Professional Documents
Culture Documents
whatispiping.com/development-of-plant-layout/
Plant layout design means efficiently placing equipment, piping, instrumentation, and
other manufacturing supports and facilities with proper planning during the design
stage to create the most effective plant layout. It is directly related to project costs as
well. The most efficient plant layout has less overall project cost and the most utilization of all
resources.
Table of Contents
The main objective of efficient plant layout design is to design and construct the plant in an
economic fashion that meets all the process requirements and client specifications while
operating in a safe reliable manner. This article provides the basic considerations for the
development of plant layout. For more details on any of the listed points, you can refer to any
standard piping books.
1/11
PRINCIPLES OF PLANT LAYOUT
Refinery
Chemical /Agro Chemical / Petro Chemical / Organic Chemical / Inorganic Chemical
Fertilizer
Pharmaceutical
Metallurgical
Power Generation
2/11
It is used to locate the unit/facility.
The following main aspects shall be considered during the development of the layout.
Process requirement
The economy of piping material and cables
Erection & Construction requirements
Safety requirements.
Operation and Maintenance requirements.
Grouping of similar equipment for the convenience of maintenance & safety wherever
possible.
Non-Plant Facilities
Administrative Block
Canteen
Workshop
R&D, QC Lab, and Pilot Plant
GateHouse/Time office
Security Arrangements
Vehicle Parking
Medical Centre
Ware House
Covered Area
3/11
Open Area
Solid Warehouse
Liquid Warehouse
Steel / Scrap Yard
Fire Station
Weigh Bridge
Staff Colony
Meteorological Data
Process Data
Data on Utilities
4/11
Statutory Requirements and process plant layout
State Industrial Development Corporation (SIDC)
Central / State Environmental Pollution Control Boards (PCBs)
Factory Inspectorate
State Electricity Boards (SEB)
Chief Controller of Explosives (CCOE)
Static and Mobile Pressure Vessel Rules (SMPV)
Tariff Advisory Committee (TAC)
National Fire Protection Association (NFPA)
Aviation Laws
Chief Inspector of Boilers (CIB)
Oil Industry Safety Directorate (OISD)
Food and Drug Administration (FDA)
Ministry of Environment and Forest (MoEF)
Normally Construction is permitted on a maximum of 50% of the plot area with a total
built-up area equal to the area of the plot (i.e. F.S.I. = 1 (Depending upon the regulation
governing the area and the type of industry))
The area reserved for tree plantation shall be 1/3 of the area occupied.
Water storage capacity – 24 hr. minimum.
Domestic water – 100 liters per person per day
Water requirement for Boiler – Steam rating x Working factor
Cooling tower – 11/4 % of capacity as drift and blowdown losses
Washing – 10-15 liters per day per sq. ft. of the floor area of the plant
Gardening – 5 liters per day per sq. ft. of garden area
Parking space – 10% of the plot area
5/11
Main plant road & roads connecting to Plant boundaries, roads for fire fighting access
are 6 meters wide (Min)
Secondary roads 4 meters wide (Min)
The turning radius of the road shall be adequate for the mobile equipment & shall clear
of any obstruction. The minimum turning radius is to be the same as the length of the
vehicle.
The finish of the road i.e. graded or blacktop shall be decided in the beginning while
developing a plot layout.
Paving should be provided around the equipment where spillage is likely to occur. For
example Pumps or machinery, below furnaces or fired heaters, compressors, etc.
Also paving should be provided below the Air fin cooler those are located at grade.
Area handling acids, alkalis, or toxic material shall be paved and bunded. Proper
surface treatment shall be provided for paving to meet the service requirements.
The below sketch (Fig. 1) shows the minimum distance required between the road and the
facility. This distance shall be reviewed on a case-to-case basis for the project.
Fig. 1: Minimum distance required between the road and the facility
Elevations Requirement
Below data for the elevations should be generally followed.
Underside the base plate of Structural steel: Min150 mm. above HP of finished
grade/paving.
Stair or ladder pads: Minimum 75 mm. above HP of finished grade/paving.
Top of Pedestal of Vessel & Tower: Min300 mm. above HP of finished grade/paving.
Top of Pump pedestal: Minimum 200 mm. above HP of finished grade/paving.
6/11
Insulation & Fire Proofing considerations in plant layout
Fireproofing requirements for pipe racks, vessel supports, and process structure should
be considered as these reduce the clearances with access, pipework, instrument &
electrical equipment.
Proper insulation thickness should be considered for pipework & equipment
clearances.
7/11
Relief valve and Flare systems
A closed relief valve system
Self-draining
No pocket to avoid condensation & backpressure.
Flare shall be located upwind process unit & storage.
8/11
Fig. 3: Typical plant layout
HAC Standard
HAZARDOUS AREA: An area in which an explosive gas atmosphere is present, or
maybe expected to be present, in quantities such as to require special precautions for
the construction, installation, and use of apparatus.
NON-HAZARDOUS AREA: An area in which an explosive gas atmosphere is not
expected to be present, in quantities such as to require special precautions for the
construction, installation, and use of apparatus.
Process Requirements
Proper interconnection between equipment to achieve intended process parameters.
Normally equipment is arranged in the process fluid flow sequence. Requirement like
gravity flow (Equipment Drain piping), Thermosyphon system should be considered,
and Limitation of pressure & temperature (process parameters) to be considered
The requirement of upstream and downstream pipe lengths for instruments.
9/11
Hazardous & Toxic fluids shall be identified. (H2S, Cyanide, Methanol, etc.)
Equipment handling hazardous fluids like flares and direct-fired equipment containing
open flame shall be located separately.
Similarly, equipment handling toxic material shall be located with restricted access or in
accordance with local statutory regulations.
Economic Considerations
Equipment shall be located without affecting the process requirement for maximum
economy of pipework & supporting steel with consistent standard clearances,
construction, and maintenance & safety requirements.
Runs of exotic material & large bore piping shall be minimized.
Optimum utilization of the structure to be ensured.
10/11
Fig. 4: Relative locations for area Layout.
11/11