RULE 5 - REQUIREMENTS OF without fire-resistivity measures (type 1,2)

FIRE ZONE ⚫ Fire Restrictive Zone - permitted


within prescribed fire-resistivity
Section 501. Fire Zones Defined measures for exterior walls of at least
⚫ Fire Zones - areas within which only two-hour fire resistivity (type 3,4,5)
certain types of buildings/structures ⚫ Highly Fire Restrictive Zone - no less
are permitted to be constructed than three to four-hour fire-resistive
construction materials are used
Section 502. Buildings Located in More throughout, including exterior walls
Than One Fire Zone (type 4,5)
⚫ A building/structure which is located
partly in one (1) fire zone and partly in
RULE 6 - FIRE-RESISTIVE
another (more highly restrictive fire
REQUIREMENTS IN CONSTRUCTION
zone), when more than one third (1/3)
of its total floor area is located in such
Section 601. Fire-Resistive Rating Defined
zone.
⚫ Fire-resistive rating means the degree
Section 503. Moved Buildings to which a material can withstand fire
Section 504. Temporary Buildings/ as determined by generally recognized
Structures and accepted testing methods
⚫ Temporary Buildings - reviewing
Section 602. Fire-Resistive Time Period
stands, sheds, canopies, fences
Rating
⚫ restrictive and highly restrictive zones
⚫ length of time a material can
- permitted for a given period of time
withstand being burned which may be
Section 505. Center Lines of STreets one- hour, two- hours, four- hours, etc.
⚫ The center line of adjoining street or
Section 603. Fire-Resistive Standards
alley may be considered an adjacent
Section 604. Fire-Resistive Regulations
property line. Distances shall be
⚫ The Secretary - testing of construction
measured at right angles to the street
materials for flame-spread
or alley.
characteristics, tests on fire damages,
fire tests of building construction and
Section 506. Restrictions on Existing
materials, door assemblies and tinclad
Buildings
fire doors and window assemblies, the
⚫ Demolished, outside the limits,
installation of fire doors and windows
⚫ Changes, alterations and repairs may
and smoke and fire detectors for fire
be made provided that in any 12-
protective signaling system,
month period, the value of the work
application and use of controlled
does not exceed 20% of the value of
interior finish, fire-resistive protection
the existing building
for structural members, fireresistive
⚫ cost of such repair shall not exceed 20%
walls and partitions, fire-resistive floor
of the replacement cost
or roof ceiling, fire-resistive
Section 507. Designation of Fire Zones assemblies for protection of openings
⚫ Non-Fire Restricted Zone - permitted and fire-retardant roof coverings.
RULE 7 - CLASSIFICATION AND ⚫ Group E - Business and Mercantile
GENERAL REQUIREMENTS OF ALL ➢ Division 1-Gasoline filling and
BUILDINGS BY USE OR OCCUPANCY service stations, storage garages
and boat storage structures
Section 701. Occupancy Classified ➢ Division 2 -Wholesale and retail
⚫ Group A – Residential Dwellings stores, office buildings, drinking
➢ Division 1 - single family and dining establishments (<100)
occupants, single family ➢ Division 3 - Aircraft hangars and
dwellings, churches, church open parking garages
rectories, community facilities, ⚫ Group F - Industrial
parks, playgrounds, pocket parks,  ice plants, power plants,
courts….. pumping plants, cold storage,
➢ Division 2 - exclusive use of non- and creameries, factories and
leasing occupants not exceeding workshops
10 persons, school dormitories, ⚫ Group G - Storage & Hazardous
convents, monasteries, pre- ➢ Division 1 - Storage and handling
schools, elementary and high of hazardous and highly
schools, provided that they do flammable material
not exceed 16 classrooms…. ➢ Division 2 - dry cleaning plants,
⚫ Group B – Residentials, Hotels and paint stores, paint shops
Apartments ➢ Division 3 - wood working
 multiple dwelling units including establishment
boarding or lodging houses, ⚫ Group H - Assembly other than group I
hotels, apartment buildings, row ➢ Division 1- stage and an occupant
houses, convents, monasteries load of less than 1000 in the
and other similar building each building.
of which accommodates more ➢ Division 2- Any assembly
than 10 persons. building without stage and
⚫ Group C – Education and Recreation having an occupant load of 300
 used for school or day-care or more in the building.
purposes, involving assemblage ➢ Division 3- Any assembly
for instruction, education, or building without a stage and
recreation, and not classified in having an occupant load of less
Group I or in Division 1 and 2 or than 300 in the building
Group H Occupancies. ➢ Division 4- Stadia, reviewing
⚫ Group D – Institutional stands, amusement park
➢ Division 1 - inmates structures not included within
➢ Division 2 - Nurseries, hospitals, Group I or in Division 1, 2, and 3
non-ambulatory, more than 5 of this Group.
➢ Division 3 -ambulatory ⚫ Group I - Assembly Occupant Load
Provided, that Group D 1000 or More
Occupancies shall not include buildings used ➢ with a stage and an occupant load
only for private or family group dwelling of 1000 or more in the building
purposes.