You are on page 1of 15

Automation in Construction 152 (2023) 104935

Contents lists available at ScienceDirect

Automation in Construction
journal homepage: www.elsevier.com/locate/autcon

Review

Integration of BIM and Value Model for Sustainability Assessment for


application in bridge projects
F. Lozano a, *, J.C. Jurado b, J.A. Lozano-Galant a, A. de la Fuente c, J. Turmo c
a
Dept. of Civil and Building Engineering, Universidad de Castilla La Mancha, 13071 Ciudad Real, Spain
b
Dept. of Civil Engineering, Universidad Politécnica Salesiana de Cuenca, EC010102 Cuenca, Ecuador
c
Dept. of Civil and Environmental Engineering, Universitat Politècnica de Catalunya BarcelonaTech, 08034 Barcelona, Spain

A R T I C L E I N F O A B S T R A C T

Keywords: The integration of multicriteria decision-making (MCDM) methods with building information modeling (BIM)
MIVES provides robust support for decision-making when assessing the sustainability of construction projects. Among
MCDM the MCDM methods, the Integrated Value Model for Sustainability Assessment (MIVES) has proven to provide a
BIM
representative and meaningful quantification of sustainability in different areas of civil engineering. Although
Sustainability
previous studies have integrated BIM and MIVES, none automated the sustainability assessment process as BIM
Bridge
Assessment was only used to define the measurements of the MIVES indicators. This study accordingly developed a new
method coupling the MIVES and BIM methodologies to realize automatic sustainability assessment of bridges.
The proposed technique was validated using a real viaduct to evaluate sustainability and conduct a sensitivity
analysis identifying the indicators with the most influence on sustainability performance. Critically, this meth­
odology is not limited to the sustainability assessment of bridges as it can be readily adapted to other types of
infrastructure.

1. Introduction may be challenging to conduct and subject to uncertainties that are


difficult to identify and quantify in the design stage [1] [2]. Life-cycle
The Sustainable Development Goals (SDGs) established by the in­ assessment (LCA) methods have traditionally been employed to facili­
ternational community in 2015 provide benchmarks for achieving tate bridge sustainability analyses. These methods are typically based on
human development without compromising the abilities of future gen­ the application of multicriteria decision-making (MCDM) and include:
erations. One of the key aspects of these goals refers to the sustainability (1) the Building Research Establishment Environmental Assessment
assessment of civil engineering projects, which are not only essential for Method (BREEAM) [3], which defines the standards for the environ­
the social and economic development of society but also have major mental performance of infrastructure and building projects throughout
impact on the environment. This impact is particularly evident in bridge their different life-cycle stages; (2) the Leadership in Energy and Envi­
engineering applications. ronmental Design (LEED) method [4], which provides a certification
The influence of the SDGs on bridge engineering is illustrated in program and international reference point for high-performance sus­
Fig. 1, which presents the evolution of publications available on the tainable building design, construction, and operation; (3) the German
Scopus database that have analyzed the sustainability of bridges since Sustainable Building Council (DGNB in German) evaluation process [5],
2000. In this figure, the research published in 2022 is estimated by which considers the environmental, economic, socio-cultural, and
interpolating the number of works published up to September of that functional aspects of buildings; (4) the Civil Engineering Environmental
year. Quality Assessment and Awards Scheme (CEEQUAL) [6], which pro­
The analysis in Fig. 1 indicates a growing interest in the application vides a sustainability assessment methodology for all types of civil en­
of sustainability quantification methods to bridge design and construc­ gineering, infrastructure, landscaping, and public sector projects and
tion over the last decade. contracts; and (5) the Integrated Value Model for Sustainability
Sustainability assessments of bridges are not easy because they Assessment (MIVES) method [7], which defines a series of global sus­
require the analysis of economic, environmental, and social issues that tainability indexes to minimize the subjectivity associated with the

* Corresponding author.
E-mail address: fidel.lozano@alu.uclm.es (F. Lozano).

https://doi.org/10.1016/j.autcon.2023.104935
Received 19 December 2022; Received in revised form 8 May 2023; Accepted 9 May 2023
Available online 24 May 2023
0926-5805/© 2023 The Authors. Published by Elsevier B.V. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-
nc-nd/4.0/).
F. Lozano et al. Automation in Construction 152 (2023) 104935

relevant indicators [8]. Table 1


A comparative analysis of the primary characteristics of these sus­ Comparison analysis of the main characteristics of sustainability methods.
tainability assessment methods is summarized in Table 1 in terms of the Adapted from [8].
name of the MCDM method; country and year of origin; economic re­ MCDM Country, year C E S Results scale References
quirements, denoted as C (cost, time); environmental requirements, Method
denoted as E (carbon footprint, energy consumption); social re­ BREEAM, [3] UK, 1990 – X L Unclassified [8–11]
quirements, denoted as S (social, health); explanation of the result scale; (<30%)
and references to examples of applications. For the economic, environ­ Pass (≥30%)
Good (≥45%)
mental, and social factors in this table, “X” indicates that the factors are
Very Good
directly considered, “L” indicates that they are given low consideration, (≥55%)
and “–“indicates they are not considered. Excellent (≥70%)
The comparison presented in Table 1 indicates that most of the Outstanding
identified MCDM methods incorporate economic, environmental, and (≥85%)
LEED, [4] USA, 2000 L X L Certified (40–49) [12–15]
social aspects. The table also presents the differences in the assessment Silver (50–59)
criteria and result scales of the various methods. On the one hand, Gold (60–79)
BREEAM, DGNB, and CEEQUAL provide the results on a percentage Platinum (80+)
scale; on the other hand, the LEED and MIVES methodologies provide DGNB, [5] Germany, X X X Bronze (<35%) [16–19]
2008 Silver (≥50%)
the results as numbers on scales of 40–100 and 0–1, respectively.
Gold (≥65%)
In contrast to most of the MCDM methods listed in Table 1, MIVES is Platinum (≥80%)
not restricted to the analysis of buildings and can be easily applied to CEEQUAL, UK, 2015 X X X Unclassified [20–23]
diverse engineering fields [28]. The versatility of this methodology is [6] (<30%)
illustrated in Table 2, which provides examples of relevant studies in Pass (≥30%)
Good (≥45%)
different engineering fields published in the Scopus database along with
Very Good
details of their objectives and the corresponding references. (≥60%)
The information presented in Table 2 confirms that the MIVES Excellent (≥75%)
method has been applied to engineering fields including energy, urban Outstanding
(≥90%)
planning, buildings, building systems, and infrastructure. Among the
MIVES, [7] Spain, 2015 X X X [0,1] [24–27]
most studied topics in the MIVES research literature are electric gener­
ation systems, structural solutions, construction procedures, facades, For the Economic (C), Environmental (E), and Social (S) requirements, X means
and general sustainability quantification. Thus, the flexibility and included, L means low consideration and – means not included.
adaptability of the MIVES approach to any type of sustainability prob­
lem can be considered its primary benefits. Indeed, the indicators and sequence coordination, visualization, productivity, and error reduction.
weights employed in this methodology can be adapted to the particu­ These benefits have motivated the promotion of BIM in the public ten­
larities of any problem under study while considering stakeholder ders of civil engineering and architectural projects in a growing number
sensitivities. of countries worldwide. Notably, this interest is not limited to the design
Building Information Modeling (BIM) is among the most promising phase, as BIM can be applied during all life-cycle stages of a project,
methodologies for evaluating the sustainability of projects in the including operation and maintenance.
architectural, engineering, and construction industries [97]. This Tan et al. [102] emphasized the need for more research to facilitate
collaborative approach enables the digital management of civil infra­ interoperability between MCDM and BIM techniques. In fact, most
structure and buildings throughout their life cycle [98] and facilitates works in the literature today base interoperability with BIM models on
the cooperation of all stakeholders involved in the project (owners, ar­ data transfer formats such as Industry Foundation Classes (IFC) and
chitects, engineers, contractors, subcontractors, and suppliers) using a Construction Operations Building Information Exchange (COBie). The
common 3D virtual model of the structure [97]. The objects in this IFC file format is an open, neutral, and standardized data model that
model are represented by parameters capturing a diverse range of allows the exchange BIM models between different software applica­
required information (e.g., Hull and Ewart [99] introduced conservation tions. This format includes a standardized set of object and property
data parameters into BIM models for heritage asset management). definitions, as well as relationships between these objects, that can be
Furthermore, the BIM model can be connected to databases that contain used to represent different aspects of a digital model. Examples of the
information describing the elements required by the different disciplines IFC's application include Kim et al. [103], who proposed a semantic
involved in a project [100]. A literature review of the primary benefits of web-based information approach for facility management using IFC
BIM presented in [101] highlights those associated with scheduling, objects, Alavi et al. [104], who presented a data model to integrate the

Fig. 1. Evolution publication in Scopus database studying sustainability in bridges.

2
F. Lozano et al. Automation in Construction 152 (2023) 104935

Table 2 BIM databases and improve the design process for domestic drinking-
Examples of the application of MIVES methodology in different fields. water and sewerage systems, and Castañeda et al. [115] developed a
Sector AIM Reference BIM-based traffic analysis method for road intersection design. Second,
BIM facilitates the collection, categorization, modification, updating,
Energy Urban electric mobility [29]
Electricity generation systems [30–34] and analysis of project information, which is crucial to enable connec­
Wind towers [35,36] tions with the information required by the different disciplines [116] as
Shell and tube heat exchanger [37] well as with different decision-making parameters [117]. Finally, the
Urban Sewerage pipe system [38] BIM methodology provides information management and exchange
Post-disaster in urban areas [39,40]
Urban-pavement conditions [41]
between the different disciplines involved in a project. For example,
Solid waste incinerator [42] Deng et al. [118] reviewed the evolution of BIM in construction industry
Development of cities [43] information management, Cursi et al. [119] solved interoperability is­
Buildings Industrial buildings [44,45] sues by introducing external knowledge into heritage BIM, and Schi­
Educational buildings [46,47]
manki et al. [120] studied the functional requirements for integrating
Prefabricate buildings [48,49]
Residential buildings [50–52] BIM using a lean construction approach.
Facilities [53–55] Many researchers have accordingly studied the integration of MCDM
Building systems and elements Structural solutions [56–60] and BIM methodologies. A literature review on this topic was recently
Construction procedures [28,61–64] presented in [121], which considered 45 papers to illustrate how the
Façades [65–70]
Steel fibers [71–73]
integration of MCDM and BIM can provide a robust approach for the
Infrastructures Railway [74] decision-making processes associated with performing multicriteria
Tunnels [75–77] analysis, developing full BIM functionality, designing synergistic ap­
Roads [78,79] proaches for target problems, adapting data collection methods, opti­
Retaining tanks [80]
mizing information management, etc. The evolution of publications in
Others General sustainability evaluation [81–85]
Instruction [86] the Scopus database linking the MCDM methods listed in Table 1 to BIM
Developing countries [87,88] is shown in Fig. 2.
Heritage [89,90] The analysis presented in Fig. 2 indicates that the connection of the
Public investments [91] LEED analysis methodology with BIM has received the most attention,
Educational innovation [92–94]
accounting for 54% of reviewed studies (53 of 98). Furthermore, only
Goods routes [95]
Risk of robbery [96] three of the MCDM methods listed in Table 1 (LEED, BREEM, and DGNB)
have been connected with BIM in the literature. However recent pub­
lications have expressed interest in connecting MIVES and BIM,
building condition risk assessment model into BIM, Alavi et al. [105], including Zolfaghari et al. [122], who proposed connecting the MIVES-
who used IFC files to integrate probabilistic occupants' comfort, Delphi model with expert seminars, on-site surveying, LCA, BIM, expert-
Sheikhkhoshkar et al. [106], who used IFC files to facilitate automated based questionnaires, bias reduction, and sensitivity analyses to
concrete joint positioning solutions, Chen et al. [107], who built IFC construct a sustainability assessment model for evaluating the interior
objects for a MCDM method, and Xun et al. [108], who used IFC files and rehabilitation of mass housing. In this approach, the BIM model was
Dynamo programming to incorporate monitoring data in a MCDM used to extract the values of certain indicators (such as rehabilitation,
process. maintenance, and demolition costs); however, the sustainability analysis
On the other hand, COBie is a structured semantic data format used was not automated within the BIM model. The same limitation can be
for sharing information among stakeholders involved in the design, identified in other studies connecting MIVES and BIM found in Google
construction, and operation of an asset. This format facilitates the ex­ Scholar, including the master theses of Jurado [123], Granoble [124],
change of data related to equipment, warranties, and maintenance and Veiskarami [125]. The objective of this study was therefore to
schedules and is widely used for facility management of buildings (see e. develop a new automatic method combining MIVES and BIM to assess
g. [109–111]). While this standard is commonly used in the building the sustainability of bridge projects. The proposed technique is based on
industry, it is less frequently applied in civil engineering, and fewer 11 economic, environmental, and social indicators and was validated
examples can be found. An example of COBie's application in this field is using the information for a real viaduct project under different sus­
Shin et al. [112], who proposed a BIM-based maintenance tool for port tainability scenarios. In addition, a sensitivity analysis was conducted to
facility management using the COBie format. The proposed methodol­ identify the most sensitive indicators of sustainability performance. In
ogy was stated to be applicable to civil engineering assets that require this methodology, all sustainability analyses were automatically per­
maintenance, such as roads and bridges. formed using the quantity tables and internal operators provided in the
Both IFC and COBie files are compatible with a wide range of soft­ Revit BIM software. Furthermore, the Dynamo parametric programming
ware applications, but not with MIVES, which is designed to work only tool was applied to automate the introduction of MIVES information into
with MIP, MIU, and MTR as input file formats. While it may be possible the BIM model. Critically, the proposed methodology is not limited to
to develop a third-party tool to convert IFC and COBie data into a format the sustainability assessment of bridges owing to the straightforward
that MIVES can read, the authors are not aware of the existence of such a adaptability of the coupled MIVES-BIM method to other assessment
tool. Moreover, there are no previous works in the literature that have targets.
automatically connected MIVES with these BIM formats. The remainder of this paper is organized as follows. In Section 2, the
The major benefits expected from the connection of BIM to MCDM proposed methodology is described according to the different steps
include database development, information processing, and information required to apply the MIVES method using BIM, including the use of
management [102]. First, BIM enables the connection of the geometric parametric algorithms to automatically extract the information required
and non-geometric information required by stakeholders using different for bridge sustainability assessments. In Section 3, a case study is pre­
virtual elements to develop advanced databases. Much of this informa­ sented to illustrate the step-by-step application of the proposed meth­
tion, including geometrical dimensions, requirement data, standards, odology to a real structure: Las Arenas Viaduct in Spain. Finally, the
existing documentation, and expert knowledge, plays a key role in primary conclusions of this study are presented in Section 4.
MCDM. For example, Collao et al. [113] linked databases contained in a
pdf describing vehicle emissions to BIM models to estimate the carbon
footprint of roads, Atencio et al. [114] developed algorithms to connect

3
F. Lozano et al. Automation in Construction 152 (2023) 104935

Fig. 2. Evolution of the publications connecting MCDM methods (LEED, BREEM and DGNB) with BIM methodology from 2009 to 2022 in Scopus Database.

2. Sustainability assessment methodology decision-making process is accomplished based on the following steps
[28]:
This section describes the proposed methodology for the sustain­ Step 1: Define the problem and the required decisions.
ability assessment of bridges. The theoretical background of the MIVES Step 2: Define the decision model, including qualitative and quan­
method is detailed, its application to the sustainability assessment of titative variables and the requirements of the problem. This information
bridges is discussed, and the proposed parametric methodology for is organized using a decision-making tree, such as that shown in Fig. 3.
integrating MIVES with BIM is derived. This tree hierarchically organizes the characteristics of the parameters
according to their requirements, criteria, and indicators (both quanti­
2.1. MIVES method tative and qualitative). According to [126,127], the indicators intro­
duced into the decision-making tree must be representative,
The objective of the MIVES method is to assess the process of discriminant, complementary, relative, quantifiable, precise, and
deciding between different alternatives based on a multicriteria anal­ traceable.
ysis. Under this approach, the Analytic Hierarchy Process (AHP) is used Step 3: Define the value functions to add homogeneity to the vari­
to integrate the hierarchical relations between the different parameters ables by transforming them to common, non-dimensional units called
of the decision-making tree and prioritize the decision-making frame­ value functions (V). The value function for each ith indicator (Vi) rep­
work [126]. In contrast to other MCDM methodologies, MIVES is based resents the preference for a certain alternative and varies between the
on a specific holistic tree of requirements that employs weights and minimum (Pmin = 0) and maximum (Pmax = 1) satisfaction levels. The
value functions to obtain homogeneous nondimensional comparison value Vi, can be obtained as follows:
units [7].
To evaluate solutions from the economic, environmental, and social
perspectives, MIVES provides a sustainability index (SI) value ranging
between 0 and 1; the calculation and use of this index during the

Fig. 3. Decision-making tree for the MIVES methodology (adapted from [28]).

4
F. Lozano et al. Automation in Construction 152 (2023) 104935

⎡ ( ) Ai ⎤ requirements. Thus, the decision tree includes three requirements


|Pi,x − Pi,min |
− mi ni (economic, R1, environmental, R2, and social, R3), six criteria (cost, C1.1,
Vi = Ki ⎣1 − e ⎦ (1)
time, C1.2, emissions, C2.1, resources, C2.2, social indices, C3.1, and safety,
C3.2), and eleven indicators, defined as follows:
where ni is the value used; mi is the value of the ordinate ni; Ai is the
- Total cost, I1.1.1 [€/m2]: This indicator refers to the final price of the
shape factor of the ith indicator value function (Ai < 1 indicates a
product obtained considering the labor, material, machinery,
concave shape, Ai = 1 a linear shape, and Ai > 1 a convex or S-shape); Pi,
equipment, and tool costs. It depends on the construction typology,
min and Pi, max denote the minimum and maximum values of the ith in­
proposed structural solutions, and materials chosen for the project. A
dicator, respectively; Pi,x is the score of the alternative x under assess­
decreasing S-shaped function can be applied to evaluate this
ment with respect to the ith indicator under study; and Ki is a factor used
indicator.
to ensure that the value of Vi is bounded between 0 and 1 and can be
- Indirect cost, I1.1.2 [%]: This indicator includes the costs of indirect
calculated as follows:
activities (such as operations, financing, construction systems, tests,
⎡ (
|Pi,max − Pi,min |
) Ai ⎤
− 1 and controls) that cannot be directly related to the work performed.
− mi ni It can be evaluated using a decreasing convex function.
Ki = ⎣1 − e ⎦ (2)
- Maintenance cost, I1.1.3 [€/m2]: This indicator includes the cost of
maintenance actions or operations (such as administrative costs,
where the parameters ni, mi, and Ai are fixed according to the prefer­ labor, spare materials and their storage, equipment rental, and en­
ences of the decision maker. Typical values for the increasing and ergy consumption). It is related to the materials and structural ty­
decreasing functions of these parameters can be found in [28]. pology used in the project. A decreasing S-shaped function can be
Step 4: Define the importance of each aspect to be considered in the applied to evaluate this indicator.
assessment. As shown in Fig. 3, this importance is assigned using relative - Dismantling cost, I1.1.4 [€/m2]: This indicator refers to the demolition
weights for each requirement (αi), criterion (βi), and indicator (γi) in and/or deconstruction costs of superstructure elements. This indi­
each branch of the requirements tree. The assignment of these weights cator has been evaluated using a decreasing S-shaped function.
can be determined either directly or through an AHP-based on a pair­ - Execution time, I1.2.1 [d]: This indicator refers to the time necessary
wise comparison of all elements [7]. The weights presented in Table 3 for each activity in the project execution plan. It can be evaluated
are traditionally considered to indicate the importance of different using a decreasing S-shaped function.
variables. This table includes the weight values, ranging between 1 and - Emissions indicator, I2.1.1 [kg CO2eq/m2]: This indicator refers to the
9 (even numbers can be considered intermediate values), definitions, carbon dioxide emissions generated by the materials employed in the
and explanations of the weight values. structure. It can be evaluated using a decreasing S-shaped function.
Step 5: Define the different alternatives for the proposed problem - Raw material consumption, I2.2.1 [kg/m2]: This indicator considers
and evaluate their parameters. the quantities of construction materials used. It can be evaluated
using a decreasing S-shaped function.
Step 6: Evaluate the defined alternatives by studying their SI values,
- Energy consumption, I2.2.2 [MJ/m2]: This indicator refers to the
which can be calculated as follows:
energy required to produce the construction materials used, such as
∑i=n ( ) concrete and steel. It can be evaluated using a decreasing S-shaped
SI = V (Px ) = αi ⋅βi ⋅γi ⋅Vi Pi,x (3)
i=1
function.
- Affected areas, I3.1.1 [m2]: This indicator represents the space
where V(Px) measures the degree of sustainability (value) of each of the
required for construction and depends on the materials and con­
defined alternatives with respect to a set of criteria Pi,x, and parameters
struction techniques employed. It can be evaluated using a
αi, βi, and γi refer to the weights of the requirements, criteria, and in­
decreasing concave-shaped function.
dicators, respectively, described in Step 4.
- General disturbances, I3.1.2 [points]: This indicator is based on the
Step 7: Compare the SI values of the defined alternatives to select the
evaluation of the different types of disturbances generated by third
most appropriate alternative (that with the highest SI).
parties and can be defined using the methodology proposed in [56],
where points are assigned to three different types of nuisances: noise,
2.2. Application of MIVES to evaluate the bridge sustainability transit, and traffic. An increasing concave-shaped function can be
applied to evaluate this indicator.
In this section, the MIVES methodology presented in Section 2.1 is - Health and safety during construction, I3.2.1 [index value]: This in­
adapted to address the specifics of bridge sustainability. The proposed dicator evaluates safety and health during construction using the
decision-making tree is illustrated in Fig. 4, in which the different Occupational Risk Index (ORI) [128]. It can be evaluated using a
criteria and indicators are named according to their corresponding decreasing concave function.

Table 3
Weight scale considered for MIVES (adapted from [7]). 2.3. Integration of BIM to automatically evaluate bridge sustainability
Weight Definition Explanation
value This section presents the connection of MIVES to BIM using the
1 Equal importance Two activities contribute equally to the
following steps to automate the calculation of SI:
objective
3 Moderate importance of Experience and judgment slightly favor - Step 1: Analysis of the problem. Information describing the bridge
one over another one activity over another project to be modeled using BIM is reviewed together with the
5 Essential or strong Experience and judgment strongly favor
definition of the problem. Examples of this information include: (1)
importance one activity over another
7 Very strong importance An activity is strongly favored, and its geometrical information such as location, dimensions of the different
dominance demonstrated in practice elements, and areas affected during construction, all of which can be
9 Extreme importance The evidence favoring one activity over obtained directly from drawings (e.g., in the AutoCAD software); and
another is of the highest possible order of (2) information from the BIM database required for sustainability
affirmation
assessment, specifically the primary characteristics of the materials,

5
F. Lozano et al. Automation in Construction 152 (2023) 104935

Fig. 4. Decision-making tree for the application of the MIVES methodology to study the bridge sustainability.

construction process, and different costs (direct, indirect, mainte­ - Step 2: Definition of the MIVES information. The following infor­
nance, and dismantling). mation is defined: (1) the MIVES decision-making tree, including the
considered sustainability requirements, criteria, and indicators as

Fig. 5. Example of the Dynamo script used to read the one parameter from Excel including references to the steps followed.

6
F. Lozano et al. Automation in Construction 152 (2023) 104935

well as their weights (α, β, and γ); and (2) indicator information, describe the primary characteristics of the case study structure, sum­
including the parameters required to evaluate the value function of marize the application of the proposed methodology, and finally obtain
each indicator i, such as ni, mi, Ai, Pi, min, Pi, max, Ki, and the function the SI values under different scenarios.
value curve type. This information can be organized into an excel
spreadsheet to automate its integration into the BIM model. 3.1. Description
- Step 3: Definition of the BIM model. A virtual model of the subject
bridge project is generated using the BIM methodology. The Las Arenas Viaduct was constructed in 2021 and is located along the
modeling process must include both the geometrical and database C-58 road between Sabadell and Terrassa, crossing the “Las Arenas”
information necessary for the sustainability assessment, as defined in stream in Barcelona (Spain). This bridge has a total length of 128 m and
Step 1. Note that both the level of detail (LOD) and level of infor­ is composed of four spans, each up to 33 m long (Fig. 7.a). Its deck is 15
mation (LOI) of the BIM model must be consistent to enable analysis m wide and composed of a slab on seven precast double-T beams, as
of the targeted sustainability indicators. The Dynamo parametric shown in Fig. 7.b.
software was used in this study to automate the introduction of the A BIM model of the viaduct was constructed in Revit using its orig­
MIVES information into the Revit BIM software as shared parameters inal blueprints in the AutoCAD .dwg format. The BIM model included
to enable their use in different projects and facilitate the visualiza­ the foundations, piers, abutments, deck beams, and deck slab with an
tion of information in quantity tables and labels. As a general illus­ LOD 300. The model also included detailed information describing the
trative example, the different steps required to read and create a location, elevation, orientation, material, and structural classification of
single parameter are presented in Fig. 5 and summarized as follows: the different bridge elements. The following structural categories were
(1) import and read the MIVES information from the excel spread­ considered in the model: (1) columns for the piles and piers, (2) foun­
sheet defined in Step 2, (2) filter the parameter data by either name dations for the pile caps, (3) walls for the abutments, (4) framing for the
or value, (3) define the type (number) and category (e.g. structural deck beams, (5) floor for the deck slab, and (6) structural rebars for steel
column) of the shared parameter, and (4) write the values defined in reinforcement in the concrete elements. Details of the construction time
(2) and (3) into the corresponding Revit parameter. and cost were directly introduced into the BIM model, as the 4D (time)
- Step 4: Calculation of SI in Revit. The SI is calculated using the Revit and 5D (cost) dimensions were not modeled. The 3D views of the BIM
software with the quantity tables. These tables include the MIVES model and rebars in the abutments are presented in Figs. 8.a, and 8.b,
information introduced into the BIM model in Step 3, and the values respectively.
of the studied indicators provided in the BIM database together with The assumptions for the different indicators were made as follows:
the numerical operators from Eqs. 1, 2, and 3. It is important to
highlight that if the LOD or the dimensions of the BIM model—e.g., - I1.1.1 [€/m2]: The total cost was calculated using the CYPE database
4D time or 5D cost—do not include the measurement of any of the [129] for labor, material, machinery, equipment, and tools.
considered parameters, the missing information can be manually - I1.1.2 [%]: The indirect cost reference value was fixed at 10%.
introduced by creating the corresponding project parameters. - I1.1.3 [€/m2]: The cost of the materials used to maintain the viaduct
superstructure for the first 10 years was obtained from the CYPE
A flowchart of the four steps of the proposed methodology for database [129].
automating the calculation of SI is presented in Fig. 6, which also de­ - I1.1.4 [€/m2]: The reference dismantling cost was obtained from the
scribes the different tools used. Technological Institute of Construction (ITEC) [130].
- I1.2.1 [d]: The execution time was obtained from an analysis of the
3. Case study: Las Arenas Viaduct viaduct construction plan. Because the BIM model did not include
time modeling, the construction time (65 d) was calculated exter­
A sustainability assessment of a case study (Las Arenas Viaduct) was nally and manually introduced as a parameter in Revit.
conducted to validate the proposed methodology. In this section, we

Fig. 6. Flow chart and tools used to calculate the sustainability index.

7
F. Lozano et al. Automation in Construction 152 (2023) 104935

(a)

(b)

Fig. 7. Las Arenas Viaduct: (a) elevation, and (b) cross section.

- I2.1.1 [kg CO2eq/m2], I2.2.1 [kg/m2], and I2.2.2 [MJ/m2]: Reference - I3.2.1 [ORI]: The following risks to health and safety were assumed in
data quantifying the emissions, raw material consumption, and en­ this evaluation: falls to lower levels, concrete and steel reinforcement
ergy consumption were obtained from the ITEC database [130]. placement, collision with a moving load, load handling, collision
- I3.1.1 [m2]: The affected area was obtained by analyzing the con­ with heavy equipment, fires owing to welding, drowning owing to
struction process. flooding, traffic accidents, and structural risks.
- I3.1.2 [points]: In this study, noise was considered the most notable
disturbance owing to the structural solutions adopted as well as the For illustrative purposes, both the reference values and value func­
location of the project. tions of these different indicators were modeled in Excel and are

8
F. Lozano et al. Automation in Construction 152 (2023) 104935

(a) (b)

Fig. 8. Las Arenas Viaduct: (a) BIM model with the software Revit, and (b) Detail of the steel reinforcements in the abutment.

presented in Fig. 9. (Pi,max, P,min, ni, mi, Ai, Ki, and the shape of the value function for each
A summary of requirements R1, R2, and R3; criteria C1.1, C1.2, C2.1, indicator) were summarized in an Excel spreadsheet. The algorithm
C2.2, C3.1, and C3.2; and the 11 indicators detailed above are presented in presented in Fig. 10 was used to automate the incorporation of this in­
Table 4, which also includes the different values of the considered formation into Revit. This algorithm first imported and read the MIVES
weights (α, β, and γ) determined according to a literature review. information and filtered the data to remove null values, then filtered the
The MIVES decision-making tree and remaining MIVES parameters parameter data either by name or value. Critically, this process created

(a) I1.1.1: Total cost (b) I1.1.2: Indirect cost (c) I1.1.3: Maintenance cost

(d) I1.1.4: Dismantling cost (e) I1.2.1: Execution time (f) I2.1.1: Emissions indicator

(g) I2.2.1: Raw material consumption (h) I2.2.2: Energy consumption indicator (i) I3.1.1: Affected areas

(j) I3.1.2: General disturbances (k) I3.2.1: Health and safety during construction

Fig. 9. Value functions of the different indicators: (a) I1.1.1: Total cost, (b) I1.1.2: Indirect cost, (c) I1.1.3: Maintenance cost, (d) I1.1.4: Dismantling cost, (e) I1.2.1:
Execution time, (f) I2.1.1: Emissions indicator, (g) I2.2.1: Raw material consumption, (h) I2.2.2: Energy consumption indicator, (i) I3.1.1: Affected areas, (j) I3.1.2: General
disturbances, and (k) I3.2.1: Health and safety during construction.

9
F. Lozano et al. Automation in Construction 152 (2023) 104935

Table 4
MIVES decision-making tree for the case study.
Requirement αi Criteria βi Indicator γi

R1. Economic 55% C1.1 Cost 70% I1.1.1 Total cost 60%
I1.1.2 Indirect cost 10%
I1.1.3 Maintenance cost 20%
I1.1.4 Dismantling cost 10%
C1.2 Time 30% I1.2.1 Execution time 100%
R2. Environmental 25% C2.1 Emissions 60% I2.1.1 CO2 emissions 100%
C2.2 Resources 40% I2.2.1 Raw material consumption 50%
I2.2.2 Energy consumption 50%
R3. Social 20% C3.1 Social indexes 40% I3.1.1 Affected area 40%
I3.1.2 General disturbances 60%
C3.2 Safety 60% I3.2.1 Health and safety 100%

(3)

(1) (2)
(4)

Fig. 10. Dynamo script used to import the MIVES information into Revit.

new variables to capture the MIVES information for each indicator. For 3.2. Results
example, the variable “I1.1.1_Pmax” included the Pmax value for the indi­
cator I1.1.1. Next, the type (number) and categories (foundations, col­ The developed methodology was applied to calculate the SI using the
umns, framing, walls, floors, and structural rebars) of the shared proposed methodology and thereby study the effects of the weights of
parameters were defined and finally written into the corresponding the requirements and deviations of the indicator reference values.
Revit parameter.
All imported MIVES information was organized in Revit using 3.2.1. Calculation of the sustainability index (SI)
quantity tables together with the P, V, and SI values for each indicator. A quantity table summarizing the MIVES information, values of Pi,
The latter two parameters (V and SI) were calculated directly in Revit Vi, and SIi for the different indicators i is shown in Fig. 12. This table
using a numerical operator. To illustrate this process, the calculation of indicates that the total cost (I1.1.1 = 0.163), execution time (I1.2.1 =
V for indicator I1.1.1 (I1.1.1_V) is presented in Fig. 11. Finally, the overall SI 0.116), and CO2 emissions (I2.1.1 = 0.087) during construction were the
was calculated from the summation of the values obtained for the most critical indicators; the general SI for this scenario (SI1) was
different indicators as shown in Eq. 3. determined to be 0.678.

3.2.2. Analysis of the effect of the requirement weights


The SI obtained for Scenario 1 (SI1) described in Table 4 was
compared with those obtained by considering Scenario 2 (SI2), “Sus­
tainability Balance,” in which the weights of the different requirements
were fixed to be equal (i.e., R1 = R2 = R3 = 33%), and Scenario 3 (SI3),
“Economic Crisis,” in which the weight of the economic requirement
was increased and those of the environmental and social requirements
were reduced with respect to the value considered in SI1 (i.e., R1 = 75%,
R2 = 10%, and R3 = 15%). The resulting SI values and relative weights
for each indicator are summarized in Table 5.
The analysis of the SI values presented in Table 5 indicates that the
index did not vary significantly among the three analyzed scenarios. A
slightly higher SI than the reference value (SI1) was obtained in Scenario
Fig. 11. Calculation of the function value (V) for the indicator I1.1.1 in Revit.

10
F. Lozano et al. Automation in Construction 152 (2023) 104935

Fig. 12. Quantity tables used to calculate the sustainability index (SI) for the different indicators.

11
F. Lozano et al. Automation in Construction 152 (2023) 104935

Table 5
Sustainability indexes (SI) in three different scenarios.
Indicator [α1β1γ1] SI1 [α2β2γ2] SI2 [α3β3γ3] SI3

I1.1.1 Total cost 23.10% 0.163 14.00% 0.099 31.50% 0.223


I1.1.2 Indirect cost 3.85% 0.023 2.33% 0.014 5.25% 0.032
I1.1.3 Maintenance cost 7.70% 0.062 4.67% 0.038 10.50% 0.084
I1.1.4 Dismantling cost 3.85% 0.027 2.33% 0.017 5.2% 0.037
I1.2.1 Execution time 16.50% 0.116 10.00% 0.071 22.50% 0.159
I2.1.1 CO2 emissions 15.00% 0.087 20.00% 0.117 6.00% 0.035
I2.2.1 Raw material 5.00% 0.030 6.67% 0.040 2.00% 0.012
I2.2.2 Energy consumption 5.00% 0.030 6.67% 0.041 2.00% 0.012
I3.1.1 Affected area 3.20% 0.019 5.33% 0.031 2.40% 0.014
I3.1.2 General disturbances 4.80% 0.034 8.00% 0.056 3.60% 0.025
I3.2.1 Health and safety 12.00% 0.085 20.00% 0.142 9.00% 0.064
100.00% 0.678 100.00% 0.664 100.00% 0.698

3 (SI3 = 0.698), which assigned greater importance to economic aspects 4. Conclusions


because environmental and social impacts do not play a minor role in
the construction of a viaduct. In contrast, a slightly smaller SI was ob­ The decision-making process for the sustainability assessment of civil
tained in Scenario 2 (SI2 = 0.664) owing to its increased consideration of engineering structures is traditionally based on an analysis of conflicting
environmental impacts. economic, environmental, and social criteria. Multicriteria decision-
making (MCDM) methods are traditionally applied to evaluate these
3.2.3. Sensitivity analysis conflicting concerns. Various studies published in the literature have
The effects of changes in the different indicators on SI were studied demonstrated that MCDM methods can be connected to the Building
by considering parametric deviations of − 10% and + 10% of the Information Modeling (BIM) methodology to improve the efficacy of
reference value for each indicator. The resulting changes in SI consid­ sustainability analyses. Among the MCDM methods presented in the
ering the weights of the requirements, criteria, and indicators described literature, the Integrated Value Model for Sustainability Assessment
in Table 4 are presented in Fig. 13. (MIVES) has been particularly applied to sustainability assessments in a
Fig. 13 shows that a change in total cost (I1.1.1) had the greatest effect number of engineering fields. Although MIVES is widely applicable, it
on the SI value. Indeed, variations of − 10% and + 10% of the reference has yet to be integrated with BIM in the literature. Therefore, this study
value of this parameter resulted in changes of +6.7%, and − 11,4%, proposed a new methodology for evaluating bridge project sustainabil­
respectively, in SI. The CO2 emissions (I2.1.1) had the second-highest ity by integrating MIVES and BIM. Connecting these two methodologies
effect on SI, with variations of 10% and + 10% resulting in changes of provides various benefits including facilitating the use of the BIM
+4.7%, and − 5.6%, respectively, in SI. In contrast, changes in the database, providing automatic sustainability analysis, and ensuring
reference values of other indicators, such as general disturbances (I3.1.2), versatility. First, the measurements of each indicator can be connected
did not have any effect on SI; variations of 10% and + 10% corresponded with the element database in the BIM model such that changes in the
to changes in SI of only − 0.3%, and 0.3%, respectively. This analysis model (e.g., modifications of the construction process or costs of the
approach clearly facilitates the identification of the indicators having elements) will automatically modify the values of the affected parame­
the greatest impact on sustainability performance, informing the ters in the MIVES analysis. Second, quantity tables and numerical op­
establishment of contingency and control measures (to be imposed by erators enable the automatic evaluation of sustainability within the BIM
stakeholders and/or authorities) to guarantee minimum sustainability model using the measurements in the BIM database and the MIVES in­
performance during construction. formation (such as the decision tree, indicator names, and their
respective weights). Third, the developed BIM methodology is quite
versatile and can be accordingly adapted to the sustainability

Fig. 13. Deviations on the SI produced by changes in the reference value of the different indicators.

12
F. Lozano et al. Automation in Construction 152 (2023) 104935

assessment of a variety of structures, as the MIVES method provides a [10] C. O’Malley, P.A.E. Piroozfar, E.R.P. Farr, J. Gates, Evaluating the efficacy of
BREEAM code for sustainable homes (CSH): a cross-sectional study, Energy
straightforward approach for capturing relevant sustainability-related
Procedia 62 (Jan. 2014) 210–219, https://doi.org/10.1016/J.
aspects. EGYPRO.2014.12.382.
The application of the proposed method was illustrated step-by-step [11] J. Holmes, G. Hudson, The application of BREEAM in corporate real estate: a case
using a real bridge (Las Arenas Viaduct) as a case study considering 11 study in the design of a city Centre office development, J. Corpor. Real Estate 5
(1) (Jan. 2003) 66–77, https://doi.org/10.1108/14630010310812019.
economic, environmental, and social indicators. The obtained results [12] D.A. ElSorady, S.M. Rizk, LEED v4.1 operations & maintenance for existing
show how the integration of the BIM methodology automates sustain­ buildings and compliance assessment: Bayt Al-Suhaymi, historic Cairo,
ability assessment and facilitates the evaluation of different scenarios. Alexandria Eng. J. 59 (1) (Feb. 2020) 519–531, https://doi.org/10.1016/J.
AEJ.2020.01.027.
This study thereby demonstrated that the BIM and MIVES methods can [13] S.H. Obata, F. Agostinho, C.M.V.B. Almeida, B.F. Giannetti, LEED certification as
be satisfactorily coupled to assess the sustainability of bridge projects. booster for sustainable buildings: insights for a Brazilian context, Resour.
A parametric analysis of the presented case study indicated that the Conserv. Recycl. 145 (Jun. 2019) 170–178, https://doi.org/10.1016/J.
RESCONREC.2019.02.037.
sustainability index (SI) was significantly sensitive to changes in the [14] Y. Zou, Certifying green buildings in China: LEED vs. 3-star, J. Clean. Prod. 208
reference value of the total cost indicator. In contrast, changes in other (Jan. 2019) 880–888, https://doi.org/10.1016/J.JCLEPRO.2018.10.204.
parameters such as general disturbances played a negligible role in [15] R.A. Moussa, A.A. Farag, The applicability of LEED of new construction (LEED-
NC) in the Middle East, Procedia Environ. Sci. 37 (Jan. 2017) 572–583, https://
determining the SI value. However, these conclusions should be doi.org/10.1016/J.PROENV.2017.03.044.
considered in the context of this particular case study: all measurements [16] A. Braune, D. Geiselmann, S. Oehler, C. Ruiz Durán, Implementation of the DGNB
of all indicators were defined theoretically, the BIM was not calibrated framework for carbon neutral buildings and sites, in: IOP Conference Series Earth
Environmental Science vol. 290, Jun. 2019, https://doi.org/10.1088/1755-
using in situ information obtained during the construction and mainte­
1315/290/1/012040 no. 1.
nance phases, and 4D (time) and 5D (cost) dimensions were not [17] M. Behnisch, A. Ultsch, Estimating the number of buildings in Germany, in:
considered. These limitations may compromise the accuracy of sus­ Conference Advances in Data Analysis, Data Handling and Business Intelligence,
tainability assessments conducted for other structures using the pro­ Jan. 2009, pp. 585–593, https://doi.org/10.1007/978-3-642-01044-6_54.
[18] DGNB certified Healthcare Centres: : – decision-making and design process. |
posed methodology and will be addressed in future studies. Request PDF, 2023, in: https://www.researchgate.net/publication/283447503_D
GNB_certified_Healthcare_Centres_-_decision-making_and_design_process
(accessed Oct. 03, 2022).
[19] L. Bjerregaard, K. Espenhein, L. Bjerregaard Jensen, Process optimization on
Declaration of Competing Interest
ambitious sustainability goals through the framework of DGNB, 2017. Accessed:
Mar. 07, 2023. [Online]. Available: https://orbit.dtu.dk/en/publications/process
The authors declare the following financial interests/personal re­ -optimization-on-ambitious-sustainability-goals-through-th.
lationships which may be considered as potential competing interests: [20] P. Bocchini, D.M. Frangopol, T. Ummenhofer, T. Zinke, Resilience and
sustainability of civil infrastructure: toward a unified approach, J. Infrastruct.
Fidel Lozano Galant reports financial support was provided by Spain Syst. 20 (2) (Jun. 2014), https://doi.org/10.1061/(ASCE)IS.1943-555X.0000177.
Ministry of Science and Innovation. [21] R. Johansson, Evaluation of experiences from using CEEQUAL in infrastructure
projects A case study of the Crossrail programme and the Olympic Park, 2011.
Accessed: Oct. 03, 2022. [Online]. Available: http://www.teknat.uu.se/student.
Data availability [22] E. Campbell, J. Feris, Trialling ceequal on a london railway embankment, in:
Proceedings of the Institution of Civil Engineers-Engineering Sustainability vol.
Data will be made available on request. 161, May 2008, pp. 71–76. ISNN: 1478–4629.
[23] S. Ghumra, J. Glass, M.W. Frost, M. Watkins, J. Mundy, Materials and energy
assessment in ceequal transport projects, Proc. Inst. Civ. Eng. Transp. 164 (3)
Acknowledgements (Aug. 2011) 153–164, https://doi.org/10.1680/TRAN.2011.164.3.153.
[24] A. de la Fuente, J. Armengou, O. Pons, A. Aguado, Multi-criteria decision-making
model for assessing the sustainability index of wind-turbine support systems:
The authors are indebted to the projects PID2021-126405OB-C31, application to a new precast concrete alternative, J. Civ. Eng. Manag. 23 (2) (Feb.
and PID2021-126405OB-C32 funded by MICIN/AEI/10.130 2017) 194–203, https://doi.org/10.3846/13923730.2015.1023347.
39/501100011033/ and FEDER funds A way to make Europe. [25] P. Pujadas, S.H.P. Cavalaro, A. Aguado, Mives multicriteria assessment of urban-
pavement conditions: application to a case study in Barcelona, Road Mater.
Pavem. Des. 20 (8) (Nov. 2019) 1827–1843, https://doi.org/10.1080/
References 14680629.2018.1474788.
[26] S.M. Amin Hosseini, A. de La Fuente, O. Pons, Multi-criteria decision-making
method for assessing the sustainability of post-disaster temporary housing units
[1] I.J. Navarro, V. Yepes, J.V. Martí, Sustainability assessment of concrete bridge
technologies: a case study in bam, 2003, Sustain. Cities Soc. 20 (Jan. 2016)
deck designs in coastal environments using neutrosophic criteria weights, Struct.
38–51, https://doi.org/10.1016/J.SCS.2015.09.012.
Infrastuct. Eng. 16 (7) (Jul. 2019) 949–967, https://doi.org/10.1080/
[27] W.G. Caballero Moreno, I. Alegre, J. Armengou-Orús, A. Aguado, W.G.C. Moreno,
15732479.2019.1676791.
Self-construction in informal settlements: a multiple-criteria decision-making
[2] T.Y. Liu, G.T. Liu, P.H. Chen, N.N.S. Chou, S.P. Ho, Establishment of a
method for assessing sustainability of floor slabs in Bucaramanga, Colombia,
sustainability assessment system for bridges, Sustainability 13 (9) (2021) 4795,
J. Housing Built Environ. 34 (Apr. 2018) 195–217, https://doi.org/10.1007/
https://doi.org/10.3390/SU13094795.
s10901-018-9606-5.
[3] BREEAM International New Construction, Cover. https://files.bregroup.co
[28] O. Pons, A. de la Fuente, A. Aguado, The use of MIVES as a sustainability
m/breeam/technicalmanuals/BREEAMInt2016SchemeDocument/, 2016
assessment MCDM method for architecture and civil engineering applications,
(accessed Sep. 07, 2022).
Sustainability (Switzerland) 8 (5) (2016), https://doi.org/10.3390/SU8050460.
[4] LEED v4 for Building Design and Construction - current version | U.S. Green
[29] N. Arango, Evaluación de la sostenibilidad de la movilidad eléctrica urbana a
Building Council. https://www.usgbc.org/resources/leed-v4-building-design-
través de un modelo MIVES, 2012. Accessed: Sep. 08, 2022. [Online]. Available:
and-construction-current-version, 2023 (accessed Sep. 07, 2022).
https://upcommons.upc.edu/handle/2099.1/19243.
[5] DGNB SYSTEM - New construction, buildings criteria set, 2023. https://static.dgn
[30] J.J. Cartelle, M. Lara, M.P. de la Cruz, A. del Caño, Assessing the global
b.de/fileadmin/dgnb-system/downloads/criteria/DGNB-Criteria-Set-New-Con
sustainability of different electricity generation systems, Energy 89 (Sep. 2015)
struction-Buildings-Version-2020-International (accessed Sep. 07, 2022).
473–489, https://doi.org/10.1016/J.ENERGY.2015.05.110.
[6] CEEQUAL Version 6 consultation information. https://www.breeam.com/wp-c
[31] K.R. Reddy, S.N. Ghimire, E. Wemeyi, R. Zanjani, L. Zhao, Life cycle sustainability
ontent/uploads/sites/3/2019/03/CEEQUAL-V6-consultation-information-March
assessment of geothermal heating and cooling system: UIC case study, E3S Web
-2019-V01-SECURED, 2023 (accessed Sep. 07, 2022).
Conf. 205 (Nov. 2020), https://doi.org/10.1051/E3SCONF/202020507003.
[7] B. Viñolas, F. Cortés, A. Marques, A. Josa Garcia-Tornel, A. Aguado de Cea,
[32] J.J. Cartelle, M. Lara, M.P. de la Cruz, A. del Caño, Probabilistic life-cycle cost
MIVES: modelo integrado de valor para evaluaciones de sostenibilidad, in: II
analysis for renewable and non-renewable power plants, Energy 112 (Oct. 2016)
Congrés Internacional de Mesura i Modelització de la Sostenibilitat, 2009,
774–787, https://doi.org/10.1016/J.ENERGY.2016.06.098.
pp. 1–24. ISBN: 978-84-96736-81-8.
[33] A.W.S. Trentin, K.R. Reddy, G. Kumar, J.K. Chetri, A. Thomé, Quantitative
[8] A. Nesteby, M. Aarrestad, J. Lohne, R. Bohne, Integration of breeamnor in
assessment of life cycle sustainability (QUALICS): framework and its application
construction projects: utilizing the last planner system, Energy Procedia 96 (Sep.
to assess electrokinetic remediation, Chemosphere 230 (Sep. 2019) 92–106,
2016) 100–111, https://doi.org/10.1016/j.egypro.2016.09.110.
https://doi.org/10.1016/J.CHEMOSPHERE.2019.04.200.
[9] P. Ponterosso, M. Gaterell, J. Williams, Post occupancy evaluation and internal
[34] S.N. Joglekar, V. Darwai, S.A. Mandavgane, B.D. Kulkarni, A methodology of
environmental monitoring of the new BREEAM ‘excellent’ land rover/ben Ainslie
evaluating sustainability index of a biomass processing enterprise: a case study of
racing team headquarters offices, Build. Environ. 146 (Dec. 2018) 133–142,
https://doi.org/10.1016/J.BUILDENV.2018.09.037.

13
F. Lozano et al. Automation in Construction 152 (2023) 104935

native cow dung–urine biorefinery, Environ. Sci. Pollut. Res. 27 (22) (Aug. 2020) [58] O. Pons, A. de La Fuente, Integrated sustainability assessment method applied to
27435–27448, https://doi.org/10.1007/S11356-019-06309-1. structural concrete columns, Constr. Build. Mater. 49 (Dec. 2013) 882–893,
[35] A. de La Fuente, J. Armengou, O. Pons, A. Aguado, Multi-criteria decision-making https://doi.org/10.1016/J.CONBUILDMAT.2013.09.009.
model for assessing the sustainability index of wind-turbine support systems: [59] B. Simona, Multi-performance evaluation of traditional and low-damage non-
application to a new precast concrete alternative, J. Civ. Eng. Manag. 23 (2) (Aug. structural components, Feb. 2021. Accessed: Mar. 07, 2023. [Online]. Available:
2015) 194–203, https://doi.org/10.3846/13923730.2015.1023347. https://iris.uniroma1.it/handle/11573/1541562.
[36] O. Pons, A. de La Fuente, J. Armengou, A. Aguado, Towards the sustainability in [60] M. Zubizarreta, J. Cuadrado, A. Orbe, H. García, Modeling the environmental
the design of wind towers, Energy Procedia 115 (Jun. 2017) 41–49, https://doi. sustainability of timber structures: a case study, Environ. Impact Assess. Rev. 78
org/10.1016/J.EGYPRO.2017.05.005. (Sep. 2019), https://doi.org/10.1016/J.EIAR.2019.106286.
[37] J.J. Cartelle, M. Lara, M.P. de la Cruz, A. del Caño, Sustainability optimisation of [61] O. Pons, et al., Roofs of the future: rooftop greenhouses to improve buildings
shell and tube heat exchanger, using a new integrated methodology, J. Clean. metabolism, Proc. Eng. 123 (Feb. 2015) 441–448, https://doi.org/10.1016/J.
Prod. 200 (Nov. 2018) 552–567, https://doi.org/10.1016/J. PROENG.2015.10.084.
JCLEPRO.2018.07.266. [62] A. del Caño, M.P. de la Cruz, J.J. Cartelle, M. Lara, Conceptual framework for an
[38] A. de La Fuente, O. Pons, A. Josa, A. Aguado, Multi-criteria decision making in integrated method to optimise sustainability of engineering systems, Renew.
the sustainability assessment of sewerage pipe systems, J. Clean. Prod. 112 (5) Energ. Power Qual. J. 1 (13) (Apr. 2015) 145–150, https://doi.org/10.24084/
(Jan. 2016) 4762–4770, https://doi.org/10.1016/j.jclepro.2015.07.002. REPQJ13.261.
[39] S.M.A. Hosseini, A. de la Fuente, O. Pons, Multicriteria decision-making method [63] M.M. Casanovas-Rubio, P. Pujadas, F. Pardo-Bosch, A. Blanco, A. Aguado,
for sustainable site location of post-disaster temporary housing in urban areas, Sustainability assessment of trenches including the new eco-trench: a multi-
J. Construct. Eng. Manage. (ASCE) 142 (9) (Sep. 2016), https://doi.org/10.1061/ criteria decision-making tool, J. Clean. Prod. 238 (Nov. 2019), https://doi.org/
(ASCE)CO.1943-7862.0001137, pp. 04016036–1. 10.1016/J.JCLEPRO.2019.117957.
[40] A. Gandini, L. Garmendia, I. Prieto, I. Álvarez, J.T. San-José, A holistic and multi- [64] I. Josa, N. Tošic, S. Marinkovic, A. de La Fuente, A. Aguado, Sustainability-
stakeholder methodology for vulnerability assessment of cities to flooding and oriented multi-criteria analysis of different continuous flight auger piles,
extreme precipitation events, Sustain. Cities Soc. 63 (Dec. 2020), https://doi.org/ Sustainability (Switzerland) 13 (14) (Jul. 2021), https://doi.org/10.3390/
10.1016/J.SCS.2020.102437. SU13147552.
[41] P. Pujadas, S.H.P. Cavalaro, A. Aguado, Mives multicriteria assessment of urban- [65] G. Gilani, A. Blanco, A.D. la Fuente, A new sustainability assessment approach
pavement conditions: application to a case study in Barcelona, Road Mater. based on Stakeholder’s satisfaction for building Façades, Energy Procedia 115
Pavem. Des. 20 (8) (Nov. 2018) 1827–1843, https://doi.org/10.1080/ (Jun. 2017) 50–58, https://doi.org/10.1016/J.EGYPRO.2017.05.006.
14680629.2018.1474788. [66] G. Gilani, O. Pons, A. de La Fuente, Towards the facądes of the future: a new
[42] S. Seraj, M. Nikravan, A.A. Ramezanianpour, P. Zendehdel, Evaluation of the sustainability assessment approach, IOP Conf. Ser. 290 (1) (Jun. 2019), https://
application of municipal solid waste incinerator (MSWI) ash in civil engineering doi.org/10.1088/1755-1315/290/1/012075.
using a sustainability approach, Detritus 9 (Mar. 2020) 113–124, https://doi.org/ [67] G. Gilani, O. Pons, A. de la Fuente, Sustainability-oriented approach to assist
10.31025/2611-4135/2020.13922. decision makers in building facade management, J. Constr. Eng. Manag. 148 (1)
[43] A. Gandini, L. Quesada, I. Prieto, L. Garmendia, Climate change risk assessment: a (Jan. 2022), https://doi.org/10.1061/(ASCE)CO.1943-7862.0002194.
holistic multi-stakeholder methodology for the sustainable development of cities, [68] G. Gilani, S.M.A. Hosseini, O. Pons-Valladares, A. de la Fuente, An enhanced
Sustain. Cities Soc. 65 (Feb. 2021), https://doi.org/10.1016/J.SCS.2020.102641. multi-criteria decision-making approach oriented to sustainability analysis of
[44] J.T. San-José, I. Garrucho, A system approach to the environmental analysis of building facades: a case study of Barcelona, J. Build. Eng. 54 (Aug. 2022), https://
industrial buildings, Build. Environ. 45 (3) (Mar. 2010) 673–683, https://doi. doi.org/10.1016/J.JOBE.2022.104630.
org/10.1016/J.BUILDENV.2009.08.012. [69] P. Sadrolodabaee, S.M.A. Hosseini, M. Ardunay, J. Claramunt, A. de la Fuente,
[45] J. Cuadrado, M. Zubizarreta, E. Roji, M. Larrauri, I. Alvarez, Sustainability A new sustainability assessment method for Façade cladding panels: a case study
assessment methodology for industrial buildings: three case studies, Civ. Eng. of Fiber/textile reinforced cement sheets, RILEM Bookseries 36 (Jan. 2022)
Environ. Syst. 33 (2) (Apr. 2016) 106–124, https://doi.org/10.1080/ 809–819, https://doi.org/10.1007/978-3-030-83719-8_69.
10286608.2016.1148143. [70] P. Sadrolodabaee, S.M.A. Hosseini, J. Claramunt, M. Ardanuy, Experimental
[46] O. Pons, A. Aguado, Integrated value model for sustainable assessment applied to characterization of comfort performance parameters and multi-criteria
technologies used to build schools in Catalonia, Spain, Build. Environ. 53 (Jul. sustainability assessment of recycled textile-reinforced cement facade cladding,
2012) 49–58, https://doi.org/10.1016/J.BUILDENV.2012.01.007. J. Clean. Prod. 356 (Apr. 2022), https://doi.org/10.1016/J.
[47] O. Pons, S. Habibi, D. Peña, Sustainability assessment of household waste based JCLEPRO.2022.131900.
solar control devices for workshops in primary schools, Sustainability [71] A. Enfedaque, M.G. Alberti, J.C. Gálvez, M. Rivera, J.M. Simón-Talero, Can
(Switzerland) 10 (11) (Nov. 2018), https://doi.org/10.3390/SU10114071. polyolefin fibre reinforced concrete improve the sustainability of a flyover
[48] O. Pons, Assessing the sustainability of prefabricated buildings, in: Eco-Efficient bridge? Sustainability (Switzerland) 10 (12) (Dec. 2018) https://doi.org/
Construction and Building Materials: Life Cycle Assessment (LCA), Eco-Labelling 10.3390/SU10124583.
and Case Studies, 2013, pp. 434–456, https://doi.org/10.1533/ [72] A. de la Fuente, M.M. Casanovas-Rubio, O. Pons, J. Armengou, Sustainability of
9780857097729.3.434. column-supported RC slabs: Fiber reinforcement as an alternative, J. Constr. Eng.
[49] S.M.A. Hosseini, R. Ghalambordezfooly, A. de la Fuente, Sustainability model to Manag. 145 (7) (Jul. 2019), https://doi.org/10.1061/(ASCE)CO.1943-
select optimal site location for temporary housing units: combining GIS and the 7862.0001667.
MIVES–Knapsack Model, Sustainability (Switzerland) 14 (8) (Apr. 2022), https:// [73] O. Pons, M.M. Casanovas-Rubio, J. Armengou, A. de la Fuente, Sustainability-
doi.org/10.3390/SU14084453. driven decision-making model: case study of Fiber-reinforced concrete foundation
[50] B. Maleki, M.D.M. Casanovas, S.M.A. Hosseini, A. de La Fuente, Multi-criteria piles, J. Constr. Eng. Manag. 147 (10) (Oct. 2021), https://doi.org/10.1061/
decision making in the social sustainability assessment of high-rise residential (ASCE)CO.1943-7862.0002073.
buildings, IOP Conf. Ser. 290 (1) (Jun. 2019), https://doi.org/10.1088/1755- [74] F. Barrientos, et al., Knowledge-based minimization of railway infrastructures
1315/290/1/012054. environmental impact, Transp. Res. Proc. 14 (Jan. 2016) 840–849, https://doi.
[51] A.J. Sánchez-Garrido, V. Yepes, Multi-criteria assessment of alternative org/10.1016/J.TRPRO.2016.05.032.
sustainable structures for a self-promoted, single-family home, J. Clean. Prod. 258 [75] A. de la Fuente, A. Blanco, J. Armengou, A. Aguado, Sustainability based-
(Jun. 2020), https://doi.org/10.1016/J.JCLEPRO.2020.120556. approach to determine the concrete type and reinforcement configuration of TBM
[52] S.H. Banirazi, O. Pons, S.M.A. Hosseini, Sustainability model to assess the tunnels linings. Case study: extension line to Barcelona airport T1, Tunn.
suitability of green roof alternatives for urban air pollution reduction applied in Undergr. Space Technol. 61 (Jan. 2017) 179–188, https://doi.org/10.1016/J.
Tehran, Build. Environ. 194 (May 2021), https://doi.org/10.1016/J. TUST.2016.10.008.
BUILDENV.2021.107683. [76] M.G. Alberti, J.C. Gálvez, A. Enfedaque, A. Carmona, C. Valverde, G. Pardo, Use
[53] I. Josa, O. Pons, A. de la Fuente, A. Aguado, Multi-criteria decision-making model of steel and polyolefin fibres in the La Canda tunnels: applying MIVES for
to assess the sustainability of girders and trusses: case study for roofs of sports assessing sustainability evaluation, Sustainability (Switzerland) 10 (12) (Dec.
halls, J. Clean. Prod. 249 (Mar. 2020), https://doi.org/10.1016/J. 2018), https://doi.org/10.3390/SU10124765.
JCLEPRO.2019.119312. [77] L.L. de Abajo, A.P. Pérez-Fortes, M.G. Alberti, J.C. Gálvez, T. Ripa, Sustainability
[54] R. Lizarralde, J. Ganzarain, M. Zubizarreta, Adaptation of the MIVES method for analysis of the m-30 Madrid tunnels and Madrid río after 14 years of service life,
the strategic selection of new technologies at an R&D Centre. Focus on the Appl. Sci. (Switzerland) 10 (20) (Oct. 2020) 1–20, https://doi.org/10.3390/
manufacturing sector, Technovation 115 (Jul. 2022), https://doi.org/10.1016/J. APP10207368.
TECHNOVATION.2022.102462. [78] A. Aguado, J.C. Gálvez, A. Aguado-Renter, P. Pujadas, D. Fernández-Ordóñez,
[55] F. Pardo-Bosch, A. Aguado, M. Pino, Holistic model to analyze and prioritize Evaluación de la sostenibilidad de carreteras, Carreteras 4 (213) (May 2017) 8–19
urban sustainable buildings for public services, Sustain. Cities Soc. 44 (Jan. 2019) (ISSN: 0212-6389).
227–236, https://doi.org/10.1016/J.SCS.2018.09.028. [79] Evaluación de la sostenibilidad de carreteras - AEC - Asociación Española de la
[56] P. Duran, Método de discriminación entre distintas soluciones de pilares mediante Carretera, 2023. https://www.aecarretera.com/servicios/publicaciones/revista
criterios de sostenibilidad, Feb. 2011. Accessed: Sep. 08, 2022. [Online]. -carreteras/articulos-publicados/257-revista-carreteras-n-213/2796-evalua
Available: https://upcommons.upc.edu/handle/2099.1/12527. cion-de-la-sostenibilidad-de-carreteras (accessed Sep. 09, 2022).
[57] M. Ballester, F.J. Vea, V. Yepes, Análisis multivariante para la estimación de la [80] A. Orbe, E. Rojí, J. Cuadrado, R. Losada, M. Zubizarreta, Sustainable alternative
contribución a la sostenibilidad de los forjados reticulares, V Congreso ACHE of structural concrete retaining tanks, Proc. Inst. Civil Eng. 171 (3) (Aug. 2018)
(Jun. 2011) 1–10, https://doi.org/10.13140/RG.2.2.10763.80164. 133–150, https://doi.org/10.1680/JENSU.15.00062.
[81] M.P. De La Cruz, A. Castro, A. del Caño, D. Gómez, M. Lara, G. Gradaille,
Comprehensive methods for dealing with uncertainty in assessing sustainability

14
F. Lozano et al. Automation in Construction 152 (2023) 104935

part 2: the fuzzy-MIVES method, Soft Comput. Appl. Renew. Energy Energy Effic. [106] M. Sheikhkhoshkar, F. Pour Rahimian, M.H. Kaveh, M.R. Hosseini, D.J. Edwards,
(Oct. 2014) 107–140, https://doi.org/10.4018/978-1-4666-6631-3.CH005. Automated planning of concrete joint layouts with 4D-BIM, Autom. Constr. 107
[82] M.P. De La Cruz, A. Castro, A. del Caño, D. Gómez, M. Lara, J.J. Cartelle, (Nov. 2019), 102943, https://doi.org/10.1016/J.AUTCON.2019.102943.
Comprehensive methods for dealing with uncertainty in assessing sustainability [107] L. Chen, Q. Lu, X. Zhao, A semi-automatic image-based object recognition system
part 1: the MIVES-Monte Carlo method, Soft Comput. Appl. Renew. Energy for constructing as-is IFC BIM objects based on fuzzy-MAUT, Int. J. Constr.
Energy Effic. (Oct. 2014) 69–106, https://doi.org/10.4018/978-1-4666-6631-3. Manag. 22 (1) (May 2019) 51–65, https://doi.org/10.1080/
CH004. 15623599.2019.1615754.
[83] A. Gandini, L. Garmendia, R. San Mateos, I. Prieto, J.T. Sanjosé, I. Piñero, The [108] X. Xun, J. Zhang, Y. Yuan, Multi-information fusion based on BIM and
historic city in the climate change. Mives methodology approach, in: REHABEND intuitionistic fuzzy D-S evidence theory for safety risk assessment of undersea
Construction Pathology, Rehabilitation Technology and Heritage Management tunnel construction projects, Buildings 12 (11) (Oct. 2022) 1802, https://doi.org/
221479, May 2018, pp. 164–172 (ISBN: 978-84-687-7032-0). 10.3390/BUILDINGS12111802.
[84] D. Biswal, S.N. Joglekar, S.A. Mandavgane, MIVES: a multi-attribute value [109] P. Pishdad-Bozorgi, X. Gao, C. Eastman, A.P. Self, Planning and developing
function-based methodology for sustainability assessment, Stud. Syst. Decis. facility management-enabled building information model (FM-enabled BIM),
Control 407 (Feb. 2022) 1–16, https://doi.org/10.1007/978-981-16-7414-3_1. Autom. Constr. 87 (Mar. 2018) 22–38, https://doi.org/10.1016/J.
[85] D. Boix-Cots, F. Pardo-Bosch, A. Blanco, A. Aguado, P. Pujadas, A systematic AUTCON.2017.12.004.
review on MIVES: a sustainability-oriented multi-criteria decision-making [110] E.A. Pärn, D.J. Edwards, M.C.P. Sing, The building information modelling
method, Build. Environ. 223 (Sep. 2022), https://doi.org/10.1016/J. trajectory in facilities management: a review, Autom. Constr. 75 (Mar. 2017)
BUILDENV.2022.109515. 45–55, https://doi.org/10.1016/J.AUTCON.2016.12.003.
[86] J. Mel, D. Gómez, P. de la Cruz, A. del Caño, Análisis de sensibilidad y estudio [111] J. Patacas, N. Dawood, M. Kassem, BIM for facilities management: a framework
crítico del modelo de evaluación de la sostenibilidad de la Instrucción Española and a common data environment using open standards, Autom. Constr. 120 (Dec.
de Hormigón Estructural, Inform. Construc. 67 (539) (2015), https://doi.org/ 2020), 103366, https://doi.org/10.1016/J.AUTCON.2020.103366.
10.3989/IC.14.126. [112] S. Shin, H. Moon, J. Shin, BIM-based maintenance data processing mechanism
[87] J.M. Diaz-Sarachaga, D. Jato-Espino, D. Castro-Fresno, Application of the through cobie standard development for port facility, Appl. Sci. 12 (3) (Jan.
sustainable infrastructure rating system for developing countries (SIRSDEC) to a 2022) 1304, https://doi.org/10.3390/APP12031304.
case study, Environ. Sci. Pol. 69 (Mar. 2017) 73–80, https://doi.org/10.1016/J. [113] J. Collao, H. Ma, J.A. Lozano-Galant, J. Turmo, Traffic road emission estimation
ENVSCI.2016.12.011. through visual programming algorithms and building information models: a case
[88] J.M. Diaz-Sarachaga, D. Jato-Espino, D. Castro-Fresno, Methodology for the study, IEEE Access 9 (Oct. 2021) 150846–150864, https://doi.org/10.1109/
development of a new sustainable infrastructure rating system for developing ACCESS.2021.3123565.
countries (SIRSDEC), Environ. Sci. Pol. 69 (Mar. 2017) 65–72, https://doi.org/ [114] E. Atencio, P. Araya, F. Oyarce, R.F. Herrera, F.M.-L. Rivera, F. Lozano-Galant,
10.1016/J.ENVSCI.2016.12.010. Towards the integration and automation of the design process for domestic
[89] I. Piñero, J.T. San-José, P. Rodríguez, M.M. Losáñez, Multi-criteria decision- drinking-water and sewerage systems with BIM, Appl. Sci. 12 (18) (Sep. 2022)
making for grading the rehabilitation of heritage sites. Application in the historic 9063, https://doi.org/10.3390/APP12189063.
center of La Habana, J. Cult. Herit. 26 (Jul. 2017) 144–152, https://doi.org/ [115] K. Castañeda, O. Sánchez, R.F. Herrera, E. Pellicer, H. Porras, BIM-based traffic
10.1016/J.CULHER.2017.01.012. analysis and simulation at road intersection design, Autom. Constr. 131 (Nov.
[90] A. Gandini, A. Egusquiza, L. Garmendia, J.T. San-José, Vulnerability assessment 2021), 103911, https://doi.org/10.1016/J.AUTCON.2021.103911.
of cultural heritage sites towards flooding events, IOP Conf. Ser. 364 (1) (Jun. [116] L. Ding, Y. Zhou, B. Akinci, Building information modeling (BIM) application
2018), https://doi.org/10.1088/1757-899X/364/1/012028. framework: the process of expanding from 3D to computable nD, Autom. Constr.
[91] F. Pardo-Bosch, A. Aguado, Sustainability as the key to prioritize investments in 46 (Oct. 2014) 82–93, https://doi.org/10.1016/J.AUTCON.2014.04.009.
public infrastructures, Environ. Impact Assess. Rev. 60 (Sep. 2016) 40–51, [117] J. Du, Z. Zou, Y. Shi, D. Zhao, Zero latency: real-time synchronization of BIM data
https://doi.org/10.1016/J.EIAR.2016.03.007. in virtual reality for collaborative decision-making, Autom. Constr. 85 (Jan.
[92] O. Pons, J. Franquesa, S.M.A. Hosseini, Integrated value model to assess the 2018) 51–64, https://doi.org/10.1016/J.AUTCON.2017.10.009.
sustainability of active learning activities and strategies in architecture lectures [118] H. Deng, Y. Xu, Y. Deng, J. Lin, Transforming knowledge management in the
for large groups, Sustainability (Switzerland) 11 (10) (May 2019), https://doi. construction industry through information and communications technology: a 15-
org/10.3390/SU11102917. year review, Autom. Constr. 142 (Oct. 2022), 104530, https://doi.org/10.1016/
[93] O. Pons-Valladares, S.M.A. Hosseini, J. Franquesa, Innovative approach to assist J.AUTCON.2022.104530.
architecture teachers in choosing practical sessions, Sustainability (Switzerland) [119] S. Cursi, L. Martinelli, N. Paraciani, F. Calcerano, E. Gigliarelli, Linking external
14 (12) (Jun. 2022), https://doi.org/10.3390/SU14127081. knowledge to heritage BIM, Autom. Constr. 141 (Sep. 2022), 104444, https://doi.
[94] M. Zubizarreta, J. Ganzarain, J. Cuadrado, R. Lizarralde, Evaluating disruptive org/10.1016/J.AUTCON.2022.104444.
innovation project management capabilities, Sustainability (Switzerland) 13 (1) [120] C.P. Schimanski, N.L. Pradhan, D. Chaltsev, G. Pasetti Monizza, D.T. Matt,
(Jan. 2021) 1–22, https://doi.org/10.3390/SU13010001. Integrating BIM with lean construction approach: functional requirements and
[95] S.N. Joglekar, G. Dalwankar, N. Qureshi, S.A. Mandavgane, Sugarcane production management software, Autom. Constr. 132 (Dec. 2021), 103969,
valorization: selection of process routes based on sustainability index, Environ. https://doi.org/10.1016/J.AUTCON.2021.103969.
Sci. Pollut. Res. 29 (7) (Feb. 2022) 10812–10825, https://doi.org/10.1007/ [121] T. Tan, G. Mills, E. Papadonikolaki, Z. Liu, Combining multi-criteria decision
S11356-021-16375-Z. making (MCDM) methods with building information modelling (BIM): a review,
[96] M.P. de la Cruz, J.J. Cartelle, A. del Caño, M.C. Garaboa, J. Blanco Leis, Assessing Autom. Constr. 121 (Jan. 2021), 103451, https://doi.org/10.1016/J.
the risk of robbery in bank branches to reduce impact on personnel, Risk Anal. 42 AUTCON.2020.103451.
(2) (Feb. 2022) 385–405, https://doi.org/10.1111/RISA.13761. [122] S.M. Zolfaghari, O. Pons, J. Nikolic, Sustainability assessment model for mass
[97] C. Eastman, P. Teicholz, R. Sacks, K. Liston, BIM Handbook: A Guide to Building housing’s interior rehabilitation and its validation to Ekbatan, Iran, J. Build. Eng.
Information Modeling for Owners, Managers, Designers, Engineers and 65 (Apr. 2023), 105685, https://doi.org/10.1016/J.JOBE.2022.105685.
Contractors, John Wiley & Sons, 2011. ISBN: 978-0-470-54137-1. [123] J.C. Jurado, A. de la Fuente, J. Turmo, J.A. Lozano-Galant, Sustainability
[98] J.K.W. Wong, J. Zhou, Enhancing environmental sustainability over building life assessment through the coupling between BIM and MIVES methodologies applied
cycles through green BIM: a review, Autom. Constr. 57 (Sep. 2015) 156–165, in viaduct projects, May 2020. Accessed: Feb. 16, 2023. [Online]. Available: https
https://doi.org/10.1016/J.AUTCON.2015.06.003. ://upcommons.upc.edu/handle/2117/192869. Accessed: Feb. 16, 2023.
[99] J. Hull, I.J. Ewart, Conservation data parameters for BIM-enabled heritage asset [Online]. Available:.
management, Autom. Constr. 119 (Nov. 2020), 103333, https://doi.org/ [124] M. Daniel, G. Arroba, Análisis del grado de sostenibilidad del uso de la
10.1016/J.AUTCON.2020.103333. prefabricación en el sector hotelero, Sep. 2020. Accessed: Feb. 16, 2023. [Online].
[100] Y. Wang, V.K. Thangasamy, Z. Hou, R.L.K. Tiong, L. Zhang, Collaborative Available: https://upcommons.upc.edu/handle/2117/340536.
relationship discovery in BIM project delivery: a social network analysis [125] M. Veiskarami, Modular construction and overview on its potential advantages
approach, Autom. Constr. 114 (Jun. 2020), 103147, https://doi.org/10.1016/J. and constrains in the project management perspective, 2020. Accessed: Feb. 16,
AUTCON.2020.103147. 2023. [Online]. Available: https://upcommons.upc.edu/handle/2117/342645.
[101] K. Barlish, K. Sullivan, How to measure the benefits of BIM — a case study [126] P. Pujadas, F. Pardo-Bosch, A. Aguado-Renter, A. Aguado, MIVES multi-criteria
approach, Autom. Constr. 24 (Jul. 2012) 149–159, https://doi.org/10.1016/J. approach for the evaluation, prioritization, and selection of public investment
AUTCON.2012.02.008. projects. A case study in the city of Barcelona, Land Use Policy 64 (May 2017)
[102] T. Tan, G. Mills, E. Papadonikolaki, Z. Liu, Combining multi-criteria decision 29–37, https://doi.org/10.1016/j.landusepol.2017.02.014.
making (MCDM) methods with building information modelling (BIM): a review, [127] I. Garrucho, Desarrollo de una metodología para el proceso de diseño sostenible
Autom. Constr. 121 (Jan. 2021), 103451, https://doi.org/10.1016/J. de edificaciones industriales bajo requerimien-tos medioambientales, 2006.
AUTCON.2020.103451. Accessed: Sep. 13, 2022. [Online]. Available: https://dialnet.unirioja.es/servle
[103] K. Kim, H. Kim, W. Kim, C. Kim, J. Kim, J. Yu, Integration of ifc objects and t/tesis?codigo=212699&info=resumen&idioma=SPA.
facility management work information using semantic web, Autom. Constr. 87 [128] M.M. Casanovas, J. Armengou, G. Ramos, Occupational risk index for assessment
(Mar. 2018) 173–187, https://doi.org/10.1016/J.AUTCON.2017.12.019. of risk in construction work by activity, J. Constr. Eng. Manag. 140 (1) (Jan.
[104] H. Alavi, R. Bortolini, N. Forcada, BIM-based decision support for building 2014), https://doi.org/10.1061/(ASCE)CO.1943-7862.0000785.
condition assessment, Autom. Constr. 135 (Mar. 2022), 104117, https://doi.org/ [129] Generador de precios de la construcción. España. CYPE Ingenieros, S.A, 2023.
10.1016/J.AUTCON.2021.104117. http://www.generadordeprecios.info/#gsc.tab=0 (accessed Oct. 04, 2022).
[105] H. Alavi, N. Forcada, R. Bortolini, D.J. Edwards, Enhancing occupants’ comfort [130] Banco de precios y pliegos construcción - INDICE, 2023. https://itec.es/b
through BIM-based probabilistic approach, Autom. Constr. 123 (Mar. 2021), anco-precios-bedec/ (accessed Oct. 04, 2022).
103528, https://doi.org/10.1016/J.AUTCON.2020.103528.

15

You might also like