Professional Documents
Culture Documents
Method Study
To simplify the job and develop more
economical methods of doing it
Work
Study
Work Measurement
To determine how long it
should take to carry out
Higher
productivity
1. Introduction to Work Measurement
2) Record – all the required data in the form suitable for time measurement.
3) Analyze – critically to check that effective method and motion are used.
5) Compile – total standard time for the task including the allowances.
6) Define – accurately the activity and method for which the standard time
applies.
1) Select
Why a task may be selected :
◼ New product / component, no time standard is yet available.
◼ Existing product or method but standard time is still not available.
◼ Changes in the task (i.e. material, method) .
◼ Complaints from worker regarding time standard.
◼ Before an incentive scheme based on time or production rate is
introduced.
◼ To identify problems such as bottleneck, high idle time, low production
rate, high operation cost.
How to approach a worker
1. Stopwatch method.
2. Predetermined Time System.
3. Standard time.
4. Activity Sampling
Stopwatch method
◼ Basic equipment required:
Where:
s = sample standard deviation
x = individual readings
x = sample mean
k = acceptable error
t = percentage point of t distribution
Example : Number of observations
Time of element 1 (seconds) xi (xi – x )2
1.02 0.0016
1.32 0.0676
1.08 0.0004
0.99 0.0049
1.04 0.0004
0.96 0.0100
1.18 0.0144
0.90 0.0256
Σx = 8.49, x = 1.061 Σ(xi – x)2 = 0.1249
Using the formula :
At confidence level 95%, error = ± 5%,
n = 2.365 x 0.1335 2
0.05 x 1.06
n = 35.48 = 36 readings.
At confidence level 90%, error = ± 10%,
n = 1.894 x 0.1335 2
0.10 x 1.06
n = 5.7 = 6 readings.
Thus, more readings are required for higher accuracy.
What is Rating?
Standard time
Factors affecting the rate of work:
◼ Outside the control of workers:
i. Variation in quality & characteristics of the material used.
ii. Variation in the efficiency of tools & equipment.
iii. Small variations in the method and condition of the
operation.
iv. Variation in mental attention.
v. Variation in weather and the environment.
◼ Within the control of workers:
i. Acceptable variation in the quality of a product.
ii. Variation due to workers ability.
iii. Variation due to attitude of mind.
British Standard rating scale:
◼ 0% – no activity
Standard rating
1) The average rate at which qualified workers will naturally
work, using the specified method without excessive stress.
2) If this is maintained & the appropriate relaxation is taken, the
worker can maintain this rate of work over the whole working
day or shift.
Rating value :
◼ 100 - if working at normal rate (standard rate).
Standard time
◼ If the rating estimated by a time study analyst is always
right, it does not matter how many times he or she rates and
records the observed time of that element, the results will be
a constant.
Standard time
Allowance
◼ Fixed allowance
1) Personal needs
2) Basic fatigue
◼ Variable allowance
- added to fixed allowance
- amount added depends on the environment and conditions of work.
3. Special allowances
◼ Given for activities that are usually not part of the operation cycle.
◼ Eg. Start-up, shut down, warm-up, set-up and change over.
Standard Time
◼ The total time in which a task should be completed at standard
performance.
OR
1. Snap back
Stop watch is returned to 0 at the start of each
element.
2. Continuous
Stop watch is allowed to keep running until the
end of the study. Time is recorded at the end
of each element. Thus further calculations
need to be done at the end of the observation
to obtain the time for each element.
Example 1 : Standard time (Lift)
Snap back method were used.
Confidence level = 95% , Acceptable error = ±5%
Element Time for each cycle (seconds) Number of observations
1 2 3 4 5 required
1. Wait for lift to arrive 10 9 9 10 10 11
(machine element)
2. Enter & instruct lift 4.5 5 5 4.5 4.8 11
(manual element)
3. Lift operate up/down 10 12 11 10 10.5 22
(machine element)
4. Exit lift 4.6 4.4 5 5 4.8 11
(manual element)
10 12 11 10 10.5 11 11 12 12 10 11
3
10 11 11 11 12 10.5 11 12 11 10 11