Professional Documents
Culture Documents
U!5t
~ (
/ •=•&L
no. 1yCorps
nee rs Technical Report M-339
M--<B9 February 1984
tion Engineering
' Laboratory
by
Fernando Castilla
Phillippe Martin
John Link
LIBRARY BRANCH
TECHNICAL INFORMATION CENTER
US ARMY
fNr.INEEfl WATERWAYS EXPERI MENT STATION
Vlf.KSRllRr, MISSISSIPPI
READ INSTRUCTIONS
REPORT DOCUMENTATION PAGE BEFORE COMPLETING FORM
1. REPORT NUMBER 2. GOVT ACCESSION NO. 3. RECIPIENT'S CATALOG NUMBER
CERL TR M-339
4. TITLE (and Subtltl9) 5. TYPE OF REPORT 8t PERIOD COVERED
February 1984
13. NUMBER OF PAGES
61
14. MONITORING AGENCY NAME 8t ADDRESS(ll dltl9ronl from Controlllnl2 Otllc9) 15.
•
SECURITY CLASS. (of this report)
UNCLASSIFIED
1Sa. DECLASSIFICATION/DOWNGRADING
SCHEDULE
17. DISTRIBUTION STATEMENT (of the abetracl entered In Block 20, II dlllerent from Report)
19. KEY WORDS (Continue on revere• 11lda II nec•••ary and ldrmtlly by block number)
pile structures
concrete
embedment length equal to or greater than twice the pile depth or diameter is required to
develop a condition approximating full fixity for a pile embedded in the base of a
concrete structure.
IINCI.ASSIFIED
SECURITY CLASSIFICATION OF THIS PAGE(When Data Entered)
FOREWORD
This investigation was performed for the St. Louis District, U.S. Army Corps of
Engineers, under Inter-Army Order FAD ED8 l-69. The work was conducted by the U.S.
Army Construction Engineering Research Laboratory (CERL), Engineering and Materials
Division (EM), in conjunction with the University of Illinois at Urbana-Champaign
(UIUC), Department of Civil Engineering. Mr. John Jaeger, St. Louis District, served as
project monitor for this investigation.
3
CONTENTS
Page
DD FORM 1473 1
FOREWORD 3
LIST OF TABLES AND FIGURES 5
1 INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Background
Objective
Approach
2 METHODOLOGY 9
Cap-Member-Soil Model
Cap-Member Model
3 CAP-MEMBER-SOIL MODELS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Introduction
Method of Analysis
Soil and Concrete Parameters
Parametric Analysis
4 CAP-MEMBER MODELS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
Introduction
Exploratory Finite clementi'.liodeis
HP 14X117 Typical Design Loading Analyses
HP 14X117 Parametric Analysis
5 CONCLUSIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
REFERENCES 52
DISTRIBUTION
4
TABLES
Number Page
FIGURES
5
FIGURES (Cont'd)
Number Page
6
FIGURES (Cont'd)
Number Page
7
FIGURES (Cont'd)
Number Page
8
FIXITY OF MEMBERS EMBEDDED IN fix the piles to limit deflection. A considerable amount
CONCRETE of theoretical and experimental research is available to
define the load transfer mechanism for a pile em-
bedded in the soil below the pile cap; however, there
appears to be little data available to define the load
1 INTRODUCTION transfer mechanism for the portion embedded in the
concrete pile cap.
9
Analytical studies were performed by CERL and Table 1
UIUC using models of the cap-member system and the Model Parameters and Ranges
cap-member-soil system. These studies were initially
Parameter Range
conducted using the parameters and ranges presented
in Table 1 and diagrammed in Figure 1. These parame- Member Spacing 3 to 50*
ters and ranges were developed by CERL in conjunc- Member Embedment 1 to 40
tion with the St. Louis District before this investigation Cap Thickness 6 to 100
began. Preliminary results from both the CERL and the
Member Configuration (D)
UIUC studies using these parameters indicated, how- Circular 10 to 24 in. in dia.
ever, that an embedment length of approximately ''H" 10 x 10 to 14 x t4Y2
twice the diameter or depth of the pile was adequate to
develop a condition approximating full fixity. The St. Modulus of Elasticity
Louis District, therefore, requested CERL and UIUC to Concrete 3 to 5 x 10 6 psi
Steel 29.6 x 10 6 psi
investigate the behavior of HP 14Xl l 7 and HP 14X73
steel piles with 2-ft and 4-ft embedments in a concrete Poi~son's
Ratio
cap and subjected to the typical design loadings condi- Concrete 0.15 to 0.20
tions presented in Table 2 and Figure 2. Steel 0.3
Soil 0.1 to 0.5
Cap-Member-Soil Model
Soil Subgrade Reaction
UIUC represented the concrete cap-pile-soil system Sands 4 to 56 tons/cu ft
as a Winkler model, i.e., the pile was supported by a Clays 50 to 200 tons/cu ft
series of independent springs. 2 Springs with linear load- Soil Embedment Length 20 to 60 ft
deformation characteristics represented the concrete
cap, and springs with nonlinear characteristics repre-
*D designates member diameter or depth depending on mem-
sented the soil. The pile was assumed to be linearly
ber con figuration.
elastic. Variations of the significant parameters were in-
vestigated to-study the relationships among the degree
/
3 to5 D
I• Spocino ..
1
=Ft/?l~
... ____
· . ,--,...,.
. '•; : . '. ·.·.
0
Q
:., ,•: Embedment
-
0
IQ
Section
10
Table 2
Typical Design Loadings for HP 14X73 and HP 14Xl 17 Piles
FI F, F3 F• F, F•
(kips) (kips) (kips) (in.·kips) (in.·kips) (in.-kips)
NORMAL OPERATING
Pinned HP 14X73 "h = .017 kips/cu in. --1.3 6.4 125 0 0 0
End HP 14Xll7 "h = .003 0 0 188 0 0 0
NORMAL OPERATING
(0.1 g E.Q.)
Pinned HP 14X73 nh = .027 -26 -1.7 123 0 0 0
End HP 14Xll 7 nh = .03 22 201 0 0 0
member-soil model. 3 The program was modified to To minimize computer costs and to produce results
model the embedment of the pile in the concrete cap. that were readily comparable with the UIUC results,
To accurately represent the different soil conditions it only two-dimensional linear and nonlinear models of
was necessary to determine soil spring constants for
sands an<l clays of various strengths and limit pressures.
Spring constants were also determined for the concrete
cap section of the model.
3
Reese, pp 287-305.
4
ANSYS User's Manual Revision 3 (Swanson Analysis Sys- Figure 2. Design loadings for HP 14X73 and HP
tems, Inc., Houston, Pennsylvania, 1977). 14Xl 17 piles.
11
the cap-member system were analyzed. Dimensions for Method of Analysis·
the two-dimensional models were based on the ranges
in Table 1 and equal orthogonal spacing of the mem- Original Method
bers was assumed. The finite element used in the two- The COM 622 program was modified to solve the
dimensional linear models was STIF 42, a general problem of a beam resting on a nonlipear Winklcr's
purpose clement for modeling solid structures. The foundation with a finite difference numerical scheme.
clement was used in a biaxial plane strain state. The The boundary conditions (four conditions arc required
clement is defined by four nodal points, each having to solve the problem) are preprogrammed at the tip of
two degrees of freedom translations in the nodal x the pile and arc input-dependent at the head of the pile
and y directions. For the two-dimensional nonlinear (soil-cap interface).
models, the STIF 42 element was also used; however,
the flanges of the pile were modeled with a plane bar The conditions of zero moment and zero shear at
element, STIF 1. The interface between the pile sec- the tip of the pile are preprogrammed in COM 622. At
tion and the concrete cap was modeled with a two- the head of the pile, the input boundary conditions can
dimensional interface element, STIF 12. The interface be shear and moment, shear and slope, or shear and
element represents two plane surfaces which may main- ratio of moment to slope (rotational spring constant).
tain or break physiqil contact and which may slide
relative to each other. The element is capable of sup- Modified Method
porting only compressive forces in the direction nor- The approach taken by UIUC consists of a two-step
mal to its surfaces, and shear (Coulomb friction) in its iterative scheme which was used because only one of
tangential direction. The element has two degrees of the two boundary conditions at the head of the pile
freedom at each node-translations in the nodal x and was known. The full pile is modeled in the cap and in
y directions. The input properties required to repre- the soil as two independent pile sections. The analysis
sent the model's materials characteristics were the is carried out for each section separately. The head of
modulus of elasticity. Poisson's ratio, coefficient of each pile section begins at the soil-cap interface. Itera-
friction, and shear modulus. tions arc performed until the continuity of boundary
conditions at the soil-cap interface is achieved.
The measure of pile fixity is based on rotational
response of the embedded pile section at the concrete A complete iterative cycle consists of the following
cap face. Since the ANSYS STIF 42 element provides steps:
only displacements at its nodal points, a procedure was
developed to interrogate the ANSYS displacement re- Step one: Analysis of pile section in concrete cap.
sults and obtain displacement values for selected nodes.
These displacements were then used to compute the (a) Assign moment: the moment is assumed to be
required rotational values at the cap face for the zero at the head of the pile for the first iteration. For
various cases analyzed. the second iteration, the moment assigned to the head
is the value computed in (d) below for the first itera-
tion. Note that the shear in the pile at the concrete soil
interface is a known value for the problem.
3 CAP-MEMBER-SOIL MODELS
(b) Perform analysis: compute the slope of the cap-
pile section at the soil-cap interface for the value of the
assigned moment and shear from (a).
Introduction
In the UIUC analytical study, the degree of fixity of Step two: Analysis of pile section in soil.
the pile embedded in a concrete cap and the underlying
soil was analyzed as two independent pile sections, i.e., (c) Assign the slope computed in (b).
one in the cap and the other in the soil. The concrete
cap was modeled as springs with linear load-deforma- (d) Perform analysis: obtain the computed value of
tion characteristics, and the soil was represented by moment in the soil-pile section at the soil-cap interface.
springs with elastic-plastic load-deformation charac-
teristics. The pile was assumed to be linearly elastic. (e) Compare the moment computed in (d) with the
UIUC modified the COM 622 computer program, to moment assigned in (a). If the two values arc not
perform the analysis. within an acceptable tolerance, perform a new iterative
12
cycle. Otherwise, the solution has been reached. of elasticity of the sand for a given depth z can be
(Acceptable tolerance is reached when defined as
The iterative procedure is automatic in the modified The soil coefficient for a vertical beam with width B
version of the COM 622 computer program. A degree is determined by the relation between the contact pres-
of convergence acceptable for engineering purposes sure p and the corresponding lateral displacement y of
was usually achieved within four cycles of iterations. the contact face. The theory of elasticity defines the
relation between p and y as
Soil and Concrete Parameters
For the solution to the problem of a laterally loaded
pile by the method used in the COM 622 computer
program, it is necessary to predict a set of load-defor-
mation curves (known as p-y curves) for each medium Hence the soil coefficient:
(soil and concrete). Figure 3 shows the graphic defini-
tion of p and y and a typical set of p-y curves. The p A'}'Z z
following two sections deal with construction of p-y k = y = 1.35 s = nh B
curves for soil and concrete.
and the load per unit length of the pile:
Soil Parameters
Sands and clays are the two soil types considered in P = p B == nh z y
this study. For pressure levels below the limit pressure,
the stiffness. values used are from Terzaghi. 5 The where the factor:
method described below was used to establish limit
pressures for both sand and clay. Elastic-plastic p-y
curves were constructed for both sands and clays by
combining Terzaghi's recommendation for the elastic
portion and using the limit pressure calculations to The value of /I. ranges from about I 00 for very loose
establish the upper limit of p. sand and 2000 for dense sand. The average unit weight
of dry or moist sand is considered as 'Y = I 00 lb/cu ft,
The derivations and values retained for analysis are and the average effective unit weight of submerged
shown in the following subsections. The soil coeffi- sand as -y' = 60 lb/cu ft. The values of nh given in
cient (spring constant) characterizes the elastic part Table 3 are consistent with these values of /I.,'}', and -y'.
while the limit pressure describes the plastic region.
2. Clays-For piles embedded in clays, the value of
Evaluation of Soil Coefficients. Soil coefficients the soil coefficient k increases approximately in simple
were evaluated for sands, clays, and a typical design proportion to the unconfined compressive strength of
situation using Terzaghi's recommendations. the clay (qu). Table 4 shows the proposed value of soil
coefficients for piles embedded in clay.
I. Sands-TI1e soil coefficient k for sands at a given
depth z below the surface depends on the width B of
the pile (measured at a right angle to the direction of
the displacement), the effective unit weight 'Y of the
sand, and the relative density of the sand. The modulus Table 3
Values of nh for Sands (tons/cu ft)
13
Ground Surface
A _I
(a)
~--- - p
(b) ~ 'i
p
-Y
i
~z
(d)
14
Table 4
Soil Coefficients for Clays
Very where
Clay Stiff Stiff Hard Kp =coefficient of passive earth pressure = tan
(45° + <P/2)
% (ton/sq ft) 1-2 2-4 >4 KA =coefficient of active earth pressure =tan (45°
k (ton/cu rt) 50 100 200
- <P/2)
r'=buoyant unit weight = 'Ysat - 'Yw = 60 lb/
cu ft
z =depth
3. Typical design situation - Under normal static
B =pile width.
operation conditions, the soil was represented by a
very loose sand with nh = 0.001 kips/cu in.= 1 ton/cu
ft. Under normal dynamic operating conditions (0.1 g The ratio p/z = (Kp - KA)r'B is a characteristic of
earthquake acceleration), the soil was represented by a both soil and pile width. The limit elastic deformation
medium dense sand with nh = 0.03 kips/cu in. = 26 (y le) is computed from the expression
tons/cu ft.
Table S
Limit Elastic Deformation (Yie) for Sands
Typical
Design
Situation x x
n11 (tons/cu ft) 0.864 4 14 26 34
<fl (deg) 30 30 37 40 45
Kp 3.0 3.0 4.0 4.6 5.83
KA 0.33 0.33 0.25 0.22 0.17
HP14Xll7
b = 14.9 in.
p .
... (lb/111.) 1.38 1.38 1.95 2.27 2.93
I.
y le (in.) 1.38 0.298 0.120 0.076 0.074
HP 14X73
b = 14.6 in.
f (lb/in.) 1.35 1.35 1.91 2.22 2.87
Y le (in.) 1.35 0.292 0.118 0.074 0.073
*z measured in inches.
15
2. Clays-In an undrained loading condition (</> = Table 6
O), the difference between passive and active pressure Limit Elastic Defonnation (Yie) for Clays
(t.) is equal to twice the unconfined compressive
Clayey Very
strength, qu: Soils Stiff Stiff Hard
p = t.B HP 14X117
p (lb/in.) 414 828 1,242
where Bis the pile width. Yle (in.) 0.597 0.596 0.447
HP 14X73
The limit elastic deflection, y le• is computed from
p (lb/in.) 406 811 1,217
the expression Ylc (in.) 0.585 0.584 0.438
p p
'------------Y
SAND CLAY
Figure 4. Typical load-deformation curves (p-y curves) for sands and clays.
16
concrete thickness on either side of a pile is at least
equal to one and a half times the width of the pile. The
value Ks = 3084 kips/sq in. was selected for all the
analyses. It was computed for a ratio of concrete thick- 20
ness to pile width equal to 1.75 and was found to be
approximately equal to the average spring constant for
.. x
values of concrete thickness to pile width ratio ranging
from one to five.
Young's Modulus
Detailed computations of Ks for both approaches Poisson's Ratio
are given in the following pages.
Q'.
Txz = 5.! [sina sin(o: + 26)] z =a cot -
. 1T 2
2a
az
.
= 5.!
1T
(a+ sina) Area
.. x
ax=; (a- sina)
2q
Oy =-;VO'.
L 8 =- ~
L
m = -a-
Txz =0
Substituting ax, ay, and Uz in the Ez equation yields:
17
dw = €z dz Table 7
Comparison Between
Substituting Ez and dz from the above equations, dw IHs and IRB
can be written as L
m=-a IHS IRB
dw = _g_ I + v a -[a(I - 2v) + sina] da 1.0 1.23 1.36
27T E . 2a 2.0 1.11 1.20
sm 2 4.0 0.86 0.9
10.0 0.51 0.5
Integration of dw between a = 7T (z = O) and 0'. 1
2 Arc cot (m) yields:
a, q l +V
w=
i 1T
dw = -27T -E- af (l - 2v)
OT
K 1TE
S =-I-+-,, -.j;:::(1=-=_=2=,,)=m=A=rc=c=o=t=(m=)=+=c=1_=,=,,=1n=o=+=m=:2=))
replacing a by L/m and simplifying,
The settlement of the surface layer of an elastic half
2q l + v space can be expressed as
w = -:;-E- L[(l - 2v) Arc cot (m)
2qL
1 w = 7TE IHs
+ (1 - v) -m Jn (I + m2 )]
where
The equivalent spring constant, K5 , is
2qa
IHs =(I + v)[(I - 2v) Arc cot (m)
Ks=- I
w +(I - v)- ln (I + m2 )]
m
1.4 2qL
~
~ - w = 7TE IRB
1.2
~oJ--
'J/
1.0 where IRs is shown in Figure 7 in terms of m = L/a for
/" a Poisson's ratio of 0.2. Table 7 shows a comparison
!Re o.e between lHs and IRs for various m = L/a values. As
0.6 '{
I can be seen from the table, both methods predict very
similar settlements of the layer under a strip load for
0.4 J m~2.0.
0.2
I Calculation of Concrete Spring Constant. Using the
0
I half-space solution, the spring constant Ks is given as
0.1 0.2 0.3 Q4 0.5
2.0 1.5 1.0 Q5 0 2qa 2qL 7TE I
K --------
s - w - mw - m IHs
j_ m
m
8
Figure 7. Plot of !RB in terms of m = 4a and v = 0.2. Poulos, pp 378-410.
18
where n(3122) I .
Ks= _ _ =3084ks1
3 5 0 91
ltts =(I + v)[(I - 2v) Arc cot (m)
I Parametric Analysis
+(1-v)-ln(I +m 2 )]
m An analysis was performed to investigate the effect
of the following parameters on the degree of fixity of
and the pile section:
L
m=- 1. Embedment length in the cap
a
2. Soil stiffness and soil type
and concrete's Young's modulus, from ACI :9
3. Shear force at the interface between the soil and
E(lb/sq in)= 57000 V((lb/sq in)
cap
Table 8
Computed Response to Typical Design Situations
Fixed End
Embedded Shear at Cap Computed Usual Design
Length Base of Cap Displacement Max. Moment Moment
Operation Soil Pile (in.) (kips) (in.) (in.·kips) (in.-kips)
19
Medium Sand
PILE HP14X117
EMBED. t....ENG H1 ~ ! 2 ! \I.
t....ATERAL LORD ~ ~ 5 '<.!PS
Figure 8. Typical moment and deflection curves for HP 14Xl 17 pile with 12 in. embedment.
20
Medium Sand
PILE f-jPl4X:·~ 1_ 7
E "1 B E. D . L. E. l\J G 11-1 · 4 8 r N .
L.ATERAL L.oqo ·. : s i.:.. ~ os
~S CONCREfE ~ 5~24 ~~
Figure 9. Typical moment and deflection curves for HP I 4XI I 7 pile with 48 in. embedment.
21
EFFECT OF Le /8 RATIO ON PILE ROTATION
AT SOIL-CAP INTERFACE
4.0-----------.------------------
3.2
~
0
....
,,,
Q 2.8
>(
Q)
~
Q)
--
(.)
0
.Q)...
.E
2.4
a.
0 2.0 Very Loose Sand, "H = 0.001 k/in.5
u Shear at Bose of Cop = 2.8 k
I
·-0
en
-
~
0 1.6
-
a.
0
c: 1.2
-
.9
.E
0
a: 0.8
Figure 10. Effect of Le/B ratio on pile rotation at soil-cap interface, typical design situation for HP 14X73 pile.
22
EFFECT OF Le/B RATIO ON PILE ROTATION
AT SOIL-CAP INTERFACE
3.2
;;
...
0
,.,
Q 2.8
><
Q)
.
--
Q)
(.J
0 2.4
...
Q)
.s
Q.
0
u 2.0
I
0
en
-0
.!!
1.6
Very Loose Sand, nH = 0.001 k/in.5
a:
-0
c: 1.2
Shear at Base of Cap = 2.2 k
-0
.2
0
Q::
0.8
Figure 11. Effect of Le/B ratio on pile rotation at soil-cap interface, typical design situation for HP 14Xl 17 pile.
23
EFFECT OF Le/B RATIO ON PILE ROTATION
AT SOIL-CAP INTERFACE
PILE HP 14x73
0.9
SHEAR AT
BASE OF CAP 15k
0.8
:a0
....
,..,
Q 0.7
)(
Q)
G>
.
0
~ 0.6 Loose Sand
....
-G>
.E
a.
nH = 4ton/ft 5
0
u 0.5
I
0
en
-0
G>
04
a.
0
c: 03
--
0
0
0
0::
0.2 Stiff Cloy
k = 50ton/ft 3 -----------0- } Sands
0.1
Very Stiff Clay
-----------<>- }Cloys
k = 100 Ian/ft'
Hord Cloy
k = 200 ton/ft'
0'---.1.~-'-~ ........._.j---_....~......~"---"'~........~~__,.__-:-':~----":"
0.5 1.0 1.5 2.0 2.5 3.0 3.5
Ratio of Embedment Length to Pile Width, Le/B (in.fin.)
Figure 12. Effect of Le/B ratio on pile rotation at soil-cap interface, HP 14X73 pile with 15 kip shear at base of cap.
24
EFFECT OF Le/B RATIO ON PILE ROTATION
AT SOIL-CAP INTERFACE
PILE HPl4xl17
3.6 SHEAR AT
BASE OF CAP 15k
3.2
:ti
...
0
2.8
Q)
0
-
.E 2.4
...
-
Q)
.E
Q.
8 2.0
I
0
en
-
0 1.6
~
-a.
0
c: 1.2
-a:-
.2
0
0
O.B Stiff Cloy
k =50 ton /ft 1
0.4
Hord Cloy
k = 200ton/ft 1
o"---L~~0~5~..1-~1.~o~..._~1.~5~"-~2~D~......--::2~.5~----;3~D~----;-3.5
Ratio of Embedment Length to Pile Width, Le /8 (in.fin.)
figure 13. Effect of Le/B ratio on pile rotation at soil-cap interface, HP I 4X 117 pile with 15 kip shear at base of
cap.
25
EFFECT OF Le/8 RATIO ON PILE ROTATION
AT SOIL-CAP INTERFACE
-...
"'d
0
3.2
..,
Q 2.8
)(
Q) \
Q) -
-
£
(.)
0
...
Q)
2.4
Q.
c 2.0
u
I
-
CJ)
~
0 1.6
-
a..
0
c: 1.2
Shear= 5k
-
.9
0
0
a::
0.8
0.4
o..__.__.__.___.______,..__.____________________
0.5 1.0 1.5 2.0 2.5 3.0 3.5
Ratio of Embedment Lenc;ith to Pile Width, Le/B (in./in.)
Figure 14. Effect of Le/B ratio of pile rotation at soil-cap interface, HP 14Xl 17 pile in loose sand, nh =4 ton/
cu ft.
26
EFFECT OF Le/B RATIO ON PILE ROTATION
AT SOIL-CAP INTERFACE
4.0~._,.-"T"""__,~...,...--r--.,--r---r-.....,.--,--"!'"-__,. _ __
3.2
:a0
...
~
Q 2.8
)(
Cb
Q) -
-:s...
(,,)
0 2.4
Q)
Q.
0 2.0
u
I
-
(/)
0 1.6
~
-
a..
0
c 1.2
-
.2
0
0 Shear =5 k
a::
0.8
0.4
o~.....i.-...i....-1.--.....1.-..i.-__.~--..-""'---'--'--""'---'-...1...--J
0.5 1.0 1.5 2D 2.5 3.0 3.5
Ratio of Embedment Length to Pile Width, Le/B (in.tin.)
Figure IS. Effect of Le/B ratio on pile rotation at soil-cap interface, HP 14XJ 17 pile in dense sand, nh = 34 ton/
cu ft.
27
EFFECT OF Le/B RATIO ON PILE ROTATION
AT SOIL-CAP INTERFACE
4.o,.--...,..-..,.....--,-_.,..-~__,-...,..._...-__,. ____.,.___,._ __
PILE HP 14x73
3.2
~
...
0
,,,
Q 2.8
)(
Cb
~
cu
--...
u
0 2.4
cu
.E
0.
0 2.0
u
I
0
en
-
~
0 1.6
-
a..
0
c: 1.2
Shear" 5k
--
.S?
0
0
0::
0.8
0.4
0'---'"-~__..___.__...___..___.__...___. _ _.__...___._~--'
Figure 16. Effect of Le/B ratio on pile rotation at soil-cap interface, HP 14X73 pile in stiff clay, k = 50 tons/cu ft.
28
' 61:
_.:'.\'
~-·£_____0_·£
______~_·z ______cr~z_____~_-,______0~·1______,;·~o--~...... o
tiO
1.0
"$)
0.9
5k
z·1
9·1
HPl4xl02
3:>'1,:j~31NI
d't:>-1105 1'1 HP 14xll7
11'110~ 311d NO 011'1~ 8/91 ,:jQ 1:>3,:j,:j3
o.__..-.__....___...__-.__...___...__..___.___..__...___.___...__.____.
0.5 1.0 1.5 2.0 2.5 3.0 3.5
Ratio of Embedment Length to Pile Width, Le I B (in.I in.)
Figure 18. Effect of Le/B ratio on pile rotation at soil-cap interface, various pile sections in medium dense sand
with S kip shear at base of cap.
30
EFFECT OF le/B RATIO ON PILE ROTATION
AT SOIL-CAP INTERFACE
2.0
MEDIUM
DENSE SAND nH = 14 ton/ ft 3
1.8 SHEAR AT
BASE OF CAP IOk
1.6
:tj
~.
...
0
..,
Q 1.4
)(
Q)
--
Q)
u
0 1.2
...
Q)
.E
Q. HP IOx 42
0 1.0
u
I
·a HPIOx57
-
CJ)
~
0 08
-
a..
0
c: 0.6
HP12x53
-
0
0
0
HP12 x 74
HP14x73
0:
0.4
02
HP14xll7
0"-.....1.~-'-~""---"~ ....~~~--......~-'-~""-~~......~----'
0.5 1.0 1.5 2.0 2.5 3.0 3.5
Ratio of Embedment Length to Pile Width, Le/8 (in.fin.)
Figure 19. Effect of Le/B ratio on pile rotation at soil-cap interface, various pile sections in medium dense sand
with I 0 kip shear at base of cap.
31
constant value independent of Le/B which indicates The effect of pile stiffness is depicted in Figures l 8
the fixed end condition is achieved. and l 9. In both figures various HP pile shapes are
examined. These two figures show that as the pile stiff-
ness increases the rotation of the pile at the soil-cap
Figures 10 through 13 show the effect of soil type
interface decre<ises for <i given value of Le/B.
and soil stiffness. As the stiffness of soil increases. the
rotation of pile at the soil-cap interface decreases for
a given value of Le/B. Figures 12 and 13 show that the Table 8 lists the computed response for a typic<il de-
rotation of the pile is less for clayey soil than sandy sign situation. In this table, shear at the base of the cap
soil for a given value of Le/B. was used as an input (from Table 2) to compute the
maximum moment and cap displacement. The analysis
was performed for l 2 in., 24 in., 36 in., and 48 in. em-
Figures 14 through l 7 show the effect of shear bedment length, and two different piles, HP l4X73
force at the interface between the soil and the cap. As and HP l4Xl l 7. The last column of the table shows
the shear force increases for a given value of Le/B, the the fixed end design moments obtained from Table 2
rotation of the pile at the soil-cap interface increases. in order to compare them with the computed maxi-
mum moments. It should be noted that the computed
moments for the l 2 in. embedment length ranged from
61 to 83 percent of the computed moments for the 48
in. embedment length. This suggests that the "rule of
thumb" commonly used in the design of HP piles, i.e.,
an embedment length of 1 ft or less into the concrete
structure is considered pinned, may be unrealistic, and
that past pile foundations designed using l ft embed-
ment length for the pinned assumption may not really
al be pinned, but rartially fixed.
01
0JI IJ ll II II l axial stress distribution
4 CAP-MEMBER MODELS
Introduction
CERL analyzed the degree of fixity of the pile em-
dl bedded in a concrete cap from a purely structural
standpoint, without considering the underlying soil and
bendin9 stress distribution
the interaction of the pile and the surrounding soil.
CERL investigated the behavior of steel HP pile sec-
tions with several lengths of embedment in various con-
crete caps using two-dimensional linear and nonlinear
finite element models. The moments, shears, and axial
loads that would normally exist in the HP pile section
at the concrete cap face were assumed to produce the
stress distributions in the HP pile sections that are pre-
Figure 20. Stress distribution in an HP pile section. sented in Figure 20. These stress distributions were
32
used to determine the nodal forces to apply to the shear force of 1 kip and an applied moment of 720
appropriate nodal points in the finite element models. in.-kips.
33
a. b.
11
3@ 12" = 36
11
6@6" =36
I·
w ~ ~ Concrete cap
"""' :a>
Concrete cap
..,.
...
~
@)
• Embedded pile section
II 4
Typical 10 locations
11111!11111111111111111111111111111
4
Typical 18 locations
c.
37.2"
0607°::::11: =H=oso1"
-..,...,
-.
"'!!!
©
.."'
~=i==t=i=lt~t~$~:::~\~::::1[1}{~i';:IW~i~E§~f-""
.·.·.·.·.·.·.·.·:·.·.·.· .:.:..·:·.·'. :-:·.·.·:·.·
:··-·.·.·.··:··.....·.·. ,.;.,.,.,..· -:·:•.·.·.·:
·:···:·:·:·:-:-:·······: :-··········
<=:Embedded pile section
g 2
-
0
c
en
10 8 6 4 2 0 -2 -4
Figure 22. Lateral displacement curves for HP l 2X74 pile with O.SD, D, 2D, and 4D embedments.
M = 480 in.-kip
V = I kip
Q)
g 2
-
0
en
0
I I ....+········--·············:!ii'.'-
10 8 6 4 2 0 -2 -4
4
Lateral DisJ?lacements, 10- in.
-c
c tt --- 2
....)~ffo's
en
0
,,,,,
,~ /
...-::''
10 8 6 4 2 0 -2 -4
4
Lateral Displacements, I0- in.
39
Table 9
Angular Rotation of HP l 2X7 4 Pile
l•:mlwtlmcnt
l.Clll(th M ~240 in.-ldp M • 4KO in.-kip M • 720 in.-kip
u V •I kit' V •I kip V •.l kip
UPpil•---
Finite element
representation
Web Flange of the pile
'\
40
y
n
'
I
~ s
~-:::re
I 9 determines element
I orientation
I
I •
L...:N~o:!::d:..:e:.s.:.:m.::::a~y..:b:.:.e....;c:.;:o,;.;,in..;.c;,;id..;.en~t----- x
µ. ]Fnl
-µ. IFnl
For .Fn< O and
initial loading
41
of friction of 0.4 for a concrete and steel interface. lO Stress contour plots for ax, ay, txy, Omax, Omin,
The American Concrete Institute (ACI) specifies a and tmax are presented in Figures 27 through 32. In
coefficient of friction of 0. 7 when surfaces of rolled each normal stress contour plot (Figs. 27, 28, 30, 31 ),
steel and concrete are interacting. 11 The ACI also maximum tensile and compressive stress levels and
specifies a coefficient of friction of 1.4 for concrete their points of occurrence are indicated with an "X"
placed monolithically, which is an upper limit for the and "O," respectively. In the shear stress contour plots
coefficient of friction. A coefficient of friction of 0.4 (Figs. 29, 32), the maximum and minimum stress levels
was selected for the initial analyses, because it repre- and their points of occurrence are similarly marked.
sented a lower limit. The stress contour interval is indicated near the lower
left corner of the plot. A dash line is used to represent
4. Boundary conditions -The same boundary con- the zero stress contour line. Figures 27 and 28 indicate
ditions were used for the HP 14X 117 pile model as for that the maximum ax and ay stresses were --308 lb/sq
the HP l 2X74 pile model. in. and -371 lb/sq in., respectively. These stresses
occurred at the concrete cap face at the interface be-
5. Loading-TI1e loading conditions for the HP tween the concrete cap and pile on its left side. Along
l 4Xl 17 pile section are shown in Table 2. The intro- the interface between the concrete cap and the left side
duction of the interface element required that the of the pile, the ax stresses gradually decreased to a
loads be gradually applied to the model to ensure con- stress level approaching zero near the end of the em-
vergence of the solution. Consequently, the shear, axial bedded pile. Along this same interface, the ay stresses
load, and moment for each of the loading conditions (see Figure 28) decreased much more slowly because
were gradually applied to the model in a series of load additional load was transferred from the pile section to
steps so that large corrections in succeeding iterations the concrete cap through the interface elements.
would not be required. After each load step the solu-
tion was allowed to iterate until convergence was ob- Figures 30 through 32 indicate that the maximum
-tained-as- represented by -the unchanged _status of the and minimum principal stresses occurred at the left
bilinear elements from the previous iteration. side of the pile section at the concrete cap face and
that the maximum shear force occurred along the left
In the analysis of the HP 14Xl 17 pile section with boundary of the concrete cap. The maximum tensile
2D and 4D embedments and the subsequent parametric stress was 199 lb/sq in. and the maximum shear stress
analysis (discussed below), the effects of various was 254 lb/sq in. The latter is slightly greater than
parameters were analyzed. Table l 0 is an index correla- 3.5-Jf;; which is the maximum allowed by the ACI
ting the analysis case number and the specific model code for members subjected to shear and flexure
parameters for the analyses summarized in this report. only. 12 Since it is standard construction practice to
Table l 0 should be used as a reference when reviewing provide concrete steel reinforcement only in the region
and comparing some of the figures which follow. above the top of the embedded pile, consideration
should be given to placement of a nominal percentage
A typical displacement field and stress contour plots of concrete steel reinforcement in the region of pile
for the HP 14Xl 17 pile under normal operations with embedment to increase the structural integrity of the
a 0.1 g earthquake condition and an embedment depth concrete.
of 2D are presented in Figures 26 through 32. The
displacement field (Figure 26) indicates that although The lateral displacements of the centerline of the
the maximum displacement was only about 0.004 in., pile sections with 4D and 2D embedment in the con-
the pile section and concrete cap separated at the right crete cap (Case I and Case 2, respectively) are shown
side of the pile section. Consequently, relative displace- in Figure 33. The displacement curve for 2D embed-
ments occurred between the concrete cap and pile ment nearly coincided with the displacement curve for
section along both vertical interfaces, as shown by the 4D embedment between 0 and 2D. In addition, the·
offset boundaries of the finite elements along these displacement curve for 4D embedment experienced a
interfaces. change in slope at a distance slightly greater than 2D
from the concrete cap face, which indicates that the
10
PC/ Manual un Design of Connections j(Jr Precast, Pre-
stressed Concrete (Prcstrcsscd Concrete Institute, 1973).
11 12
ACI 318-77. AC! 318-77.
42
Table IO
Index Correlating Analysis Case and Model Parameters
Model Parameters
1 4D 3D 6D 14.9 0.4
2 2D 3D 4D 14.9 0.4
3 2D 3D 4D 14.9 0.7
4 2D 3D 4D 14.9 1.4
s 2D 3D 4D 44.7 0.4
6 2D SD 4D 14.9 0.4
7 2D SD SD 14.9 0.4
8 2D SD 6D 14.9 0.4
9 2D SD 7D 14.9 0.4
1;1111111
43
/
I
I
/
I I
/ I
I /
/
/
I
/
I
Ll!4 x -:m
CONTOUR INTERVAL :s 25 psi
44
2!51
Lx
CONTOUR INTERVAL =20 psi
199
45
Lx
CONTOUR INTERVAL =25 psi
-Figure 31. 'fyrpicaLStress £',ontourPJot for O'min-
46
pile section has achieved a condition of full fixity. The I. Coefficient of friction between the concrete cap
maximum lateral displacement at the face of concrete and the pile section
cap for the pile section with 4D embedment was
slightly greater than the pile section with 2D em- 2. Effective width of the concrete cap
bedment. Considering the nonlinear aspects of the
concrete pile system, this difference is not considered 3. Pile spacing
significant.
4. Concrete cap thickness.
The rotations of the pile section at the face of the
Different finite element models were developed and
concrete cap, </>max• for these same conditions of 2D
and 40 embcdment were computed to be 3.22 X I 0- 4 analyzed based in part on the range of parameters pre-
rad and 3.29 X 10 4 rad, respectively. A difference of sented in Table I. Table I 0 is an index which correlates
about 2 percent between the maximum rotations for the model parameters with a specific analysis case.
the 20 and 40 embed men ts was not considered signifi-
cant. Also, tho magnitudes of these rotations were The following is a summary of the results from the
quite similar to those obtained in the analysis of the parametric analysis:
exploratory finite clement models for the case of 2D
cmbcdment and a bending moment of 720 in.-kip. I. Coefficient of friction between the concrete cap
and the pile section. A degree of adhesion exists be-
tween the concrete cap and the pile section. TI1is ad-
The compression and shear forces developed in the hesion occurs at the interface between the concrete cap
interface elements in the models are shown in Figures and the exterior surface of the flanges of the pile sec-
34 and 35 for the 20 and 40 embedments, respec- tion, and at the concrete cap and the end of the pile.
tively, together with the nodal forces simulating the Consequently, three different values for the coefficient
applied loads. The forces transmitted by the first two of friction were investigated: 0.4, 0.7, and 1.4. Three
interface elements on the lower left side of the pile sec- analyses were performed and_identified_as_Case_2--(µ__=
tion were nearly identical for the 2D and 4D embed- 0.4), Case 3 (µ = 0.7), and Case 4 (µ = 1.4).
ments. Forces in the other interface elements along the
left side of the pile section tended to degenerate to The lateral displacement curves for the centerline of
zero, thus indicating that contact between the pile sec- the embedded pile section for the three analysis are
tion and the concrete cap had been broken. This sug- shown in Figure 36. The shapes of the three displace-
gests that the pile section attempts to pivot about the ment curves are basically similar. However, as the
edge of the concrete cap and thereby reduce the forces coefficient of friction was increased from 0.4 to 1.4,
acting 011 the upper portion of the left side of the pile the maximum displacement of the centerline of the
section: this increases the forces acting 011 the upper pile section at the concrete cap face decreased from
portion of the right side of the pile. 2.49 X I0- 3 in. to 1.62 X 10- 3 in., or about 35 per-
cent. The maximum rotation decreased from 3.22 X
Due to the nonlinear aspects of the interface cle- I 0- 4 rad to 2.23 X I 0- 4 rad, or about 30 percent.
ments and the solution convergence criteria, the forces These effects were due to the transfer of forces in the
acting at the interface elements do not fully satisfy pile section to the concrete cap due to the increase in
statics. However, the estimated error was less than 4 the coefficient of friction. Comparison of the interface
percent. element forces in Figures 34 (Case 2), 37 (Case 3), and
38 (Case 4) clearly indicated this to be the load trans-
fer mechanism.
HP 14X117 Parametric Analysis
A parametric analysis of the HP 14Xl 17 pile em- Stresses in the concrete cap were also compared at
bedded 2D in a concrete cap was performed to deter- the sections indicated in Figure 39. As a result of the
mine if other parameters would significantly affect the nonconforming quadrilateral element used to repre-
degree of fixity of the pile section. TI1e loadings ap- sent the concrete cap, the stress obtained from the
plied to the pile were those associated with normal analyses was average stress at the center of the element.
operations with 0.1 g earthquake conditions. The basic The distribution of forces in the horizontal direction
parameters for the models were the same as those used (fx) and the vertical direction (fy) were calculated
in previous analysis and are summarized in Table I I. using the normal stress, ax; the shear stress, txy; and
The following parameters were investigated: the thickness of the concrete cap, 14.9 in. These forces
47
4
0
Q)
0
~
0. 3
0
u
E
0
....
IJ...
Q)
0 2
c:
0
+-
I/)
Figure 33. Lateral displacement curves for centerline of HP 14Xl 17 pile with 2D and 4D embedments, µ = 0.4.
64490 27 36 27091
2691
"""'~~~~;w;.;.,:,;,:,:,;~;,;,;,;,;,~~~6952
904
2717 -+<oof'tilil~~~~~~~~~
10416
26081
Figure 34. Interface element forces for HP 14Xl 17 pile with 2D embedment, µ = 0.4.
48
thickness of the elements representing the concrete cap
outside the region of the pile was increased to 44. 7 in.
352 while the thickness of the clements representing the
9~4 concrete between the flanges of the pile section was in-
creased to 43.9 in. The latter number rcprcsrnts the
effective widlh of44.7 in. less lhc lhick11ess ol"thL· WL'h
747 of the pile section. Analysis Case 5 was performed and
2204
compared with the results from Case 2. The hiteral
displacement curves for the centerline of the embed-
0 ded pile section with an effective width of concrete
0 cap of 14.9 in and 44.7 in. are presented in Figure 44.
The maximum displacement at the centerline of the
pile section at the concrete cap face was reduced from
0 2.49 X 10- 4 in. to 1.16 X 10- 4 in., or about 50 per-
0 cent. The maximum rotation at the concrete cap face
was reduced from 3.22 X 10- 4 rad, to 1.76 X 10- 4
rad or about 4S percent, with the increase in the effec-
0
0 tive width of the concrete cap. The shape of the Case
S displacement curve was different in that the slope of
the curve changed sign at an embedment depth of
0 about 1.7SD. Likewise the distributed forces shown in
0 Figures 40 through 43 for Case 2 and Case S do not
indicate significant differences.
were plotted in Figures 40 through 43. In general, the 4. Concrete Cap Thickness. A series of analyses was
force distributions arc similar to each other, which performed in which the pile section was embedded 2D
indicates that the concrete cap stresses were not signifi- in the concrete cap and the thickness of concrete cover
cantly influenced by the coefficient of friction, at least above the pile section was varied from 4D to 7D
for the range of values that were investigated. (represented as Case 7, Case 8, and Case 9). Compari-
sons of the distributed forces calculated from the
2. Effective width of the concrete cap. The effec- results of these analyses are presented in Figures 46
tive width of the concrete cap was increased from through 49, respectively. These plots show that the
14.9 in. to 44.7 in. to determine if the effective width thickness of concrete cover above the pile section docs
of the concrete cap significantly affected the behavior not alter the distribution of forces in the region of the
of the cap-member system. To model this condition, the depth of embedment for the pile section.
49
Table 11
Basic Parameters for HP 14Xl 17
Pile Parametric Analysis
Parameter Value
Modulus of Elasticity
Concrete 3.0 X 10 6 lb/sq in.
Steel 29.6 x 1o• lb/sq in.
Poisson Ratio
Concrete 0.15
Steel 0.3
4
0
Q)
0
~
0. 3
0
u
E
0
....
l.J..
Q)
0
c:
-0
.!!?
0
Cose 4
~~
- --2.::""-
-- -:: ;:-..----
--.o--- -:;.,,,
,,,_ .,,,
-----
----==---=------
28 24 20 16 12 8 4 0 -4
4
Lateral Displacement, I0- in.
Figure 36. Lateral displacement curves for centerline of HP 14XI 17 pile with 2D embedment, µ = 0.4, 0. 7, and 1.4.
50
56691 24651 23124
3496 8257
0
43075 19 87 15902
0 6299
4499
2715
0
1552
0
0
0
0
242
Figure 38. Interface element forces for HP I 4XI 17 pile with 2D embedment, µ = 1.4.
51
concrete structure is considered pinned may be un-
realistic. The computed response of the cap-member-
soil model for the typical design situations indicated a
B A
I 1 ft emhedmcnt length would develop 61 to 83 percent
I of the moments for a 4 ft embedment length. There-
I fore existing pile foundations designed using I ft cm-
I bedmcnt length into the concrete structure for the
I pinned assumption may not really be pinned, but par-
I tially fixed.
I
I
I REFERENCES
I
I
I ANSYS User's Manual, Revision 3 (Swanson Analysis
System, Inc., Houston, Pennsylvania).
I
I ACI 318-77, Building Code Requirements for Rein-
I
forced Concrete (American Concrete Institute,
fy I I June 1978).
L B A
52
I.
(D)
7
---------- Case 5
- - - - Case 4
-·-·-·- Case 3
Case 2 6
11
o= 14.9
I
I
fx (Section A-A)
Figure 40. Normal force distribution at Section A-A for cap thickness of 4D.
53
Distance from cap face, D
(D)
7
Case 5
Case 4
Case 3 6
----.Case 2
'--~...r....~.....i.~-.._-~ 0
(lbs/in) 4000 3000 2000 1000
Negative
fy (Section A-A)
Figure 41. Shear force distribution at Section A-A for cap thickness of 4D.
54
Distance from cap face, D
(D)
7
------- Case 5
--- Case 4
-·-·-·- Case 3
Case 2
6
11
0=14.9
(lbs/In)
Compression
fx (Section B-B)
Figure 42. Normal force distribution at Section B-B for cap thickness of 4D.
55
Distance from cop face,O
(0)
7
------- Case 5
- - - - Case 4
-·-·-·-· Case 3 6
Case 2
11
D: 14.9
O'--~"'-~....._-a.:__...~~...___.
1000 2000 3000 4000 5000 (lbs/in)
Positive
fy (Section B-8)
Figure 43. Shear force distribution at Section B-B for cap thickness of 4D.
56
4
Q)
(.)
ti. 3
Q.
0
u
E
0
~
u..
Q) 2
(.)
-cs
c:
0
en
Cose 5
-- ---- ----
.,;4"'
28 24
----- 20 16 12 8 4 0 -4
4
Lateral Displacements, I0- in.
Figure 44. Lateral displacement curves for centerline of HJ> !4Xl 17 pile for effective widths -ofconaete cap of
14.9 in. and 44.7 in.
4
0
Q)
(.)
if
Q. 3
0
u
E
0
~
u..
Q)
(.)
2
c:
-
0
en
0
Cose 6
----- ---
----------~Cose
28 24
------ 20 ~ ~
2
8 4 0 -4
4
Lateral Displacements, 10- in.
Figure 45. Lateral displacement curves for centerline of HP 14Xl 17 pile for pile spacings of 3D to SD.
57
Distance from cap face 1 D
(O)
7
I
I
I
I
I
I
I
------- Case 9
- - - Case 8
-·-·-·- Case 7
Case 6
11
D= 14.9
fx (Section A-A)
Figure 46. Normal force distribution at Section A-A for cap thicknesses of 4D to 7D.
58
Distance from cap face, 0
(D)
7
------- Case 9
I
I
---- Case 8
/1 1' 6
-·-·-·- Case 7 / I
I
Case 6 / I
/ I
I
,,,,
11
0 = 14.9 I I
I
I 5
I.
I L
I I/
I
\
\
,,,.,,
I .
I·
'' "
\
Negative
fy (Section A-A)
Figure 47. Shear force distribution at Section A-A for cap thicknesses of 4D to 7D.
59
Distance from cap face, D
(0)
Compression
fx (Section B-B)
Figure 48. Normal force distribution at Section B-B for cap thicknesses of 4D to 7D.
60
Distance from cap face, 0
(0)
7
------- Case 9
---- Case 8
---·-·- Case 7
Case 6 6
11
D = 14.9
O'--~.L---11~~..i....~-1...~...1
1000 2000 3000 4000 5000 (lbs/in.)
Positive
fy (Section 8-8)
Figure 49. Shear force distribution at Section B-B for cap thicknesses of 4D to 70.
61
CERL DISTRIBUTION
C:hl•f of £n9tn•er1
HSC
ATIN1 Tech Monitor
ATTN1 HSLO-f 18234
ATIN1 DAEN-ASl-L C 2)
ATTN1 fac1l ltles Engineer
ATIN1 DAEN-CCP Fitzsimons AMC 80240
ATIN1 DAEN-CW
Walter Reed A~IC 20012
ATIN1 OAEN-CWE
ATlN1 OAEN-CWM-R
!NSCOM - Ch, lnstl. D1v.
ATIN1 DAEN-CWO ATIN1 Fac11 ltles Eng1neer (3)
ATIN1 OAEN-CWP
ATIN1 OAEN-EC
MOW
ATIN1 OAEN-ECC
ATIN1 DEH 13)
ATIN1 OAEN-ECE
ATIN1 OAEN-ZCF
MTMC
ATIN1 OAEN-ECB
ATIN: MTMC-SA 20315
ATIN1 DAEN-RO
ATIN: Fac111tles Eng1neer (3)
ATIN1 DAEN-ROC
ATIN1 OAEN-RDM
NARADCOM, ATIN1 ORDNA-F 07l160
ATIN1 DAEN-RM
ATIN1 OAEN-ZCZ
TARCOM, Fae. D1v. 48090
ATIN: OAEN-ZCE
ATIN1 DAEN-ZCI
TRADOC
ATIN1 DAEN-ZCM
HQ, TRAOOC, ATTN: ATEN-DEH
ATTN: DEH (19!
FESA, ATIN1 Library 22060
ATIN1 OET III 79906
TSARCOM, ATTN: STSAS-F 63120
US Army Engineer Districts
ATIN1 Library (41)
USACC
US Army Engineer Divisions ATTN: Fac11 lt1es Engineer (2)
ATIN1 L lbrary <14)
WESTCOM
US Army Europe ATIN1 DEH
AEAEN-ODCS/Engr 09403 Fort Shafter 96858
!SAE 09081 ATTN: APEN-IM
V Corps
ATTN1 OEH ( lll SHAPE 09055
VII Corps ATTN: Survlvab11 lty Sact1on, CCB-OPS
ATIN1 DEH (15) Infrastructure Branch, LANDA
21st Support Command
ATIN: OEH (12) HQ USEUCOM 09128
USA Berl In ATIN1 ECJ 417-LOE
ATTN: DEH (15)
USASETAF
U.S. Army, Fort Belvoir 22060
ATIN: DEH (6)
ATTN: Canadian Liaison Officer
Allied Command Europe (ACE)
ATTN: Water Resources Support Center
ATIN1 DEH 13) -AT-TN: -E;ngr St-ud-i-e--5 -C-en-t-e-r
ATTN: Engr Topographic Lab
8th USA, Korea (14)
ATTN: ATZA-DTE-SU
ATlN: ATZA-DTE-EM
ROK/US Combined Forces Command 96301
ATIN: EUSA-HHC-CFC/Engr ATT~: R & D Co111!1and
JOO
I /9/84
EME Team Dfstrfbution
Chief of Engineers
ATTN: DAEN-ECZ-A
US Army Engineer District Los Angeles 90053
New York 10007 ATTN: Chief, SPLE0-0
ATTN: Chief, Design Or. San Francisco 94105
Pittsburgh 15222 ATTN: Chief, Engr Div
ATTN: Chief, Engr Dfv Sacramento 95814
Philadelphia 19106 ATTN: Chief, SPKED-D
ATTN: Chief, NAPEN-D Far East 96301
Baltimore 21203 ATTN: Chief, Engr Div
ATTN: Chief, Engr Div Portland 97208
Norfolk 23510 ATTN: Chief, OB-6
ATTN: Chief, NAOEN-M ATTN: Chief, OB-3
ATTN: Chief, NAOEN-D Seattle 98124
Huntington 25721 ATTN: Chief, NPSCO
ATTN: Chief, ORHED-D ATTN: Chief, EN-OB-EM
Wilmington 28401 ATTN: Chief, EN-DB-ST
ATTN: Chief, SAWEN-DS ATTN: Chief, NPSEN-PL-WC
ATTN: Chief, SAWEN-D Walla Walla 99362
Charleston 29402 ATTN: Chfef, Engr Div
ATTN: Chief, Engr Div Alaska 99501
Savannah Jl40? ATTN: Chief, NPASA-R
ATTN: Chief, SASAS-L I
Jacksonville 32232
ATTN: Const Div US Army Engineer Division
ATTN: Design Br., Structures Sec. New England 02154
Mobile 36128 ATTN: Chief, NEDED-T
ATTN: Chief, SAMEN-D Middle East (Rear) 22601
ATTN: Chief, SAMEN-C ATTN: Chief, MEDED-T
Nashville 37202 North Atlantic 10007
ATTN: Chief, ORNED-D ATTN: Chief, NADEN-T
Memphis 38103 South Atlantic 30303
ATTN: Chief, LMMED-DT ATTN: Chief, SADEN-TS
ATTN: Chief, LMMED-DM ATTN: Chief, SADEN-TE/TM
Vicksburg 39180 Huntsville 35807
ATTN: Chief, EngrDiv ATTN: Chief, HNDED-CS
lo~ts~ille 4D20L ATTN: Chief,HNDE!),.ME
ATTN: Chief, Engr Div ATTN: Chief, HNDED-SR
Detroit 48231 Ohio River 45201
ATTN: Chief, NCEED-T ATTN: Chief, Engr Div
St. Paul 55101 North Central 60605
ATTN: Chief, ED-D ATTN: Chief, Engr Div
Chicago 60604 Missouri River 68101
ATTN: Chief, NCCED-DS ATTN: Chief, MRDEO-T
Rock Island 61201 Southwestern 75202
ATTN: Chief, Engr Div ATTN: Chief, SWDED-TS
ATTN: Chief, NCRED-D ATTN: Chief, SWOEO-TM
St. Louis 63101 South Pacific 94111
ATTN: Chief, ED-D ATTN: Chief, SPDEO-TG
Kansas City 64106 Pacific Ocean 96858
ATTN: Chief, Engr Div ATTN: Chief, Engr Div
Omaha 68102 ATTN: Chief, FM&S Branch
ATTN: Chief, Engr Div ATTN: Chief, PODE0-0
New Orleans 70160 North Pacific 97208
ATTN: Chief, LMNED-DG ATTN: Chief, Engr Div
Little Rock 72203
ATTN: Chief, Engr Div
Tulsa 74102 Ft. Clayton Canal Zone 34004
ATTN: Chief, Engr Div ATTN: OFAE
Fort Worth 76102
ATTN: Chief, SWFED-D Dept. of Transportation Library 20590
Galveston 77550
ATTN: Chief, SWGAS-L Transportation Research Board 20418
ATTN: Chief, SWGED-DS
ATTN: Chief, SWGED-DM
Albuquerque 87103
ATTN: Chief, Engr Div
Castilla, Fernando
Fixity of members embedded in concrete I by Fernando Castilla, Phillippe
Martin, John Link. - Champaign, IL : Construction Engineering Research Lab-
oratory ; available from NTIS, 1984.
61 p. (Technical report I Construction Engineering Research Laboratory ;
M-JJ9).