Professional Documents
Culture Documents
Hydrostatic Test Procedure Version 0
Hydrostatic Test Procedure Version 0
Contract No 16/2012
Company:
Page 1 of 24
Company: Contractor:
CONTENTS
Page 2 of 24
Company: Contractor:
1. INTRODUCTION
This procedure shall specify the minimum requirements and steps to be followed during
Hydrostatic test as stated in the approved codes, standards and specifications.
2. SCOPE
This procedure shall apply to hydrostatic testing following steps: cleaning, gauging, Hydrostatic
testing and Bulk Dewatering of pipeline and piping sections for ARAYAN – JANDER Gas
Pipeline Project without any harm to people or damage to environment.
3. SEQUENCE OF OPERARIONS
3.1. Pipeline
Sequence of operations for each pipeline test section shall be as follows:
Water cleaning
Gauging
Water filling
Pressurization (entrapped air test)
Temperature stabilization
Strength test
Leak test
Depressurization
Bulk dewatering (if required)
Removal of temporary pipework and facilities
3.2. Station Piping
Sequence of operations for testing the station pipework as a separate unit, shall be as
follows:
Water cleaning
Filling
Pressurization (entrapped air test)
Combined strength and leak test
Depressurization
Dewatering
Final tie-in work and removal of temporary pipework and facilities
4. REFERENCES AND CODES
Page 3 of 24
Company: Contractor:
API RP 1110 - Pressure Testing of Steel Pipelines for the Transportation of Gas
5. RESPONSIBILITIES
Contractor shall be responsible for safety requirements for all employees engaged in
testing work activities and consequences of a pipe or fitting failure under pressure test
conditions and carry out all co-ordinations required with all third parties.
Hydrostatic testing operations shall be carried out by an experienced test engineer who
shall have no other duties during the hydrostatic testing operations
Contractor shall provide Company:
A list of nominated personnel who are to supervise the pressure test operations with their
qualifications, tasks, responsibilities and authorities.
Detailed schedule giving proposed dates of main activities, test and mobilization and date
of main personnel.
Details of the selected sections, including assemblies and pre – test sections.
Details regarding the hydrostatic testing activities including this procedure, program and
schedule for the work.
Provide with the necessary quality and quantity of the water supply for the hydrostatic
testing.
Supply all materials, consumables, equipment, spares, labor, supervision and other
services incidental to and necessary for safe and successful performance of the
hydrostatic testing work in a satisfactory manner for the Company.
Identify potential environmental hazards, including the necessary measures for on land
water disposal
6. SAFETY
While applying this procedure Contractor’s HSE manual approved by Company shall be adhered
to. Emphasis shall be given to the followings issues:
HSE manager shall be consulted for planning and implementation of safety issues.
Ensuring that all workers involved in hydro test works are properly instructed regarding
prescribed steps to be taken prior pneumatic and hydrostatic tests being carried out for all
test packages
Page 4 of 24
Company: Contractor:
Warning of the hazards associated with the energy stored within a pipe under test; in
particular the energy stored within a pipe containing water and air shall be given to
employees.
Safety of employees engaged in testing work, or work associated with testing in particular
due to the energy stored within line pipe containing water and air and possible
consequences of pipe and fittings failure under pressure test conditions.
Safety of public and environment as a sequence of hydro testing failure.
Discharge of test water to land at the end of hydro pressure test.
No works are permitted on the pressurized sections during the period of the test and
during subsequent pressure reducing operations.
Monitoring special points of hazard during the identified section test, as in particular road
crossings and points of public access.
Providing warning notices “Warning! Pipeline is under Test” in English and Arabic
Languages, such as:
ATTENTION!
PIPELINE UNDER TEST
KEEP AWAY
انتباه
تجارب ضغط خط الغاز
ممنوع التوقف
Providing boundaries of the test equipment. The locations shall be defined by marker
tapes or a fence and by lights at night.
Assuring no person approaching within 30 m of the test end manifold on pipe before
pressurizing the test section and during the test.
Locating pressurizing pump, pressure release valve and instrument caravan in a safe
area.
Page 5 of 24
Company: Contractor:
Communication shall be available to provide good tracing of the work and good
controlling for every event. Such communication will be mobile phones and the number of
these phones will be provided to the Company before any activity started.
Only authorized personnel shall be allowed to approach of the work area.
The hydrostatic test caravan and machine shall be located at accessible area and away
from the public activities.
Pressure pump, test cabin and other ancillaries shall be placed at a distance of at least 30
m from the test manifold.
Distribution hoses must be the correct size and suitable for the expected maximum
working pressure and will be perfectly supported.
The tightness of compression fittings must be checked regularly.
Use only the correct type and size of hose and fittings and connections, as clamps
especially made for compressed air.
Approved PPE for eye, ear, skin, body and head shall be available.
Never apply compressed air to the skin or direct it to a person, even air pressure of 1 bar
can cause serious injury.
Never operate any part of a compressed air system at a higher pressure than that for
which it has been designed and rated.
Shut off the isolating valve and release the air pressure before disconnection a hose or
line.
Dry powder fire extinguishers have to be available at equipment location.
During Operation: Check all pressures and temperatures are correct.
During Operation:
Don’t make adjustment when a machine is running unless appropriate precaution is
taken.
Don’t use the machine in a fire hazard area.
Ensure that all pneumatic control equipment and airline accessories are always
operated below their maximum rated pressure and temperature.
Page 6 of 24
Company: Contractor:
Replace hoses which have the signs of cracking or any mechanical damage are
evident.
Launcher and / or Receiver Location nearby populated area will be avoided, if they are, an
additional safety personnel will be required, to prevent any unauthorized person from
approaching the above ground parts of the pipe and also the launcher and receiver.
7. PERSONNEL QUALIFICATION
Only qualified and well experienced personnel shall be selected for carrying out the activities
involved within this procedure.
8. EQUIPMENTS INSTRUMENTS AND CONSUMABLES
Contractor shall provide the required equipment, instrument and consumable needed for
conducting the activities involved with the procedure.
8.1. Calibration Certificates/Certificate
The Contractor shall prepare the following certificate for the calibration of the following, prior
starting hydrostatic test:
Pressure gauges
Pressure records
Dead weight tester
Thermometers
Dew point meter
Page 7 of 24
Company: Contractor:
8 Pressure recorder 2
17 Generator 1
Page 8 of 24
Company: Contractor:
Page 9 of 24
Company: Contractor:
8.4. Consumables:
Ser
Item Descriptions
. QYT
No.
1 24 in Bi – directional pig equipped with 2 guide/ support discs and 6
4 scraper /seal discs (Complete Set) – for cleaning and filling
With spare sealing Discs
with spare guiding Discs
2 24 in. Cleaning pig equipped with 3 scraper / seal discs and 1 6
brush wraps (Complete Set) – And
With spare caps
With spare brushes
With spare spring blades
24 in. Bi – Batching pig equipped with 4 Conical cups (Complete
4 6
Set
24 in. Scarlet Crisscross Hard foam with wire brushes pig-for
5 6
scraping
6 24 in. Scarlet Crisscross Hard foam pig-for heavy scraping 6
7 24 in. Poly foam Scarlet bare –for drying 10
8 24 in. Poly foam ( red Swab ) – for drying 5
9 24 in soft foam pigs 50
11 Aluminum gauging plate ( Locally) 6
Note:
1. Pigs shall be designed for passing 1.5 radius bend and transverse a full
size branch opening
Page 10 of 24
Company: Contractor:
9. TEST SECTIONS
Gas pipeline will be divided into 3 separate sections for hydrostatic test. Date of each section
shall be registered in a report form as identified in Appendix (1) – Test Section Data sheet.
Schematic drawing of each test section, showing filling and pressurizing point, test pressure,
elevation, differential elevation, theoretical length of the section and volume, theoretical volume
to pressurizing per Appendixes: 1 – 1; 1 – 2 and 1 – 3
10. CLEANING
Prior to section cleaning, Contactor shall submit:
Approved Section Release for Hydrostatic test – Appendix No.2
Approved Section cleaning report form – Appendix No.3
Approved Pig Launcher and Receiver head test drawing - Appendix No. 4
Contractor shall pass air through the pipeline for period of 3 hours at minimum speed of 3 m/s
in order to blow out all loose welding slag, sand and debris from the pipeline.
Contractor shall install an impingement plate at the receiving end to ensure that pipeline debris
carried by the air is deflected to the ground.
All personnel at the receiving end will wear eye protection goggles.
Compressors shall supply oil free air with suitable rates to ensure a pig travelling speed
controllable between 1.2 and 1.7 m/sec.
Compressors shall be equipped with non-return valve at the outer let, pressure regulating
device and relieve valve set at 15 bars.
Cleaning will be accomplished by pushing a Two Caps Wire Brush Pigs run through the
tested section of the pipeline.
Page 11 of 24
Company: Contractor:
Each brush pig will be launched individually and propelled with compressed air through the
entire test section until retrieved at the pig receiver.
When the pig arrives to the pig receiver, the section shall be depressurized and the pig shall
be taken out.
Pressure gauge with suitable range (0-10) bar will be place on the pig launcher.
A report shall be kept for all pigging runs according to Appendix No. 3.
If the pig becomes stuck, the pressure shall be increased up to 7 bars; the location will be
identified by sending another pig with locator to determine location of stuck pig. The pipe shall
be exposed and the cause shall be investigated and repaired to the satisfaction of SGC
11. GAUGING
An aluminum gauging plate of diameter at least (d = 564.00 mm) (0.96x 586.2=562.75 mm)
shall be fitted on stiff pig (disc pig or 4 cup pig) to run through each section propelled by
water to confirm the geometric integrity of the section.
The gauging plate diameter shall be at least 562.70 mm which is 96% of the smallest pipe
internal diameter.
Page 12 of 24
Company: Contractor:
d/D0 = 564.00/586.2=0.9621
d = 564.20 mm
Internal diameter:
Total clearance:
28.6/2= 11.0 mm
Aluminum plate 10 mm thickness with edge will be machined with 4 mm shoulder and 45
degree bevel shall be used as a gauging plate.
Gauging plate shall be identified with section number, pipeline kilometers and date of test.
Gauging pig velocity should be approximately 0.6 m/s and should not exceed 1.7m/s.
The gauging plate shall be inspected by the Company before it is used and after it is removed
from the manifold. The following activities shall be undertaken in the presence of the
Company’s hydrostatic test representative:
Measurement and recording of the cup/disc and gauge plate dimensions, immediately
prior to gauge pig installation.
Page 13 of 24
Company: Contractor:
Measurement and recording of the gauge plate dimensions immediately after gauge
pig removal.
All recovered pigs shall be carefully examined to establish the degree of wear or damage to
cups or discs.
All Measurements of the cup/disc dimensions shall be taken and the results recorded in a
report form. See appendix No. 5. The results of the pig run shall be analyzed and the
evaluation submitted to Company within 24 hours.
Contractor shall determine the cause and make all necessary repairs of the pipeline if the
gauging plate shows any damage.
Should a gauging pig get stuck in the pipeline, the contractor shall not employ pressure
greater than the cleaning pressure (7 bars) to dislodge it.
If 7 bar is insufficient to dislodge the pig, the pig must be located and removed from the
pipeline by back pressure (applying pressure at the receiver end) or by cutting or other
method to be approved by company.
Contractor shall determine the cause and make all necessary repairs of the pipeline if the
gauging plate shows any damage.
Contractor shall not proceed with the testing procedure before the rerun gauging plate is
accepted by Company.
Page 14 of 24
Company: Contractor:
Where:
For 1 Km length, the volume of required water for filling will be:
2
(0.593) 3
V =Π × ×1000=272m /km
4
Filling shall be continuing up to all interrupted air is disposed and calculation check is done.
Contractor will transfer the water from the tested section to another section.
Page 15 of 24
Company: Contractor:
Water source will be from the wells in the local area. Water quality as specified in PL-CP
specifications.
Water filling data shall be fulfilled in a water filling report, see Appendix No. 6.
A pre-check shall be performed, detailing the status and location of each item to be inspected
before pressurizing is commenced. This shall include as a minimum:
The test section has been isolated from all other pipeline sections.
All the temporary piping, test head and other equipment connected to test section have
been tested to a pressure of at least 1.5 times the test pressure.
The test section has been filled completely and air has been vented off.
All instruments and gauging to be used during pressurization and testing have been
calibrated and valid test certificate have been approved by Company and available
All warning notices “The Pipeline Under Test”, markers, protective barriers and other
safety equipment have been positioned and appropriate authorities have been informed
All relevant personnel at the affected section have been informed of the commencement
and duration of the hydro test
The personnel engaged in the testing work have been briefed on the emergency plan
The person operating the pressurizing equipment has been instructed by the test
engineer regarding the limiting pressure which shall apply to the test section
Pressurizing equipment and other ancillaries have been placed at a distance of at least
30 m from test manifold
The thermo couple type temperature recorders (soil temperature recorder) 24 hours
before starting the pressure test have been placed at a distance of 100 m from the
buried end of the test section
All temporary and permanent valves have blinded prior to start the test
All flexible hoses have been fixes by approved method
Prior to commence the hydrostatic test, there shall be a stabilization period in which the
temperature of the water in the line shall increase or decrease to within 5.0 oC of soil
temperature. This shall be determined as the difference between average water pipe
temperature and average ground temperature over the test section length.
Page 16 of 24
Company: Contractor:
During the stabilization period the following measurements shall be taken and recorded every
1 hour:
Line pressure
Pipe water temperature
Soil temperature
Air temperature
Volume of air
Percentage of air content = ×100
Volume of line
The test engineer shall draw a plot of pressure add/bleed volume (P/V plot) see Figure 1,
taking the volume added as measured either by pump strokes or flow meter and pressure as
measured by dead weight tester or pressure date logger. A tank should be available to enable
the volume rating of the pressurizing pump or flow meter to be checked. The rate of the
pressurization should be constant and should not exceed 1 bar/minute until a pressure of 35
bars has been attained. During this period, volume and pressure reading should be recorded
at 1 bar intervals.
Page 17 of 24
Company: Contractor:
If the measured volume of entrapped air, reduced to atmospheric pressure, is less than 0.2%
of the test section volume thin filling of the line will be deemed acceptable for proceeding with
the hydrostatic test.
If the volume of the entrapped air exceeds 0.2% then Contractor shall take measures to
reduce the quantity of air in the test section, either by venting or by refilling the line. In any
case the line shall be fully depressurized and another air entrapment test shall be carried out
to determine acceptability of the filling operation
The person operating the pressurizing equipment shall immediately report to the test engineer
any variation in the rate of pressure increase resulting from the same volume added water.
During pressurization, all potential leak points shall be checked. When the pressure of 35 bars
has been reached, the air content shall be determined.
Page 18 of 24
Company: Contractor:
When the air content is within the maximum allowable limit of 0.2% of the test section, volume
pressurization should continue, at the rate of 1 bar/minute maximum as follows:
If the flanges are installed, pressurization shall continue up to 70 bars and held whilst the
flanges are checked for leaks. this is the highest pressure permitted at which any leaking
flanges may be tightened up.
Pressurization shall continue up 90 bars and shall be held for 2 h., during this period, if any
leak found, the test section shall be depressurized at a rate not more than 2 bars /minute down
to 70 bars prior to any bolt tighting.
The volume and pressure readings should be raised to 95 bars and held for 30 minutes, and
then the pressurization should continue to the 99 bars as slow as possible, at a rate not
exceeding 0.5 bars/ minute
During pressurization, actual hydrostatic test and bleeding operations, all globe, gate and ball
valves shall be fully opened
During this period, the pressure and added volume should be continuously plotted until 99 bars
pressure have been attained. The plot should be constantly checked and, in the event of any
deviation of 10 % or more from the theoretical line corresponding to 100% water content, the
test should be terminated. The pressure should be released and an investigation shall be
carried out to determine the cause of the deviation prior to re-pressurization.
Company shall confirm that the TP does not exceed the pressure to which the pipe has been
subjected during the mill test and that it is higher than the test pressure of the fittings specified
for the pipeline.
The pressure test shall be maintained during the strength test at TP ± 1bar by bleeding or
adding water as required. The volumes of water added or removed shall be measured and
recorded.
Page 19 of 24
Company: Contractor:
Air temperature
Barometric pressure
Every 3 hours.
The test section temperature and ambient temperature against time plot for the stabilization
period should be maintained.
If any leak is found during the strength test then the test shall be discontinued and necessary
repairs made. Contractor shall supply, install and tighten gland packing on those valves that
leak during hydrostatic test.
8.3.1 General
The leak tightness test should commence immediately after the strength test have completed
satisfactorily. No water shall be added or removed during the tightness test.
To allow pressure variation caused by temperature fluctuation during the test duration, the leak
tightness test pressure shall be combined strength/ leak tightness test at strength test
pressure, without water addition or removal. Pressure variation due to temperature fluctuation
shall be controlled so that the PT will not exceed 99 bars.
During the test, the pressure shall be recorded continuously, and the dead weight tester and
air temperature shall be recorded every 30 minutes. The pipe and soil temperature shall be
recorded at maximum 3 hours intervals. The temperature recording interval should be reduced
to a1 hour duration for the first and last 3 hours periods of the 24 hours to assist with the
pressure/temperature variation calculation. The test section temperature and ambient
temperature against time plot create for the stabilization period should be maintained.
Page 20 of 24
Company: Contractor:
On the basis of pressure and temperature measurements made during 24 hours leak and
measurements recorded during the entrapped air test, and taking into account possible
inaccuracies in measured or assumed parameters, CONTRACTOR shall demonstrate to
COMPANY’s satisfaction that the section under test has not leaked during leak test period.
The pressure, the test section temperature and ambient temperature should be plotted against
time during the period of the leak tightness test.
The tightness test shall be deemed acceptable if any change can be accounted for by
corresponding temperature change using formula above. Allowance should be made for any
recording inaccuracy.
If the event of any doubt about the leak tightness of the line, for example if the temperature
and pressure trends are different, the test shall be extended until such time as the acceptability
can be demonstrated.
Section Hydrostatic Testing Acceptance Report will be filled as shown in Appendix No. 9
15. LEAK DETECTION DURING HYDROSTAIC TEST
If a leak is suspected, the Contractor shall reduce the pressure to less than 79 Bars and carry
out visual examinations and due means for locating the leak without endangering the
personnel carrying out the work.
16. DEPRESSUTIZATION
After the satisfactory completion of strength and leak tightness tests, the test section shall be
depressurized to hydrostatic head plus 1 bar so that air does not enter into the test section.
Pressure let-down valves shall be opened slowly and depressurization continued at a rate that
does generate vibrations in associated pipe work.
The depressurization should not exceed 1 bar per minute until the pressure has been
reduced to 35 bars. Then depressurization should continue at a rate of less than 2 bars per
minute.
Page 21 of 24
Company: Contractor:
Measured data during Bulk De-watering will be recorded in report form shown in appendix No.
10
The water shall be transferred via a breaking tank and fill pump into the next section, if water
within the specifications, using 4 cup type pig as stated in the filling requirements.
Time lapse between bulk dewatering and drying shall be as short as possible to exclude
running the corrosion inhibitor (dosed) slug.
Page 22 of 24
Company: Contractor:
28. ATTACHMENTS
Page 23 of 24
Company: Contractor:
Crossing sections:
1. At 00.00 (after insulation joint + sock and over + Anchor block). Boring length =36 m
(insulation joint)
2. At Homs Phosphate main road: 2 km +634.02 m. length 120 m to 2 km 754.02 m
3. At km 12 + 571.37 m (center of crossing).
4. Rail way crossing: from Km 18 + 082.09m of 30 m length to 18 km 112.09m
Test sections
From 00.00 to 8km + 705m (Km 9 +342.26) (point no. 77)
From 00.00 to 7km + 404m (Km 9 +342.26) (point no. 57)
From
Page 24 of 24