day 350.00 2,100.00
Labor Cost 3,750.00
Equipment :
1 bagger mixer 1.00 day 1,376.00 1,376.00
1 concrete vibrator 1.00 day 730.00 730.00
Equipment Cost 2,106.00
Page 6 of 9
900(1)c2 Concrete Apron & flooring 7.65 cu.m.
Materials:
Portland Cement 69.00 bags. P 370.00 P 25,530.00
Screened Sand 4.00 cu.m. 1,200.00 4,800.00
Gravel, 3/8 8.00 cu.m. 1,200.00 9,600.00
# 16 G.I. Tie Wires 4.00 kls. 120.00 480.00
Materials Cost 40,410.00
Manpower :
1 Construction Foreman 3.00 days 650.00 P 1,950.00
2 Skilled Labor 3.00 days 500.00 3,000.00
6 Unskilled Labor 3.00 days 350.00 6,300.00
Labor Cost 11,250.00
Equipment :
1 bagger mixer 3.00 days 1,376.00 4,128.00
1 concrete vibrator 3.00 days 730.00 2,190.00
Equipment Cost 6,318.00
900(1)c2 Tie Beam 0.90 cu.m.
Materials:
Portland Cement 9.00 bags. P 370.00 P 3,330.00
Screened Sand 0.50 cu.m. 1,200.00 600.00
Gravel, 3/8 1.00 cu.m. 1,200.00 1,200.00
# 16 G.I. Tie Wires 2.00 kls. 120.00 240.00
Materials Cost 5,370.00
Manpower :
1 Construction Foreman 1.00 days 650.00 P 650.00
2 Skilled Labor 1.00 days 500.00 1,000.00
6 Unskilled Labor 1.00 days 350.00 2,100.00
Labor Cost 3,750.00
Equipment :
1 bagger mixer 1.00 days 1,376.00 1,376.00
1 concrete vibrator 1.00 days 730.00 730.00
Equipment Cost 2,106.00
Materials:
16mm dia. X 6.0m RSB 16 pcs. 620.00 9,920.00
Materials Cost 9,920.00
Manpower :
1 Construction Foreman 1.00 day 650.00 P 650.00
2 Skilled Labor 1.00 day 500.00 1,000.00
6 Unskilled Labor 1.00 day 350.00 2,100.00
Labor Cost 3,750.00
Equipment :
1 Bar Cutter 1.00 day 1,758.00 P 1,758.00
1 Bar Bender 1.00 day 2,800.00 2,800.00
Equipment Cost 4,558.00
Materials:
12mm dia. X 6.0m RSB 50.00 pcs. 420.00 21,000.00
Materials Cost 21,000.00
Manpower :
1 Construction Foreman 2.00 days 650.00 P 1,300.00
2 Skilled Labor 2.00 days 500.00 2,000.00
6 Unskilled Labor 2.00 days 350.00 4,200.00
Labor Cost 7,500.00
Equipment :
1 Bar Cutter 2.00 days 1,758.00 P 3,516.00
1 Bar Bender 2.00 days 2,800.00 5,600.00
Equipment Cost 9,116.00
Materials:
12mm dia. X 6.0m RSB 35.0 pcs. 420.00 14,700.00
Materials Cost 14,700.00
Manpower :
1 Construction Foreman 2.00 day 650.00 P 1,300.00
2 Skilled Labor 2.00 day 500.00 2,000.00
6 Unskilled Labor 2.00 day 350.00 4,200.00
Labor Cost 7,500.00
Page 7 of 9
Equipment :
1 Bar Cutter 2.00 day 1,758.00 P 3,516.00
1 Bar Bender 2.00 day 2,800.00 5,600.00
Equipment Cost 9,116.00
Materials:
12mm dia. X 6.0m RSB 58.00 pcs. 420.00 24,360.00
Materials Cost 24,360.00
Manpower :
1 Construction Foreman 2.00 days 650.00 P 1,300.00
1 Skilled Labor 2.00 days 500.00 1,000.00
6 Unskilled Labor 3.00 days 350.00 6,300.00
Labor Cost 8,600.00
Equipment :
1 Bar Cutter 2.00 days 1,758.00 P 3,516.00
1 Bar Bender 2.00 days 2,800.00 5,600.00
Equipment Cost 9,116.00
902(1)a4 Tie Beam 19.00 pcs.
Materials:
12mm dia. X 6.0m RSB 19.00 pcs. 420.00 7,980.00
Materials Cost 7,980.00
Manpower :
1 Construction Foreman 1.00 days 650.00 P 650.00
1 Skilled Labor 1.00 days 500.00 500.00
6 Unskilled Labor 1.00 days 350.00 2,100.00
Labor Cost 3,250.00
Equipment :
1 Bar Cutter 1.00 days 1,758.00 P 1,758.00
1 Bar Bender 1.00 days 2,800.00 2,800.00
Equipment Cost 4,558.00
Page 8 of 9
Direct Cost 145,024.00
Mark -Up 23,203.84
VAT ( 7% ) 11,775.95
Indirect Cost 34,979.79
Item Total Cost P 180,003.79
BREAKDOWN OF INDIRECT COST: ( BASED ON DAO NO. 197, DATED OCT. 07 2016 OF DPWH)
1.) Contractor's :10%
2.) OCM :5%
3.) Mob./Demob. :1%
4.) EVAT :7%
Approved By:
Page 9 of 9