Document Comment Response

Every equipment and its description must be indicated at the The equipment descriptions and details are included on the P&ID.
V-TAL-MEC-00-OC-01-OX-Z-001-0219_00
upper part of the PFD. They are not included as a part of the PFD.
No control loops are shown in the PFD's. All control loops are
V-TAL-MEC-00-OC-01-OX-Z-001-0219_00 Simplified control loops must be shown in PFD's.
provided in the P&ID's.
The venturi and separator are close-coupled. There is no true
V-TAL-MEC-00-OC-01-OX-Z-001-0019_03 Identify this stream and include in the HMB. stream here as the flow goes directly from the venturi into the
separator/sump.
PROYECTO MODERNIZACIÓN REFINERÍA TALARA
UNIDADES AUXILIARES Y TRABAJOS COMPLEMENTARIOS

PROCESS FLOW DIAGRAM


SPENT CAUSTIC THERMAL OXIDIZER

DT-9035191-150 1 1 04
PROYECTO MODERNIZACIÓN REFINERÍA TALARA
UNIDADES AUXILIARES Y TRABAJOS COMPLEMENTARIOS

PROCESS FLOW DIAGRAM


SPENT CAUSTIC THERMAL OXIDIZER
HMB - DESIGN CASE REFINERY GAS FUEL

DT-9035191-151 1 1 04
PROYECTO MODERNIZACIÓN REFINERÍA TALARA
UNIDADES AUXILIARES Y TRABAJOS COMPLEMENTARIOS

PROCESS FLOW DIAGRAM


SPENT CAUSTIC THERMAL OXIDIZER
HMB - DESIGN CASE PSA GAS FUEL

DT-9035191-152 1 1 04
PROYECTO MODERNIZACIÓN REFINERÍA TALARA
UNIDADES AUXILIARES Y TRABAJOS COMPLEMENTARIOS

PROCESS FLOW DIAGRAM


SULFURIC ACID NEUTRALIZATION SYSTEM

DT-9035191-153 1 1 04