Project Cost Management
* Neeraj Sharma
SPO ery Oia cy
¢ Prasansa Shrestha
* Sajeeb ChandWhat is Cost and Project Cost
Management?
Cost is a resource sacrificed or foregone to achieve a specific
objective or something given up in exchange
= Costs are usually measured in monetary units like Rupees,
Cele Ue)
Project cost management includes the processes required to
ensure that the project is completed within an approved budget .It
is also called life —cycle cost.
= Project managers must make sure their projects are well
defined, have accurate time and cost estimates and have a
realistic budget that they were involved in approvingProject Cost Management
preliminary concern with the cost of the resources
needed to complete schedule activities.
Consider the effect of project decisions on the cost of
using, maintaining and supporting the product, service
or result of the project.
Considers the information requirements of the project
stakeholdersOO EVE een
» Acost management plan is a document that describes
how the organization will manage cost variance on the
project
= For example, how to respond to proposals from
suppliers that are higher or lower than estimates
= Alarge percentage of total project costs are often
labor costs, so project managers must develop and
track estimates for labor
= Many organizations estimate the number of
people or hours they need by department or skill
over the life cycle of a projectCost management plan can be
establish as:
Precision level
Units of measure
Organizational procedures links
Control thresholds
Earned value rules
Reporting formats
Process descriptionProject Cost Management Processes
There are three project cost management
processes:
= Cost estimating: developing an approximation or
estimate of the costs of the resources needed to
complete a project
= Cost budgeting: allocating the overall cost estimate
to individual work items to establish a baseline for
measuring performance
= Cost control: controlling changes to the project
budgeteu
DOOD
camer s yd
Sere eect
aggregation
cece
? d cost char
18 Project management planCost Estimating
Cost estimating: developing an approximation or estimate of the costs of
the resources needed to complete a project
Estimating schedule activity costs involves developing an approximation of
the costs of the resources needed to complete each schedule activity.
= Calculate risk
= Identifying and considering various costing alternatives.
LOT etal oe- Uc} aad Cools eR MUR RC Uo mete}
Rupees, Dollars, etc and also can use units of measure such as staff hours
or Staff days along with their cost estimates.
After developing a good resource requirements list, PMs and their teams
must develop several estimates of the costs for these resources.Cost Estimating
» The accuracy of a project estimate will increase as the project
progresses through the project life cycle.
» Arough order of magnitude (ROM) estimate provides an estimate
of what a project will cost.
» Also referred to as a ballpark estimate, a guesstimate, a swag, ora
broad gauge.
» Aproject in the initial phase could have a rough order of magnitude
(ROM) estimate in the range of -50 to +100 %.Cost Estimating
» AROM estimate that actually cost $100,000 would range between
$50,000 to $200,000. The accuracy range is often much wider for IT
projects.
= Often IT project estimates for software development are
doubled because of the history of cost overruns.
Project managers must take cost estimates seriously if they want
to complete projects within budget constraints.
The costs for schedule activities are estimated for all resources that
will be charged to the project which is not limited to labor,
materials, equipment, services, and facilities, as well as special
categories such as inflation allowance or a contingency cost.Inputs / Tools & Techniques / Outputs
icy Tools & Techniques feet)Cost Estimation Inputs
Beer iM eee ele
EVA a a -Comerolsco | ola aeatal- Ny Me) RNA kel0l0 (ol oR Le
and results are available in the market place, from whom
and under what terms and conditions.
terol ul co MPIC lel ea ool fe Roe MIU}
available from commercial database that tracks skills and
TUM ecelU ero coreoe
Published seller price listsCost Estimation Inputs
» Organizational Process Assets
= Cost estimating policies. Some organizations have
predefined approaches to cost estimating. Where these
exist, the project operates within the boundaries defined by
these policies.
= Cost estimating templates. Some organizations have
developed templates (or a pro forma standard)
The organization can continuously improve the template
based on its application and usefulness in prior projects.Cost Estimation Inputs
Historical information. Information that pertains to the project's
product or service, and is obtained from various sources within the
organization, can influence the cost of the project.
Project files. One or more of the organizations involved in the
project will maintain records of previous project performance that
are detailed enough to aid in developing cost estimates.
Project team knowledge. Members of the project team may recall
previous actual costs or cost estimates. While such recollections
can be useful, they are generally far less reliable than documented
performance.Cost Estimation Inputs
Lessons learned: cost estimates obtained from previous projects
that are similar in scope and size.
» Project Scope Statement
Describes the business need, justification, requirements, and
current boundaries for the project.
The project scope statement includes constraints, assumptions,
and requirements. Constraints are specific fovea (eln teers
estimating options.
Most common constraints for many projects is a limited project
budget, required delivery dates, available skilled resources, and
organizational policies.Cost Estimation Inputs
» Work Breakdown Structure:
= The project's work breakdown structure (WBS) defines the total
scope of the project.
= WBS is often used to develop or confirm a common
understanding of project scope.
WBS Dictionary
The WBS dictionary (Section Shean and related detailed
statements of work provide an identification of the deliverables and
a description of the work in each WBS component required to
produce each deliverable.
dey eMC i eo)
The project management plan (Section 4.3) provides the overall
plan for executing, monitoring, and controlling the project, and
includes subsidiary plans that provide guidance and direction for
n anninCost Estimation Inputs
emer M Uitte (Ut 1
= Schedule activity resources and their respective duration.
= Activity Resource Estimating involves determining the
availability and quantities required of staff, equipment, and
materiel needed to perform schedule activities.
= Activity Duration Estimating involves determining the total
Ele AUR AMMO R- Ura mees as tCoeCost Estimation Inputs
» Staffing management plan
= when and how human resource requirements will be brought
and taken off the project team.
ae 19 |) em Reed) ors) aL eTo EMAL OO
responses when producing cost estimates. Risks, which can be
either threats or opportunities, typically have an impact on both
schedule activity and project costs. As a general rule, when the
project experiences a negative risk event, the cost of the project will
nearly always increase, and there will be a delay in the project
schedule.Cost Estimation Tools and Techniques
Analogous or top-down estimates: use the actual cost of a
previous, similar project as the basis for estimating the cost of the
current project
= How similar the current and previous project are determines the
accuracy of the estimate.
Bottom-up estimates or Activity Based Costing : involve
estimating individual work items or activities and summing them to
get a project total cost.
= The smaller the work items, the better the estimate but these
estimates are usually time intensive and expensive to develop.Cost Estimation Tools and Techniques
Bee UUme ie 9
= Atechnique that uses a statistical relationship between
historical data and other variables e.g. square footage in
construction, required labor hours.
= Higher lever of accuracy
» Project Management Software
= PM software, such as cost estimating software applications,
computerized spreadsheets, and simulation and statistical tools,
are used to assist with cost estimating.
= Such tools can simplify the use of some cost estimating
= Provides various cost estimate alternatives.Cost Estimation Tools and Techniques
» Vendor Bid Analysis
= methods include vendor bid analysis and an analysis of what
the project should cost.
= Incases where projects are won under competitive
processes, additional cost estimating work can be required
of the project team to examine the price of individual
deliverables, and derive a cost that supports the final total
project cost.Cost Estimation Tools and Techniques
» Reserve Analysis
= Many cost estimators include reserves, also called contingency
Eells
= Contingency reserves-costs to be used at the discretion of the
project manager to deal with anticipated, but not certain, events
(o-1| (To alo aM La cule)
Cost of Quality
= Total costs incurred by investment in preventing non standard to
requirements,
Appraising the product or
requirements,
and failing to meet requirements (rework).
Failure costs are often categorized into internal and external.
Failure costs are also called cost of poor quality.
service for conformance toCost Estimating: Outputs
» Activity Cost Estimates
= An activity cost estimate is a quantitative assessment of the
likely costs of the resources required to complete schedule
activities.
Costs are estimated for all resources like labor, materials,
equipment, services, facilities, information technology, and
special categories such as an inflation allowance or cost
contingency reserve.
» Activity Cost Estimate Supporting Detail includes
* Description of the schedule activity’s project scope of work
CoB yeler annie ela Re lm om erm Om Rl e (R-e ged
developed)
CMB ole lan nc ole melm-laN meron lira)
+ Indication of the range of possible estimatesCost Estimating: Outputs
» Requested Changes
The Cost Estimating process may generate requested changes
(Section 4.4.3.2) that may affect the cost management plan
(Chapter 7 introductory material), activity resource requirements
(Section 6.3.3.1), and other components of the project management
plan. Requested changes are processed for review and disposition
through the Integrated Change Control process (Section 4.6).
Cost Management Plan (Updates)
If approved change requests (Section 4.4.1.4) result from the Cost
Estimating process, then the cost management plan component of
the project management plan (Chapter 7 introductory material) is
updated if those approved changes impact the management of
olehCost Budgeting
Cost budgeting involves allocating the project cost estimate to
individual work items over time
» The WBS is a required input to the cost budgeting process
since it defines the work items
» An important goal is to produce a cost baseline
= Atime-phased budget that project managers use to measure and
monitor cost performance
= Estimating costs for each major project activity over time provides
management with a foundation for project cost control
= Cost budgeting also provides info for project funding requirements
a= V Var Leal MMA AML UA MOA) LMI 10 <1Inputs / Tools & Techniques / Outputs
ey | Tools & Techniques ) cette}Cost Budgeting: Inputs
Drege ee cuca
Formal periodic limitations of the expenditure of project funds can be given in the
OUR Cm meen oem -Ced Mile teks Ce Rel ret RLEUTN el toe
eet Cuan Keane Men ea alee rez Un os
Piecing kegel uae Seale keane ucae
eT) eeu at
The project work breakdown structure (WBS) provides the relationship among all the
components of the project and the project deliverables
WBS Dictionary The WBS dictionary and related detailed statements of work
provide an identtication ofthe deliverables and a description of the work in each
Eten enue Nicer ones tect eine NeesCost Budgeting: Inputs
ee g cry
Desa ae usage eC ARs sce reir)
octet echoes ects
Pee eee et rT
Rue Uh, Roe Onur eee oun Roe on gen
Se COR ae Ree ORI Rec iaani!
Peete eae Cmca Ku eter sae
Ree sheen Cuan)Cost Budgeting: Inputs
Deer
Bi io een Tae tuners U Me Maun
the project's schedule activities, schedule milestones, work packages, planning
OCC MMe use cco CMON IC uneMeee eit kee oCN UI
calendar periods when the costs are planned to be incurred.
eee eee
Le eee Rei mun eee etna eR Ve
Te CCAR Coun amet cline
UAW ocleLe AOL L-com Cea eae oeCost Budgeting: Inputs
(eerie
Cen aOR RES ccee eso
et Ol ee coun tise ce eee ake eee nee Rane eaten
Piers
era Cur ago)
SERS TU USUI a euReu u Cem uel aC eauCueC Cucne eueU Rue
Btctc lena use iReousie eek Mute Reca teersCost Budgeting: Tools and Techniques
Bee ec
Soret eget clu Cc creel er cc mUanes rc aie erected
Prank SMR ne tee Reece cine Corian ane ieee crema ie
Ce eu nun eee icra centaur Mam
Sree ge
fee ae Uy
Beene usc ar amc RUC
management contingency reserve, that are allowances for unplanned, but
POCRn AC i Rencue eect te cue ee meet me st ee nUry
Fi core Colm Ur LU MLO LAT? Lie CoN eRe mo) Cee (ol Roo ROMA) OL ULLaI ore
PMie acinar Meru Seen Ie) eacec a arKocitCost Budgeting: Tools and Techniques
Parametric Estimating
BO ee Senge MA a ares Case Cac ey
(eae CS REA Cemuee Rl ate [ea Cit ere tees cm ee Rene
simple (e.g., residential home construction will cost a certain amount per square
eae moos ak es Re uae
eee teaser Cr eae eee aCe Okano
PROMS unu keen Reels ecieutteauee ek SAT Nanny
most likely to be reliable when:
See eae euch OR Res ee
eee nue Ime Reta
cise anc ae eerie Oct koe rnr |
eeCost Budgeting: Tools and Techniques
» Funding Limit Reconciliation
Large variations in the periodic expenditure of funds are
usually undesirable for organizational operations. Therefore,
the expenditure of funds is reconciled with the funding limits
set by the customer or performing organization on the
disbursement of funds for the project. Reconciliation will
necessitate the scheduling of work to be adjusted to smooth
or regulate those expenditures.Rescheduling can impact the
allocation of resources.Cost Budgeting: Output
aT
The cost baseline is a time-phased budget that is used as a basis against which to
TUUTcroTOCCPMLUL ACARI MOCO COR) URL SS18 110M US ROL Se Ce) oe OC ele
baseline is a component of the project management plan
Pres atar at Ba tee
Funding requirements, total and periodic (e.g.. annual or quarterly), are derived from
koa eo rurkcur esc ica knoe mitc ae Murer a Cg
Cae aad lil eee eR era RRL eu
EU eMule Mae meela vel oMe- Ue REC ele seer EPR nine (emmy
ERMC Umum CRIs Eesinn tea mueurecacutg
Cen ie USa Sat atCost Budgeting: Output
bea CTT uae)
If approved change requests result from the Cost Budgeting process, then the cost
RUEeCna una ear Koma CMa a eunee- Cen anc
EEC Rcue Cone Cmur neue ecm RmS
Peete Rural ey
Ske ae te eiued yee eet Wie inet cee Ren ueeCRUr ee Ceaaeteces
UCU UReIR UUme CoC R RUN UO Come eM cre crt)
changes are processed for review and disposition through the Integrated Change
Control process.Cost Control : Change is inevitable, success is
ya CU eT
» Project cost control includes:
Monitoring cost performance
Ensuring that only appropriate project changes are included ina
revised cost baseline
Recording all appropriate changes accurately against the cost
eet
Preventing incorrect, inappropriate, or unapproved changes from
eing
included in the reported cost or resource usage
Informing project stakeholders of authorized changes to the
project that will affect costs
Acting to bring expected cost overruns within acceptable limitsCost Control
ALSO
» Performance review meetings can be a powerful
tool to help control project costs
= Knowing you have to report on your progress is an
incentive for people to perform better
» Performance measurement is another important
tool for cost control
= There are many general accounting approaches for
measuring cost performance but earned value
ie eam M ae Roe ied (MUL ltCost Control
Project cost control searches out the causes
of positive and negative variances.
For example, inappropriate responses to cost
variances can cause quality or schedule
problems or produce an unacceptable level of
risk later in the project.Cost Control
BOC. Mr rd Outputs
4 Cost change 4 Cost estimate (updates)
stem :2 Cost baseline (updates
2 Performance measurement 3 Performance
4 Fo completion
5 Requested changes
roved change re ‘6 Recommended
5 Project management corrective actions
ganizational process
2 Project funding
requirements
3 Performance
information 4 Project performance
que
66 Project manage oftware
plan’ 5 Variance management assets (updat
8 Project management
plan (updates)Earned Value Management (EVM)
EVM is a project performance measurement technique that
integrates scope, time, and cost data
Given a baseline (original plan plus approved changes), you
can determine how well the project is meeting its goals
You must enter actual information periodically to use EVM
= Was a WBS item completed or approximately how much of the
work was completed
= Actual start and end dates
Peeve 19
More and more organizations around the world are using
EVM to help control project costsBest Practice
» The most successful organizations are
taking a holistic view of focusing, managing
and measuring their organizational efforts
with an integrated combination of best
practice processes, training and technology
= Unfortunately, most organizations today are not
taking that approachTHANK YOU