MEGGER TEST REPORT

PROJECT NUMBER DATE (M/D/YYYY)

PROJECT STATION MCMURDO PALMER SOUTH POLE

CIRCUIT VOLTS/ PHASE “A” PHASE “A” PHASE “B” PHASE “A” PHASE “B” PHASE “C” PHASE “A” PHASE “B” PHASE “C”
FEEDER PANEL NUMBER/FEEDER PHASE/ TO TO TO TO TO TO TO GROUND TO GROUND TO GROUND
IDENTIFICATION NUMBER CYCLES PHASE “B” PHASE “C” PHASE “C” NEUTRAL NEUTRAL NEUTRAL CONDUCTOR CONDUCTOR CONDUCTOR

RPSC FIELD ENGINEER


PROJECT ENGINEER/DESIGNEE: DATE

RPSC ELECTRICAL FOREMAN: DATE

NSF REP/TITLE II INSPECTOR: DATE

EN-MPS-725e FEMC / RPSC Paget 1 of 1 Revision 1 11/16//06 Approved by Wayne L. Cornell