You are on page 1of 13

Journal of Rock Mechanics and Geotechnical Engineering 7 (2015) 1e13

Contents lists available at ScienceDirect

Journal of Rock Mechanics and


Geotechnical Engineering
journal homepage: www.rockgeotech.org

Review

Rock engineering design of post-tensioned anchors for


dams e A review
E.T. Brown*
Golder Associates Pty Ltd., PO Box 1734, Milton, Queensland 4064, Australia

a r t i c l e i n f o a b s t r a c t

Article history: High-capacity, post-tensioned anchors have found wide-spread use, originally in initial dam design and
Received 15 August 2014 construction, and more recently in the strengthening and rehabilitation of concrete dams to meet
Accepted 18 August 2014 modern design and safety standards. Despite the advances that have been made in rock mechanics and
Available online 18 September 2014
rock engineering during the last 80 years in which post-tensioned anchors have been used in dam en-
gineering, some aspects of the rock engineering design of high-capacity rock anchors for dams have
Keywords:
changed relatively little over the last 30 or 40 years. This applies, in particular, to the calculations usually
Dam engineering
carried out to establish the grouted embedment lengths required for deep, post-tensioned anchors.
Post-tensioned anchors
Rock engineering design
These calculations usually make simplified assumptions about the distribution and values of rockegrout
Groutetendon bond interface shear strengths, the shape of the volume of rock likely to be involved in uplift failure under the
Rockegrout bond influence of a system of post-tensioned anchors, and the mechanism of that failure. The resulting designs
Rock mass uplift failure are generally conservative. It is concluded that these aspects of the rock engineering design of large, post-
tensioned rock anchors for dams can be significantly improved by making greater use of modern,
comprehensive, numerical analyses in conjunction with three-dimensional (3D) models of the rock mass
structure, realistic rock and rock mass properties, and the results of prototype anchor tests in the rock
mass concerned.
Ó 2015 Institute of Rock and Soil Mechanics, Chinese Academy of Sciences. Production and hosting by
Elsevier B.V. All rights reserved.

1. Introduction orientation with respect to vertical, in size (including in both length


and diameter), in the nature and size of the tendon (bar, wire or
Ground or rock anchors (sometimes referred to as anchorages) of strand, either singly or in groups) providing the essential tensile
a number of types have long been used for a range of purposes in capacity, and in the ultimate load-carrying capacity of the anchor.
rock engineering and in geotechnical engineering more generally In this paper, emphasis will be placed on large-scale, high-capacity,
(Hobst and Zajíc, 1977; Hanna, 1982; Habib, 1989; Xanthakos, 1991; permanent rock anchors of the type illustrated schematically in
Littlejohn, 1993, 1997). Rock anchors are capable of transmitting an Fig. 1. Features of this class of rock anchor include the provision of a
applied tensile load to the rock mass and may be used, for example, fixed anchor or tendon bond length, a free tendon length, a
to reinforce rock slopes and underground excavations; stabilise stressable (and preferably re-stressable) anchor head, and double
sheet pile, diaphragm and retaining walls; anchor building, bridge, corrosion protection. Obviously, in terms of their scale, purposes,
power transmission line and other tower or mast structure foun- rock engineering design and detailed design and installation, these
dations; anchor marine structures; stabilise large excavations such large rock anchors can differ significantly from the rock bolts, cable
as dry or graving docks potentially subject to uplift; and for a bolts and rock socketed piles used widely in surface and under-
number of purposes in dam engineering to be discussed in Section 2. ground construction and mining. However, these elements all have
Depending on their purpose, rock anchors may be temporary or some features in common that allow data, understandings and el-
permanent, and may be passive or post-tensioned (sometimes ements of design approaches to be transferred from one application
referred to as pre-stressed). They may also vary greatly in to another.
The purpose of this paper is to review international practice in
the rock mechanics and rock engineering design of rock anchors
* Tel.: þ61 7 3721 5451. which, as will be shown, has remained largely unchanged since the
E-mail addresses: tbrown@golder.com.au, et_brown@bigpond.com. 1970s. The paper will deal mainly, but not exclusively, with the
Peer review under responsibility of Institute of Rock and Soil Mechanics, design of large anchors of the type shown in Fig. 1 and with their
Chinese Academy of Sciences.
application in dam engineering, particularly for concrete gravity,
1674-7755 Ó 2015 Institute of Rock and Soil Mechanics, Chinese Academy of Sci-
ences. Production and hosting by Elsevier B.V. All rights reserved. buttress and arch dams. Some emphasis will be placed on Austra-
http://dx.doi.org/10.1016/j.jrmge.2014.08.001 lian practice which is the source of the author’s practical experience
2 E.T. Brown / Journal of Rock Mechanics and Geotechnical Engineering 7 (2015) 1e13

dams using post-tensioned anchors. They listed the main reasons


Stressing jack for strengthening existing dams as being to:
Anchor head
Bearing plate
 meet changes in safety standards;
 overcome deficiencies in design and construction;
Tendon  recover loss of strength due to deterioration; and
 raise the heights of dams.
Drilled hole
Free length unbonded
Stressing length

Cement grout In many countries, the former dam safety standards and design
length criteria based on historical flood levels have been replaced by
criteria based on probable maximum flood (PMF) or probable
maximum precipitation design flood (PMP DF) water flows and
levels. The predicted design flood levels based on annual exceed-
Free

Smooth p.c.
sheath ance probabilities (AEPs) can be higher than the historical levels
used in the original designs, so that the design spillway capacities of
many existing dams are inadequate to pass the new design floods
safely. Furthermore, the dams may potentially fail by overturning
and/or sliding. This is particularly the case for dams designed
length
Bond

before about 1946 (in Australia, and at other times elsewhere)


length
Bond

Corrugated when uplift forces acting on the base of the dam were not allowed
p.c. sheath for adequately in design calculations (ANCOLD, 1992; Cavill, 1997;
Kline et al., 2007; Duffaut, 2013). As a result, many existing dams
Over
drill

have been in need of upgrading, including raising, to meet the new


Fig. 1. Components of a typical large, permanent, post-tensioned dam rock anchor design flood and related stability criteria. Another change in safety
(Cavill, 1997). standards has been the application of maximum credible or design
earthquake (MCE or MDE) criteria (Xu and Benmokrane, 1996;
in this area. It is recognised that some of the terminology used may Bruce, 1997). Detailed discussion of these issues is beyond the
differ from country to country. scope of this paper. However, it is important to note that safety
standards and terminologies may differ between countries and
2. Post-tensioned anchors in dam engineering jurisdictions. For example, in the author’s home State of Queens-
land, Australia, the acceptable flood capacity (AFC) for a High A
Post-tensioned, and in some cases, passive (Hobst and Zajíc, Hazard Category dam is the PMP DF (DEWS, 2013).
1977; Bretas et al., 2010) rock anchors have been used for a range Xu and Benmokrane (1996) collected and analysed data on 60
of applications in dam engineering over the last 80 years (Bruce, concrete dams that had been strengthened using post-tensioned
1988). These applications include providing: anchors, mainly in the USA, Canada, Australia and Europe. They
found that most dams had been strengthened for one or more of
 resistance to overturning (Banks, 1957; Khaoua et al., 1969); the following purposes:
 restraint against downstream sliding (Maddox et al., 1967;
Gosschalk and Taylor, 1970);  increasing spillway capacity and stability relating to the PMF;
 reinforcement of excavated abutment and other slopes (Liang,  upgrading to the MCE;
1995; She, 2004);  upgrading dam stability relating to other conditions such as
 stabilisation of thrust blocks (Dickson and Loar, 2011); ageing and deterioration;
 additional seismic resistance (Singhal and Nuss, 1991; Bianchi  raising dam height related to the PMF;
and Bruce, 1993; Lawrence and Martin, 2007);  raising dam height for greater storage;
 tying down of spillway, training wall and stilling basin struc-  remedying deficiencies in design (e.g. not allowing adequately
tures (Hobst and Zajíc, 1977; Cavill, 1997; Topham et al., 2013); for uplift);
 stabilisation of plunge pools and other erosion features (Lowe  stabilising concrete cracks;
et al., 1979; La Villa and Golser, 1982); and  strengthening dam abutments;
 raising and/or strengthening older dams that no longer meet  stabilising dam foundations; and
safety or capacity requirements (ANCOLD, 1992; Xu and  reinforcing lock walls or building locks into cofferdams.
Benmokrane, 1996; Cavill, 1997; Snape, 2002).
Fig. 2 illustrates schematically the classical uses of post-
The first recognised use of post-tensioned anchors in dam en- tensioned rock anchors in stabilising concrete gravity dams
gineering was for the raising and strengthening of the 30 m high against (a) overturning, and (b) downstream sliding. Fig. 2a shows
Cherfas gravity dam in Algeria in 1936 (Hobst and Zajíc, 1977; the main forces used in calculating the anchor tension, T, required
Khaoua et al., 1969). For some time following their introduction to maintain moment equilibrium about the downstream toe of the
into dam engineering, post-tensioned anchors were used in the dam. Fig. 2b shows the forces involved in a limiting equilibrium
initial design and construction of concrete dams and their appur- analysis of one of the several possible forms of downstream sliding
tenant structures (e.g. Banks, 1957; Wilkins and Fidler, 1959; (USACE, 1995; Fell et al., 2005). It must be recognised that, in
Maddox et al., 1967; Gosschalk and Taylor, 1970; Hobst and Zajíc, practice, concrete dams located in valleys with sloped rock foun-
1977). More recently, the major use of post-tensioned anchors in dation abutments will behave as three-dimensional (3D) structures
dam engineering has been for the raising or strengthening of and so will require 3D stability analyses (Lombardi, 2007; Bretas
existing dams. et al., 2012). Clearly, different analytical models from those
Xu and Benmokrane (1996) carried out a major review of the shown in Fig. 2 would have to be used for the design of post-
then state-of-the-art of the strengthening of existing concrete tensioned anchors for stabilising other components of the overall
E.T. Brown / Journal of Rock Mechanics and Geotechnical Engineering 7 (2015) 1e13 3

Anchor
tension, T

Upstream water Upstream water


pressure force, H pressure force, H
Dam Anchor
tension, T
Dam Downstream water weight, W Downstream water
weight, W pressure force, H pressure force, H

Drained uplift Uplift pressure


pressure force, V force, U
Drained uplift
pressure force, U
Bond length Bond
length

(a) (b)

Fig. 2. Schematic illustration of the use of post-tensioned anchors to resist (a) overturning, and (b) downstream sliding (after ANCOLD (1992) and USACE (1995)).

dam structure such as thrust blocks for arch dams, and spillway, safety required by the Standards, Codes of Practice or Guidelines
training wall and stilling basin structures. under which the design is being carried out (ANCOLD, 1991, 1992,
Since the time of the review by Xu and Benmokrane (1996), the 2013; BC Hydro, 1995; USACE, 1995, 2005; CDSA, 1999). It is
numbers of concrete dams being strengthened or raised around the important to note that different load factors or factors of safety may
world have increased significantly, although the main reasons for be required by different authorities for similar load cases. Infor-
doing so have remained essentially the same. In a 2007 review of mative comparisons between a number of these approaches are
rock anchoring of North American dams over the previous 40 years, given by Ebeling et al. (2000) and Fell et al. (2005).
Bruce and Wolfhope (2007, 2008) identified 400 relevant cases and More recently, linear and nonlinear numerical stress analysis
accessed 230 technical publications dealing with more than 200 approaches have been used to calculate forces, stresses and dis-
dams. By this time, the sizes of the high-capacity anchors being placements in the concrete of the dam, the foundation and abut-
used in dam engineering had increased considerably with tendons ment rock, and at interfaces, and when assessing the dynamic
being made up of several tens of 15.2 mm diameter strands, each of stability of dams under earthquake loading (Alonso et al., 1996; Yu
which generally consists of seven twisted, low relaxation, high et al., 2005; Bureau et al., 2007; Scott and Mills-Bria, 2008; Lemos,
tensile steel wires. A frequently used high-capacity tendon 2011, 2014; Chopra, 2012). Some Standards, Codes of Practice and
configuration consists of 91 (or 92) 15.2 mm diameter strands Guidelines now require the use of limit state approaches or of
providing an ultimate axial tensile force capacity of 24 MN partial, rather than overall, factors of safety (Merrifield et al., 1997;
(Aschenbroich, 2007; Cavill, 2000; Harman et al., 2010). Even larger Herweynen, 1998; ANCOLD, 2013; Farrell, 2013). However, it has
anchors than this have been used in some cases. been recognised recently that the partial factor, limit state design
approach used in Eurocode 7 (CEN, 2004), for example, may not be
3. Overview of post-tensioned anchor design applicable to a range of rock engineering problems in which some
of the uncertainty in parameter values is epistemic rather than fully
3.1. General principles aleatory as is assumed in the Eurocode approach (Bedi and Orr,
2014; Harrison, 2014; Lamas et al., 2014). Increasingly, reliability,
This sub-section will discuss the basic mechanics and general risk-based, probabilistic and fragility methods of dam analysis and
principles on which post-tensioned rock anchor design is based. assessment are being used in rock anchor design for dams and
The rock mechanics and rock engineering aspects of anchor design other applications (Ellingwood and Tekie, 2001; Phoon et al., 2003;
will be considered in more detail in Sections 4 and 5. Although Barker, 2011; Westberg Wilde and Johansson, 2013). Further dis-
strictly they lie somewhat outside the rock mechanics and rock cussion of these approaches is outside the purpose and scope of this
engineering emphasis of this paper, for completeness and because paper.
they impact on the effectiveness of the rock engineering design, a
number of important investigation, design and construction issues, 3.2. Principal modes of failure of grouted, post-tensioned anchors
including anchor stressing and testing, will be referred to briefly in
Section 6. As well as providing the resistance or stabilising forces required
Traditionally, the dimensioning of rock anchor systems for dams for the purposes referred to at the beginning of Section 2, grouted
has been based on two-dimensional (2D) static limiting equilib- post-tensioned anchors themselves must be able to resist the four
rium analyses of problem configurations such as those illustrated principal modes of applied tension-induced failure illustrated in
schematically in Fig. 2. From these analyses, the anchor forces Fig. 3:
required to maintain stability per metre run, or at a particular
location, can be established for particular load cases (often called  Mode A e steel tendon tensile failure.
normal or usual, unusual and extreme) and the associated factors of  Mode B e groutetendon bond or interface failure.
4 E.T. Brown / Journal of Rock Mechanics and Geotechnical Engineering 7 (2015) 1e13

3.3. Design against tendon tensile failure (Mode A)

In Mode A failure, the applied axial tensile stress exceeds the


Bars break yield and, ultimately, the ultimate tensile strength of the steel in the
tendon. If At is the cross-sectional area of steel in the tendon and stu
is the ultimate tensile strength of the steel, then the ultimate tensile
Bars pull capacity is given by
out of grout

Qtu ¼ stu At (2)


This value is sometimes referred to as the minimum breaking
load (MBL) (ANCOLD, 1992). In practice, it is usual to define the
(a) Steel. (b) Steel-grout interface.
design working load (WL) as a proportion of the MBL, often taken as
60%e65% in Australia. During installation of the anchor, it is com-
mon practice to test load the anchor and fittings beyond the normal
WL (for example, up to 78%e80% MBL) and to “lock-off” the load
with sufficient allowance above the WL (for example, to 68%e72%
MBL) to allow for subsequent load losses caused by creep, relaxa-
tion and draw-in (ANCOLD, 1992). This is one of the areas in which
different terminologies may be used in different countries and by
Failure
surface different authorities.
Slip surface
For the large, high-capacity, post-tensioned anchors now being
used for concrete dams, it is unusual for Mode A failure to be a
controlling feature of the design. However, as will be discussed
briefly in Section 6, several other factors which are beyond the
(c) Grout-rock interface. (d) Rock mass uplift. scope of this paper have to be taken into account in the detailed
design, fabrication, installation, stressing and monitoring of the
Fig. 3. Principal modes of failure of grouted rock anchors under applied axial tension.
(a) Mode A e steel tendon tensile failure; (b) Mode B e groutetendon bond or anchors.
interface failure; (c) Mode C e rockegrout bond or interface failure; and (d) Mode D e
rock mass uplift failure (Pease and Kulhawy, 1984).
3.4. Design against groutetendon bond or interface failure
 Mode C e rockegrout bond or interface failure. (Mode B)
 Mode D e shear or uplift failure within the surrounding rock
mass. The shear resistance developed at the groutetendon interface
arises from adhesion, friction and mechanical interlock between
Following Kim and Cho (2012), if the ultimate tensile load ca- the grout and the tendon. On the initial application of the axial
pacities of an anchor for failure Modes A, B, C and D are Qtu, Qtgu, tensile load to the anchor, shear failure at the groutetendon
Qrgu and Qru, respectively, then the ultimate tensile capacity of the interface is resisted by adhesion and interlocking. Then as
anchor, Qu, will be the minimum of these four values, i.e. displacement increases, these components of shear resistance may
  be overcome at points along the bond length and friction then
Qu ¼ minQtu ; Qtgu ; Qrgu ; Qru  (1) makes the major contribution to shear resistance (Kim and Cho,
2012). Because of the difficulty of distinguishing between and
In addition to these four major modes of failure under applied evaluating these components of shear resistance, it is common
tension, for large-scale post-tensioned rock anchors of the type practice to calculate the groutetendon shear resistance as
illustrated in Fig. 1, it is necessary to consider the possibility of shear
failure at the internal and external interfaces between the grout Zlbtg
and the corrugated sheathing providing a layer of corrosion pro- Qtgu ¼ 2prt stgu ðzÞdz (3)
tection. In the usual case, the depth of the corrugations in the 0
sheathing provides an adequate degree of interlock.
In design practice, it is a common procedure to carry out design where rt is the radius of the steel tendon, lbtg is the length of the
calculations to select the length of anchor embedment required to groutetendon bond, and stgu(z) is the shear resistance generated at
produce pre-determined factors of safety against failure Modes B, C distance z along the groutetendon interface where 0  z  lbtg.
and D. The design length of embedment is then selected as the It is often assumed that the mobilised shear resistance, stgu, is
largest of these values (USACE, 2005). In most practical cases it is constant over the groutetendon interface length, lbtg, greatly
found that Mode C is more critical than Mode B. simplifying the calculation of Qtgu. It is often further assumed that
The essential purpose of the remainder of this paper will be to the constant value of stgu depends on the composition and surface
review the rock mechanics and rock engineering aspects of design properties of the tendon and the compressive or shear strength of
against failure Modes C and D. However, for completeness, sum- the grout. Littlejohn and Bruce (1977) and Littlejohn (1993), among
mary discussions of design against failure Modes A and B will be others, provided presumptive values of stgu for a range of condi-
given. In the discussions of failure Modes A, B, C and D to follow, a tions. Most Codes of Practice or Standards stipulate maximum
single post-tensioned anchor will be generally considered. It must allowable values of bond stress for different types of tendon and
be recognised, however, that in dam engineering practice, anchors grout, generally in the range 1.0e3.0 MPa. In practice, if the tendon
are usually used in relatively closely-spaced rows and sometimes in WL is pre-determined, the groutetendon bond length required to
multiple rows. The interactions between adjacent anchors, partic- generate a particular factor of safety for a given bond strength can
ularly in the Mode D case, must be taken into account in design be calculated readily from a simplified version of Eq. (3). It is
calculations. sometimes assumed that consideration of groutetendon bond
E.T. Brown / Journal of Rock Mechanics and Geotechnical Engineering 7 (2015) 1e13 5

failure is not necessary because consideration of the rockegrout discontinuity crosses the tensioned tendon or bolt (Zou, 2004; Zhao
bond failure (Mode C) alone will produce a more than adequate and Yang, 2011). A number of authors have shown how the non-
tendon embedment length (Littlejohn and Bruce, 1977). uniform distribution of shear stress along the anchor length,
A number of detailed investigations have demonstrated that the including the effects of de-bonding, may be modelled by piece-wise
simplifying assumptions made using the approach outlined in the linear shear stress distributions (Jarred and Haberfield, 1997;
preceding paragraphs are rarely justified. For example, several au- Woods and Barkhordari, 1997; Ivanovic and Neilson, 2009; Ren
thors have shown that the groutetendon interface shear strength et al., 2010).
depends on the normal confining pressure and stiffness, the
roughness of the tendon, whether or not the cement in the grout is 4. Design against rockegrout interface failure (Mode C)
expansive, and the grouted bond length (Benmokrane et al., 1995;
Barley, 1997; Jarred and Haberfield, 1997). 4.1. The standard approach
The recorded influence of the grouted bond length probably
reflects the now widely accepted finding that the distribution of In an analogous manner to the groutetendon interface, the
shear stress along the grouted length is far from uniform, tending to shear resistance at the rockegrout interface is developed by
decay exponentially from the free-length value at the end of the adhesion, friction and mechanical interlock with friction playing
grouted length or proximal end, towards zero at the bottom of the the major role after the other components have been overcome
grouted length or distal end (see Fig. 4), depending on the as- through initial relative axial displacement. As with the groute
sumptions made in the analysis (Coates and Yu, 1970; Farmer, 1975; tendon interface, the ultimate rockegrout axial shear resistance is
Benmokrane et al., 1995; Ivanovic and Neilson, 2009; Liu et al., commonly evaluated as
2013). The ratio of the elastic modulus of the steel tendon, Ea, to
that of the grout, Eg (if there is a thick annulus of grout), or alter- Zlbrg
natively of the rock, has been found to have a particularly important Qrgu ¼ 2prg srgu ðzÞdz (4)
influence on the distribution of elastic shear stress along the 0
embedment length. As shown in Fig. 4 for the case of a fully
embedded, shallow anchor, for low modulus ratios of between 0.1 where rg is the outside radius of the grouted annulus around the
and 1.0 for stiffer grouts and rocks, the stress distribution is tendon, lbrg is the length of the rockegrout bond, and srgu(z) is the
markedly non-uniform, but as this ratio increases in softer grouts shear resistance generated at distance z along the rockegrout
and rocks, the stress distribution becomes more closely uniform interface.
(Coates and Yu, 1970; Liu et al., 2013). Again, in common with design against groutebond tendon
In practice, the possibility must be considered that de-bonding failure, it is generally assumed that the shear resistance is distrib-
will occur at the more highly stressed proximal end of the uted uniformly over the rockegrout bond length, lbrg, so that the
bonded length (the top in Fig. 3b), most probably during pre- ultimate shear resistance may be calculated as
stressing (Benmokrane et al., 1995), resulting in a modification to
the elastic stress distribution as illustrated schematically in Fig. 4 Qrgu ¼ 2prg lbrg srgu (5)
for the Ea/Eg ¼ 0.1 case. Distributions of shear stress of the types
illustrated in Fig. 4 have been obtained analytically and numeri- where a constant value of srgu is assumed. Many Standards and
cally, and measured in a range of instrumented laboratory and field Codes of Practice indicate that it is required, or at least preferable,
tests on rock bolts, cable bolts and rock anchors (Kaiser et al., 1992; that the value of srgu used in design be based on the results of pull-
Benmokrane et al., 1995; Hyett et al., 1995; Woods and Barkhordari, out tests of trial anchors installed at the site (see Section 6 below).
1997; Ivanovic and Neilson, 2009). The stress distribution has also However, it is still often selected on the basis of the rock type and
been found to vary with imperfect bonding and when a condition using tables of presumptive values generally derived
from those first published by Littlejohn and Bruce (1975e76, 1977).
Table 1 is a condensed version of the table given by Littlejohn (1992,
De-bonding 1993) in which the sources of Littlejohn’s entries have been
τ/ρ
0 0.1 0.2 0.3 0.4 0.5 omitted. As shown in Table 1, working bond values are lower than
0
ultimate values. Commonly, the working rockegrout shear strength
is assumed to be approximately 10% of the uniaxial compressive
E /E=0.1 strength (UCS) of the rock up to a maximum of 4.2 MPa. In some
1
E /E =1.0 cases, the value is based on the grout compressive strength. Barley
(1988) also estimated rockegrout bond strengths from the instal-
2 lation and testing of 10,000 anchors in a wide range of rock con-
ditions in the United Kingdom.
E /E =10.0 This standard approach which has been used in several coun-
z/r

3
tries for several decades suffers from a number of deficiencies to be
ρ outlined in the following sub-section.
4
z 4.2. Deficiencies in the standard approach
τ
5 Deficiencies in the standard simplified approach to design
r
against rockegrout interface failure have been found to include:

6
 a uniform shear stress along the rockegrout interface is
assumed as discussed in Section 3.4 for the tendon-grout bond.
Fig. 4. Distribution of elastic shear stress along the grouteanchor interface (adapted As noted by Bruce (1997) in a review of the stabilisation of
from Coates and Yu (1970)). concrete dams by post-tensioned anchors in the U.S.A., this
6 E.T. Brown / Journal of Rock Mechanics and Geotechnical Engineering 7 (2015) 1e13

Table 1  as with the groutetendon interface, no allowance is made for


Some rockegrout bond values recommended for use in design (after Littlejohn and the influence of the normal stress acting on the grouterock
Bruce (1975e76, 1977); Littlejohn (1992, 1993)).
interface before and during shearing, its variation over the
Rock type Working Ultimate Factor of safety embedment length (Barley, 1997), or the influence of grouting
bond (MPa) bond (MPa) methods and pressures on the normal stresses generated (Park
Igneous et al., 2013);
Medium hard basalt 5.73 3e4  no recognition is taken of the progressive nature of the rocke
Weathered granite 1.5e2.5
grout bond failure process in which at least three distinct stages
Basalt 1.21e1.38 3.86 2.8e3.2
Granite 1.38e1.55 4.83 3.1e3.5 may be identified e pseudo-elastic behaviour at small de-
Serpentine 0.45e0.59 1.55 2.6e3.5 formations, failure or de-bonding development at the rocke
Granite and basalt 1.72e3.1 1.5e2.5 grout interface, and residual behaviour after larger displace-
Metamorphic ments (Pease and Kulhawy, 1984; Park et al., 2013);
Manhattan schist 0.7 2.8 4
Slate and hard shale 0.83e1.38 1.5e2.5
 no allowance is made for the effects of structural features such
Calcareous sediments as faults, shear zones and jointing in the rock mass or of other
Limestone 1 2.83 2.8 local variations in rock strength (Dados, 1984; Zou, 2004);
Chalk e Grades IeIII 0.005N 0.22e1.07 2 (Temporary)  the influence of the borehole roughness and diameter, and
(N ¼ SPT in
therefore the thickness of the grout annulus, are not considered;
blows/0.3 m)
0.01N 3e4 (Permanent) and
Tertiary limestone 0.83e0.97 2.76 2.9e3.3  the type of cement used in the grout can have a significant in-
Chalk limestone 0.86e1 2.76 2.8e3.2 fluence on the shear resistance generated (Haberfield and
Soft limestone 1.03e1.52 1.5e2.5 Baycan, 1997).
Dolomitic limestone 1.38e2.07 1.5e2.5
Arenaceous sediments
Hard coarse-grained 2.45 1.75 In dam engineering practice, the preferred way of overcoming
sandstone some of these deficiencies is by the use of a necessarily average
Weathered sandstone 0.69e0.85 3 interface shear strength value established through full-scale pull-
Well-cemented 0.69 2e2.5
out tests on trial anchors of the anticipated design, carried out in
mudstone
Bunter sandstone 0.4 3 the rock mass concerned before the design is finalised (Scott and
Bunter sandstone 0.6 2e2.5 Bruce, 1992; Feddersen, 1997; Cavill, 2000). In tests carried out
(UCS > 2.0 MPa) for this purpose, it is important that the test configuration is
Hard fine sandstone 0.69e0.83 2.24 2.7e3.3 selected to ensure that the failure occurs at the rockegrout
Sandstone 0.83e1.73 1.5e2.5
Argillaceous sediments
interface.
Keuper marl 0.17e0.25 3
(0.45cu)
Weak shale 0.35 5. Design against rock mass failure (Mode D)
Soft sandstone and 0.1e0.14 0.37 2.7e3.7
shale 5.1. The standard approach
Soft shale 0.21e0.83 1.5e2.5
General
Although it is generally found to be conservative, from a rock
Competent rock UCS e 30 UCS e 10 3
(where UCS > 20 MPa) (up to a (up to a mechanics or rock engineering perspective, the commonly-used or
maximum maximum standard approach to the design of post-tensioned anchors against
value of value of rock mass failure by uplift (Mode D), is probably the least satis-
1.4 MPa) 4.2 MPa)
factory of the design approaches discussed in this paper.
Weak rock 0.35e0.7
Medium rock 0.7e1.05 As illustrated in Fig. 5 for the case of a single anchor, the simplest
Strong rock 1.05e1.4 standard approach assumes that the uplift force generated by the
Wide variety of igneous 1.05 2 post-tensioned anchor is resisted by the weight of a cone of ho-
and metamorphic rocks mogeneous rock. It generally ignores the fact that for uplift to occur,
Wide variety or rocks 0.98
not only the weight of the rock cone, but also the shear and/or
0.5
0.7 tensile strength of the rock mass must be overcome. Depending on
1.2e2.5 the nature of the anchorage and the assumed properties of the rock
0.7 2e2.5 (Temporary) mass, the cone angle and the location of the apex of the cone may
3 (Permanent)
vary. Fig. 5 illustrates the commonly assumed cases in which the
0.69 2.76 4
1.4 4.2 3
cone angle is either 60 or 90 , and the apex of the cone is located at
15%e20% or 3 the mid-point or at the distal end of the grouted embedment
grout crushing length. Some designers may also locate the apex of the cone at the
strength
Concrete 1.38e2.76 1.5e2.5
D

approach using a uniform shear stress and “average” bond Ө ° °


L/2 L/2

values can lead to “extraordinarily and wastefully long bond


L

60° or 90°
zones”;
 the wide-spread use of decades old, empirically-based, pre- d

sumptive interface shear strengths based on rock type and Fig. 5. Cone geometries used in uplift capacity calculations for single tensioned an-
condition and, more rarely, grout compressive strength (see chors (after Littlejohn and Bruce (1975e76, 1977), Hobst and Zajíc (1977) and Littlejohn
Table 1); (1993)).
E.T. Brown / Journal of Rock Mechanics and Geotechnical Engineering 7 (2015) 1e13 7

proximal or upper end of the bonded length. A cone angle of 60 is rock defined by the one sub-horizontal plane is avoided (Xu and
usually used if the rock mass is soft, heavily fissured or weathered, Benmokrane, 1996). In the writer’s experience, this practice has
with an angle of 90 being used for all other rock mass conditions been used when the dam is founded on igneous rock in which
(Hobst and Zajíc, 1977; Littlejohn, 1993) which is generally the case sheeting jointing has developed in an incised river valley.
for concrete dam strengthening or stabilisation. For grouted an- Secondly, in the calculations of uplift resistance in a range of
chors of the type being considered here, the apex of the cone is applications, some authorities and authors seek to allow for the
usually taken to be at the mid-point of the grouted anchor length. tensile or shear strength of the rock mass, generally through the use
This assumption with a 90 cone angle has been used in dam en- of assumed values of rock mass tensile strength, shear strength or
gineering at least since the 1950s (Morris and Garrett, 1956; Banks, cohesion (Coates, 1970; Hobst and Zajíc, 1977; Anon, 1996; Kim and
1957). Cho, 2012). The estimated values of tensile or shear resistance may
For a general cone angle of qc (qc ¼ 60 or 90 in Fig. 5) and the be used either instead of, or in addition to, the resistance to uplift
apex of the cone located at the mid-point of the grouted embed- provided by the weight of the cone of rock. In presenting ap-
ment length, the uplift force required to overcome the weight of the proaches of this type, some authors use idealised 2D representa-
cone of rock, Wc, may be calculated as tions with a triangular section as shown in Fig. 6b rather than the
3D cone. For example, Hobst and Zajíc (1977) gave a number of
 
1 q L 3 solutions in terms of the rock mass shear strength. Following
Qru ¼ pg tan2 c D þ (6) Coates and Yu (1971), Kim and Cho (2012) suggested that the ten-
3 2 2
sile resistance on the failure surface of the rock cone in Fig. 5, fr, is
where g is the unit weight of the rock, D is the depth from the given by
surface to the top or proximal end of the embedment length, and L
is the grouted embedment or bond length. Although it is more str pD2c tan q2c
fr ¼ (8)
conservative to use the full unit weight of the rock in this calcula- cos q2c
tion, in some applications in dam engineering the buoyant or
submerged unit weight should be used. Commonly in design, the where str is the tensile strength of the rock mass and Dc is the depth
required bond length, L, is calculated by equating the rockegrout of the rock cone, equal to D þ L/2 in Fig. 5.
bond resistance given by Eq. (5) to the uplift force required to Of course, this approach begs the question of the exact physical
overcome the weight of the cone of rock given by Eq. (6) and meaning of the assumed parameter, str, and how it might best be
applying a factor of safety, often taken to be 2. estimated. In an alternative approach, Weerasinghe and Adams
In the author’s experience, this simple, conservative approach is (1997) proposed the use of a rock mass shear strength, rather
generally used in dam engineering in the dimensioning of large than a tensile strength, back-calculated from the results of pull-out
post-tensioned anchors against failure of the rock mass by uplift. tests, assuming a theoretical failure cone of the type being dis-
However, two modifications may be made to allow more realisti- cussed here. Clearly, the use of this approach to estimate rock mass
cally for the circumstances and conditions met in practice. shear strength would be impracticable for the very high-capacity,
Firstly, for major applications such as the anchoring of concrete large-scale anchors such as those described by Cavill (1997, 2000)
dams in the manner illustrated in Fig. 2a and the anchoring of dam now being used in dam engineering, not least because it is diffi-
toes, spillways and training walls, anchors are generally installed in cult to understand how the assumed failure mechanism could
rows at relatively close spacings of a few metres. In these cases, develop in most practical circumstances. This and related issues
cones such as those illustrated in Fig. 5 will overlap or interact as will be discussed in more detail in Section 5.2 to follow.
shown conceptually in two dimensions in Fig. 6a. In this case, the
calculation of the weight of the cone given by Eq. (6) may be
5.2. Deficiencies of the standard approach
replaced by a simple approximate 2D calculation assuming a
triangular cross-section to give the uplift resistance available per
As with the approaches used to design against groutetendon
unit length along the row of anchors as
(Mode B) and rockegrout (Mode C) bond failures discussed previ-
  ously, from a rock mechanics and rock engineering perspective, the
1g L 2 qc commonly-used approach to design against rock mass uplift (Mode
Qru ¼ Dþ tan (7)
2 s 2 2 D) failure assuming a conical uplift failure mechanism, suffers from
a number of deficiencies. The major rock mechanics and rock en-
where s is the spacing of anchors along the row. gineering deficiencies will be discussed briefly below in terms of
An important practical case arises when the rock mass contains the implicitly assumed stress distribution imposed within the rock
sub-horizontal bedding or structural features including jointing. In mass, the rock mass uplift failure mechanism, the influence of the
this case, the anchorage horizons within a row of anchors may be rock mass structure, and the assumed uniform values of rock mass
staggered vertically such that the tendency to uplift a volume of tensile and/or shear strengths.

5.2.1. Stress distribution induced in the overlying rock mass


If failure of, or large deformations in, a rock mass influenced by a
single anchor or a system of post-tensioned anchors is to be
assumed, knowledge is required of the distribution of stresses
induced in the rock mass by the anchor and other means. In many
cases, concrete dams are constructed in or across incised valleys or
gorges. In these cases, the major principal in situ stress near the
(a) (b) surface is likely to be oriented parallel to the valley surface. In the
Fig. 6. Interaction of uplift cones in a single row of tensioned anchors. (a) A vertical
cases illustrated in Figs. 5 and 6, the weight of the rock and the
section along the row of anchors (after Littlejohn (1993)); and (b) a simplified trian- transfer of stress from the tensioned anchor to the rock mass must
gular cross-section normal to the row (after Hobst and Zajíc (1977)). also be considered in calculating the distribution of stresses within
8 E.T. Brown / Journal of Rock Mechanics and Geotechnical Engineering 7 (2015) 1e13

the rock mass around and above the anchor(s). In many cases, the
Surface disturbance due to Active cone fails in shear
rock mass can be expected to have anisotropic elastic properties. In displacement of central cone
the case of a deep, post-tensioned anchor loaded through a surface
bearing plate, a bulb of compressive vertical stress will be induced
in the rock mass around the anchor head, and the stress distribu-
tion around the anchor embedment length at some depth can be
expected to be quite complex and non-uniform. Furthermore, it
must be expected that the final induced stress distribution will be Tensile cracking
Monolithic displacement
influenced by weathering profiles, changes in rock type and any of fixed anchor
major structural features transecting the section of the rock mass
influenced by the anchor-related stresses. Because of this range of
influences, it is not easy to conceptualise a general pattern of stress
Shaft below cone fails
induced in the rock mass by a single, deep, post-tensioned anchor through the rock
or by a system of deep, post-tensioned anchors that is likely to lead
to a conical failure surface.
The assumption of a cone of failure discussed in Section 5.1
implies that either the tensile or shear strengths of the rock mass,
or both, must be overcome over the surface of the cone before uplift Fig. 7. Failure by uplift of a fully grouted, straight-shafted, shallow, tensioned anchor in
can occur. If, as is usually the case, it is assumed that the shear and weak mudstone (Weerasinghe and Littlejohn, 1997).
tensile strengths of the rock mass are constant over any given
depth, this implies, in turn, that the shear and/or tensile stresses
induced in the rock mass must reach their maxima along some bedding or jointing and vertical cross-jointing can have a major
cone-like surface (in the case of a single anchor). While, as will be influence on the observed uplift failure mechanism in near-surface
discussed in Section 5.2.2 below, it can be readily envisaged that anchors. Similarly, a set of persistent, inclined discontinuities can
this will occur in the case of a short anchor that is grouted to, or exert a controlling influence on the failure surface geometry. In
close to, the surface, it is more difficult to understand why this general, rock masses having the main discontinuity set perpen-
should be the case when the anchor is grouted only over an dicular to the anchor axis are the most suitable in which to fix
embedment length, L, which is often significantly less than D, the anchors (Hobst and Zajíc, 1977). Fig. 8 shows some simple repre-
depth below the ground surface of the proximal end of the grouted sentations of possible influences of rock mass structure for the case
length. In the first instance, the distribution of induced elastic of a shallow anchor that is fully grouted to the ground surface. In a
stresses could be investigated through a series of relatively simple number of the shallow anchor cases illustrated in Figs. 7 and 8, it is
numerical stress analyses of sample problem configurations. easy to postulate a conical or pseudo-conical failure surface,
remembering that the in situ problem is 3D and not 2D as shown in
5.2.2. Rock mass uplift failure mechanism the sketches of Figs. 7 and 8.
Most direct observations of the rock mass uplift failure mech- It appears reasonable to suggest that, in the cases of the deep
anism of which the author is aware, were associated with field pull- anchors used in dam engineering, the near-surface rock mass
out tests in which, almost of necessity, the anchor was short in structure may not exert the same immediate controlling influence,
comparison to the lengths of the large post-tensioned anchors used and the 90 uplift cone assumption may not be as valid, as in the
in dam construction and rehabilitation projects, and the anchor was shallow anchor case. In any event, the deeper the anchor, or the
grouted to, or close to, the ground surface (Dados, 1984; greater the ratio of the anchor depth, D, to the embedment length,
Benmokrane et al., 1995; Carter, 1995; Weerasinghe and L, in Fig. 5, the less likely the conical rock mass uplift mechanism is
Littlejohn, 1997; Serrano and Olalla, 1999; Thomas-Lepine, 2012). to control the behaviour of the post-tensioned anchor.
Furthermore, in some of these cases, the test anchor was installed Weerasinghe and Littlejohn (1997) argued that, for fully grouted
in near-surface, weak rock. anchors, as anchorage depth increases, the resistance of the rock
A number of such investigations have found that while mass cone will become smaller compared to the shaft (grouterock)
discernible surface uplift extends for some distance laterally from resistance. Numerical experiments using discrete element codes
the anchor borehole, the limit of “significant” uplift can be repre- provide perhaps the most promising means of exploring potential
sented reasonably well by a 90 cone. For example, Fig. 7 shows the failure mechanisms of deep anchors in rock masses for which rock
failure mechanism observed and inferred by Weerasinghe and mass structure models or discrete fracture network (DFN) simula-
Littlejohn (1997) for a straight shafted anchor grouted to the tions are available (Panton et al., 2014). Ideally, numerical analyses
ground surface in a weak mudstone and subjected to uplift. The test of this type should be 3D rather than 2D.
anchor was composed of a seven 15.2 mm 7-wire drawn strand As was noted at the end of Section 5.1, in dam engineering, the
tendon with nodes in the fixed anchor length to reduce the possi- potential influence of a continuous or near-continuous horizontal
bility of groutetendon failure. Weerasinghe and Littlejohn (1997) or sub-horizontal structural feature such as a bedding plane or
noted that the central cone at the top of the anchor was formed sheeting joint can be reduced by staggering the elevations of the
by rock mass failure in shear. It is suggested that the failure anchor lengths of adjacent anchors in a row. In either the shallow or
mechanism would be quite different if the same anchor was
installed in the same rock mass in a configuration such as that
shown in Fig. 5 with the relatively high values of D/L used in
modern dam engineering practice.

5.2.3. Influence of rock mass structure


Clearly, the structure of the rock mass will influence the shape of
the “failure” surface. Dados (1984), Wyllie (1999) and Thomas- Fig. 8. Influence of rock mass structure on the uplift failure mechanism of a shallow,
Lepine (2012), among others, have shown how horizontal fully grouted, tensioned anchor (after Wyllie (1999)).
E.T. Brown / Journal of Rock Mechanics and Geotechnical Engineering 7 (2015) 1e13 9

deep anchor case, or in the case of a row of anchors as illustrated in other geotechnical engineering applications, including some
Fig. 6, it must be recognised that, as shown by a range of pull-out involving anchored structures, the upper and lower bound theo-
tests and by preliminary numerical simulations carried out by rems of limit state theory have been used to identify likely failure
Panton et al. (2014), the rock mass uplift failure mechanism will be mechanisms and the associated limit loads (Sloan, 1989, 2013;
progressive. Regenass and Soubra, 1997; Soubra and Regenass, 1997). In these
geotechnical engineering applications, numerical methods, notably
5.2.4. Estimation of rock mass shear and/or tensile strengths finite element methods, including large deformation finite element
Existing design approaches using the 90 or 60 uplift cone methods, have been used in conjunction with limit state analysis to
hypotheses, variously assume shear, cohesive and/or tensile obtain solutions to otherwise intractable problems (Sloan, 1989,
strengths of the rock mass which may be the presumptive values or 2013; Wang et al., 2013). It is suggested that such an approach
be back-calculated from the results of pull-out tests using a could be used to good effect to identify potential rock mass uplift
“theoretical” failure cone (Hobst and Zajíc, 1977; USACE, 1995; conditions associated with the use of large post-tensioned anchors
Weerasinghe and Adams, 1997). Clearly, these simple approaches to stabilise or strengthen dams.
do not take into account the variability of the governing strength
parameters with depth and with varying local rock mass structure,
6. Other investigation, design and construction issues
or the progressive and complex nature of the rock mass failure
mechanisms involved. Nor do they always allow for the influence of
6.1. Overview
the total distribution of stresses within the rock mass. It is sug-
gested that these simplistic approaches can, and should, be
The major rock mechanics and rock engineering issues associ-
improved.
ated with the design of post-tensioned rock anchors for concrete
dams have been discussed in the preceding sections of this paper.
5.3. Suggested alternative approaches
However, in order to ensure acceptable performance of the anchors
and of the structures that they are intended to stabilise or reinforce,
At the end of Section 3.1, it was noted that linear and nonlinear
a range of other site investigation, design and construction issues
static and dynamic numerical stress analyses (Alonso et al., 1996;
associated with the anchors have to be planned and executed
Yu et al., 2005; Bureau et al., 2007; Scott and Mills-Bria, 2008;
satisfactorily. To discuss all of them in detail would extend the
Lemos, 2011, 2014; Chopra, 2012), limit state (Merrifield et al., 1997;
scope of this paper beyond reasonable limits. However, for
Herweynen, 1998; ANCOLD, 2013; Farrell, 2013), reliability, risk-
completeness, they will be referred to briefly here. These issues
based, probabilistic and fragility methods (Ellingwood and Tekie,
include:
2001; Phoon et al., 2003; Barker, 2011; Westberg Wilde and
Johansson, 2013) are now being used for dam design analysis and
 site investigation and characterisation;
assessment. These approaches may be used when analysing the
 the installation and testing of trial anchors;
overall stability of dams stabilised by post-tensioned anchors in the
 grout design and grouting trials;
manner illustrated schematically in Fig. 2. As well as the traditional
 the fabrication, installation, tensioning and possibly re-
limiting equilibrium analyses, numerical stress analysis methods
tensioning of the anchors;
may use continuum, equivalent continuum or discontinuum
 the provision of corrosion protection to the anchors and anchor
methods. As was indicated in Section 5.2.3 and has been demon-
heads; and
strated by Panton et al. (2014), numerical methods, particularly
 the in service monitoring and maintenance of anchors and their
discontinuum methods used in conjunction with a structural or
fittings.
DFN model of the rock mass concerned, potentially provide a
powerful means of investigating the likely responses of rock masses
Many of these issues are covered by Standards, Codes of Practice
to the uplift imposed by post-tensioned anchors. Provided
and Guidelines. Some of them will be discussed briefly below.
adequate input data are available (see Section 6.1 below), these
methods can also allow the influence of the in situ stresses and the
stresses induced in the rock mass to be evaluated more rationally 6.2. Site investigation and characterisation
and more fully than does the standard design approach discussed
in Section 5.1. However, in the author’s experience, detailed design As the author has argued elsewhere (Brown, 2011), the design
analyses of this proposed type are rarely carried out in practice. and construction of large dams played a significant role in the
Although the previous discussion concerned Mode D or rock development of rock mechanics and rock engineering knowledge
mass uplift failure, it should also be noted that, for any given case, and techniques that took place in the middle decades of the 20th
comprehensive numerical analyses can be used to improve the century. This applied particularly to site investigation methods and
methods generally used to estimate the distribution of normal and to the assessment of the mechanical properties of rocks and rock
shear stresses along tendonegrout and rockegrout interfaces and masses, including discontinuities. In modern dam engineering,
to evaluate the onset and progression of interface bond failure and adequate site investigation and the resulting site characterisation,
slip. Although this may appear to be relatively straight-forward, for and geological, structural and geotechnical model development
its complete numerical analysis, this problem requires the evalua- remain of paramount importance. In terms of the various types of
tion and input of a number of rock and grout properties, including design analyses discussed in this paper, particular site characteri-
stiffnesses. As noted in Section 3.4, historically a significant number sation requirements include:
of analyses of this type have been carried out for rock and cable
bolts and for shallow or near-surface anchors, but to the best of the  estimating the in situ stresses at the dam site, particularly under
author’s knowledge rarely, if at all, for the large post-tensioned incised valleys;
anchors currently being used for dam stabilisation.  mapping discontinuities in the foundation rock mass and
As discussed in Section 5.2, there are a number of problem developing complete 3D structural models for the geotechnical
configurations for which the 60 or 90 uplift cone assumptions do domains identified, preferably using a DFN approach;
not provide realistic models for use in design analysis. In a range of  estimating rock and rock mass strengths and deformabilities;
10 E.T. Brown / Journal of Rock Mechanics and Geotechnical Engineering 7 (2015) 1e13

 measuring or estimating the basic friction angles, roughnesses 7. Conclusions


and normal and shear stiffnesses of persistent discontinuities
likely to be involved in the sliding mode of failure illustrated in High-capacity, post-tensioned anchors have found wide-spread
Fig. 2b; use, originally in initial dam design and construction, and more
 establishing design values of the shear and tensile strengths of recently in the strengthening and rehabilitation of concrete dams to
old and new foundation rockemass concrete interfaces (Lo et al., meet modern design and safety standards. Despite the advances
1991; EPRI, 1992); and that have been made in rock mechanics and rock engineering
 measuring or estimating rock mass permeabilities and identi- during the almost 80 years in which post-tensioned anchors have
fying significant water-bearing discontinuities in the foundation been used in dam engineering, the author’s reading of the litera-
(Farinha et al., 2011). ture, and his own practical experience in Australia, suggest that
some aspects of the rock mechanics and rock engineering design of
Examples of some of the modern approaches and techniques rock anchors for dams have changed relatively little over the last 30
used to obtain data of these types are given by Brown and Marley or 40 years. This applies, in particular, to the calculations usually
(2008), Powell et al. (2008), Shaffner et al. (2009), Friz et al. carried out to establish the grouted embedment lengths required
(2011), Hencher et al. (2011) and Agharazi et al. (2012). for deep, post-tensioned anchors. These calculations usually make
simplified assumptions about the distribution and values of rocke
grout interface shear strengths, the shape of the volume of rock
6.3. Anchor and grouting trials
likely to be involved in uplift failure under the influence of a system
of post-tensioned anchors, and the mechanism of that failure. The
It is essential that before the detailed design of a system of large,
resulting designs are generally conservative. While this is under-
post-tensioned anchors is completed, trial anchors of prototype
standable for important structures like dams for which public
size should be installed in the rock mass concerned and load tested.
safety is a major consideration, in some cases, the degree of
This overall process should include tests of drilling accuracy and
conservatism is considered to be excessive and to represent poor
drill hole stability in the candidate rock mass; tests of proposed
engineering practice.
grout mixes and grouting tests to enable suitable grouting pres-
It is concluded that the aspects of rock mechanics and rock
sures to be determined and the extent of the likely loss of grout into
engineering design of large, post-tensioned rock anchors for dams
the surrounding rock mass to be assessed; and, perhaps most
of major concern here, the rockegrout bond and the uplift failure
importantly, load testing of a generally small number of trial an-
mechanism, can be significantly improved by making greater use of
chors for a range of possible purposes, including the identification
modern, comprehensive, numerical analyses in conjunction with
of potential failure mechanisms and, with suitable test design, the
3D models of the rock mass structure, realistic rock and rock mass
estimation of mean rockegrout interface strengths. As will be dis-
properties, and the results of prototype anchor tests in the rock
cussed in Section 6.4 to follow, it is also common or required
mass concerned.
practice to test load each prototype anchor on installation and
subsequently during the anchor’s service life. Examples of anchor
testing procedures and results are given by Habib (1989), Scott and Conflict of interest
Bruce (1992), Littlejohn (1993), Bruce (1997), Feddersen (1997) and
Cavill (2000). The author has no known conflict of interest associated with this
review paper.

6.4. Anchor stressing and in service monitoring


Acknowledgements
The initial anchor stressing and proof-testing, and the inspec-
The author wishes to thank those who gave him the opportunity
tion, monitoring, maintenance and re-stressing of anchors during
to become involved in dam engineering at a relatively late stage of
their service lives, are critically important in ensuring the satis-
his career, and those with whom he has worked on projects and
factory in service performance of post-stressed anchor systems. As
discussed the issues addressed in this paper. They include: Brian
Littlejohn (1993) noted, “stressing is required to fulfil two func-
Cooper, Peter Foster, Tim Griggs, Richard Herweynen, Mike Marley,
tions. (i) To tension the tendon and to anchor it at its secure load. (ii)
Peter Richardson and Richard Rodd. He would also thank the
To ascertain and record the behaviour of the anchorage so that it
management and Principals of the Brisbane office of Golder Asso-
can be compared with the behaviour of control anchorages, sub-
ciates for facilitating his work in dam engineering and supporting
jected to on-site suitability tests.” The structural design of the an-
the preparation of this paper; Mike Marley and Rob Morphet for
chor stressing system, including the load cell, anchor head and
internally reviewing of the paper; Guy Green for preparing the
bearing plate, is an important element of this undertaking
drawings; and Jo-Anne Sandilands for her word processing
(Littlejohn, 1993). As was noted in Section 3.3, during installation of
assistance.
the anchor, it is common practice in Australia to test load the an-
chor and fittings beyond the normal WL (for example, up to 78%e
80% MBL) and to “lock-off” the load with sufficient allowance above References
the WL (for example, to 68%e72% MBL) to allow for subsequent
Agharazi A, Tannant DD, Martin CD. Characterizing rock mass deformation mech-
load losses caused by creep, relaxation and draw-in (ANCOLD, anisms during plate load tests at the Bakhtiary project. International Journal of
1992). Following this initial stressing, it is necessary to protect Rock Mechanics and Mining Sciences 2012;49(1):1e11.
the anchor head against corrosion while ensuring that it remains Alonso E, Carol I, Delahaye C, Gens A, Prat P. Evaluation of safety factors in
discontinuous rock. International Journal of Rock Mechanics and Mining Sci-
accessible for subsequent inspection and re-stressing (Littlejohn
ences 1996;33(5):513e37.
and Mothersille, 2007). ANCOLD. Guidelines on design criteria for concrete gravity dams. Australian Na-
The volume edited by Littlejohn (2007) contains a wide range of tional Committee on Large Dams (ANCOLD); 1991.
papers on the in service inspection, maintenance and monitoring of ANCOLD. Guidelines on strengthening and raising concrete gravity dams. Australian
National Committee on Large Dams Working Group; 1992.
ground anchors and anchored structures, including dams ANCOLD. Draft guidelines on design criteria for concrete gravity dams. Australian
(Aschenbroich, 2007; Wolfhope et al., 2007; Zicko et al., 2007). National Committee on Large Dams; 2013 [unpublished].
E.T. Brown / Journal of Rock Mechanics and Geotechnical Engineering 7 (2015) 1e13 11

Anon. Rock foundations e technical engineering and design guidelines as adapted Coates DF, Yu YS. Rock anchor design mechanics. Research Report No R233. Mines
from the US Army Corps of Engineers, No.16. New York: ASCE Press; 1996. 129 pp. Branch, Canadian Department of Energy, Mines and Resources; 1971.
Aschenbroich H. Case histories of high capacity anchors for two dams in Canada Dados AT. Design of anchors in horizontally jointed rocks. Journal of Geotechnical
involving long term monitoring. In: Littlejohn GS, editor. Ground anchorages Engineering, ASCE 1984;110(11):1637e47.
and anchored structures in service, Proceedings of the International Confer- DEWS. Guidelines on acceptable flood capacity for water dams. State of Queens-
ence, London. London: Thomas Telford; 2007. p. 144e54. land: Department of Energy and Water Supply; 2013.
Banks JA. Allt-na-Lairige prestressed concrete dam. Proceedings of the Institution of Dickson PD, Loar TN. Abutment stability analyses and design solutions for Tekeze
Civil Engineers 1957;6(3):409e28. Dam, Ethiopia. In: Proceedings of the 45th US Rock Mechanics/Geomechanics
Barker M. Australian risk approach for assessment of dams. In: 21st century dam Symposium, San Francisco; 2011. Paper 11e315 (on CD-ROM).
design e advances and adaptations, proceedings of the 31st Annual USSD Duffaut P. The traps behind the failure of Malpasset arch dam, France, in 1959.
Conference, San Diego. Denver: US Society on Dams; 2011. p. 69e91. Journal of Rock Mechanics and Geotechnical Engineering 2013;5(5):335e41.
Barley AD. Ten thousand anchorages in rock. Ground Engineering 1988;21(6):20e9. Ebeling RM, Nuss LK, Tracy FT, Brand B. Evaluation and comparison of stability
21(7): 24e35; 21(8): 35e9. analysis and uplift criteria for concrete gravity dams by three federal agencies.
Barley AD. Properties of grouts in a confined state. In: Littlejohn GS, editor. Ground Report ERDC/ITL TR-00-1. Information Technology Laboratory, U.S. Army Engi-
anchorages and anchored structures, Proceedings of the International Confer- neer Research and Development Center; 2000.
ence, London. London: Thomas Telford; 1997. p. 13e22. Ellingwood B, Tekie PB. Fragility analysis of concrete gravity dams. Journal of
BC Hydro. Guidelines for the assessment of rock foundations of existing concrete Infrastructure Systems, ASCE 2001;7(2):41e8.
gravity dams. BC Hydro Report No. MEP67, Vancouver, Canada. 1995. EPRI. Uplift pressures, shear strengths and tensile strengths for stability analysis of
Bedi A, Orr TLL. On the applicability of the Eurocode 7 partial factor method for rock concrete dams, vol. 1. Palo Alto: Electric Power Research Institute; 1992. Report
mechanics. In: Alejano LR, Perucho A, Olalla C, Jiménez R, editors. Rock engi- TR-100345.
neering and rock mechanics: structures in and on rock, Proceedings of Eurock Farinha MLB, Lemos JV, Maranha das Neves E. Numerical modelling of borehole
2014, ISRM European Regional Symposium, Vigo. Leiden: CRC Press/Balkema; water-inflow tests in the foundation of the Alqueva arch dam. Canadian
2014. p. 1517e23. Geotechnical Journal 2011;48(1):72e88.
Benmokrane B, Chekired M, Xu H. Monitoring behavior of grouted anchors using Farmer IW. Stress distribution along a resin grouted anchor. International Journal of
vibrating wire gauges. Journal of Geotechnical Engineering, ASCE 1995;121(6): Rock Mechanics and Mining Sciences and Geomechanics Abstracts 1975;12(11):
466e75. 347e52.
Bianchi RH, Bruce DA. The use of post-tensioned anchorages on the arch portion of Farrell ER. Harmonisation of anchor design within Eurocode. In: Arnold P,
Stewart Mountain Dam. In: Anderson LR, editor. Geotechnical practice in dam Fenton GA, Hicks MA, Schweckendiek T, Simpson B, editors. Modern geotech-
rehabilitation. Geotechnical Special Publication No. 35. New York: American nical design codes of practice: implementation, application and development.
Society of Civil Engineers; 1993. p. 791e802. Amsterdam: IOS Press; 2013. p. 15e24.
Bretas EM, Léger P, Lemos JV. 3D stability analysis of gravity dams on sloped rock Feddersen I. Improvement of the overall stability of a gravity dam with 4500 kN
foundations using the limit equilibrium method. Computers and Geotechnics anchors. In: Littlejohn GS, editor. Ground anchorages and anchored structures,
2012;44:147e56. Proceedings of the International Conference, London. London: Thomas Telford;
Bretas EM, Léger P, Lemos JV, Lourenço PB. Analysis of a gravity dam considering the 1997. p. 318e25.
application of passive reinforcement. In: Garcia RR, Mir MA, Bitrian FH, Dios RL, Fell R, MacGregor P, Stapledon D, Bell G. Geotechnical engineering of dams. Leiden:
Caballero MRC, editors. Dam maintenance and rehabilitation II, Proceedings II A.A. Balkema; 2005.
International Congress on Dam Maintenance and Rehabilitation, Zaragoza. Friz PC, Curtis D, Rutherford JH, Hart S, Johnston DC, Orbison D. Blue Lake Dam left
Leiden: CRC Press/Balkema; 2010. abutment geological modelling for dam raise. In: 21st century dam design e
Brown ET. Fifty years of the ISRM and associated progress in rock mechanics. In: advances and adaptations, Proceedings of the 31st Annual USSD Conference,
Qian Q, Zhou YX, editors. Harmonising rock engineering and the environment, San Diego. Denver: US Society on Dams; 2011. p. 147e61.
Proceedings of the 12th Congress, International Society for Rock Mechanics, Gosschalk EM, Taylor RW. Strengthening of Muda Dam foundation using cable
Beijing. Leiden: CRC Press/Balkema; 2011. p. 29e43. anchors. In: Proceedings of the 2nd Congress, International Society for Rock
Brown ET, Marley M. Estimating rock mass properties for stability analyses of new Mechanics, Belgrade3. Rotterdam: A.A. Balkema; 1970. p. 205e10.
and existing dams. In: Proceedings of the Symposium on Operation, Rehabili- Haberfield CM, Baycan S. Field performance of the grout/rock interface in anchors.
tation and Up-grading of Dams, ICOLD 76th Annual Meeting, Sofia; 2008. Paper In: Littlejohn GS, editor. Ground anchorages and anchored structures, Pro-
2e48 (on CD-ROM). ceedings of the International Conference, London. London: Thomas Telford;
Bruce DA. Practical aspects of rock anchorages for dams. In: Dam safety in the 1997. p. 45e54.
states: Proceedings of the Association of State Dam Safety Officials Fifth Annual Habib P, editor. Recommendations for the design calculation, construction and
Conference, Manchester, New Hampshire; 1988. monitoring of ground anchors. Rotterdam: A.A. Balkema; 1989.
Bruce DA. The stabilization of concrete dams by post-tensioned rock anchors: the Hanna TH. Foundations in tension: ground anchors. Clausthal: Trans Tech Publi-
state of American practice. In: Littlejohn GS, editor. Ground anchorages and cations and New York: McGraw-Hill. 1982.
anchored structures, Proceedings of the International Conference, London. Harman T, Herweynen R, Gosh M. Analysis and design challenges associated with
London: Thomas Telford; 1997. p. 508e21. the Catagunya Dam Restoration Project. In: Dam decisions: past experiences,
Bruce D, Wolfhope J. Rock anchors for North American dams: The National Research future challenges, Proceedings of the ANCOLD 2010 Conference, Hobart; 2010.
Program bibliography and data base. In: Littlejohn GS, editor. Ground anchor- 15 pp. (on CD-ROM).
ages and anchored structures in service, Proceedings of the International Harrison JP. Eurocode 7 and rock engineering: current problems and future op-
Conference, London. London: Thomas Telford; 2007. p. 121e31. portunities. In: Alejano LR, Perucho A, Olalla C, Jiménez R, editors. Rock engi-
Bruce D, Wolfhope J. 40 years of rock anchors for dams in North America e lessons neering and rock mechanics: structures in and on rock, Proceedings of Eurock
learned. In: The sustainability of experience e investing in the human factor, 2014, ISRM European Regional Symposium, Vigo. Leiden: CRC Press/Balkema;
Proceedings of the 28th Annual USSD Conference, Portland. Denver: US Society 2014. p. 1531e6.
on Dams; 2008. p. 47e56. Hencher SR, Lee SG, Carter TG, Richards LR. Sheeting joints: characterisation, shear
Bureau G, Keller TO, Zhou J. Nonlinear structural analysis for San Vicente Dam raise. strength and engineering. Rock Mechanics and Rock Engineering 2011;44(1):
In: Modernization and optimization of existing dams and reservoirs, Pro- 1e22.
ceedings of the 27th Annual USSD Conference, Philadelphia. Denver: US Society Herweynen RI. Safety of Meadowbank Dam against sliding parameter uncertainty.
on Dams; 2007. p. 405e19. ANCOLD Bulletin No. 112. August 1998. p. 77e87.
Carter TG. Observations on cone pull-out anchor behaviour in very weak rock. In: Hobst L, Zajíc J. Anchoring in rock. Amsterdam: Elsevier; 1977.
Widmann R, editor. Anchors in theory and practice, Proceedings of the Inter- Hyett AJ, Bawden WF, Macsporran GR, Moosavi M. A constitutive law for bond
national Symposium on Anchors in Theory and Practice, Salzburg. Rotterdam: failure of fully-grouted cable bolts using a modified Hoek cell. International
A.A. Balkema; 1995. p. 17e23. Journal of Rock Mechanics and Mining Sciences 1995;32(1):11e36.
Cavill BA. Very high capacity ground anchors used in strengthening concrete gravity Ivanovi c A, Neilson RD. Modelling of debonding along the fixed anchor length.
dams. In: Littlejohn GS, editor. Ground anchorages and anchored structures, International Journal of Rock Mechanics and Mining Sciences 2009;46(4):699e
Proceedings of the International Conference, London. London: Thomas Telford; 707.
1997. p. 262e71. Jarred DJ, Haberfield CM. Tendon/grout interface performance in grouted anchors.
Cavill BA. Full scale testing of a 2400 tonne capacity rock anchor. ANCOLD Bulletin In: Littlejohn GS, editor. Ground anchorages and anchored structures, Pro-
No 114. April 2000. p. 213e23. ceedings of the International Conference, London. London: Thomas Telford;
CDSA. Dam safety guidelines. Canadian Dam Safety Association; 1999. 1997. p. 262e71.
CEN (European Committee for Standardisation). Geotechnical design: part 1, gen- Kaiser PK, Yazici S, Nosé J. Effect of stress change on the bond strength of fully
eral rules. EN-1997-1. Brussels: CEN; 2004. grouted cables. International Journal of Rock Mechanics and Mining Sciences
Chopra AK. Earthquake analysis of arch dams: factors to be considered. Journal of 1992;29(3):293e306.
Structural Engineering, ASCE 2012;138(2):205e14. Khaoua M, Montel B, Civaro A, Luga A. Cheurfas Dam anchorages: 30 years of
Coates DF. Rock mechanics principles. Mines branch monograph 874. Ottawa: In- control and recent reinforcement. In: Proceedings of the 7th International
formation Canada; 1970. Conference on Soil Mechanics and Foundation Engineering, Mexico CitySpeci-
Coates DF, Yu YS. Three-dimensional stress distributions around a cylindrical hole alty Session 15; 1969. p. 167e71.
and anchor. In: Proceedings of the 2nd Congress, International Society for Rock Kim HK, Cho NJ. A design method to incur ductile failure of rock anchors subjected to
Mechanics, Belgrade, 3; 1970. p. 175e82. tensile loads. Electronic Journal of Geotechnical Engineering 2012;17:2737e46.
12 E.T. Brown / Journal of Rock Mechanics and Geotechnical Engineering 7 (2015) 1e13

Kline RA, Howard B, Davidheiser SM. Current state-of-the-art for existing gravity Ren FF, Yang ZJ, Chen JF, Chen WW. An analytical analysis of the full-range
dam stability analysis. In: Modernization and optimization of existing dams and behaviour of grouted rockbolts based on tri-linear bond-slip. Construction
reservoirs, Proceedings of the 27th Annual USSD Conference, Philadelphia. and Building Materials 2010;24(3):361e70.
Denver: US Society on Dams; 2007. p. 341e51. Scott GA, Bruce DA. Full scale field tests of high capacity rock anchors. In:
Lamas L, Perucho A, Alejano LR. Some key issues regarding application of Eurocode Tillerson JR, Wawersik WR, editors. Proceedings of the 33rd US Symposium on
7 to rock engineering design. In: Alejano LR, Perucho A, Olalla C, Jiménez R, Rock Mechanics, Santa Fe. Rotterdam: A.A. Balkema; 1992. p. 471e80.
editors. Rock engineering and rock mechanics: structures in and on rock, Pro- Scott GA, Mills-Bria BL. Nonlinear, 3D, dynamic coupled dam-foundation analyses
ceedings of Eurock 2014, ISRM European Regional Symposium, Vigo. Leiden: for estimating risks at Hungry Horse Dam. In: The sustainability of experience e
CRC Press/Balkema; 2014. p. 1459e64. investing in the human factor, Proceedings of the 28th Annual USSD Confer-
La Villa G, Golser J. Slopes of the Tarbela Dam Project. Rock Mechanics ence, Portland. Denver: US Society on Dams; 2008. p. 135e50.
1982;(Suppl. 12):179e90. Serrano A, Olalla C. Tensile resistance of rock anchors. International Journal of Rock
Lawrence MS, Martin CD. Estimating rock mass strength for a concrete dam foun- Mechanics and Mining Sciences 1999;36(4):449e74.
ded on good rock: Blind Slough Dam, British Columbia, Canada. In: Eberhardt E, Shaffner P, Heisler R, Krosley L, Kottenstette J, Wright J. Characterization of dam
Stead D, Morrison T, editors. Rock mechanics: meeting society’s challenges and foundation blocks using digital photogrammetric mapping and borehole
demands, Proceedings of the 1st Canada e US Rock Mechanics Symposium, geophysical logging to create comprehensive 3D foundation models. In: Man-
Vancouver2. London: Taylor and Francis; 2007. p. 1007e14. aging our water retention systems, Proceedings of the 29th Annual USSD
Lemos J. Discontinuum models for dam foundation failure analysis. In: Qian Q, Conference, Nashville. Denver: US Society on Dams; 2009. p. 473e505.
Zhao YX, editors. Harmonising rock engineering and the environment, Pro- She CX. Deformation and stability of the right arch dam abutment of the Danjiang
ceedings of the 12th Congress, International Society for Rock Mechanics, Bei- hydro-power project, China. International Journal of Rock Mechanics and
jing. Leiden: CRC Press/Balkema; 2011. p. 91e8. Mining Sciences 2004;41(Suppl. 1):792e7. Paper 3B 04, ISRM SinoRock 2004
Lemos JV. Representation of rock discontinuities in safety analysis of large dams. In: Symposium (on CD-ROM).
Alejano LR, Perucho A, Olalla C, Jiménez R, editors. Rock engineering and rock Singhal AC, Nuss LK. Cable anchoring of deteriorated arch dam. Journal of the
mechanics: structures in and on rock, Proceedings of Eurock 2014, ISRM Eu- Performance of Constructed Facilities, ASCE 1991;5(1):19e36.
ropean Regional Symposium, Vigo. Leiden: CRC Press/Balkema; 2014. p. 29e38. Sloan SW. Upper bound limit analysis using finite elements and linear program-
Liang J. Development and problems of prestressed anchor cables for geotechnical ming. International Journal for Numerical and Analytical Methods in Geo-
engineering in China. ISRM News Journal 1995;2(3e4):10e7. mechanics 1989;13(3):263e82.
Littlejohn GS. Overview of rock anchorages. In: Hudson JA, Brown ET, Fairhurst C, Sloan SW. Geotechnical stability analysis. Géotechnique 2013;63(7):531e72.
Hoek E, editors. Comprehensive rock engineering4. Oxford: Pergamon Press; Snape D. Sustainable rehabilitation of gravity dams using post-tensioned anchors.
1993. p. 413e50. ANCOLD Bulletin No 120. April 2002. p. 47e56.
Littlejohn GS. Rock anchorage practice in civil engineering. In: Kaiser PK, Soubra AH, Regenass P. Overall stability of anchored sheet pile structures. In:
McCreath DR, editors. Rock support in mining and underground construction, Littlejohn GS, editor. Ground anchorages and anchored structures: Proceedings of
Proceedings of the International Symposium on Rock Support, Sudbury. Rot- the International Conference, London. London: Thomas Telford; 1997. p. 100e8.
terdam: A.A. Balkema; 1992. p. 257e68. Thomas-Lepine C. Rock bolts e improved design and possibilities. MSc Thesis.
Littlejohn GS, editor. Ground anchorages and anchored structures: Proceedings of Trondheim: Norwegian University of Science and Technology; 2012.
the International Conference, London. London: Thomas Telford; 1997. Topham C, Nicholson E, Tanner D. Managing risk of under-designed spillway
Littlejohn GS, editor. Ground anchorages and anchored structures in service: Pro- training walls: an owner’s guide. In: McSaveney ER, editor. Multiple use of dams
ceedings of the International Conference, London. London: Thomas Telford; and reservoirs: needs, benefits and risks, Proceedings of the NZSOLD e ANCOLD
2007. 2013 Conference, Rotorua, 39(1(LD)). Wellington: IPENZ Proceedings of Tech-
Littlejohn GS, Bruce DA. Rock anchors: state of the art. Ground Engineering 1975e nical Groups; 2013. p. 384e98.
76;8(3):25e32. 8(4): 41e8; 8(5): 34e45; 8(6): 36e45; 9(2): 20e9; 9(3): 55e60; USACE. Gravity dam design. Engineer Manual EM1110-2-2200. U.S. Army Corps of
9(4): 33e44. Engineers; 1995.
Littlejohn GS, Bruce DA. Rock anchors e design and quality control. In: Fairhurst C, USACE. Stability analysis of concrete structures. Engineer Manual EM1110-2-2100.
Crouch SL, editors. Design methods in rock mechanics, Proceedings of the 16th U.S. Army Corps of Engineers; 2005.
Symposium on Rock Mechanics, Minneapolis. New York: ASCE; 1977. p. 77e88. Wang D, Merifield RS, Gaudin C. Uplift behaviour of helical anchors in clay. Cana-
Littlejohn GS, Mothersille D. Maintenance testing and service behaviour monitoring dian Geotechnical Journal 2013;50(6):575e84.
of permanent ground anchorages. In: Littlejohn GS, editor. Ground anchorages Weerasinghe RB, Adams D. A technical review of rock anchorage practice 1976e
and anchored structures in service: Proceedings of the International Confer- 1996. In: Littlejohn GS, editor. Ground anchorages and anchored structures:
ence, London. London: Thomas Telford; 2007. p. 1e16. Proceedings of the International Conference, London. London: Thomas Telford;
Liu X, Zhou Y, Chen C, Zheng Y, Xia K. Anchoring characteristic of tension-type 1997. p. 481e91.
anchor cable and grout length design. In: Feng XT, Hudson JA, Tan F, editors. Weerasinghe RB, Littlejohn GS. Uplift capacity of shallow anchorages in weak
Rock characterisation, modelling and engineering design methods, Proceedings mudstone. In: Littlejohn GS, editor. Ground anchorages and anchored struc-
of the 3rd ISRM SinoRock Symposium, Shanghai. Leiden: CRC Press/Balkema; tures: Proceedings of the International Conference, London. London: Thomas
2013. p. 697e702. Telford; 1997. p. 23e33.
Lo KY, Ogawa T, Lukajic B, Dupak DD. Measurements of strength parameters of Westberg Wilde M, Johansson F. System reliability of concrete dams with respect to
concrete-rock contact at the dam-foundation interface. Geotechnical Testing foundation stability: application to a spillway. Journal of Geotechnical and
Journal 1991;14(4):383e94. Geoenvironmental Engineering, ASCE 2013;139(2):308e19.
Lombardi G. 3-D analysis of gravity dams. Hydropower and Dams 2007;1:98e102. Wilkins JK, Fidler BE. Design of Catagunya prestressed dam. Civil Engineering
Lowe J, Chao PC, Leucker AR. Tarbela service spillway plunge pool development. Transactions, Institution of Engineers, Australia 1959;CE1:47e63.
Water Power and Dam Construction 1979;31(11):85e90. Wolfhope J, Bruce D, Forbes G, Boyd L. Post-tensioned rehabilitation applied to
Maddox JM, Kinstler FL, Mather RP. Meadowbank Dam e foundations. Civil Engi- hydropower dams. In: Littlejohn GS, editor. Ground anchorages and anchored
neering Transactions, Institution of Engineers, Australia 1967;9(2):321e9. structures in service, Proceedings of the International Conference, London.
Merrifield CM, Barley AD, Von Matt U. The execution of ground anchor works: the London: Thomas Telford; 2007. p. 132e43.
European Standard prEN1537. In: Littlejohn GS, editor. Ground anchorages and Woods RI, Barkhordari K. The influence of bond stress distribution on ground an-
anchored structures: Proceedings of the International Conference, London. chor design. In: Littlejohn GS, editor. Ground anchorages and anchored struc-
London: Thomas Telford; 1997. p. 492e501. tures: Proceedings of the International Conference, London. London: Thomas
Morris SS, Garrett WS. The raising and strengthening of Steenbras Dam. Pro- Telford; 1997. p. 55e64.
ceedings of the Institution of Civil Engineers, Part 1 1956;5(1):23e48. Wyllie DC. Foundations on rock: engineering practice. 2nd ed. London: E & FN
Panton B, Elmo D, Schotfeldt P, Carvalho J. Design of rock foundation anchorage Spon; 1999.
using Discrete Fracture Networks. In: Proceedings of the International Discrete Xanthakos PP. Ground anchors and anchored structures. New York: John Wiley;
Fracture Network Engineering Conference, Vancouver; 2014. 1991.
Park J, Qiu T, Kim Y. Field and laboratory investigation of pullout resistance of steel Xu H, Benmokrane B. Strengthening of existing concrete dams using post-tensioned
anchors in rock. Journal of Geotechnical and Geoenvironmental Engineering, anchors: a state-of-the-art review. Canadian Journal of Civil Engineering
ASCE 2013;139(12):2219e24. 1996;23(6):1151e71.
Pease KA, Kulhawy FH. Load transfer mechanisms in rock sockets and anchors. Yu X, Zhou YF, Peng SZ. Stability analyses of dam abutments by 3D elasto-plastic
Report EL-3777. Palo Alto: Electric Power Research Institute; 1984. finite-element method: a case study of Houhe gravity-arch dam in China. In-
Powell CN, Shaffner PT, Wright J. Exploration and geotechnical characterization for ternational Journal of Rock Mechanics and Mining Sciences 2005;42(3):415e30.
evaluating the stability of Hungry Horse Dam. In: The sustainability of expe- Zhao YM, Yang MJ. Pull-out behaviour of an imperfectly bonded anchor system. In-
rience e investing in the human factor, Proceedings of the 28th Annual USSD ternational Journal of Rock Mechanics and Mining Sciences 2011;48(3):469e75.
Conference, Portland. Denver: US Society on Dams; 2008. p. 115e33. Zicko KE, Bruce DA, Kline RA. The stabilization of Gilboa Dam, New York, using
Phoon KK, Kulhawy FH, Grigoriu MD. Development of a reliability-based design high capacity rock anchors: addressing service performance issues. In:
framework for transmission line structure foundations. Journal of Geotechnical Littlejohn GS, editor. Ground anchorages and anchored structures in service,
and Geoenvironmental Engineering, ASCE 2003;129(9):798e806. Proceedings of the International Conference, London. London: Thomas Tel-
Regenass P, Soubra AH. Limit loads of strip anchors. In: Littlejohn GS, editor. Ground ford; 2007. p. 153e65.
anchorages and anchored structures: Proceedings of the International Confer- Zou DHS. Analysis of in situ rock bolt loading status. International Journal of Rock
ence, London. London: Thomas Telford; 1997. p. 109e18. Mechanics and Mining Sciences 2004;41(Suppl. 1):762e7.
E.T. Brown / Journal of Rock Mechanics and Geotechnical Engineering 7 (2015) 1e13 13

E.T. (Ted) Brown is a graduate of the Universities of Mel- Boards. Professor Brown has wide international experience as a researcher, teacher,
bourne (BE 1960; MEngSc 1964), Queensland (PhD 1969) consultant and writer on rock mechanics and its applications in the mining, civil engi-
and London (DSc(Eng) 1985). He began his engineering neering and energy resources industries. He served as Chairman of the British
career in the then State Electricity Commission of Victo- Geotechnical Society in 1982 and 1983, and as President of the International Society
ria’s brown coal mining operations in 1960. After several for Rock Mechanics from 1983 to 1987. He was elected an International Fellow of
years at what became James Cook University in Townsville, The Royal Academy of Engineering, UK, in 1989, and a Fellow of the Australian Acad-
he joined the staff of the Royal School of Mines, Imperial emy of Technological Sciences and Engineering in 1990. In 2001, he was appointed a
College of Science and Technology, London, in 1975. He Companion in the Order of Australia for “services to the engineering profession as a
was appointed Professor of Rock Mechanics in 1979, and world expert in rock mechanics and to scholarship through promotion of the highest aca-
served as Dean of the Royal School of Mines (1983e1986) demic and professional standards.” He was awarded the Consolidated Gold Fields Gold
and Head, Department of Mineral Resources Engineering Medal of the then Institute of Mining & Metallurgy in 1984; a Centenary Medal by the
(1985e1987). In October 1987, Professor Brown returned Australian Government in 2003 “for service to Australian society in mining and civil en-
to Australia as the University of Queensland’s first full- gineering”; the John Jaeger Memorial Award of the Australian Geomechanics Society in
time Dean of Engineering. He became Deputy Vice- 2004; the President’s Award of the Australasian Institute of Mining & Metallurgy for
Chancellor of the University in October 1990 and Senior Deputy Vice-Chancellor in 2006; the International Society for Rock Mechanics’ highest honour, the Müller Award,
January 1996. Since retiring early from that position in early 2001, he has worked as in 2007; the SME Rock Mechanics Award in 2010; and the Douglas Hay Medal of the
a Senior Consultant to Golder Associates Pty Ltd. and had served on a number of Institute of Metals, Minerals & Mining in 2013.

You might also like