Owner CM Contractor PREPARED CHECKED APPROVED

DAILY REPORT HSE

Project Name : SELATOX GMP MANUFACTORY


Weather : Sunny Temp. 24°C~31°C
Date : October 22, 2023
No. Description
1 ■ Zero Incident Time
Normal Working Hours 07.00 - 18.00 (10 Hours)
Overtime Working Hours 19.00 - 22.00 (3 Hours) 171
Extra Working Hours 22.00 - until finish (Conditional Hours)

Man Power Working Hours Total Accumulative


Indirect 26 8 208 Previous Today Total
Direct 133 8 1064 143,733 1,272 145,005
Overtime 0 0
Extratime 0 0

2 ■ Activity
1 Progress Tool Box Meeting
- Participant all Staff, Supervisor and Foreman
- Progress to work and continue to work in area nabota, utiliy and animal building
2 Daily inspection heavy equipment
- Excavator, Vibro, Generator, Dumptruck etc.
3 House Keeping all area
4 Monitoring all work activity
5 Carpenter worker safety education additional
6 Monitoring CCTV

PHOTOGRAPH (PROJECT SITE ACTIVITY)

Project : Selatox Bio Pharma Project : Selatox Bio Pharma


Location : CG Bio Area Location : CG Bio Area
Description : Progress Tool Box Meeting Description : Daily Inspection heavy equipment Excavator
Date : 22 October 2023 Date : 22 October 2023

Project : Selatox Bio Pharma Project : Selatox Bio Pharma


Location : All Area Office Location : Nabota Area
Description : Housekeeping Description : Monitoring all work activity
Date : 22 October 2023 Date : 22 October 2023

Project : Selatox Bio Pharma Project : Selatox Bio Pharma


Location : Utility Area Location : Meeting room
Description : Monitoring all work activity Description : Carpenter worker safety education additional
Date : 22 October 2023 Date : 22 October 2023

Project : Selatox Bio Pharma


Location : All Area Office
Description : Monitoring CCTV
Date : 22 October 2023
Project : Selatox Bio Pharma
Location : All Area Office
Description : Monitoring CCTV
Date : 22 October 2023