LIST OF THERMAL POWER STATIONS AS ON 31.03.

2018
Sl. No. Region/State/UT Sector Owner

1. Northern Region (NR)


1 Delhi State Sector IPGCL
Delhi State Sector IPGCL
2 Delhi State Sector IPGCL
Delhi State Sector IPGCL
Delhi State Sector IPGCL
Delhi State Sector IPGCL
Delhi State Sector IPGCL
Delhi State Sector IPGCL
Delhi State Sector IPGCL
Delhi State Sector IPGCL
Delhi State Sector IPGCL
3 Delhi State Sector PPCL
Delhi State Sector PPCL
Delhi State Sector PPCL
4 Delhi State Sector PPCL
Delhi State Sector PPCL
Delhi State Sector PPCL
Delhi State Sector PPCL
Delhi State Sector PPCL
Delhi State Sector PPCL
5 Delhi Private Sector TPDDL
Delhi Private Sector TPDDL
Delhi Private Sector TPDDL
Total (Delhi)
6 Haryana State Sector HPGCL
Haryana State Sector HPGCL
7 Haryana State Sector HPGCL
Haryana State Sector HPGCL
8 Haryana State Sector HPGCL
Haryana State Sector HPGCL
Haryana State Sector HPGCL
Haryana State Sector HPGCL
9 Haryana Private Sector JHAJJAR POWER LTD.
Haryana Private Sector JHAJJAR POWER LTD.
Total (Haryana)
10 Jammu & Kashmir State Sector JKSPDC
Jammu & Kashmir State Sector JKSPDC
Jammu & Kashmir State Sector JKSPDC
Jammu & Kashmir State Sector JKSPDC

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Jammu & Kashmir State Sector JKSPDC


Jammu & Kashmir State Sector JKSPDC
Jammu & Kashmir State Sector JKSPDC
Total (Jammu & Kashmir)
11 Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
12 Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
13 Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
14 Punjab Private Sector Nabha Power Ltd
Punjab Private Sector Nabha Power Ltd
15 Punjab Private Sector Talwandi Sabo Power Ltd
Punjab Private Sector Talwandi Sabo Power Ltd
Punjab Private Sector Talwandi Sabo Power Ltd
16 Punjab Private Sector GPGSL (GVK)
Punjab Private Sector GPGSL (GVK)
Total (Punjab)
17 Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
18 Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
19 Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

20 Rajasthan State Sector RRVUNL


Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVVNL
Rajasthan State Sector RRVVNL
21 Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
22 Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
23 Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
24 Rajasthan Private Sector Adani Power Ltd
Rajasthan Private Sector Adani Power Ltd
25 Rajasthan Private Sector RWPL (JSW)
Rajasthan Private Sector RWPL (JSW)
Rajasthan Private Sector RWPL (JSW)
Rajasthan Private Sector RWPL (JSW)
Rajasthan Private Sector RWPL (JSW)
Rajasthan Private Sector RWPL (JSW)
Rajasthan Private Sector RWPL (JSW)
Rajasthan Private Sector RWPL (JSW)
Total (Rajasthan)
26 Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
27 Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
28 Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Uttar Pardesh State Sector UPRVUNL


Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
29 Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
Uttar Pardesh State Sector UPRVUNL
30 Uttar Pardesh Private Sector BEPL
Uttar Pardesh Private Sector BEPL
31 Uttar Pardesh Private Sector BEPL
Uttar Pardesh Private Sector BEPL
32 Uttar Pardesh Private Sector BEPL
Uttar Pardesh Private Sector BEPL
33 Uttar Pardesh Private Sector BEPL
Uttar Pardesh Private Sector BEPL
34 Uttar Pardesh Private Sector BEPL
Uttar Pardesh Private Sector BEPL
35 Uttar Pardesh Private Sector LAPPL
Uttar Pardesh Private Sector LAPPL
36 Uttar Pardesh Private Sector RPSCL
Uttar Pardesh Private Sector RPSCL
Uttar Pardesh Private Sector RPSCL
Uttar Pardesh Private Sector RPSCL
37 Uttar Pardesh Private Sector LPGCL
Uttar Pardesh Private Sector LPGCL
Uttar Pardesh Private Sector LPGCL
38 Uttar Pardesh Private Sector PPGCL (Jaypee)
Uttar Pardesh Private Sector PPGCL (Jaypee)
Uttar Pardesh Private Sector PPGCL (Jaypee)
Total (Uttar Pardesh)
39 Uttarakhand Private Sector Gama infraprop Pvt. Ltd.
40 Uttarakhand Private Sector Sravanthi Energy Pvt. Ltd.
Total (Uttarakhand)
41 Delhi Central Sector NTPC
Delhi Central Sector NTPC
Delhi Central Sector NTPC

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Delhi Central Sector NTPC


Delhi Central Sector NTPC
42 Haryana Central Sector NTPC
Haryana Central Sector NTPC
Haryana Central Sector NTPC
43 Haryana Central Sector NTPC
Haryana Central Sector NTPC
Haryana Central Sector NTPC
44 Rajasthan Central Sector NLC
Rajasthan Central Sector NLC
45 Rajasthan Central Sector NTPC
Rajasthan Central Sector NTPC
Rajasthan Central Sector NTPC
Rajasthan Central Sector NTPC
46 Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
47 Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
48 Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
49 Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
50 Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Uttar Pardesh Central Sector NTPC


Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
51 Uttar Pardesh Central Sector MUNPL
52 Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
53 Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Uttar Pardesh Central Sector NTPC
Total Central Sector (Northern Region)
Northern Region Total
2. Western Region
54 Chhattisgarh State Sector CSPGCL
Chhattisgarh State Sector CSPGCL
Chhattisgarh State Sector CSPGCL
Chhattisgarh State Sector CSPGCL
55 Chhattisgarh State Sector CSPGCL
Chhattisgarh State Sector CSPGCL
56 Chhattisgarh State Sector CSPGCL
Chhattisgarh State Sector CSPGCL
57 Chhattisgarh State Sector CSPGCL
Chhattisgarh State Sector CSPGCL
Chhattisgarh State Sector CSPGCL
Chhattisgarh State Sector CSPGCL
Chhattisgarh State Sector CSPGCL
58 Chhattisgarh State Sector CSPGCL
Chhattisgarh State Sector CSPGCL
59 Chhattisgarh Private Sector Vandana Energy & Steel Pvt Ltd
60 Chhattisgarh Private Sector Lanco Amarkantak Power Ltd
Chhattisgarh Private Sector Lanco Amarkantak Power Ltd
61 Chhattisgarh Private Sector ACB (India) Ltd
Chhattisgarh Private Sector ACB (India) Ltd
62 Chhattisgarh Private Sector ACB (India) Ltd

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

63 Chhattisgarh Private Sector Jindal Power Limited


Chhattisgarh Private Sector Jindal Power Limited
Chhattisgarh Private Sector Jindal Power Limited
Chhattisgarh Private Sector Jindal Power Limited
64 Chhattisgarh Private Sector Jindal Power Limited
Chhattisgarh Private Sector Jindal Power Limited
Chhattisgarh Private Sector Jindal Power Limited
Chhattisgarh Private Sector Jindal Power Limited
65 Chhattisgarh Private Sector Spectrum Coal and Power Ltd
Chhattisgarh Private Sector Spectrum Coal and Power Ltd
66 Chhattisgarh Private Sector S V Power Private Limited
67 Chhattisgarh Private Sector Wardha Power Co Ltd
Chhattisgarh Private Sector Wardha Power Co Ltd
Chhattisgarh Private Sector Wardha Power Co Ltd
68 Chhattisgarh Private Sector Korba West Power Co Ltd
69 Chhattisgarh Private Sector DB Power Corp. Ltd
Chhattisgarh Private Sector DB Power Corp. Ltd
70 Chhattisgarh Private Sector GMR Chhattisgarh Energy Ltd
Chhattisgarh Private Sector GMR Chhattisgarh Energy Ltd
71 Chhattisgarh Private Sector Vandana Vidhyut Ltd
72 Chhattisgarh Private Sector ACB (India) Ltd
73 Chhattisgarh Private Sector RKM Powergen Pvt Ltd
Chhattisgarh Private Sector RKM Powergen Pvt Ltd
Chhattisgarh Private Sector RKM Powergen Pvt Ltd
74 Chhattisgarh Private Sector Maruti Clean Coal & Power Ltd
75 Chhattisgarh Private Sector Bharat Aluminium Co Ltd
Chhattisgarh Private Sector Bharat Aluminium Co Ltd
76 Chhattisgarh Private Sector TRN Energy Private Limited
Chhattisgarh Private Sector TRN Energy Private Limited
77 Chhattisgarh Private Sector SKS Power Generation Ltd
Chhattisgarh Private Sector SKS Power Generation Ltd
Total (Chhattisgarh)
78 Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
79 Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
80 Gujarat State Sector GSECL

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Gujarat State Sector GSECL


81 Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
82 Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
83 Gujarat State Sector GMD Corp. Ltd
Gujarat State Sector GMD Corp. Ltd
84 Gujarat State Sector Bhavnagar Energy Co. Ltd
Gujarat State Sector Bhavnagar Energy Co. Ltd
85 Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
86 Gujarat State Sector GSECL
87 Gujarat State Sector GSECL
Gujarat State Sector GSECL
88 Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
89 Gujarat State Sector GSECL
Gujarat State Sector GSECL
90 Gujarat Private Sector Torrent Power Generation Ltd
Gujarat Private Sector Torrent Power Generation Ltd
Gujarat Private Sector Torrent Power Generation Ltd
91 Gujarat Private Sector Torrent Power Generation Ltd
Gujarat Private Sector Torrent Power Generation Ltd
92 Gujarat Private Sector Torrent Power Generation Ltd
Gujarat Private Sector Torrent Power Generation Ltd
Gujarat Private Sector Torrent Power Generation Ltd
93 Gujarat Private Sector Torrent Power Generation Ltd
94 Gujarat Private Sector Essar Power Ltd
Gujarat Private Sector Essar Power Ltd

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Gujarat Private Sector Essar Power Ltd


Gujarat Private Sector Essar Power Ltd
95 Gujarat Private Sector Essar Power Gujarat Ltd
Gujarat Private Sector Essar Power Gujarat Ltd
96 Gujarat Private Sector Adani Power Ltd
Gujarat Private Sector Adani Power Ltd
Gujarat Private Sector Adani Power Ltd
Gujarat Private Sector Adani Power Ltd
Gujarat Private Sector Adani Power Ltd
Gujarat Private Sector Adani Power Ltd
Gujarat Private Sector Adani Power Ltd
Gujarat Private Sector Adani Power Ltd
Gujarat Private Sector Adani Power Ltd
97 Gujarat Private Sector Coastal Gujarat Power Ltd
Gujarat Private Sector Coastal Gujarat Power Ltd
Gujarat Private Sector Coastal Gujarat Power Ltd
Gujarat Private Sector Coastal Gujarat Power Ltd
Gujarat Private Sector Coastal Gujarat Power Ltd
98 Gujarat Private Sector GIPCL
Gujarat Private Sector GIPCL
99 Gujarat Private Sector GIPCL
Gujarat Private Sector GIPCL
Gujarat Private Sector GIPCL
Gujarat Private Sector GIPCL
100 Gujarat Private Sector CLP India Pvt Ltd
Gujarat Private Sector CLP India Pvt Ltd
Gujarat Private Sector CLP India Pvt Ltd
Gujarat Private Sector CLP India Pvt Ltd
101 Gujarat Private Sector Torrent Power Generation Ltd
Gujarat Private Sector Torrent Power Generation Ltd
Gujarat Private Sector Torrent Power Generation Ltd
Total (Gujarat)
102 Madhya Pradesh State Sector MPPGCL
103 Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
104 Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Madhya Pradesh State Sector MPPGCL


Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
105 Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
106 Madhya Pradesh Private Sector Essar Power MP Ltd
107 Madhya Pradesh Private Sector Jaipraksh Power Venture Ltd
Madhya Pradesh Private Sector Jaipraksh Power Venture Ltd
108 Madhya Pradesh Private Sector BLA Pvt Ltd
109 Madhya Pradesh Private Sector Sasan Power Ltd
Madhya Pradesh Private Sector Sasan Power Ltd
Madhya Pradesh Private Sector Sasan Power Ltd
Madhya Pradesh Private Sector Sasan Power Ltd
Madhya Pradesh Private Sector Sasan Power Ltd
Madhya Pradesh Private Sector Sasan Power Ltd
110 Madhya Pradesh Private Sector Jaipraksh Power Venture Ltd
Madhya Pradesh Private Sector Jaipraksh Power Venture Ltd
111 Madhya Pradesh Private Sector MB Power Madhya Pradesh Ltd
Madhya Pradesh Private Sector MB Power Madhya Pradesh Ltd
112 Madhya Pradesh Private Sector Jhabua Power Ltd
Total (Madhya Pradesh )
113 Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
114 Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
115 Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
116 Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Maharashtra State Sector MSPGCL


Maharashtra State Sector MSPGCL
117 Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
118 Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
119 Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
120 Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
Maharashtra State Sector MSPGCL
121 Maharashtra Private Sector Rattan India Power Ltd
Maharashtra Private Sector Rattan India Power Ltd
Maharashtra Private Sector Rattan India Power Ltd
Maharashtra Private Sector Rattan India Power Ltd
Maharashtra Private Sector Rattan India Power Ltd
122 Maharashtra Private Sector GMR Emco Energy Ltd
Maharashtra Private Sector GMR Emco Energy Ltd
123 Maharashtra Private Sector Adani Power Ltd
Maharashtra Private Sector Adani Power Ltd
Maharashtra Private Sector Adani Power Ltd
Maharashtra Private Sector Adani Power Ltd
Maharashtra Private Sector Adani Power Ltd
124 Maharashtra Private Sector Gupta Energy Pvt Ltd
Maharashtra Private Sector Gupta Energy Pvt Ltd
125 Maharashtra Private Sector Vidarbha Industries Power Ltd
Maharashtra Private Sector Vidarbha Industries Power Ltd
126 Maharashtra Private Sector Ideal Energy Projects Ltd
127 Maharashtra Private Sector Rattan India Power Ltd
Maharashtra Private Sector Rattan India Power Ltd
Maharashtra Private Sector Rattan India Power Ltd
Maharashtra Private Sector Rattan India Power Ltd
Maharashtra Private Sector Rattan India Power Ltd

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

128 Maharashtra Private Sector JSW Energy Ltd


Maharashtra Private Sector JSW Energy Ltd
Maharashtra Private Sector JSW Energy Ltd
Maharashtra Private Sector JSW Energy Ltd
129 Maharashtra Private Sector Abhijeet MADC Nagpur EPL
130 Maharashtra Private Sector Reliance Infrastructure Ltd
Maharashtra Private Sector Reliance Infrastructure Ltd
131 Maharashtra Private Sector Wardha Power Co. Ltd
Maharashtra Private Sector Wardha Power Co. Ltd
Maharashtra Private Sector Wardha Power Co. Ltd
Maharashtra Private Sector Wardha Power Co. Ltd
132 Maharashtra Private Sector Dhariwal Infrastructure Pvt Ltd
Maharashtra Private Sector Dhariwal Infrastructure Pvt Ltd
133 Maharashtra Private Sector Shirpur Power Pvt Ltd
134 Maharashtra Private Sector Tata Power Co. Ltd
Maharashtra Private Sector Tata Power Co. Ltd
Maharashtra Private Sector Tata Power Co. Ltd
135 Maharashtra Private Sector Tata Power Co. Ltd
Maharashtra Private Sector Tata Power Co. Ltd
136 Maharashtra Private Sector Pioneer Gas Power Ltd
Total (Maharashtra)
137 Goa Private Sector Reliance Energy Trading (P) Ltd
Total (Goa)
138 Chhattiagarh Central Sector NTPC
Chhattiagarh Central Sector NTPC
Chhattiagarh Central Sector NTPC
Chhattiagarh Central Sector NTPC
Chhattiagarh Central Sector NTPC
Chhattiagarh Central Sector NTPC
Chhattiagarh Central Sector NTPC
139 Chhattiagarh Central Sector NTPC-SAIL Power Co. LTD
Chhattiagarh Central Sector NTPC-SAIL Power Co. LTD
140 Chhattiagarh Central Sector NTPC
Chhattiagarh Central Sector NTPC
Chhattiagarh Central Sector NTPC
Chhattiagarh Central Sector NTPC
Chhattiagarh Central Sector NTPC
141 Chhattiagarh Central Sector NTPC
142 Gujarat Central Sector NTPC
Gujarat Central Sector NTPC

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Gujarat Central Sector NTPC


Gujarat Central Sector NTPC
143 Gujarat Central Sector NTPC
Gujarat Central Sector NTPC
Gujarat Central Sector NTPC
Gujarat Central Sector NTPC
Gujarat Central Sector NTPC
Gujarat Central Sector NTPC
144 Madhya Pradesh Central Sector NTPC
Madhya Pradesh Central Sector NTPC
Madhya Pradesh Central Sector NTPC
Madhya Pradesh Central Sector NTPC
Madhya Pradesh Central Sector NTPC
Madhya Pradesh Central Sector NTPC
Madhya Pradesh Central Sector NTPC
Madhya Pradesh Central Sector NTPC
Madhya Pradesh Central Sector NTPC
Madhya Pradesh Central Sector NTPC
Madhya Pradesh Central Sector NTPC
Madhya Pradesh Central Sector NTPC
Madhya Pradesh Central Sector NTPC
145 Maharashtra Central Sector NTPC
Maharashtra Central Sector NTPC
Maharashtra Central Sector NTPC
Maharashtra Central Sector NTPC
146 Maharashtra Central Sector NTPC
147 Maharashtra Central Sector RGPPL
Maharashtra Central Sector RGPPL
Maharashtra Central Sector RGPPL
Maharashtra Central Sector RGPPL
Maharashtra Central Sector RGPPL
Maharashtra Central Sector RGPPL
Maharashtra Central Sector RGPPL
Maharashtra Central Sector RGPPL
Maharashtra Central Sector RGPPL
Total Central Sector (Western Region)
Western Region Total
3. Southern Region
148 Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Andhra Pradesh State Sector APGENCO


Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
149 Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
150 Andhra Pradesh State Sector APPDCL
Andhra Pradesh State Sector APPDCL
151 Andhra Pradesh Private Sector LVS Power Ltd
Andhra Pradesh Private Sector LVS Power Ltd
152 Andhra Pradesh Private Sector Simhapuri Energy Pvt Ltd
Andhra Pradesh Private Sector Simhapuri Energy Pvt Ltd
Andhra Pradesh Private Sector Simhapuri Energy Pvt Ltd
Andhra Pradesh Private Sector Simhapuri Energy Pvt Ltd
153 Andhra Pradesh Private Sector Minakshi Energy Ltd
Andhra Pradesh Private Sector Minakshi Energy Ltd
154 Andhra Pradesh Private Sector Sembcorp Energy India Ltd
Andhra Pradesh Private Sector Sembcorp Energy India Ltd
155 Andhra Pradesh Private Sector HNPC
Andhra Pradesh Private Sector HNPC
156 Andhra Pradesh Private Sector Sembcorp Gayatri Power Ltd
Andhra Pradesh Private Sector Sembcorp Gayatri Power Ltd
157 Andhra Pradesh Private Sector Lanco Kondapalli Power Pvt Ltd
Andhra Pradesh Private Sector Lanco Kondapalli Power Pvt Ltd
Andhra Pradesh Private Sector Lanco Kondapalli Power Pvt Ltd
158 Andhra Pradesh Private Sector Lanco Kondapalli Power Pvt Ltd
Andhra Pradesh Private Sector Lanco Kondapalli Power Pvt Ltd
159 Andhra Pradesh Private Sector Lanco Kondapalli Power Pvt Ltd
Andhra Pradesh Private Sector Lanco Kondapalli Power Pvt Ltd
160 Andhra Pradesh Private Sector Gautami Power Ltd
Andhra Pradesh Private Sector Gautami Power Ltd
Andhra Pradesh Private Sector Gautami Power Ltd
161 Andhra Pradesh Private Sector APGPCL
Andhra Pradesh Private Sector APGPCL
Andhra Pradesh Private Sector APGPCL
LIST OF THERMAL POWER STATIONS AS ON 31.03.2018
Sl. No. Region/State/UT Sector Owner

Andhra Pradesh Private Sector APGPCL


Andhra Pradesh Private Sector APGPCL
162 Andhra Pradesh Private Sector Konaseema Gas Power Ltd
Andhra Pradesh Private Sector Konaseema Gas Power Ltd
Andhra Pradesh Private Sector Konaseema Gas Power Ltd
163 Andhra Pradesh Private Sector Reliance Infrastructure Ltd - A.P.
Andhra Pradesh Private Sector Reliance Infrastructure Ltd - A.P.
164 Andhra Pradesh State Sector APEPDCL
Andhra Pradesh State Sector APEPDCL
Andhra Pradesh State Sector APEPDCL
Andhra Pradesh State Sector APEPDCL
165 Andhra Pradesh Private Sector GVK Energy Ltd
Andhra Pradesh Private Sector GVK Energy Ltd
166 Andhra Pradesh Private Sector GMR Vemagiri Power Gen Ltd
Andhra Pradesh Private Sector GMR Vemagiri Power Gen Ltd
167 Andhra Pradesh Private Sector SPGL
Andhra Pradesh Private Sector SPGL
Andhra Pradesh Private Sector SPGL
Andhra Pradesh Private Sector SPGL
168 Andhra Pradesh Private Sector GMR Energy Ltd
Andhra Pradesh Private Sector GMR Energy Ltd
Andhra Pradesh Private Sector GMR Energy Ltd
Andhra Pradesh Private Sector GMR Energy Ltd
Andhra Pradesh Private Sector GMR Energy Ltd
169 Andhra Pradesh Private Sector GMR Rajahmundry Energy Ltd
Andhra Pradesh Private Sector GMR Rajahmundry Energy Ltd
Total (Andhra Pradesh)
170 Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
171 Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
172 Telangana State Sector TSGENCO
Telangana State Sector TSGENCO

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

173 Telangana State Sector TSGENCO


174 Telangana State Sector Singareni Collieries Co. Ltd
Telangana State Sector Singareni Collieries Co. Ltd
Total (Telangana)
175 Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
176 Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
177 Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
178 Karnataka State Sector KPCL
Karnataka State Sector KPCL
179 Karnataka Private Sector Shri Rayalseema pvt Ltd
180 Karnataka Private Sector JSW Energy Ltd
Karnataka Private Sector JSW Energy Ltd
181 Karnataka Private Sector JSW Energy Ltd
Karnataka Private Sector JSW Energy Ltd
182 Karnataka Private Sector Udupi Power Corp. Ltd
Karnataka Private Sector Udupi Power Corp. Ltd
Total (Karnataka)
183 Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
184 Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

185 Kerala Private Sector BSES Kerala Power Ltd


Kerala Private Sector BSES Kerala Power Ltd
Kerala Private Sector BSES Kerala Power Ltd
Kerala Private Sector BSES Kerala Power Ltd
Total (Kerala)
186 Puducherry State Sector PPCL
Puducherry State Sector PPCL
Total (Puducherry)
187 Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
188 Tamil Nadu State Sector TANGEDCO
189 Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
190 Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
191 Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
192 Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
193 Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
194 Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
195 Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
196 Tamil Nadu Private Sector Madurai Power Corp. Pvt Ltd
197 Tamil Nadu Private Sector GMR Power Corp. Pvt Ltd
198 Tamil Nadu Private Sector Samalpatti Power Co. Pvt Ltd

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

199 Tamil Nadu Private Sector Ind Barath Power infra Ltd
Tamil Nadu Private Sector Ind Barath Power infra Ltd
200 Tamil Nadu Private Sector ST-CMS Electric Co. Pvt ltd
201 Tamil Nadu Private Sector Coastal Energen Pvt Ltd
Tamil Nadu Private Sector Coastal Energen Pvt Ltd
202 Tamil Nadu Private Sector IL&FS Tamil Nadu Power Co. Ltd
Tamil Nadu Private Sector IL&FS Tamil Nadu Power Co. Ltd
203 Tamil Nadu Private Sector PPN Power Gen. Co. Pvt Ltd
Tamil Nadu Private Sector PPN Power Gen. Co. Pvt Ltd
204 Tamil Nadu Private Sector Aban Power Co. Ltd
Tamil Nadu Private Sector Aban Power Co. Ltd
205 Tamil Nadu Private Sector Pioneer Power Ltd
Tamil Nadu Private Sector Pioneer Power Ltd
Total (Tamil Nadu)
206 Andhra Pradesh Central Sector NTPC
Andhra Pradesh Central Sector NTPC
Andhra Pradesh Central Sector NTPC
Andhra Pradesh Central Sector NTPC
207 Telangana Central Sector NTPC
Telangana Central Sector NTPC
Telangana Central Sector NTPC
Telangana Central Sector NTPC
Telangana Central Sector NTPC
Telangana Central Sector NTPC
Telangana Central Sector NTPC
208 Karnataka Central Sector NTPC
Karnataka Central Sector NTPC
Karnataka Central Sector NTPC
209 Kerala Central Sector NTPC
Kerala Central Sector NTPC
Kerala Central Sector NTPC
210 Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

211 Tamil Nadu Central Sector Neyveli Lignite


Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
212 Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
213 Tamil Nadu Central Sector Neyveli Lignite
Tamil Nadu Central Sector Neyveli Lignite
214 Tamil Nadu Central Sector NTECL
Tamil Nadu Central Sector NTECL
Tamil Nadu Central Sector NTECL
215 Tamil Nadu Central Sector NTPL
Tamil Nadu Central Sector NTPL
Total Central Sector (Southern Region)
Southern Region Total
4. Eastern Region
216 A & N Islands State Sector Govt. Deptt.
Total (A & N Islands)
217 Bihar State Sector BSEB
Bihar State Sector BSEB
Bihar State Sector BSEB
Bihar State Sector BSEB
Total (Bihar)
218 Jharkhand State Sector Tenughat Vidyut Nigam Ltd
Jharkhand State Sector Tenughat Vidyut Nigam Ltd
219 Jharkhand Private Sector Tata Power Co. Ltd
Jharkhand Private Sector Tata Power Co. Ltd
220 Jharkhand Private Sector Adhunik Power Ltd
Jharkhand Private Sector Adhunik Power Ltd
221 Jharkhand Private Sector Maithon Power Ltd
Jharkhand Private Sector Maithon Power Ltd
Total (Jharkhand)
222 Odisha State Sector OPGCL
Odisha State Sector OPGCL
223 Odisha Private Sector Sterlite Energy Ltd
Odisha Private Sector Sterlite Energy Ltd
224 Odisha Private Sector GMR Energy Ltd

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner
Odisha Private Sector GMR Energy Ltd
Odisha Private Sector GMR Energy Ltd
225 Odisha Private Sector JITPL
Odisha Private Sector JITPL
226 Odisha Private Sector IBPIL
Total (Odisha)
227 West Bengal State Sector DPL
West Bengal State Sector DPL
West Bengal State Sector DPL
228 West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
229 West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
230 West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
231 West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
232 West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
233 West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
234 West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
235 West Bengal State Sector WBPDC
236 West Bengal Private Sector CESC Ltd
West Bengal Private Sector CESC Ltd
West Bengal Private Sector CESC Ltd
237 West Bengal Private Sector CESC Ltd

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

West Bengal Private Sector CESC Ltd


238 West Bengal Private Sector CESC Ltd
West Bengal Private Sector CESC Ltd
West Bengal Private Sector CESC Ltd
West Bengal Private Sector CESC Ltd
239 West Bengal Private Sector Haldia Energy Ltd
West Bengal Private Sector Haldia Energy Ltd
240 West Bengal Private Sector Hiranmaye Energy Ltd
West Bengal Private Sector Hiranmaye Energy Ltd
Total (West Bengal)
241 Bihar Central Sector NTPC
Bihar Central Sector NTPC
Bihar Central Sector NTPC
Bihar Central Sector NTPC
Bihar Central Sector NTPC
Bihar Central Sector NTPC
Bihar Central Sector NTPC
242 Bihar Central Sector NTPC
Bihar Central Sector NTPC
243 Bihar Central Sector KBUNL
Bihar Central Sector KBUNL
Bihar Central Sector KBUNL
Bihar Central Sector KBUNL
244 Bihar Central Sector BRBCL
Bihar Central Sector BRBCL
245 Jharkhand Central Sector DVC
246 Jharkhand Central Sector DVC
Jharkhand Central Sector DVC
247 Jharkhand Central Sector DVC
Jharkhand Central Sector DVC
Jharkhand Central Sector DVC
248 Jharkhand Central Sector DVC
Odisha Central Sector NTPC
249 Odisha Central Sector NTPC
Odisha Central Sector NTPC
Odisha Central Sector NTPC
Odisha Central Sector NTPC
Odisha Central Sector NTPC
250 Odisha Central Sector NTPC
Odisha Central Sector NTPC

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Odisha Central Sector NTPC


Odisha Central Sector NTPC
Odisha Central Sector NTPC
Odisha Central Sector NTPC
251 West Bengal Central Sector DVC
252 West Bengal Central Sector DVC
West Bengal Central Sector DVC
253 West Bengal Central Sector DVC
West Bengal Central Sector DVC
West Bengal Central Sector DVC
West Bengal Central Sector DVC
West Bengal Central Sector DVC
West Bengal Central Sector DVC
West Bengal Central Sector DVC
West Bengal Central Sector DVC
254 West Bengal Central Sector DVC
West Bengal Central Sector DVC
255 West Bengal Central Sector NTPC
West Bengal Central Sector NTPC
West Bengal Central Sector NTPC
West Bengal Central Sector NTPC
West Bengal Central Sector NTPC
West Bengal Central Sector NTPC
Total (DVC)
Total (NTPC)
Total Central Sector (DVC+NTPC) (Eastern Region)
Eastern Region Total
5. North Eastern Region
256 Assam State Sector APGCL
Assam State Sector APGCL
Assam State Sector APGCL
Assam State Sector APGCL
Assam State Sector APGCL
Assam State Sector APGCL
257 Assam State Sector APGCL
Assam State Sector APGCL
Assam State Sector APGCL
Assam State Sector APGCL
Assam State Sector APGCL
Assam State Sector APGCL

LIST OF THERMAL POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

258 Assam Private Sector DLF Power Supply Co. Ltd


Assam Private Sector DLF Power Supply Co. Ltd
Assam Private Sector DLF Power Supply Co. Ltd
259 Assam Private Sector DLF Power Supply Co. Ltd
Assam Private Sector DLF Power Supply Co. Ltd
Assam Private Sector DLF Power Supply Co. Ltd
Assam Private Sector DLF Power Supply Co. Ltd
Total (Assam)
260 Manipur State Sector Electricity Department Manipur
Manipur State Sector Electricity Department Manipur
Manipur State Sector Electricity Department Manipur
Manipur State Sector Electricity Department Manipur
Manipur State Sector Electricity Department Manipur
Manipur State Sector Electricity Department Manipur
Total (Manipur)
261 Tripura State Sector TSECL
Tripura State Sector TSECL
262 Tripura State Sector TSECL
Tripura State Sector TSECL
Tripura State Sector TSECL
Tripura State Sector TSECL
Tripura State Sector TSECL
Tripura State Sector TSECL
Tripura State Sector TSECL
Tripura State Sector TSECL
Tripura State Sector TSECL
Total (Tripura)
263 Tripura Central Sector NEEPCO
Tripura Central Sector NEEPCO
Tripura Central Sector NEEPCO
Tripura Central Sector NEEPCO
Tripura Central Sector NEEPCO
Tripura Central Sector NEEPCO
264 Tripura Central Sector NEEPCO
Tripura Central Sector NEEPCO
265 Tripura Central Sector ONGC
Tripura Central Sector ONGC
266 Assam Central Sector NTPC
Assam Central Sector NTPC
267 Assam Central Sector NEEPCO
L POWER STATIONS AS ON 31.03.2018
Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW

RAJGHAT TPS Steam 1 1 67.50 67.500


RAJGHAT TPS Steam 2 1 67.50 67.500
I.P. CCPP GT-Gas 1 1 30.00 30.000
I.P. CCPP GT-Gas 2 1 30.00 30.000
I.P. CCPP GT-Gas 3 1 30.00 30.000
I.P. CCPP GT-Gas 4 1 30.00 30.000
I.P. CCPP GT-Gas 5 1 30.00 30.000
I.P. CCPP GT-Gas 6 1 30.00 30.000
I.P. CCPP ST-Gas 7 1 30.00 30.000
I.P. CCPP ST-Gas 8 1 30.00 30.000
I.P. CCPP ST-Gas 9 1 30.00 30.000
PRAGATI CCPP GT-Gas 1 1 104.60 104.600
PRAGATI CCPP GT-Gas 2 1 104.60 104.600
PRAGATI CCPP ST-Gas 3 1 121.20 121.200
PRAGATI CCGT-III GT-Gas 1 1 250.00 250.000
PRAGATI CCGT-III GT-Gas 2 1 250.00 250.000
PRAGATI CCGT-III ST-Gas 3 1 250.00 250.000
PRAGATI CCGT-III GT-Gas 4 1 250.00 250.000
PRAGATI CCGT-III GT-Gas 5 1 250.00 250.000
PRAGATI CCGT-III ST-Gas 6 1 250.00 250.000
RITHALA CCPP GT-Gas 1 1 35.75 35.750
RITHALA CCPP GT-Gas 2 1 35.75 35.750
RITHALA CCPP ST-Gas 3 1 36.50 36.500
2343.400
YAMUNA NAGAR TPS Steam 1 1 300.00 300.000
YAMUNA NAGAR TPS Steam 2 1 300.00 300.000
RAJIV GANDHI TPS Steam 1 1 600.00 600.000
RAJIV GANDHI TPS Steam 2 1 600.00 600.000
PANIPAT TPS Steam 5 1 250.00 250.000
PANIPAT TPS Steam 6 1 250.00 250.000
PANIPAT TPS Steam 7 1 210.00 210.000
PANIPAT TPS Steam 8 1 210.00 210.000
MAHATMA GANDHI TPS Steam 1 1 660.00 660.000
MAHATMA GANDHI TPS Steam 2 1 660.00 660.000
4040.000
PAMPORE GPS (Liq.) GT-Gas 1 1 25.00 25.000
PAMPORE GPS (Liq.) GT-Gas 2 1 25.00 25.000
PAMPORE GPS (Liq.) GT-Gas 3 1 25.00 25.000
PAMPORE GPS (Liq.) GT-Gas 4 1 25.00 25.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
PAMPORE GPS (Liq.) GT-Gas 5 1 25.00 25.000
PAMPORE GPS (Liq.) GT-Gas 6 1 25.00 25.000
PAMPORE GPS (Liq.) GT-Gas 7 1 25.00 25.000
175.000
GND TPS(BHATINDA) Steam 1 1 110.00 110.000
GND TPS(BHATINDA) Steam 2 1 110.00 110.000
GND TPS(BHATINDA) Steam 3 1 110.00 110.000
GND TPS(BHATINDA) Steam 4 1 110.00 110.000
GH TPS (LEH.MOH.) Steam 1 1 210.00 210.000
GH TPS (LEH.MOH.) Steam 2 1 210.00 210.000
GH TPS (LEH.MOH.) Steam 3 1 250.00 250.000
GH TPS (LEH.MOH.) Steam 4 1 250.00 250.000
ROPAR TPS Steam 1 1 210.00 210.000
ROPAR TPS Steam 2 1 210.00 210.000
ROPAR TPS Steam 3 1 210.00 210.000
ROPAR TPS Steam 4 1 210.00 210.000
ROPAR TPS Steam 5 1 210.00 210.000
ROPAR TPS Steam 6 1 210.00 210.000
RAJPURA TPP Steam 1 1 700.00 700.000
RAJPURA TPP Steam 2 1 700.00 700.000
TALWANDI SABO TPP Steam 1 1 660.00 660.000
TALWANDI SABO TPP Steam 2 1 660.00 660.000
TALWANDI SABO TPP Steam 3 1 660.00 660.000
GOINDWAL SAHIB TPP Steam 1 1 270.00 270.000
GOINDWAL SAHIB TPP Steam 2 1 270.00 270.000
6540.000
KOTA TPS Steam 1 1 110.00 110.000
KOTA TPS Steam 2 1 110.00 110.000
KOTA TPS Steam 3 1 210.00 210.000
KOTA TPS Steam 4 1 210.00 210.000
KOTA TPS Steam 5 1 210.00 210.000
KOTA TPS Steam 6 1 195.00 195.000
KOTA TPS Steam 7 1 195.00 195.000
GIRAL TPS Steam 1 1 125.00 125.000
GIRAL TPS Steam 2 1 125.00 125.000
CHHABRA TPP Steam 1 1 250.00 250.000
CHHABRA TPP Steam 2 1 250.00 250.000
CHHABRA TPP Steam 3 1 250.00 250.000
CHHABRA TPP Steam 4 1 250.00 250.000
CHHABRA TPP Steam 5 1 660.00 660.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
SURATGARH TPS Steam 1 1 250.00 250.000
SURATGARH TPS Steam 2 1 250.00 250.000
SURATGARH TPS Steam 3 1 250.00 250.000
SURATGARH TPS Steam 4 1 250.00 250.000
SURATGARH TPS Steam 5 1 250.00 250.000
SURATGARH TPS Steam 6 1 250.00 250.000
KALISINDH TPS Steam 1 1 600.00 600.000
KALISINDH TPS Steam 2 1 600.00 600.000
DHOLPUR CCPP GT-Gas 1 1 110.00 110.000
DHOLPUR CCPP GT-Gas 2 1 110.00 110.000
DHOLPUR CCPP GT-Gas 3 1 110.00 110.000
RAMGARH CCPP GT-Gas 1 1 3.00 3.000
RAMGARH CCPP GT-Gas 2 1 35.50 35.500
RAMGARH CCPP GT-Gas 3 1 37.50 37.500
RAMGARH CCPP GT-Gas 4 1 37.80 37.800
RAMGARH CCPP GT-Gas 5 1 110.00 110.000
RAMGARH CCPP GT-Gas 6 1 50.00 50.000
KAWAI TPS Steam 1 1 660.00 660.000
KAWAI TPS Steam 2 1 660.00 660.000
JALIPA KAPURDI TPP Steam 1 1 135.00 135.000
JALIPA KAPURDI TPP Steam 2 1 135.00 135.000
JALIPA KAPURDI TPP Steam 3 1 135.00 135.000
JALIPA KAPURDI TPP Steam 4 1 135.00 135.000
JALIPA KAPURDI TPP Steam 5 1 135.00 135.000
JALIPA KAPURDI TPP Steam 6 1 135.00 135.000
JALIPA KAPURDI TPP Steam 7 1 135.00 135.000
JALIPA KAPURDI TPP Steam 8 1 135.00 135.000
8853.800
ANPARA TPS Steam 1 1 210.00 210.000
ANPARA TPS Steam 2 1 210.00 210.000
ANPARA TPS Steam 3 1 210.00 210.000
ANPARA TPS Steam 4 1 500.00 500.000
ANPARA TPS Steam 5 1 500.00 500.000
ANPARA TPS Steam 6 1 500.00 500.000
ANPARA TPS Steam 7 1 500.00 500.000
HARDUAGANJ TPS Steam 7 1 105.00 105.000
HARDUAGANJ TPS Steam 8 1 250.00 250.000
HARDUAGANJ TPS Steam 9 1 250.00 250.000
OBRA TPS Steam 7 1 94.00 94.000
OBRA TPS Steam 8 1 94.00 94.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
OBRA TPS Steam 9 1 200.00 200.000
OBRA TPS Steam 10 1 200.00 200.000
OBRA TPS Steam 11 1 200.00 200.000
OBRA TPS Steam 12 1 200.00 200.000
OBRA TPS Steam 13 1 200.00 200.000
PARICHHA TPS Steam 1 1 110.00 110.000
PARICHHA TPS Steam 2 1 110.00 110.000
PARICHHA TPS Steam 3 1 210.00 210.000
PARICHHA TPS Steam 4 1 210.00 210.000
PARICHHA TPS Steam 5 1 250.00 250.000
PARICHHA TPS Steam 6 1 250.00 250.000
KHAMBARKHERA TPS Steam 1 1 45.00 45.000
KHAMBARKHERA TPS Steam 2 1 45.00 45.000
MAQSOODPUR TPS Steam 1 1 45.00 45.000
MAQSOODPUR TPS Steam 2 1 45.00 45.000
BARKHERA TPS Steam 1 1 45.00 45.000
BARKHERA TPS Steam 2 1 45.00 45.000
UTRAULA TPS Steam 1 1 45.00 45.000
UTRAULA TPS Steam 2 1 45.00 45.000
KUNDARKI TPS Steam 1 1 45.00 45.000
KUNDARKI TPS Steam 2 1 45.00 45.000
ANPARA C TPS Steam 1 1 600.00 600.000
ANPARA C TPS Steam 2 1 600.00 600.000
ROSA TPP Ph-I Steam 1 1 300.00 300.000
ROSA TPP Ph-I Steam 2 1 300.00 300.000
ROSA TPP Ph-I Steam 3 1 300.00 300.000
ROSA TPP Ph-I Steam 4 1 300.00 300.000
LALITPUR TPS Steam 1 1 660.00 660.000
LALITPUR TPS Steam 2 1 660.00 660.000
LALITPUR TPS Steam 3 1 660.00 660.000
PRAYAGRAJ TPP Steam 1 1 660.00 660.000
PRAYAGRAJ TPP Steam 2 1 660.00 660.000
PRAYAGRAJ TPP Steam 3 1 660.00 660.000
12373.000
GAMA CCPP Steam 1 1 225.00 225.000
KASHIPUR CCPP Steam 1 1 225.00 225.000
450.000
BADARPUR TPS Steam 1 1 95.00 95.000
BADARPUR TPS Steam 2 1 95.00 95.000
BADARPUR TPS Steam 3 1 95.00 95.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
BADARPUR TPS Steam 4 1 210.00 210.000
BADARPUR TPS Steam 5 1 210.00 210.000
INDIRA GANDHI STPP Steam 1 1 500.00 500.000
INDIRA GANDHI STPP Steam 2 1 500.00 500.000
INDIRA GANDHI STPP Steam 3 1 500.00 500.000
FARIDABAD CCPP GT-Gas 1 1 137.76 137.760
FARIDABAD CCPP GT-Gas 2 1 137.76 137.760
FARIDABAD CCPP ST-Gas 3 1 156.07 156.070
BARSINGSAR LIGNITE Steam 1 1 125.00 125.000
BARSINGSAR LIGNITE Steam 2 1 125.00 125.000
ANTA CCPP GT-Gas 1 1 88.71 88.710
ANTA CCPP GT-Gas 2 1 88.71 88.710
ANTA CCPP GT-Gas 3 1 88.71 88.710
ANTA CCPP ST-Gas 4 1 153.20 153.200
DADRI (NCTPP) Steam 1 1 210.00 210.000
DADRI (NCTPP) Steam 2 1 210.00 210.000
DADRI (NCTPP) Steam 3 1 210.00 210.000
DADRI (NCTPP) Steam 4 1 210.00 210.000
DADRI (NCTPP) Steam 5 1 490.00 490.000
DADRI (NCTPP) Steam 6 1 490.00 490.000
RIHAND STPS Steam 1 1 500.00 500.000
RIHAND STPS Steam 2 1 500.00 500.000
RIHAND STPS Steam 3 1 500.00 500.000
RIHAND STPS Steam 4 1 500.00 500.000
RIHAND STPS Steam 5 1 500.00 500.000
RIHAND STPS Steam 6 1 500.00 500.000
SINGRAULI STPS Steam 1 1 200.00 200.000
SINGRAULI STPS Steam 2 1 200.00 200.000
SINGRAULI STPS Steam 3 1 200.00 200.000
SINGRAULI STPS Steam 4 1 200.00 200.000
SINGRAULI STPS Steam 5 1 200.00 200.000
SINGRAULI STPS Steam 6 1 500.00 500.000
SINGRAULI STPS Steam 7 1 500.00 500.000
TANDA TPS Steam 1 1 110.00 110.000
TANDA TPS Steam 2 1 110.00 110.000
TANDA TPS Steam 3 1 110.00 110.000
TANDA TPS Steam 4 1 110.00 110.000
UNCHAHAR TPS Steam 1 1 210.00 210.000
UNCHAHAR TPS Steam 2 1 210.00 210.000
UNCHAHAR TPS Steam 3 1 210.00 210.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
UNCHAHAR TPS Steam 4 1 210.00 210.000
UNCHAHAR TPS Steam 5 1 210.00 210.000
UNCHAHAR TPS Steam 6 1 500.00 500.000
MEJA STPP Steam 1 1 660.00 660.000
DADRI CCPP GT-Gas 1 1 130.19 130.190
DADRI CCPP GT-Gas 2 1 130.19 130.190
DADRI CCPP GT-Gas 3 1 130.19 130.190
DADRI CCPP GT-Gas 4 1 130.19 130.190
DADRI CCPP ST-Gas 5 1 154.51 154.510
DADRI CCPP ST-Gas 6 1 154.51 154.510
AURAIYA CCPP GT-Gas 1 1 111.19 111.190
AURAIYA CCPP GT-Gas 2 1 111.19 111.190
AURAIYA CCPP GT-Gas 3 1 111.19 111.190
AURAIYA CCPP GT-Gas 4 1 111.19 111.190
AURAIYA CCPP ST-Gas 5 1 109.30 109.300
AURAIYA CCPP ST-Gas 6 1 109.30 109.300
14269.060
49044.260

KORBA-II TPS Steam 1 1 50.00 50.000


KORBA-II TPS Steam 2 1 50.00 50.000
KORBA-II TPS Steam 3 1 50.00 50.000
KORBA-II TPS Steam 4 1 50.00 50.000
KORBA-III TPS Steam 1 1 120.00 120.000
KORBA-III TPS Steam 2 1 120.00 120.000
DSPM TPS Steam 1 1 250.00 250.000
DSPM TPS Steam 2 1 250.00 250.000
KORBA-WEST TPS Steam 1 1 210.00 210.000
KORBA-WEST TPS Steam 2 1 210.00 210.000
KORBA-WEST TPS Steam 3 1 210.00 210.000
KORBA-WEST TPS Steam 4 1 210.00 210.000
KORBA-WEST TPS Steam 5 1 500.00 500.000
MARWA TPS Steam 1 1 500.00 500.000
MARWA TPS Steam 2 1 500.00 500.000
KATGHORA TPP Steam 1 1 35.00 35.000
PATHADI TPP Steam 1 1 300.00 300.000
PATHADI TPP Steam 2 1 300.00 300.000
KASAIPALLI TPP Steam 1 1 135.00 135.000
KASAIPALLI TPP Steam 2 1 135.00 135.000
CHAKABURA TPP Steam 2 1 30.00 30.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
TAMNAR TPP Steam 1 1 600.00 600.000
TAMNAR TPP Steam 2 1 600.00 600.000
TAMNAR TPP Steam 3 1 600.00 600.000
TAMNAR TPP Steam 4 1 600.00 600.000
OP JINDAL TPS Steam 1 1 250.00 250.000
OP JINDAL TPS Steam 2 1 250.00 250.000
OP JINDAL TPS Steam 3 1 250.00 250.000
OP JINDAL TPS Steam 4 1 250.00 250.000
RATIJA TPS Steam 1 1 50.00 50.000
RATIJA TPS Steam 2 1 50.00 50.000
SVPL TPP Steam 1 1 63.00 63.000
AKALTARA TPS Steam 2 1 600.00 600.000
AKALTARA TPS Steam 3 1 600.00 600.000
AKALTARA TPS Steam 4 1 600.00 600.000
AVANTHA BHANDAR Steam 1 1 600.00 600.000
BARADARHA TPS Steam 1 1 600.00 600.000
BARADARHA TPS Steam 2 1 600.00 600.000
RAIKHEDA TPP Steam 1 1 685.00 685.000
RAIKHEDA TPP Steam 2 1 685.00 685.000
SALORA TPP Steam 1 1 135.00 135.000
SWASTIK KORBA TPP Steam 1 1 25.00 25.000
UCHPINDA TPP Steam 1 1 360.00 360.000
UCHPINDA TPP Steam 2 1 360.00 360.000
UCHPINDA TPP Steam 3 1 360.00 360.000
BANDAKHAR TPP Steam 1 1 300.00 300.000
BALCO TPS Steam 1 1 300.00 300.000
BALCO TPS Steam 2 1 300.00 300.000
NAWAPARA TPP Steam 1 1 300.00 300.000
NAWAPARA TPP Steam 2 1 300.00 300.000
BINJKOTE TPP Steam 1 1 300.00 300.000
BINJKOTE TPP Steam 2 1 300.00 300.000
16088.000
GANDHI NAGAR TPS Steam 3 1 210.00 210.000
GANDHI NAGAR TPS Steam 4 1 210.00 210.000
GANDHI NAGAR TPS Steam 5 1 210.00 210.000
KUTCH LIGNITE TPS Steam 1 1 70.00 70.000
KUTCH LIGNITE TPS Steam 2 1 70.00 70.000
KUTCH LIGNITE TPS Steam 3 1 75.00 75.000
KUTCH LIGNITE TPS Steam 4 1 75.00 75.000
SIKKA REP. TPS Steam 3 1 250.00 250.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
SIKKA REP. TPS Steam 4 1 250.00 250.000
UKAI TPS Steam 3 1 200.00 200.000
UKAI TPS Steam 4 1 200.00 200.000
UKAI TPS Steam 5 1 210.00 210.000
UKAI TPS Steam 6 1 500.00 500.000
WANAKBORI TPS Steam 1 1 210.00 210.000
WANAKBORI TPS Steam 2 1 210.00 210.000
WANAKBORI TPS Steam 3 1 210.00 210.000
WANAKBORI TPS Steam 4 1 210.00 210.000
WANAKBORI TPS Steam 5 1 210.00 210.000
WANAKBORI TPS Steam 6 1 210.00 210.000
WANAKBORI TPS Steam 7 1 210.00 210.000
AKRIMOTA LIG TPS Steam 1 1 125.00 125.000
AKRIMOTA LIG TPS Steam 2 1 125.00 125.000
BHAVNAGAR CFBC TPP Steam 1 1 250.00 250.000
BHAVNAGAR CFBC TPP Steam 2 1 250.00 250.000
HAZIRA CCPP GT-Gas 1 1 52.00 52.000
HAZIRA CCPP GT-Gas 2 1 52.00 52.000
HAZIRA CCPP GT-Gas 3 1 52.10 52.100
HAZIRA CCPP EXT GT-Gas 1 1 351.00 351.000
PIPAVAV CCPP GT-Gas 1 1 351.00 351.000
PIPAVAV CCPP GT-Gas 2 1 351.00 351.000
DHUVARAN CCPP GT-Gas 1 1 67.85 67.850
DHUVARAN CCPP GT-Gas 2 1 38.77 38.770
DHUVARAN CCPP GT-Gas 3 1 72.00 72.000
DHUVARAN CCPP GT-Gas 4 1 40.00 40.000
DHUVARAN CCPP GT-Gas 5 1 376.10 376.100
UTRAN CCPP GT-Gas 5 1 240.00 240.000
UTRAN CCPP GT-Gas 6 1 134.00 134.000
SABARMATI (D-F STATIONS) Steam 1 1 120.00 120.000
SABARMATI (D-F STATIONS) Steam 2 1 121.00 121.000
SABARMATI (D-F STATIONS) Steam 3 1 121.00 121.000
SABARMATI (C STATION) Steam 15 1 30.00 30.000
SABARMATI (C STATION) Steam 16 1 30.00 30.000
SUGEN CCPP GT-Gas 1 1 382.50 382.500
SUGEN CCPP GT-Gas 2 1 382.50 382.500
SUGEN CCPP GT-Gas 3 1 382.50 382.500
UNOSUGEN CCPP GT-Gas 1 1 382.50 382.500
ESSAR CCPP GT-Gas 1 1 110.00 110.000
ESSAR CCPP GT-Gas 2 1 110.00 110.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
ESSAR CCPP GT-Gas 3 1 110.00 110.000
ESSAR CCPP GT-Gas 4 1 185.00 185.000
SALAYA TPP Steam 1 1 600.00 600.000
SALAYA TPP Steam 2 1 600.00 600.000
MUNDRA TPS Steam 1 1 330.00 330.000
MUNDRA TPS Steam 2 1 330.00 330.000
MUNDRA TPS Steam 3 1 330.00 330.000
MUNDRA TPS Steam 4 1 330.00 330.000
MUNDRA TPS Steam 5 1 660.00 660.000
MUNDRA TPS Steam 6 1 660.00 660.000
MUNDRA TPS Steam 7 1 660.00 660.000
MUNDRA TPS Steam 8 1 660.00 660.000
MUNDRA TPS Steam 9 1 660.00 660.000
MUNDRA UMTPP Steam 1 1 800.00 800.000
MUNDRA UMTPP Steam 2 1 800.00 800.000
MUNDRA UMTPP Steam 3 1 800.00 800.000
MUNDRA UMTPP Steam 4 1 800.00 800.000
MUNDRA UMTPP Steam 5 1 800.00 800.000
BARODA CCPP GT-Gas 5 1 106.00 106.000
BARODA CCPP GT-Gas 6 1 54.00 54.000
SURAT LIG. TPS Steam 1 1 125.00 125.000
SURAT LIG. TPS Steam 2 1 125.00 125.000
SURAT LIG. TPS Steam 3 1 125.00 125.000
SURAT LIG. TPS Steam 4 1 125.00 125.000
PEGUTHAN CCPP GT-Gas 1 1 135.00 135.000
PEGUTHAN CCPP GT-Gas 2 1 135.00 135.000
PEGUTHAN CCPP GT-Gas 3 1 135.00 135.000
PEGUTHAN CCPP ST-Gas 4 1 250.00 250.000
DGEN MEGA CCPP GT-Gas 1 1 400.00 400.000
DGEN MEGA CCPP GT-Gas 2 1 400.00 400.000
DGEN MEGA CCPP GT-Gas 3 1 400.00 400.000
21729.820
AMARKANTAK EXT TPS Steam 3 1 210.00 210.000
SANJAY GANDHI TPS Steam 1 1 210.00 210.000
SANJAY GANDHI TPS Steam 2 1 210.00 210.000
SANJAY GANDHI TPS Steam 3 1 210.00 210.000
SANJAY GANDHI TPS Steam 4 1 210.00 210.000
SANJAY GANDHI TPS Steam 5 1 500.00 500.000
SATPURA TPS Steam 6 1 200.00 200.000
SATPURA TPS Steam 7 1 210.00 210.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
SATPURA TPS Steam 8 1 210.00 210.000
SATPURA TPS Steam 9 1 210.00 210.000
SATPURA TPS Steam 10 1 250.00 250.000
SATPURA TPS Steam 11 1 250.00 250.000
SHRI SINGHAJI TPP Steam 1 1 600.00 600.000
SHRI SINGHAJI TPP Steam 2 1 600.00 600.000
MAHAN TPP Steam 1 1 600.00 600.000
BINA TPS Steam 1 1 250.00 250.000
BINA TPS Steam 2 1 250.00 250.000
NIWARI TPP Steam 1 1 45.00 45.000
SASAN UMTPP Steam 1 1 660.00 660.000
SASAN UMTPP Steam 2 1 660.00 660.000
SASAN UMTPP Steam 3 1 660.00 660.000
SASAN UMTPP Steam 4 1 660.00 660.000
SASAN UMTPP Steam 5 1 660.00 660.000
SASAN UMTPP Steam 6 1 660.00 660.000
NIGRI TPP Steam 1 1 660.00 660.000
NIGRI TPP Steam 2 1 660.00 660.000
ANUPPUR TPP Steam 1 1 600.00 600.000
ANUPPUR TPP Steam 2 1 600.00 600.000
SEIONI TPP Steam 1 1 600.00 600.000
12305.000
BHUSAWAL TPS Steam 3 1 210.00 210.000
BHUSAWAL TPS Steam 4 1 500.00 500.000
BHUSAWAL TPS Steam 5 1 500.00 500.000
CHANDRAPUR(MAHARASHTRA) STPS Steam 3 1 210.00 210.000
CHANDRAPUR(MAHARASHTRA) STPS Steam 4 1 210.00 210.000
CHANDRAPUR(MAHARASHTRA) STPS Steam 5 1 500.00 500.000
CHANDRAPUR(MAHARASHTRA) STPS Steam 6 1 500.00 500.000
CHANDRAPUR(MAHARASHTRA) STPS Steam 7 1 500.00 500.000
CHANDRAPUR(MAHARASHTRA) STPS Steam 8 1 500.00 500.000
CHANDRAPUR(MAHARASHTRA) STPS Steam 9 1 500.00 500.000
KHAPARKHEDA TPS Steam 1 1 210.00 210.000
KHAPARKHEDA TPS Steam 2 1 210.00 210.000
KHAPARKHEDA TPS Steam 3 1 210.00 210.000
KHAPARKHEDA TPS Steam 4 1 210.00 210.000
KHAPARKHEDA TPS Steam 5 1 500.00 500.000
KORADI TPS Steam 6 1 210.00 210.000
KORADI TPS Steam 7 1 210.00 210.000
KORADI TPS Steam 8 1 660.00 660.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
KORADI TPS Steam 9 1 660.00 660.000
KORADI TPS Steam 10 1 660.00 660.000
NASIK TPS Steam 3 1 210.00 210.000
NASIK TPS Steam 4 1 210.00 210.000
NASIK TPS Steam 5 1 210.00 210.000
PARAS TPS Steam 1 1 250.00 250.000
PARAS TPS Steam 2 1 250.00 250.000
PARLI TPS Steam 4 1 210.00 210.000
PARLI TPS Steam 5 1 210.00 210.000
PARLI TPS Steam 6 1 250.00 250.000
PARLI TPS Steam 7 1 250.00 250.000
PARLI TPS Steam 8 1 250.00 250.000
URAN CCPP GT-Gas 5 1 108.00 108.000
URAN CCPP GT-Gas 6 1 108.00 108.000
URAN CCPP GT-Gas 7 1 108.00 108.000
URAN CCPP GT-Gas 8 1 108.00 108.000
URAN CCPP ST-Gas 9 1 120.00 120.000
URAN CCPP ST-Gas 10 1 120.00 120.000
NASIK (P) TPS Steam 1 1 270.00 270.000
NASIK (P) TPS Steam 2 1 270.00 270.000
NASIK (P) TPS Steam 3 1 270.00 270.000
NASIK (P) TPS Steam 4 1 270.00 270.000
NASIK (P) TPS Steam 5 1 270.00 270.000
EMCO WARORA TPS Steam 1 1 300.00 300.000
EMCO WARORA TPS Steam 2 1 300.00 300.000
TIRORA TPS Steam 1 1 660.00 660.000
TIRORA TPS Steam 2 1 660.00 660.000
TIRORA TPS Steam 3 1 660.00 660.000
TIRORA TPS Steam 4 1 660.00 660.000
TIRORA TPS Steam 5 1 660.00 660.000
GEPL TPP Ph-I Steam 1 1 60.00 60.000
GEPL TPP Ph-I Steam 2 1 60.00 60.000
BUTIBORI TPP Steam 1 1 300.00 300.000
BUTIBORI TPP Steam 2 1 300.00 300.000
BELA TPS Steam 1 1 270.00 270.000
AMARAVATI TPS Steam 1 1 270.00 270.000
AMARAVATI TPS Steam 2 1 270.00 270.000
AMARAVATI TPS Steam 3 1 270.00 270.000
AMARAVATI TPS Steam 4 1 270.00 270.000
AMARAVATI TPS Steam 5 1 270.00 270.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
JSW RATNAGIRI TPP Steam 1 1 300.00 300.000
JSW RATNAGIRI TPP Steam 2 1 300.00 300.000
JSW RATNAGIRI TPP Steam 3 1 300.00 300.000
JSW RATNAGIRI TPP Steam 4 1 300.00 300.000
MIHAN TPS Steam 1 1 246.00 246.000
DAHANU TPS Steam 1 1 250.00 250.000
DAHANU TPS Steam 2 1 250.00 250.000
WARDHA WARORA TPP Steam 1 1 135.00 135.000
WARDHA WARORA TPP Steam 2 1 135.00 135.000
WARDHA WARORA TPP Steam 3 1 135.00 135.000
WARDHA WARORA TPP Steam 4 1 135.00 135.000
DHARIWAL TPP Steam 1 1 300.00 300.000
DHARIWAL TPP Steam 2 1 300.00 300.000
SHIRPUR TPP Steam 1 1 150.00 150.000
TROMBAY TPS Steam 5 1 500.00 500.000
TROMBAY TPS Steam 6 1 500.00 500.000
TROMBAY TPS Steam 8 1 250.00 250.000
TROMBAY CCPP GT-Gas 1 1 120.00 120.000
TROMBAY CCPP GT-Gas 2 1 60.00 60.000
MANGAON CCPP GT-Gas 1 1 388.00 388.000
23486.000
GOA CCPP (Liq.) GT-Gas 1 48.00 48.000
48.000
KORBA STPS Steam 1 1 200.00 200.000
KORBA STPS Steam 2 1 200.00 200.000
KORBA STPS Steam 3 1 200.00 200.000
KORBA STPS Steam 4 1 500.00 500.000
KORBA STPS Steam 5 1 500.00 500.000
KORBA STPS Steam 6 1 500.00 500.000
KORBA STPS Steam 7 1 500.00 500.000
BHILAI TPS Steam 1 1 250.00 250.000
BHILAI TPS Steam 2 1 250.00 250.000
SIPAT STPS Steam 1 1 660.00 660.000
SIPAT STPS Steam 2 1 660.00 660.000
SIPAT STPS Steam 3 1 660.00 660.000
SIPAT STPS Steam 4 1 500.00 500.000
SIPAT STPS Steam 5 1 500.00 500.000
LARA TPP Steam 1 1 800.00 800.000
GANDHAR CCPP GT-Gas 1 1 144.30 144.300
GANDHAR CCPP GT-Gas 2 1 144.30 144.300

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
GANDHAR CCPP GT-Gas 3 1 144.30 144.300
GANDHAR CCPP ST-Gas 4 1 224.49 224.490
KAWAS CCPP GT-Gas 1 1 106.00 106.000
KAWAS CCPP GT-Gas 2 1 106.00 106.000
KAWAS CCPP GT-Gas 3 1 106.00 106.000
KAWAS CCPP GT-Gas 4 1 106.00 106.000
KAWAS CCPP ST-Gas 5 1 116.10 116.100
KAWAS CCPP ST-Gas 6 1 116.10 116.100
VINDHYACHAL STPS Steam 1 1 210.00 210.000
VINDHYACHAL STPS Steam 2 1 210.00 210.000
VINDHYACHAL STPS Steam 3 1 210.00 210.000
VINDHYACHAL STPS Steam 4 1 210.00 210.000
VINDHYACHAL STPS Steam 5 1 210.00 210.000
VINDHYACHAL STPS Steam 6 1 210.00 210.000
VINDHYACHAL STPS Steam 7 1 500.00 500.000
VINDHYACHAL STPS Steam 8 1 500.00 500.000
VINDHYACHAL STPS Steam 9 1 500.00 500.000
VINDHYACHAL STPS Steam 10 1 500.00 500.000
VINDHYACHAL STPS Steam 11 1 500.00 500.000
VINDHYACHAL STPS Steam 12 1 500.00 500.000
VINDHYACHAL STPS Steam 13 1 500.00 500.000
MAUDA TPS Steam 1 1 500.00 500.000
MAUDA TPS Steam 2 1 500.00 500.000
MAUDA TPS Steam 3 1 660.00 660.000
MAUDA TPS Steam 4 1 660.00 660.000
SOLAPUR STPS Steam 1 1 660.00 660.000
RATNAGIRI CCPP GT-Gas 1 1 205.00 205.000
RATNAGIRI CCPP GT-Gas 2 1 205.00 205.000
RATNAGIRI CCPP ST-Gas 3 1 230.00 230.000
RATNAGIRI CCPP GT-Gas 4 1 213.00 213.000
RATNAGIRI CCPP GT-Gas 5 1 213.00 213.000
RATNAGIRI CCPP ST-Gas 6 1 237.54 237.540
RATNAGIRI CCPP GT-Gas 7 1 213.00 213.000
RATNAGIRI CCPP GT-Gas 8 1 213.00 213.000
RATNAGIRI CCPP ST-Gas 9 1 237.54 237.540
17900.670
91557.490

RAYALASEEMA TPS Steam 1 1 210.00 210.000


RAYALASEEMA TPS Steam 2 1 210.00 210.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
RAYALASEEMA TPS Steam 3 1 210.00 210.000
RAYALASEEMA TPS Steam 4 1 210.00 210.000
RAYALASEEMA TPS Steam 5 1 210.00 210.000
RAYALASEEMA TPS Steam 6 1 600.00 600.000
Dr. N.TATA RAO TPS Steam 1 1 210.00 210.000
Dr. N.TATA RAO TPS Steam 2 1 210.00 210.000
Dr. N.TATA RAO TPS Steam 3 1 210.00 210.000
Dr. N.TATA RAO TPS Steam 4 1 210.00 210.000
Dr. N.TATA RAO TPS Steam 5 1 210.00 210.000
Dr. N.TATA RAO TPS Steam 6 1 210.00 210.000
Dr. N.TATA RAO TPS Steam 7 1 500.00 500.000
DAMODARAM SANJEEVAIAH TPS Steam 1 1 800.00 800.000
DAMODARAM SANJEEVAIAH TPS Steam 2 1 800.00 800.000
L.V.S. Diesel Power Station Diesel 1 1 18.40 18.400
L.V.S. Diesel Power Station Diesel 2 1 18.40 18.400
SIMHAPURI TPS Steam 1 1 150.00 150.000
SIMHAPURI TPS Steam 2 1 150.00 150.000
SIMHAPURI TPS Steam 3 1 150.00 150.000
SIMHAPURI TPS Steam 4 1 150.00 150.000
THAMMINAPATNAM TPS Steam 1 1 150.00 150.000
THAMMINAPATNAM TPS Steam 2 1 150.00 150.000
PAINAMPURAM TPP Steam 1 1 660.00 660.000
PAINAMPURAM TPP Steam 2 1 660.00 660.000
VIZAG TPP Steam 1 1 520.00 520.000
VIZAG TPP Steam 2 1 520.00 520.000
SGPL TPP Steam 1 1 660.00 660.000
SGPL TPP Steam 2 1 660.00 660.000
KONDAPALLI CCPP GT-Gas 1 1 112.00 112.000
KONDAPALLI CCPP GT-Gas 2 1 112.00 112.000
KONDAPALLI CCPP ST-Gas 3 1 126.00 126.000
KONDAPALLI EXTN CCPP GT-Gas 1 1 233.00 233.000
KONDAPALLI EXTN CCPP GT-Gas 2 1 133.00 133.000
KONDAPALLI ST-3 CCPP GT-Gas 1 1 371.00 371.000
KONDAPALLI ST-3 CCPP GT-Gas 2 1 371.00 371.000
GAUTAMI CCPP GT-Gas 1 1 145.00 145.000
GAUTAMI CCPP GT-Gas 2 1 145.00 145.000
GAUTAMI CCPP ST-Gas 3 1 174.00 174.000
VIJJESWARAM CCPP GT-Gas 1 1 33.00 33.000
VIJJESWARAM CCPP GT-Gas 2 1 33.00 33.000
VIJJESWARAM CCPP GT-Gas 3 1 34.00 34.000
L POWER STATIONS AS ON 31.03.2018
Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
VIJJESWARAM CCPP GT-Gas 4 1 112.00 112.000
VIJJESWARAM CCPP GT-Gas 5 1 60.00 60.000
KONASEEMA CCPP GT-Gas 1 1 140.00 140.000
KONASEEMA CCPP GT-Gas 2 1 140.00 140.000
KONASEEMA CCPP ST-Gas 3 1 165.00 165.000
PEDDAPURAM CCPP GT-Gas 1 1 142.00 142.000
PEDDAPURAM CCPP GT-Gas 2 1 78.00 78.000
JEGURUPADU PHASE I CCPP GT-Gas 1 1 52.80 52.800
JEGURUPADU PHASE I CCPP GT-Gas 2 1 52.80 52.800
JEGURUPADU PHASE I CCPP GT-Gas 3 1 52.80 52.800
JEGURUPADU PHASE I CCPP ST-Gas 4 1 77.00 77.000
JEGURUPADU PHASE II CCPP GT-Gas 1 1 140.00 140.000
JEGURUPADU PHASE II CCPP GT-Gas 2 1 80.00 80.000
VEMAGIRI CCPP GT-Gas 1 1 233.00 233.000
VEMAGIRI CCPP GT-Gas 2 1 137.00 137.000
GODAVARI CCPP GT-Gas 1 1 47.00 47.000
GODAVARI CCPP GT-Gas 2 1 47.00 47.000
GODAVARI CCPP GT-Gas 3 1 47.00 47.000
GODAVARI CCPP ST-Gas 4 1 67.00 67.000
GMR Energy Ltd - Kakinada GT-Gas 1 1 42.50 42.500
GMR Energy Ltd - Kakinada GT-Gas 2 1 42.50 42.500
GMR Energy Ltd - Kakinada GT-Gas 3 1 42.50 42.500
GMR Energy Ltd - Kakinada GT-Gas 4 1 42.50 42.500
GMR Energy Ltd - Kakinada ST-Gas 5 1 50.00 50.000
GREL CCPP (Rajahmundry) GT-Gas 1 1 384.00 384.000
GREL CCPP (Rajahmundry) GT-Gas 2 1 384.00 384.000
14507.200
KOTHAGUDEM TPS (NEW) Steam 1 1 250.00 250.000
KOTHAGUDEM TPS (NEW) Steam 2 1 250.00 250.000
KOTHAGUDEM TPS (NEW) Steam 3 1 500.00 500.000
KOTHAGUDEM TPS Steam 1 1 60.00 60.000
KOTHAGUDEM TPS Steam 2 1 60.00 60.000
KOTHAGUDEM TPS Steam 3 1 60.00 60.000
KOTHAGUDEM TPS Steam 4 1 60.00 60.000
KOTHAGUDEM TPS Steam 5 1 120.00 120.000
KOTHAGUDEM TPS Steam 6 1 120.00 120.000
KOTHAGUDEM TPS Steam 7 1 120.00 120.000
KOTHAGUDEM TPS Steam 8 1 120.00 120.000
KAKATIYA TPS Steam 1 1 500.00 500.000
KAKATIYA TPS Steam 2 1 600.00 600.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
RAMAGUNDEM - B TPS Steam 1 1 62.50 62.500
SINGARENI TPP Steam 1 1 600.00 600.000
SINGARENI TPP Steam 2 1 600.00 600.000
4082.500
YELHANKA (DG) Diesel 1 1 21.32 21.320
YELHANKA (DG) Diesel 2 1 21.32 21.320
YELHANKA (DG) Diesel 3 1 21.32 21.320
YELHANKA (DG) Diesel 4 1 21.32 21.320
YELHANKA (DG) Diesel 5 1 21.32 21.320
YELHANKA (DG) Diesel 6 1 21.32 21.320
RAICHUR TPS Steam 1 1 210.00 210.000
RAICHUR TPS Steam 2 1 210.00 210.000
RAICHUR TPS Steam 3 1 210.00 210.000
RAICHUR TPS Steam 4 1 210.00 210.000
RAICHUR TPS Steam 5 1 210.00 210.000
RAICHUR TPS Steam 6 1 210.00 210.000
RAICHUR TPS Steam 7 1 210.00 210.000
RAICHUR TPS Steam 8 1 250.00 250.000
BELLARY TPS Steam 1 1 500.00 500.000
BELLARY TPS Steam 2 1 500.00 500.000
BELLARY TPS Steam 3 1 700.00 700.000
YERMARUS TPP Steam 1 1 800.00 800.000
YERMARUS TPP Steam 2 1 800.00 800.000
BELLARY DG Diesel 2 12.60 25.200
TORANGALLU TPS(SBU-I) Steam 1 1 130.00 130.000
TORANGALLU TPS(SBU-I) Steam 2 1 130.00 130.000
TORANGALLU TPS(SBU-II) Steam 1 1 300.00 300.000
TORANGALLU TPS(SBU-II) Steam 2 1 300.00 300.000
UDUPI TPP Steam 1 1 600.00 600.000
UDUPI TPP Steam 2 1 600.00 600.000
7233.120
BRAMHAPURAM DG Diesel 1 1 21.32 21.320
BRAMHAPURAM DG Diesel 4 1 21.32 21.320
BRAMHAPURAM DG Diesel 5 1 21.32 21.320
KOZHIKODE DG Diesel 2 1 16.00 16.000
KOZHIKODE DG Diesel 3 1 16.00 16.000
KOZHIKODE DG Diesel 5 1 16.00 16.000
KOZHIKODE DG Diesel 6 1 16.00 16.000
KOZHIKODE DG Diesel 7 1 16.00 16.000
KOZHIKODE DG Diesel 8 1 16.00 16.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
COCHIN CCPP (Liq.) GT-Gas 1 1 45.00 45.000
COCHIN CCPP (Liq.) GT-Gas 2 1 45.00 45.000
COCHIN CCPP (Liq.) GT-Gas 4 1 45.00 45.000
COCHIN CCPP (Liq.) GT-Gas 3 1 39.00 39.000
333.960
KARAIKAL CCPP GT-Gas 1 1 22.90 22.900
KARAIKAL CCPP GT-Gas 2 1 9.60 9.600
32.500
METTUR TPS Steam 1 1 210.00 210.000
METTUR TPS Steam 2 1 210.00 210.000
METTUR TPS Steam 3 1 210.00 210.000
METTUR TPS Steam 4 1 210.00 210.000
METTUR TPS-II Steam 1 1 600.00 600.000
NORTH CHENNAI TPS Steam 1 1 210.00 210.000
NORTH CHENNAI TPS Steam 2 1 210.00 210.000
NORTH CHENNAI TPS Steam 3 1 210.00 210.000
NORTH CHENNAI TPS Steam 4 1 600.00 600.000
NORTH CHENNAI TPS Steam 5 1 600.00 600.000
TUTICORIN TPS Steam 1 1 210.00 210.000
TUTICORIN TPS Steam 2 1 210.00 210.000
TUTICORIN TPS Steam 3 1 210.00 210.000
TUTICORIN TPS Steam 4 1 210.00 210.000
TUTICORIN TPS Steam 5 1 210.00 210.000
KUTTALAM CCPP GT-Gas 1 1 63.00 63.000
KUTTALAM CCPP GT-Gas 2 1 37.00 37.000
BASIN BRIDGE GT (Liq.) GT-Gas 1 1 30.00 30.000
BASIN BRIDGE GT (Liq.) GT-Gas 2 1 30.00 30.000
BASIN BRIDGE GT (Liq.) GT-Gas 3 1 30.00 30.000
BASIN BRIDGE GT (Liq.) GT-Gas 4 1 30.00 30.000
KOVIKALPAL CCPP GT-Gas 1 1 69.65 69.650
KOVIKALPAL CCPP GT-Gas 2 1 38.23 38.230
NARIMANAM GPS GT-Gas 1 1 5.00 5.000
NARIMANAM GPS GT-Gas 2 1 5.00 5.000
VALUTHUR CCPP GT-Gas 1 1 60.00 60.000
VALUTHUR CCPP GT-Gas 2 1 59.80 59.800
VALUTHUR CCPP GT-Gas 3 1 34.00 34.000
VALUTHUR CCPP GT-Gas 4 1 32.40 32.400
SAMAYANALLUR DG Diesel 7 15.14 106.001
B. BRIDGE DG Diesel 4 50.00 200.000
SAMALPATTI DG Diesel 7 15.10 105.700

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
TUTICORIN (P) TPP Steam 1 1 150.00 150.000
TUTICORIN (P) TPP Steam 2 1 150.00 150.000
NEYVELI TPS(Z) Steam 1 1 250.00 250.000
MUTHIARA TPP Steam 1 1 600.00 600.000
MUTHIARA TPP Steam 2 1 600.00 600.000
ITPCL TPP Steam 1 1 600.00 600.000
ITPCL TPP Steam 2 1 600.00 600.000
P.NALLUR CCPP GT-Gas 1 1 225.00 225.000
P.NALLUR CCPP GT-Gas 2 1 105.50 105.500
KARUPPUR CCPP GT-Gas 1 1 70.00 70.000
KARUPPUR CCPP ST-Gas 2 1 49.80 49.800
VALANTARVY CCPP GT-Gas 1 1 38.00 38.000
VALANTARVY CCPP GT-Gas 2 1 14.80 14.800
8708.881
SIMHADRI TPS Steam 1 1 500.00 500.000
SIMHADRI TPS Steam 2 1 500.00 500.000
SIMHADRI TPS Steam 3 1 500.00 500.000
SIMHADRI TPS Steam 4 1 500.00 500.000
RAMAGUNDEM STPS Steam 1 1 200.00 200.000
RAMAGUNDEM STPS Steam 2 1 200.00 200.000
RAMAGUNDEM STPS Steam 3 1 200.00 200.000
RAMAGUNDEM STPS Steam 4 1 500.00 500.000
RAMAGUNDEM STPS Steam 5 1 500.00 500.000
RAMAGUNDEM STPS Steam 6 1 500.00 500.000
RAMAGUNDEM STPS Steam 7 1 500.00 500.000
KUDGI STPP Steam 1 1 800.00 800.000
KUDGI STPP Steam 2 1 800.00 800.000
KUDGI STPP Steam 3 1 800.00 800.000
R. GANDHI CCPP (Liq.) GT-Gas 1 1 115.20 115.200
R. GANDHI CCPP (Liq.) GT-Gas 2 1 115.20 115.200
R. GANDHI CCPP (Liq.) ST-Gas 3 1 129.18 129.180
NEYVELI TPS- I Steam 1 1 50.00 50.000
NEYVELI TPS- I Steam 2 1 50.00 50.000
NEYVELI TPS- I Steam 3 1 50.00 50.000
NEYVELI TPS- I Steam 4 1 50.00 50.000
NEYVELI TPS- I Steam 5 1 50.00 50.000
NEYVELI TPS- I Steam 6 1 50.00 50.000
NEYVELI TPS- I Steam 7 1 100.00 100.000
NEYVELI TPS- I Steam 8 1 100.00 100.000
NEYVELI TPS- I Steam 9 1 100.00 100.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
NEYVELI TPS- II Steam 1 1 210.00 210.000
NEYVELI TPS- II Steam 2 1 210.00 210.000
NEYVELI TPS- II Steam 3 1 210.00 210.000
NEYVELI TPS- II Steam 4 1 210.00 210.000
NEYVELI TPS- II Steam 5 1 210.00 210.000
NEYVELI TPS- II Steam 6 1 210.00 210.000
NEYVELI TPS- II Steam 7 1 210.00 210.000
NEYVELI TPS-II EXP Steam 1 1 250.00 250.000
NEYVELI TPS-II EXP Steam 2 1 250.00 250.000
NEYVELI ( EXT) TPS Steam 1 1 210.00 210.000
NEYVELI ( EXT) TPS Steam 2 1 210.00 210.000
VALLUR TPP Steam 1 1 500.00 500.000
VALLUR TPP Steam 2 1 500.00 500.000
VALLUR TPP Steam 3 1 500.00 500.000
TUTICORIN (JV) TPP Steam 1 1 500.00 500.000
TUTICORIN (JV) TPP Steam 2 1 500.00 500.000
12849.580
47747.741

AND. NICOBAR DG Diesel 1 40.05 40.048


40.048
BARAUNI TPS Steam 6 1 105.00 105.000
BARAUNI TPS Steam 7 1 105.00 105.000
BARAUNI TPS Steam 8 1 250.00 250.000
BARAUNI TPS Steam 9 1 250.00 250.000
710.000
TENUGHAT TPS Steam 1 1 210.00 210.000
TENUGHAT TPS Steam 2 1 210.00 210.000
JOJOBERA TPS Steam 2 1 120.00 120.000
JOJOBERA TPS Steam 3 1 120.00 120.000
MAHADEV PRASAD STPP Steam 1 1 270.00 270.000
MAHADEV PRASAD STPP Steam 2 1 270.00 270.000
MAITHON RB TPP Steam 1 1 525.00 525.000
MAITHON RB TPP Steam 2 1 525.00 525.000
2250.000
IB VALLEY TPS Steam 1 1 210.00 210.000
IB VALLEY TPS Steam 2 1 210.00 210.000
STERLITE TPP Steam 1 1 600.00 600.000
STERLITE TPP Steam 2 1 600.00 600.000
KAMALANGA TPS Steam 1 1 350.00 350.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
KAMALANGA TPS Steam 2 1 350.00 350.000
KAMALANGA TPS Steam 3 1 350.00 350.000
DERANG TPP Steam 1 1 600.00 600.000
DERANG TPP Steam 2 1 600.00 600.000
UTKAL TPP (IND BARATH) Steam 1 1 350.00 350.000
4220.000
D.P.L. TPS Steam 6 1 110.00 110.000
D.P.L. TPS Steam 7 1 300.00 300.000
D.P.L. TPS Steam 8 1 250.00 250.000
BAKRESWAR TPS Steam 1 1 210.00 210.000
BAKRESWAR TPS Steam 2 1 210.00 210.000
BAKRESWAR TPS Steam 3 1 210.00 210.000
BAKRESWAR TPS Steam 4 1 210.00 210.000
BAKRESWAR TPS Steam 5 1 210.00 210.000
BANDEL TPS Steam 1 1 210.00 210.000
BANDEL TPS Steam 2 1 60.00 60.000
BANDEL TPS Steam 3 1 60.00 60.000
BANDEL TPS Steam 4 1 60.00 60.000
BANDEL TPS Steam 5 1 60.00 60.000
KOLAGHAT TPS Steam 1 1 210.00 210.000
KOLAGHAT TPS Steam 2 1 210.00 210.000
KOLAGHAT TPS Steam 3 1 210.00 210.000
KOLAGHAT TPS Steam 4 1 210.00 210.000
KOLAGHAT TPS Steam 5 1 210.00 210.000
KOLAGHAT TPS Steam 6 1 210.00 210.000
SANTALDIH TPS Steam 5 1 250.00 250.000
SANTALDIH TPS Steam 6 1 250.00 250.000
SAGARDIGHI TPS Steam 1 1 300.00 300.000
SAGARDIGHI TPS Steam 2 1 300.00 300.000
SAGARDIGHI TPS Steam 3 1 500.00 500.000
SAGARDIGHI TPS Steam 4 1 500.00 500.000
HALDIA GT (Liq.) GT-Gas 1 1 20.00 20.000
HALDIA GT (Liq.) GT-Gas 2 1 20.00 20.000
KASBA GT (Liq.) GT-Gas 1 1 20.00 20.000
KASBA GT (Liq.) GT-Gas 2 1 20.00 20.000
SILIGURI GPS GT-Gas 1 1 20.00 20.000
BUDGE BUDGE TPS Steam 1 1 250.00 250.000
BUDGE BUDGE TPS Steam 2 1 250.00 250.000
BUDGE BUDGE TPS Steam 3 1 250.00 250.000
SOUTHERN REPL. TPS Steam 1 1 67.50 67.500

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
SOUTHERN REPL. TPS Steam 2 1 67.50 67.500
TITAGARH TPS Steam 1 1 60.00 60.000
TITAGARH TPS Steam 2 1 60.00 60.000
TITAGARH TPS Steam 3 1 60.00 60.000
TITAGARH TPS Steam 4 1 60.00 60.000
HALDIA TPP Steam 1 1 300.00 300.000
HALDIA TPP Steam 2 1 300.00 300.000
HIRANMAYE TPP Steam 1 1 150.00 150.000
HIRANMAYE TPP Steam 2 1 150.00 150.000
7645.000
KAHALGAON TPS Steam 1 1 210.00 210.000
KAHALGAON TPS Steam 2 1 210.00 210.000
KAHALGAON TPS Steam 3 1 210.00 210.000
KAHALGAON TPS Steam 4 1 210.00 210.000
KAHALGAON TPS Steam 5 1 500.00 500.000
KAHALGAON TPS Steam 6 1 500.00 500.000
KAHALGAON TPS Steam 7 1 500.00 500.000
BARH II STPP Steam 4 1 660.00 660.000
BARH II STPP Steam 5 1 660.00 660.000
MUZAFFARPUR TPS Steam 1 1 110.00 110.000
MUZAFFARPUR TPS Steam 2 1 110.00 110.000
MUZAFFARPUR TPS Steam 3 1 195.00 195.000
MUZAFFARPUR TPS Steam 4 1 195.00 195.000
NABI NAGAR TPP Steam 1 1 250.00 250.000
NABI NAGAR TPP Steam 2 1 250.00 250.000
BOKARO `B` TPS Steam 3 1 210.00 210.000
KODARMA TPP Steam 1 1 500.00 500.000
KODARMA TPP Steam 2 1 500.00 500.000
CHANDRAPURA(DVC) Steam 3 1 130.00 130.000
CHANDRAPURA(DVC) Steam 7 1 250.00 250.000
CHANDRAPURA(DVC) Steam 8 1 250.00 250.000
BOKARO `A` TPS Steam 1 1 500.00 500.000
TALCHER STPS Steam 1 1 500.00 500.000
TALCHER STPS Steam 2 1 500.00 500.000
TALCHER STPS Steam 3 1 500.00 500.000
TALCHER STPS Steam 4 1 500.00 500.000
TALCHER STPS Steam 5 1 500.00 500.000
TALCHER STPS Steam 6 1 500.00 500.000
TALCHER (OLD) TPS Steam 1 1 60.00 60.000
TALCHER (OLD) TPS Steam 2 1 60.00 60.000

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
TALCHER (OLD) TPS Steam 3 1 60.00 60.000
TALCHER (OLD) TPS Steam 4 1 60.00 60.000
TALCHER (OLD) TPS Steam 5 1 110.00 110.000
TALCHER (OLD) TPS Steam 6 1 110.00 110.000
DURGAPUR TPS Steam 4 1 210.00 210.000
DURGAPUR STEEL TPS Steam 1 1 500.00 500.000
DURGAPUR STEEL TPS Steam 2 1 500.00 500.000
MEJIA TPS Steam 1 1 210.00 210.000
MEJIA TPS Steam 2 1 210.00 210.000
MEJIA TPS Steam 3 1 210.00 210.000
MEJIA TPS Steam 4 1 210.00 210.000
MEJIA TPS Steam 5 1 250.00 250.000
MEJIA TPS Steam 6 1 250.00 250.000
MEJIA TPS Steam 7 1 500.00 500.000
MEJIA TPS Steam 8 1 500.00 500.000
RAGHUNATHPUR TPP Steam 1 1 600.00 600.000
RAGHUNATHPUR TPP Steam 2 1 600.00 600.000
FARAKKA STPS Steam 1 1 200.00 200.000
FARAKKA STPS Steam 2 1 200.00 200.000
FARAKKA STPS Steam 3 1 200.00 200.000
FARAKKA STPS Steam 4 1 500.00 500.000
FARAKKA STPS Steam 5 1 500.00 500.000
FARAKKA STPS Steam 6 1 500.00 500.000
7090.000
10330.000
17420.000
32285.048

LAKWA GT GT-Gas 2 1 15.00 15.000


LAKWA GT GT-Gas 3 1 15.00 15.000
LAKWA GT GT-Gas 5 1 20.00 20.000
LAKWA GT GT-Gas 6 1 20.00 20.000
LAKWA GT GT-Gas 7 1 20.00 20.000
LAKWA GT GT-Gas 8 1 37.20 37.200
NAMRUP CCPP GT-Gas 2 1 21.00 21.000
NAMRUP CCPP GT-Gas 3 1 21.00 21.000
NAMRUP CCPP GT-Gas 4 1 11.00 11.000
NAMRUP CCPP GT-Gas 5 1 24.00 24.000
NAMRUP CCPP GT-Gas 6 1 22.00 22.000
NAMRUP CCPP GT-Gas 7 1 62.25 62.250

L POWER STATIONS AS ON 31.03.2018


Name of Project Prime Unit No. No. of Units Capacity Total Capacity
Mover
MW MW
Adamtilla CCPP GT-Gas 1 1 3.00 3.000
Adamtilla CCPP GT-Gas 2 1 3.00 3.000
Adamtilla CCPP GT-Gas 3 1 3.00 3.000
Baskhandi CCPP GT-Gas 1 1 3.50 3.500
Baskhandi CCPP GT-Gas 2 1 3.50 3.500
Baskhandi CCPP GT-Gas 3 1 3.50 3.500
Baskhandi CCPP GT-Gas 4 1 5.00 5.000
312.950
LEIMAKHONG DG Diesel 1 6.00 6.000
LEIMAKHONG DG Diesel 1 6.00 6.000
LEIMAKHONG DG Diesel 1 6.00 6.000
LEIMAKHONG DG Diesel 1 6.00 6.000
LEIMAKHONG DG Diesel 1 6.00 6.000
LEIMAKHONG DG Diesel 1 6.00 6.000
36.000
BARAMURA GT GT-Gas 4 1 37.50 37.500
BARAMURA GT GT-Gas 5 1 21.00 21.000
ROKHIA GT GT-Gas 1 1 8.00 8.000
ROKHIA GT GT-Gas 2 1 8.00 8.000
ROKHIA GT GT-Gas 3 1 8.00 8.000
ROKHIA GT GT-Gas 4 1 8.00 8.000
ROKHIA GT GT-Gas 5 1 8.00 8.000
ROKHIA GT GT-Gas 6 1 8.00 8.000
ROKHIA GT GT-Gas 7 1 21.00 21.000
ROKHIA GT GT-Gas 8 1 21.00 21.000
ROKHIA GT GT-Gas 9 1 21.00 21.000
169.500
AGARTALA GT GT-Gas 1 1 21.00 21.000
AGARTALA GT GT-Gas 2 1 21.00 21.000
AGARTALA GT GT-Gas 3 1 21.00 21.000
AGARTALA GT GT-Gas 4 1 21.00 21.000
AGARTALA GT GT-Gas 5 1 25.50 25.500
AGARTALA GT GT-Gas 6 1 25.50 25.500
MONARCHAK CCPP GT-Gas 1 1 65.40 65.400
MONARCHAK CCPP GT-Gas 3 1 35.60 35.600
TRIPURA CCPP GT-Gas 1 1 363.30 363.300
TRIPURA CCPP GT-Gas 2 1 363.30 363.300
BONGAIGAON TPP Steam 1 1 250.00 250.000
BONGAIGAON TPP Steam 2 1 250.00 250.000
KATHALGURI CCPP GT-Gas 1 1 33.50 33.500
Appendix-A

Year of Comm.

1989
1989
1986
1986
1986
1986
1986
1986
1995
1995
1996
2002
2002
2003
2010
2011
2012
2012
2013
2014
2010
2010
2011

2007
2008
2010
2010
1989
2001
2004
2005
2012
2012

1989
1989
1989
1994
Appendix-A

Year of Comm.

1994
1994
1995

1974
1975
1978
1979
1997
1998
2008
2008
1984
1985
1988
1989
1992
1993
2014
2014
2014
2015
2016
2016
2016

1983
1983
1988
1989
1994
2003
2009
2007
2010
2009
2010
2013
2014
2017
Appendix-A

Year of Comm.

1998
2000
2001
2002
2003
2009
2014
2015
2007
2007
2007
1994
1996
2002
2003
2013
2013
2013
2013
2009
2010
2011
2011
2013
2013
2013
2013

1986
1987
1988
1993
1994
2015
2016
1978
2011
2012
1974
1975
Appendix-A

Year of Comm.

1980
1979
1977
1981
1982
1984
1985
2006
2006
2012
2013
2011
2011
2011
2012
2011
2012
2012
2012
2012
2012
2011
2011
2010
2010
2011
2012
2016
2016
2016
2015
2016
2017

2016
2016

1973
1974
1975
Appendix-A

Year of Comm.

1978
1981
2010
2011
2012
1999
1999
2000
2010
2011
1989
1989
1989
1989
1991
1992
1993
1994
2010
2010
1988
1989
2005
2005
2012
2013
1982
1982
1983
1983
1984
1986
1987
1988
1989
1990
1998
1988
1989
1999
Appendix-A
Year of Comm.

1999
2006
2017
2018
1992
1992
1992
1992
1994
1994
1989
1989
1989
1989
1989
1990

1966
1967
1968
1968
1976
1981
2007
2007
1984
1983
1985
1986
2013
2014
2016
2012
2009
2010
2011
2012
2014
Appendix-A

Year of Comm.

2014
2014
2015
2015
2007
2008
2008
2008
2013
2016
2011
2018
2013
2014
2014
2014
2015
2015
2016
2015
2015
2015
2016
2017
2015
2015
2016
2016
2017
2017
2018

1990
1991
1998
1990
1991
1997
2009
2015
Appendix-A

Year of Comm.

2015
1979
1979
1985
2013
1982
1983
1984
1986
1986
1987
1998
2005
2005
2016
2017
2001
2001
2002
2012
2014
2013
2003
2003
2006
2007
2014
2009
2009
1978
1984
1988
1962
1963
2009
2009
2009
2013
1995
1995
Appendix-A

Year of Comm.

1995
1997
2012
2012
2009
2010
2010
2010
2010
2011
2011
2012
2012
2012
2012
2012
2013
2013
1997
1997
2000
1999
2010
2010
1997
1997
1998
1998
2014
2014
2014

2008
1993
1994
1999
1999
2007
1979
1980
Appendix-A

Year of Comm.

1983
1984
2013
2013
2013
2014
2013
2012
2013
2013
2013
2013
2014
2014
2014
2015
2014
2015
2015
2016
2016

1982
2012
2012
1985
1986
1991
1992
1997
2015
2016
1989
1990
2000
2001
2011
1982
1983
2015
Appendix-A

Year of Comm.

2016
2016
1979
1980
1981
2007
2010
1985
1987
2007
2010
2016
1985
1985
1985
1985
1994
1994
2014
2017
2017
2017
2017
2013
2013
2012
2013
2013
2014
2014
2012
2012
2012
2014
2013
2013
2014
2015
2015
2015
Appendix-A

Year of Comm.

2010
2010
2011
2011
2012
1995
1995
2010
2010
2011
2011
2013
2014
2017
1984
1990
2009
1993
1994
2016

1999

1983
1983
1984
1987
1988
1989
2010
2008
2009
2011
2011
2012
2007
2008
2018
1994
1994
Appendix-A

Year of Comm.

1994
1995
1992
1992
1992
1992
1993
1993
1987
1988
1989
1989
1990
1991
1999
2000
2006
2007
2012
2013
2015
2012
2013
2016
2017
2017
1998
1998
1998
2006
2006
2006
2007
2007
2007

1994
1995
Appendix-A

Year of Comm.

2007
2007
2010
2018
1979
1980
1989
1990
1994
1995
2009
2014
2015
2001
2001
2012
2012
2014
2015
2012
2013
2015
2015
2015
2016
2016
2017
2000
2000
2000
2009
2010
2015
2015
2009
2009
2009
2012
2012
2012
Appendix-A
Year of Comm.

2012
2012
2009
2009
2010
2002
2002
1996
1996
1996
1997
2005
2005
2006
2006
1997
1997
1997
1998
2001
2001
2001
2001
2001
2015
2015

1997
1998
2011
1966
1966
1967
1967
1974
1974
1977
1978
2010
2015
Appendix-A

Year of Comm.

1971
2016
2016

1999
1999
1999
1999
1999
1999
1985
1986
1991
1994
1999
1999
2002
2010
2007
2012
2016
2016
2017
2000
1999
1999
2009
2009
2010
2011

1997
1997
1997
1999
1999
1999
1999
1999
1999
Appendix-A

Year of Comm.

1999
1999
1999
2000

1998
1999

1987
1987
1989
1990
2012
1994
1995
1996
2013
2013
1979
1980
1982
1992
1991
2003
2004
1996
1996
1996
1996
2001
2001
1992
1992
2002
2008
2003
2009
2001
1998
2000
Appendix-A

Year of Comm.

2013
2013
2002
2015
2016
2015
2016
2001
2001
2005
2005
2005
2006

2002
2002
2011
2012
1983
1984
1984
1988
1989
1989
2004
2016
2017
2018
1998
1999
1999
1962
1963
1963
1963
1964
1965
1967
1969
1970
Appendix-A

Year of Comm.

1988
1987
1986
1991
1991
1992
1993
2012
2015
2002
2003
2012
2013
2014
2015
2015

2000

1983
1985
2018
2018

1994
1996
2001
2002
2012
2013
2011
2012

1994
1995
2010
2010
2013
Appendix-A

Year of Comm.
2013
2014
2014
2015
2016

1985
2007
2014
1999
2000
2001
2007
2009
1982
1965
1965
1966
1966
1990
1985
1984
1993
1991
1993
2007
2011
2007
2008
2015
2016
1979
1979
1979
1979
1980
1997
1999
2009
1991
Appendix-A

Year of Comm.

1990
1985
1982
1983
1984
2015
2015
2017
2017

1992
1994
1995
1996
2007
2008
2009
2013
2015
1985
1986
2015
2017
2016
2017
1993
2011
2013
1968
2009
2010
2016
1995
1996
2003
2003
2004
2005
1967
1968
Appendix-A

Year of Comm.

1968
1969
1982
1983
1982
2011
2012
1995
1997
1998
2004
2007
2007
2010
2011
2014
2016
1986
1986
1987
1992
1994
2011
1981
1983
1994
1994
1995
2012
1965
1965
1975
1976
1985
2017
Appendix-A

Year of Comm.

1997
1997
1998
1997
1997
1997
1998

2002
2002
2002
2002
2002
2002

2002
2010
1990
1990
1995
1995
1997
1997
2002
2006
2013

1998
1998
1998
1998
2015
2016
2015
2016
2013
2014
2015
2017
1995
Appendix-A
LIST OF THERMAL POWER STATIONS AS ON 31.03.2018
Sl. No. Region/State/UT Sector Owner Name of Project

Assam Central Sector NEEPCO KATHALGURI CCPP


Assam Central Sector NEEPCO KATHALGURI CCPP
Assam Central Sector NEEPCO KATHALGURI CCPP
Assam Central Sector NEEPCO KATHALGURI CCPP
Assam Central Sector NEEPCO KATHALGURI CCPP
Assam Central Sector NEEPCO KATHALGURI CCPP
Assam Central Sector NEEPCO KATHALGURI CCPP
Assam Central Sector NEEPCO KATHALGURI CCPP
Total Central Sector (North Eastern Region)
North Eastern Region Total
Total All India Thermal
Prime Unit No. No. of Units Capacity Total Capacity Year of Comm.
Mover
MW MW
P GT-Gas 2 1 33.50 33.500 1995
P GT-Gas 3 1 33.50 33.500 1995
P GT-Gas 4 1 33.50 33.500 1995
P GT-Gas 5 1 33.50 33.500 1996
P GT-Gas 6 1 33.50 33.500 1996
P GT-Gas 7 1 30.00 30.000 1998
P GT-Gas 8 1 30.00 30.000 1998
P GT-Gas 9 1 30.00 30.000 1998
1753.600
2272.050
222906.589
LIST OF HYDRO POWER STATIONS AS ON 31.03.2018
Sl. No. Region/State/UT Sector Owner

1. Northern Region (NR)


1 BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
2 BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
3 BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
4 BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
5 BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
BBMB State Sector BBMB
Total (BBMB)
6 Himachal Pradesh State Sector HPSEB
Himachal Pradesh State Sector HPSEB
Himachal Pradesh State Sector HPSEB
Himachal Pradesh State Sector HPSEB
7 Himachal Pradesh State Sector HPSEB
Himachal Pradesh State Sector HPSEB
8 Himachal Pradesh State Sector HPSEB

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Himachal Pradesh State Sector HPSEB


Himachal Pradesh State Sector HPSEB
9 Himachal Pradesh State Sector HPSEB
Himachal Pradesh State Sector HPSEB
Himachal Pradesh State Sector HPSEB
10 Himachal Pradesh State Sector HPPCL
Himachal Pradesh State Sector HPPCL
Himachal Pradesh State Sector HPPCL
11 Himachal Pradesh State Sector HPPCL
Himachal Pradesh State Sector HPPCL
12 Himachal Pradesh Private Sector JKHCL
Himachal Pradesh Private Sector JKHCL
Himachal Pradesh Private Sector JKHCL
Himachal Pradesh Private Sector JKHCL
13 Himachal Pradesh Private Sector EPPL
Himachal Pradesh Private Sector EPPL
14 Himachal Pradesh Private Sector ADHPL
Himachal Pradesh Private Sector ADHPL
15 Himachal Pradesh Private Sector HBPCL
Himachal Pradesh Private Sector HBPCL
Himachal Pradesh Private Sector HBPCL
16 Himachal Pradesh Private Sector MPCL
Himachal Pradesh Private Sector MPCL
17 Himachal Pradesh Private Sector GBHPPL
Himachal Pradesh Private Sector GBHPPL
18 Himachal Pradesh Private Sector IAEPL
Himachal Pradesh Private Sector IAEPL
Himachal Pradesh Private Sector IAEPL
Total (Himachal Pradesh)
19 Jammu & Kashmir State Sector JKSPDC
Jammu & Kashmir State Sector JKSPDC
Jammu & Kashmir State Sector JKSPDC
20 Jammu & Kashmir State Sector JKSPDC
Jammu & Kashmir State Sector JKSPDC
Jammu & Kashmir State Sector JKSPDC
21 Jammu & Kashmir State Sector JKSPDC
Jammu & Kashmir State Sector JKSPDC
Jammu & Kashmir State Sector JKSPDC

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

22 Jammu & Kashmir State Sector JKSPDC


Jammu & Kashmir State Sector JKSPDC
Jammu & Kashmir State Sector JKSPDC
Total (Jammu & Kashmir)
23 Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
24 Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
25 Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
26 Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Punjab State Sector PSPCL
Total (Punjab)
27 Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
28 Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
29 Rajasthan State Sector RRVUNL

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Rajasthan State Sector RRVUNL


Rajasthan State Sector RRVUNL
Rajasthan State Sector RRVUNL
Total (Rajasthan)
30 Uttar Pardesh State Sector UPJVNL
Uttar Pardesh State Sector UPJVNL
Uttar Pardesh State Sector UPJVNL
31 Uttar Pardesh State Sector UPJVNL
Uttar Pardesh State Sector UPJVNL
Uttar Pardesh State Sector UPJVNL
32 Uttar Pardesh State Sector UPJVNL
Uttar Pardesh State Sector UPJVNL
Uttar Pardesh State Sector UPJVNL
33 Uttar Pardesh State Sector UPJVNL
Uttar Pardesh State Sector UPJVNL
Uttar Pardesh State Sector UPJVNL
Uttar Pardesh State Sector UPJVNL
Uttar Pardesh State Sector UPJVNL
Uttar Pardesh State Sector UPJVNL
Total (Uttar Pardesh)
34 Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
35 Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
36 Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
37 Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
38 Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
39 Uttrakhand State Sector UJVNL

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Uttrakhand State Sector UJVNL


Uttrakhand State Sector UJVNL
40 Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
41 Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
42 Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
43 Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
Uttrakhand State Sector UJVNL
44 Uttrakhand Private Sector JPPVL
Uttrakhand Private Sector JPPVL
Uttrakhand Private Sector JPPVL
Uttrakhand Private Sector JPPVL
45 Uttrakhand Private Sector AHPC (GVK)
Uttrakhand Private Sector AHPC (GVK)
Uttrakhand Private Sector AHPC (GVK)
Uttrakhand Private Sector AHPC (GVK)
Total (Uttrakhand)
46 Himachal Pradesh Central Sector NHPC
Himachal Pradesh Central Sector NHPC
Himachal Pradesh Central Sector NHPC
47 Himachal Pradesh Central Sector NHPC
Himachal Pradesh Central Sector NHPC
Himachal Pradesh Central Sector NHPC
48 Himachal Pradesh Central Sector NHPC
Himachal Pradesh Central Sector NHPC
Himachal Pradesh Central Sector NHPC
49 Himachal Pradesh Central Sector NHPC
Himachal Pradesh Central Sector NHPC
Himachal Pradesh Central Sector NHPC
50 Himachal Pradesh Central Sector SJVNL

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Himachal Pradesh Central Sector SJVNL


Himachal Pradesh Central Sector SJVNL
Himachal Pradesh Central Sector SJVNL
Himachal Pradesh Central Sector SJVNL
Himachal Pradesh Central Sector SJVNL
51 Himachal Pradesh Central Sector NHPC
Himachal Pradesh Central Sector NHPC
Himachal Pradesh Central Sector NHPC
Himachal Pradesh Central Sector NHPC
52 Himachal Pradesh Central Sector SJVNL
Himachal Pradesh Central Sector SJVNL
Himachal Pradesh Central Sector SJVNL
Himachal Pradesh Central Sector SJVNL
Himachal Pradesh Central Sector SJVNL
Himachal Pradesh Central Sector SJVNL
53 Himachal Pradesh Central Sector NTPC
Himachal Pradesh Central Sector NTPC
Himachal Pradesh Central Sector NTPC
Himachal Pradesh Central Sector NTPC
54 Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
55 Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
56 Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
57 Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
58 Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Jammu & Kashmir Central Sector NHPC


59 Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
60 Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
61 Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
Jammu & Kashmir Central Sector NHPC
62 Uttarakhand Central Sector NHPC
Uttarakhand Central Sector NHPC
Uttarakhand Central Sector NHPC
Uttarakhand Central Sector NHPC
63 Uttarakhand Central Sector NHPC
Uttarakhand Central Sector NHPC
Uttarakhand Central Sector NHPC
64 Uttarakhand Central Sector NHPC
Uttarakhand Central Sector NHPC
Uttarakhand Central Sector NHPC
Uttarakhand Central Sector NHPC
65 Uttarakhand Central Sector THDC
Uttarakhand Central Sector THDC
Uttarakhand Central Sector THDC
Uttarakhand Central Sector THDC
Total Central Sector (Northern Region)
Northern Region Total
2. Western Region
66 Chhattisgarh State Sector CSPGCL
Chhattisgarh State Sector CSPGCL
Chhattisgarh State Sector CSPGCL
Total (Chhattisgarh)
67 Gujarat State Sector SSNNL
Gujarat State Sector SSNNL
Gujarat State Sector SSNNL
Gujarat State Sector SSNNL
Gujarat State Sector SSNNL

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

68 Gujarat State Sector SSNNL


Gujarat State Sector SSNNL
Gujarat State Sector SSNNL
Gujarat State Sector SSNNL
Gujarat State Sector SSNNL
Gujarat State Sector SSNNL
69 Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
70 Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
Gujarat State Sector GSECL
Total (Gujarat)
71 Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
72 Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
73 Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
74 Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
75 Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
76 Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
77 Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
78 Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL
Madhya Pradesh State Sector MPPGCL

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Total (Madhya Pradesh)


79 Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
80 Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
81 Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
82 Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
83 Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
84 Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
85 Maharashtra State Sector MAHAGENCO
86 Maharashtra State Sector MAHAGENCO
87 Maharashtra State Sector MAHAGENCO
Maharashtra State Sector MAHAGENCO
88 Maharashtra State Sector DLHP
89 Maharashtra Private Sector Tata Hydro Power Co. Ltd
90 Maharashtra Private Sector Tata Hydro Power Co. Ltd
Maharashtra Private Sector Tata Hydro Power Co. Ltd
Maharashtra Private Sector Tata Hydro Power Co. Ltd
Maharashtra Private Sector Tata Hydro Power Co. Ltd
Maharashtra Private Sector Tata Hydro Power Co. Ltd
Maharashtra Private Sector Tata Hydro Power Co. Ltd
91 Maharashtra Private Sector Tata Hydro Power Co. Ltd
Maharashtra Private Sector Tata Hydro Power Co. Ltd
Maharashtra Private Sector Tata Hydro Power Co. Ltd
Maharashtra Private Sector Tata Hydro Power Co. Ltd
Maharashtra Private Sector Tata Hydro Power Co. Ltd
LIST OF HYDRO POWER STATIONS AS ON 31.03.2018
Sl. No. Region/State/UT Sector Owner

92 Maharashtra Private Sector Tata Hydro Power Co. Ltd


Maharashtra Private Sector Tata Hydro Power Co. Ltd
Maharashtra Private Sector Tata Hydro Power Co. Ltd
Maharashtra Private Sector Tata Hydro Power Co. Ltd
Maharashtra Private Sector Tata Hydro Power Co. Ltd
Maharashtra Private Sector Tata Hydro Power Co. Ltd
Total (Maharashtra)
93 Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
94 Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
Madhya Pradesh Central Sector NHDC
Total Central Sector (Western Region)
Western Region Total
3. Southern Region
95 Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
96 Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
97 Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Andhra Pradesh State Sector APGENCO


Andhra Pradesh State Sector APGENCO
98 Andhra Pradesh State Sector APGENCO
Andhra Pradesh State Sector APGENCO
Total (Andhra Pradesh)
99 Telangana State Sector APGENCO
Telangana State Sector APGENCO
Telangana State Sector APGENCO
Telangana State Sector APGENCO
100 Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
101 Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
102 Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
103 Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
104 Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
105 Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Telangana State Sector TSGENCO


Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
106 Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Telangana State Sector TSGENCO
Total (Telangana)
107 Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
108 Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
109 Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
110 Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
111 Karnataka State Sector KPCL
Karnataka State Sector KPCL
112 Karnataka State Sector KPCL
Karnataka State Sector KPCL

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Karnataka State Sector KPCL


113 Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
114 Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
115 Karnataka State Sector KPCL
Karnataka State Sector KPCL
116 Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
117 Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
118 Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
119 Karnataka State Sector KPCL
Karnataka State Sector KPCL
120 Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
Karnataka State Sector KPCL
121 Karnataka State Sector APGENCO

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Karnataka State Sector APGENCO


Karnataka State Sector APGENCO
Karnataka State Sector APGENCO
122 Karnataka State Sector APGENCO
Karnataka State Sector APGENCO
Karnataka State Sector APGENCO
Karnataka State Sector APGENCO
Total (Karnataka)
123 Kerala State Sector KSEB
Kerala State Sector KSEB
124 Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
125 Kerala State Sector KSEB
Kerala State Sector KSEB
126 Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
127 Kerala State Sector KSEB
Kerala State Sector KSEB
128 Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
129 Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
130 Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
131 Kerala State Sector KSEB

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Kerala State Sector KSEB


132 Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
133 Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
134 Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
135 Kerala State Sector KSEB
Kerala State Sector KSEB
Kerala State Sector KSEB
Total (Kerala)
136 Tamil Nadu State Sector TENGEDCO
137 Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
138 Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TANGEDCO
139 Tamil Nadu State Sector TANGEDCO
Tamil Nadu State Sector TANGEDCO
140 Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
141 Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
142 Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Tamil Nadu State Sector TENGEDCO


Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
143 Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
144 Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
145 Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
146 Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
147 Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
148 Tamil Nadu State Sector TENGEDCO
149 Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
150 Tamil Nadu State Sector TENGEDCO

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Tamil Nadu State Sector TENGEDCO


Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
151 Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
152 Tamil Nadu State Sector TENGEDCO
153 Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
Tamil Nadu State Sector TENGEDCO
154 Tamil Nadu State Sector TENGEDCO
Total (Tamil Nadu)
Southern Region Total
4. Eastern Region
155 Jharkhand State Sector JSEB
Jharkhand State Sector JSEB
Total (Jharkhand)
156 Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
157 Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
158 Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
159 Odisha State Sector OHPC

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

Odisha State Sector OHPC


Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
160 Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
161 Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
Odisha State Sector OHPC
162 Odisha State Sector APGENCO
Odisha State Sector APGENCO
Odisha State Sector APGENCO
Odisha State Sector APGENCO
Odisha State Sector APGENCO
Odisha State Sector APGENCO
Total (Odisha)
163 West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
164 West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
165 West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
West Bengal State Sector WBPDC
Total (West Bengal)
166 Sikkim State Sector TEESTA Urja Ltd
Sikkim State Sector TEESTA Urja Ltd
Sikkim State Sector TEESTA Urja Ltd
Sikkim State Sector TEESTA Urja Ltd
Sikkim State Sector TEESTA Urja Ltd
Sikkim State Sector TEESTA Urja Ltd

LIST OF HYDRO POWER STATIONS AS ON 31.03.2018


Sl. No. Region/State/UT Sector Owner

167 Sikkim Private Sector GATI Infrastructure Ltd


Sikkim Private Sector GATI Infrastructure Ltd
168 Sikkim Private Sector DANS Energy Pvt Ltd
Sikkim Private Sector DANS Energy Pvt Ltd
169 Sikkim Private Sector DANS Energy Pvt Ltd
Sikkim Private Sector DANS Energy Pvt Ltd
170 Sikkim Private Sector Sneha Kinetics Projects Ltd
Sikkim Private Sector Sneha Kinetics Projects Ltd
Total (Sikkim)
171 Jharkhand Central Sector DVC
Jharkhand Central Sector DVC
Jharkhand Central Sector DVC
172 Jharkhand Central Sector DVC
Jharkhand Central Sector DVC
173 West Bengal Central Sector NHPC
West Bengal Central Sector NHPC
West Bengal Central Sector NHPC
West Bengal Central Sector NHPC
174 West Bengal Central Sector NHPC
West Bengal Central Sector NHPC
West Bengal Central Sector NHPC
West Bengal Central Sector NHPC
175 Sikkim Central Sector NHPC
Sikkim Central Sector NHPC
Sikkim Central Sector NHPC
176 Sikkim Central Sector NHPC
Sikkim Central Sector NHPC
Sikkim Central Sector NHPC
Total (DVC)
Total (NHPC)
Total Central Sector (DVC+NHPC) (Eastern Region)
Eastern Region Total
5. North Eastern Region
177 Assam State Sector APGCL
Assam State Sector APGCL
Total (Assam)
178 Meghalaya State Sector MeECL
Meghalaya State Sector MeECL
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

MW MW

BHAKRA HPS-LEFT BANK 1 1 108.00 108.00 1960


BHAKRA HPS-LEFT BANK 2 1 108.00 108.00 1961
BHAKRA HPS-LEFT BANK 3 1 108.00 108.00 1961
BHAKRA HPS-LEFT BANK 4 1 108.00 108.00 1961
BHAKRA HPS-LEFT BANK 5 1 108.00 108.00 1961
BHAKRA HPS-RIGHT BANK 6 1 157.00 157.00 1966
BHAKRA HPS-RIGHT BANK 7 1 157.00 157.00 1966
BHAKRA HPS-RIGHT BANK 8 1 157.00 157.00 1967
BHAKRA HPS-RIGHT BANK 9 1 157.00 157.00 1967
BHAKRA HPS-RIGHT BANK 10 1 157.00 157.00 1968
DEHAR HPS 1 1 165.00 165.00 1977
DEHAR HPS 2 1 165.00 165.00 1978
DEHAR HPS 3 1 165.00 165.00 1979
DEHAR HPS 4 1 165.00 165.00 1979
DEHAR HPS 5 1 165.00 165.00 1983
DEHAR HPS 6 1 165.00 165.00 1983
GANGUWAL HPS 1 1 24.20 24.20 1962
GANGUWAL HPS 2 1 24.20 24.20 1955
GANGUWAL HPS 3 1 29.25 29.25 1955
KOTLA HPS 1 1 24.20 24.20 1961
KOTLA HPS 2 1 29.25 29.25 1956
KOTLA HPS 3 1 24.20 24.20 1956
PONG HPS 1 1 66.00 66.00 1978
PONG HPS 2 1 66.00 66.00 1978
PONG HPS 3 1 66.00 66.00 1978
PONG HPS 4 1 66.00 66.00 1979
PONG HPS 5 1 66.00 66.00 1982
PONG HPS 6 1 66.00 66.00 1983
2866.30
BASSI HPS 1 1 16.50 16.50 1970
BASSI HPS 2 1 16.50 16.50 1971
BASSI HPS 3 1 16.50 16.50 1970
BASSI HPS 4 1 16.50 16.50 1981
GIRI BATA HPS 1 1 30.00 30.00 1978
GIRI BATA HPS 2 1 30.00 30.00 1978
LARJI HPS 1 1 42.00 42.00 2006
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

LARJI HPS 2 1 42.00 42.00 2006


LARJI HPS 3 1 42.00 42.00 2006
SANJAY HPS 1 1 40.00 40.00 1989
SANJAY HPS 2 1 40.00 40.00 1989
SANJAY HPS 3 1 40.00 40.00 1989
KASHANG INTEGRATED HEP 1 1 65.00 65.00 2016
KASHANG INTEGRATED HEP 2 1 65.00 65.00 2016
KASHANG INTEGRATED HEP 3 1 65.00 65.00 2017
SAINJ HPS 1 1 50.00 50.00 2017
SAINJ HPS 2 1 50.00 50.00 2017
KARCHAM WANGTOO HPS 1 1 250.00 250.00 2011
KARCHAM WANGTOO HPS 2 1 250.00 250.00 2011
KARCHAM WANGTOO HPS 3 1 250.00 250.00 2011
KARCHAM WANGTOO HPS 4 1 250.00 250.00 2011
MALANA-II HPS 1 1 50.00 50.00 2011
MALANA-II HPS 2 1 50.00 50.00 2011
ALLAIN DUHANGAN HPS 1 1 96.00 96.00 2010
ALLAIN DUHANGAN HPS 2 1 96.00 96.00 2010
BASPA HPS 1 1 100.00 100.00 2003
BASPA HPS 2 1 100.00 100.00 2003
BASPA HPS 3 1 100.00 100.00 2003
MALANA HPS 1 1 43.00 43.00 2001
MALANA HPS 2 1 43.00 43.00 2001
BUDHIL HPS 1 1 35.00 35.00 2012
BUDHIL HPS 2 1 35.00 35.00 2012
CHANJU-I HPS 1 1 12.00 12.00 2017
CHANJU-I HPS 2 1 12.00 12.00 2017
CHANJU-I HPS 3 1 12.00 12.00 2017
2451.00
LOWER JHELUM HPS 1 1 35.00 35.00 1978
LOWER JHELUM HPS 2 1 35.00 35.00 1979
LOWER JHELUM HPS 3 1 35.00 35.00 1979
UPPER SINDH-II HPS 1 1 35.00 35.00 2001
UPPER SINDH-II HPS 2 1 35.00 35.00 2001
UPPER SINDH-II HPS 3 1 35.00 35.00 2002
BAGLIHAR HPS 1 1 150.00 150.00 2008
BAGLIHAR HPS 2 1 150.00 150.00 2008
BAGLIHAR HPS 3 1 150.00 150.00 2008
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

BAGLIHAR II HPS 1 1 150.00 150.00 2015


BAGLIHAR II HPS 2 1 150.00 150.00 2015
BAGLIHAR II HPS 3 1 150.00 150.00 2015
1110.00
ANANDPUR SAHIB HPS 1 1 33.50 33.50 1985
ANANDPUR SAHIB HPS 2 1 33.50 33.50 1985
ANANDPUR SAHIB HPS 3 1 33.50 33.50 1985
ANANDPUR SAHIB HPS 4 1 33.50 33.50 1985
MUKERIAN HPS 1 1 15.00 15.00 1983
MUKERIAN HPS 2 1 15.00 15.00 1983
MUKERIAN HPS 3 1 15.00 15.00 1983
MUKERIAN HPS 4 1 15.00 15.00 1988
MUKERIAN HPS 5 1 15.00 15.00 1988
MUKERIAN HPS 6 1 15.00 15.00 1989
MUKERIAN HPS 7 1 19.50 19.50 1989
MUKERIAN HPS 8 1 19.50 19.50 1989
MUKERIAN HPS 9 1 19.50 19.50 1989
MUKERIAN HPS 10 1 19.50 19.50 1989
MUKERIAN HPS 11 1 19.50 19.50 1989
MUKERIAN HPS 12 1 19.50 19.50 1989
RANJIT SAGAR HPS 1 1 150.00 150.00 2000
RANJIT SAGAR HPS 2 1 150.00 150.00 2000
RANJIT SAGAR HPS 3 1 150.00 150.00 2000
RANJIT SAGAR HPS 4 1 150.00 150.00 2000
SHANAN HPS 1 1 15.00 15.00 1932
SHANAN HPS 2 1 15.00 15.00 1932
SHANAN HPS 3 1 15.00 15.00 1932
SHANAN HPS 4 1 15.00 15.00 1932
SHANAN HPS 5 1 50.00 50.00 1982
1051.00
JAWAHAR SAGAR HPS 1 1 33.00 33.00 1972
JAWAHAR SAGAR HPS 2 1 33.00 33.00 1973
JAWAHAR SAGAR HPS 3 1 33.00 33.00 1973
R P SAGAR HPS 1 1 43.00 43.00 1968
R P SAGAR HPS 2 1 43.00 43.00 1968
R P SAGAR HPS 3 1 43.00 43.00 1968
R P SAGAR HPS 4 1 43.00 43.00 1968
MAHI BAJAJ HPS 1 1 25.00 25.00 1986
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

MAHI BAJAJ HPS 2 1 25.00 25.00 1986


MAHI BAJAJ HPS 3 1 45.00 45.00 1989
MAHI BAJAJ HPS 4 1 45.00 45.00 1989
411.00
KHARA HPS 1 1 24.00 24.00 1992
KHARA HPS 2 1 24.00 24.00 1992
KHARA HPS 3 1 24.00 24.00 1992
MATATILA HPS 1 1 10.20 10.20 1965
MATATILA HPS 2 1 10.20 10.20 1965
MATATILA HPS 3 1 10.20 10.20 1965
OBRA HPS 1 1 33.00 33.00 1970
OBRA HPS 2 1 33.00 33.00 1970
OBRA HPS 3 1 33.00 33.00 1971
RIHAND HPS 1 1 50.00 50.00 1961
RIHAND HPS 2 1 50.00 50.00 1961
RIHAND HPS 3 1 50.00 50.00 1961
RIHAND HPS 4 1 50.00 50.00 1961
RIHAND HPS 5 1 50.00 50.00 1961
RIHAND HPS 6 1 50.00 50.00 1965
501.60
CHIBRO (YAMUNA) HPS 1 1 60.00 60.00 1975
CHIBRO (YAMUNA) HPS 2 1 60.00 60.00 1975
CHIBRO (YAMUNA) HPS 3 1 60.00 60.00 1975
CHIBRO (YAMUNA) HPS 4 1 60.00 60.00 1976
DHAKRANI HPS 1 1 11.25 11.25 1965
DHAKRANI HPS 2 1 11.25 11.25 1966
DHAKRANI HPS 3 1 11.25 11.25 1970
DHALIPUR HPS 1 1 17.00 17.00 1965
DHALIPUR HPS 2 1 17.00 17.00 1966
DHALIPUR HPS 3 1 17.00 17.00 1970
KHATIMA HPS 1 1 13.80 13.80 1955
KHATIMA HPS 2 1 13.80 13.80 1956
KHATIMA HPS 3 1 13.80 13.80 1956
KHODRI HPS 1 1 30.00 30.00 1984
KHODRI HPS 2 1 30.00 30.00 1984
KHODRI HPS 3 1 30.00 30.00 1984
KHODRI HPS 4 1 30.00 30.00 1984
KULHAL HPS 1 1 10.00 10.00 1975
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

KULHAL HPS 2 1 10.00 10.00 1975


KULHAL HPS 3 1 10.00 10.00 1975
MANERI BHALI - I HPS 1 1 30.00 30.00 1984
MANERI BHALI - I HPS 2 1 30.00 30.00 1984
MANERI BHALI - I HPS 3 1 30.00 30.00 1984
MANERI BHALI - II HPS 1 1 76.00 76.00 2008
MANERI BHALI - II HPS 2 1 76.00 76.00 2008
MANERI BHALI - II HPS 3 1 76.00 76.00 2008
MANERI BHALI - II HPS 4 1 76.00 76.00 2008
RAMGANGA HPS 1 1 66.00 66.00 1975
RAMGANGA HPS 2 1 66.00 66.00 1976
RAMGANGA HPS 3 1 66.00 66.00 1977
CHILLA HPS 1 1 36.00 36.00 1980
CHILLA HPS 2 1 36.00 36.00 1980
CHILLA HPS 3 1 36.00 36.00 1980
CHILLA HPS 4 1 36.00 36.00 1981
VISHNU PRAYAG HPS 1 1 100.00 100.00 2006
VISHNU PRAYAG HPS 2 1 100.00 100.00 2006
VISHNU PRAYAG HPS 3 1 100.00 100.00 2006
VISHNU PRAYAG HPS 4 1 100.00 100.00 2006
SRINAGAR HPS 1 1 82.50 82.50 2015
SRINAGAR HPS 2 1 82.50 82.50 2015
SRINAGAR HPS 3 1 82.50 82.50 2015
SRINAGAR HPS 4 1 82.50 82.50 2015
1982.15
BAIRA SIUL HPS 1 1 60.00 60.00 1980
BAIRA SIUL HPS 2 1 60.00 60.00 1980
BAIRA SIUL HPS 3 1 60.00 60.00 1981
CHAMERA- I HPS 1 1 180.00 180.00 1994
CHAMERA- I HPS 2 1 180.00 180.00 1994
CHAMERA- I HPS 3 1 180.00 180.00 1994
CHAMERA- II HPS 1 1 100.00 100.00 2003
CHAMERA- II HPS 2 1 100.00 100.00 2003
CHAMERA- II HPS 3 1 100.00 100.00 2004
CHAMERA-III HPS 1 1 77.00 77.00 2012
CHAMERA-III HPS 2 1 77.00 77.00 2012
CHAMERA-III HPS 3 1 77.00 77.00 2012
NATHPA JHAKRI HPS 1 1 250.00 250.00 2004
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

NATHPA JHAKRI HPS 2 1 250.00 250.00 2003


NATHPA JHAKRI HPS 3 1 250.00 250.00 2003
NATHPA JHAKRI HPS 4 1 250.00 250.00 2004
NATHPA JHAKRI HPS 5 1 250.00 250.00 2004
NATHPA JHAKRI HPS 6 1 250.00 250.00 2004
PARBATI-III HPS 1 1 130 130.00 2014
PARBATI-III HPS 2 1 130 130.00 2014
PARBATI-III HPS 3 1 130 130.00 2014
PARBATI-III HPS 4 1 130 130.00 2014
RAMPUR HPS 1 1 68.67 68.67 2014
RAMPUR HPS 2 1 68.67 68.67 2014
RAMPUR HPS 3 1 68.67 68.67 2014
RAMPUR HPS 4 1 68.67 68.67 2014
RAMPUR HPS 5 1 68.67 68.67 2014
RAMPUR HPS 6 1 68.67 68.67 2014
KOLDAM 1 1 200 200.00 2015
KOLDAM 2 1 200 200.00 2015
KOLDAM 3 1 200 200.00 2015
KOLDAM 4 1 200 200.00 2015
SEWA-II HPS 1 1 40.00 40.00 2010
SEWA-II HPS 2 1 40.00 40.00 2010
SEWA-II HPS 3 1 40.00 40.00 2010
DULHASTI HPS 1 1 130.00 130.00 2007
DULHASTI HPS 2 1 130.00 130.00 2007
DULHASTI HPS 3 1 130.00 130.00 2007
SALAL HPS 1 1 115.00 115.00 1987
SALAL HPS 2 1 115.00 115.00 1987
SALAL HPS 3 1 115.00 115.00 1987
SALAL HPS 4 1 115.00 115.00 1993
SALAL HPS 5 1 115.00 115.00 1994
SALAL HPS 6 1 115.00 115.00 1995
URI-I HPS 1 1 120.00 120.00 1997
URI-I HPS 2 1 120.00 120.00 1997
URI-I HPS 3 1 120.00 120.00 1997
URI-I HPS 4 1 120.00 120.00 1996
CHUTAK HPS 1 1 11.00 11.00 2012
CHUTAK HPS 2 1 11.00 11.00 2012
CHUTAK HPS 3 1 11.00 11.00 2012
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

CHUTAK HPS 4 1 11.00 11.00 2013


NIMBOO BAZDO HPS 1 1 15.00 15.00 2013
NIMBOO BAZDO HPS 2 1 15.00 15.00 2013
NIMBOO BAZDO HPS 3 1 15.00 15.00 2013
URI-II HPS 1 1 60.00 60.00 2013
URI-II HPS 2 1 60.00 60.00 2013
URI-II HPS 3 1 60.00 60.00 2013
URI-II HPS 4 1 60.00 60.00 2014
KISHANGANGA HPS 1 1 110.00 110.00 2018
KISHANGANGA HPS 2 1 110.00 110.00 2018
KISHANGANGA HPS 3 1 110.00 110.00 2018
DHAULI GANGA HPS 1 1 70.00 70.00 2005
DHAULI GANGA HPS 2 1 70.00 70.00 2005
DHAULI GANGA HPS 3 1 70.00 70.00 2005
DHAULI GANGA HPS 4 1 70.00 70.00 2005
TANAKPUR HPS 1 1 31.40 31.40 1992
TANAKPUR HPS 2 1 31.40 31.40 1992
TANAKPUR HPS 3 1 31.40 31.40 1992
TEHRI ST-1 HPS 1 1 250.00 250.00 2006
TEHRI ST-1 HPS 2 1 250.00 250.00 2006
TEHRI ST-1 HPS 3 1 250.00 250.00 2007
TEHRI ST-1 HPS 4 1 250.00 250.00 2007
KOTESHWAR HPS 1 1 100.00 100.00 2011
KOTESHWAR HPS 2 1 100.00 100.00 2011
KOTESHWAR HPS 3 1 100.00 100.00 2012
KOTESHWAR HPS 4 1 100.00 100.00 2012
8596.22
18969.27

HASDEOBANGO HPS 1 1 40.00 40.00 1994


HASDEOBANGO HPS 2 1 40.00 40.00 1994
HASDEOBANGO HPS 3 1 40.00 40.00 1995
120.00
S SAROVAR CHPH HPS 1 1 50.00 50.00 2004
S SAROVAR CHPH HPS 2 1 50.00 50.00 2004
S SAROVAR CHPH HPS 3 1 50.00 50.00 2004
S SAROVAR CHPH HPS 4 1 50.00 50.00 2004
S SAROVAR CHPH HPS 5 1 50.00 50.00 2004
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

S SAROVAR RBPH HPS 1 1 200.00 200.00 2005


S SAROVAR RBPH HPS 2 1 200.00 200.00 2005
S SAROVAR RBPH HPS 3 1 200.00 200.00 2005
S SAROVAR RBPH HPS 4 1 200.00 200.00 2005
S SAROVAR RBPH HPS 5 1 200.00 200.00 2006
S SAROVAR RBPH HPS 6 1 200.00 200.00 2006
KADANA HPS 1 1 60.00 60.00 1990
KADANA HPS 2 1 60.00 60.00 1990
KADANA HPS 3 1 60.00 60.00 1997
KADANA HPS 4 1 60.00 60.00 1998
UKAI HPS 1 1 75.00 75.00 1974
UKAI HPS 2 1 75.00 75.00 1974
UKAI HPS 3 1 75.00 75.00 1975
UKAI HPS 4 1 75.00 75.00 1976
1990.00
PENCH HPS 1 1 80.00 80.00 1986
PENCH HPS 2 1 80.00 80.00 1987
GANDHI SAGAR HPS 1 1 23.00 23.00 1960
GANDHI SAGAR HPS 2 1 23.00 23.00 1960
GANDHI SAGAR HPS 3 1 23.00 23.00 1960
GANDHI SAGAR HPS 4 1 23.00 23.00 1963
GANDHI SAGAR HPS 5 1 23.00 23.00 1966
BANSAGAR TONS HPS -I 1 1 105.00 105.00 1976
BANSAGAR TONS HPS -I 2 1 105.00 105.00 1970
BANSAGAR TONS HPS -I 3 1 105.00 105.00 1992
BANSAGAR TONS HPS -II 1 1 15.00 15.00 2002
BANSAGAR TONS HPS -II 2 1 15.00 15.00 2002
BANSAGAR TONS HPS -III 1 1 20.00 20.00 2000
BANSAGAR TONS HPS -III 2 1 20.00 20.00 2001
BANSAGAR TONS HPS -III 3 1 20.00 20.00 2002
BARGI HPS 1 1 45.00 45.00 1988
BARGI HPS 2 1 45.00 45.00 1988
MADHIKHERA HPS 1 1 20.00 20.00 2006
MADHIKHERA HPS 2 1 20.00 20.00 2006
MADHIKHERA HPS 3 1 20.00 20.00 2006
RAJGHAT HPS 1 1 15.00 15.00 1999
RAJGHAT HPS 2 1 15.00 15.00 1999
RAJGHAT HPS 3 1 15.00 15.00 1999
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

875.00
BHIRA TAIL RACE HPS 1 1 40.00 40.00 1988
BHIRA TAIL RACE HPS 2 1 40.00 40.00 1987
KOYNA DPH HPS 1 1 18.00 18.00 1980
KOYNA DPH HPS 2 1 18.00 18.00 1981
KOYNA-I HPS 1 1 70.00 70.00 1962
KOYNA-I HPS 2 1 70.00 70.00 1962
KOYNA-I HPS 3 1 70.00 70.00 1963
KOYNA-I HPS 4 1 70.00 70.00 1963
KOYNA-II HPS 1 1 80.00 80.00 1967
KOYNA-II HPS 2 1 80.00 80.00 1966
KOYNA-II HPS 3 1 80.00 80.00 1967
KOYNA-II HPS 4 1 80.00 80.00 1966
KOYNA-III HPS 1 1 80.00 80.00 1975
KOYNA-III HPS 2 1 80.00 80.00 1976
KOYNA-III HPS 3 1 80.00 80.00 1977
KOYNA-III HPS 4 1 80.00 80.00 1978
KOYNA-IV HPS 1 1 250.00 250.00 2000
KOYNA-IV HPS 2 1 250.00 250.00 2000
KOYNA-IV HPS 3 1 250.00 250.00 1999
KOYNA-IV HPS 4 1 250.00 250.00 1999
TILLARI HPS 1 1 60.00 60.00 1986
VAITARNA HPS 1 1 60.00 60.00 1976
GHATGHAR PSS HPS 1 1 125.00 125.00 2008
GHATGHAR PSS HPS 2 1 125.00 125.00 2008
BHANDARDHARA HPS ST-II 1 1 34.00 34.00 1996
BHIRA PSS HPS 1 1 150.00 150.00 1995
BHIRA HPS 1 1 25.00 25.00 1927
BHIRA HPS 2 1 25.00 25.00 1927
BHIRA HPS 3 1 25.00 25.00 1927
BHIRA HPS 4 1 25.00 25.00 1927
BHIRA HPS 5 1 25.00 25.00 1927
BHIRA HPS 6 1 25.00 25.00 1949
BHIVPURI HPS 1 1 24.00 24.00 1998
BHIVPURI HPS 2 1 24.00 24.00 1997
BHIVPURI HPS 3 1 24.00 24.00 1998
BHIVPURI HPS 4 1 1.50 1.50 1997
BHIVPURI HPS 5 1 1.50 1.50 1999
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

KHOPOLI HPS 1 1 12.00 12.00 2002


KHOPOLI HPS 2 1 12.00 12.00 2003
KHOPOLI HPS 3 1 12.00 12.00 2001
KHOPOLI HPS 4 1 12.00 12.00 2002
KHOPOLI HPS 5 1 12.00 12.00 2002
KHOPOLI HPS 6 1 12.00 12.00 2002
2887.00
OMKARESHWAR HPS 1 1 65.00 65.00 2007
OMKARESHWAR HPS 2 1 65.00 65.00 2007
OMKARESHWAR HPS 3 1 65.00 65.00 2007
OMKARESHWAR HPS 4 1 65.00 65.00 2007
OMKARESHWAR HPS 5 1 65.00 65.00 2007
OMKARESHWAR HPS 6 1 65.00 65.00 2007
OMKARESHWAR HPS 7 1 65.00 65.00 2007
OMKARESHWAR HPS 8 1 65.00 65.00 2007
INDIRA SAGAR HPS 1 1 125.00 125.00 2004
INDIRA SAGAR HPS 2 1 125.00 125.00 2004
INDIRA SAGAR HPS 3 1 125.00 125.00 2004
INDIRA SAGAR HPS 4 1 125.00 125.00 2004
INDIRA SAGAR HPS 5 1 125.00 125.00 2004
INDIRA SAGAR HPS 6 1 125.00 125.00 2004
INDIRA SAGAR HPS 7 1 125.00 125.00 2004
INDIRA SAGAR HPS 8 1 125.00 125.00 2005
1520.00
7392.00

NAGARJUN SGR RBC HPS 1 1 30.00 30.00 1983


NAGARJUN SGR RBC HPS 2 1 30.00 30.00 1990
NAGARJUN SGR RBC HPS 3 1 30.00 30.00 1983
SRISAILAM HPS 1 1 110.00 110.00 1982
SRISAILAM HPS 2 1 110.00 110.00 1982
SRISAILAM HPS 3 1 110.00 110.00 1983
SRISAILAM HPS 4 1 110.00 110.00 1984
SRISAILAM HPS 5 1 110.00 110.00 1986
SRISAILAM HPS 6 1 110.00 110.00 1986
SRISAILAM HPS 7 1 110.00 110.00 1987
UPPER SILERU HPS 1 1 60.00 60.00 1967
UPPER SILERU HPS 2 1 60.00 60.00 1968
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

UPPER SILERU HPS 3 1 60.00 60.00 1994


UPPER SILERU HPS 4 1 60.00 60.00 1997
NAGARJUN SGR TPD 1 1 25.00 25.00 2017
NAGARJUN SGR TPD 2 1 25.00 25.00 2017
1150.00
LOWER SILERU HPS 1 1 115.00 115.00 1976
LOWER SILERU HPS 2 1 115.00 115.00 1976
LOWER SILERU HPS 3 1 115.00 115.00 1977
LOWER SILERU HPS 4 1 115.00 115.00 1978
NAGARJUN SGR HPS 1 1 110.00 110.00 1978
NAGARJUN SGR HPS 2 1 100.80 100.80 1980
NAGARJUN SGR HPS 3 1 100.80 100.80 1981
NAGARJUN SGR HPS 4 1 100.80 100.80 1982
NAGARJUN SGR HPS 5 1 100.80 100.80 1983
NAGARJUN SGR HPS 6 1 100.80 100.80 1984
NAGARJUN SGR HPS 7 1 100.80 100.80 1985
NAGARJUN SGR HPS 8 1 100.80 100.80 1985
NAGARJUN SGR LBC HPS 1 1 30.00 30.00 1983
NAGARJUN SGR LBC HPS 2 1 30.00 30.00 1983
POCHAMPAD HPS 1 1 9.00 9.00 1987
POCHAMPAD HPS 2 1 9.00 9.00 1987
POCHAMPAD HPS 3 1 9.00 9.00 1988
POCHAMPAD HPS 4 1 9.00 9.00 2010
PRIYADARSHNI JURALA HPS 1 1 39.00 39.00 2008
PRIYADARSHNI JURALA HPS 2 1 39.00 39.00 2008
PRIYADARSHNI JURALA HPS 3 1 39.00 39.00 2009
PRIYADARSHNI JURALA HPS 4 1 39.00 39.00 2010
PRIYADARSHNI JURALA HPS 5 1 39.00 39.00 2010
PRIYADARSHNI JURALA HPS 6 1 39.00 39.00 2011
SRISAILAM LB HPS 1 1 150.00 150.00 2001
SRISAILAM LB HPS 2 1 150.00 150.00 2001
SRISAILAM LB HPS 3 1 150.00 150.00 2002
SRISAILAM LB HPS 4 1 150.00 150.00 2002
SRISAILAM LB HPS 5 1 150.00 150.00 2003
SRISAILAM LB HPS 6 1 150.00 150.00 2003
LOWER JURALA HPS 1 1 40.00 40.00 2015
LOWER JURALA HPS 2 1 40.00 40.00 2015
LOWER JURALA HPS 3 1 40.00 40.00 2016
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

LOWER JURALA HPS 4 1 40.00 40.00 2016


LOWER JURALA HPS 5 1 40.00 40.00 2016
LOWER JURALA HPS 6 1 40.00 40.00 2016
PULICHINTALA HPS 1 1 30.00 30.00 2016
PULICHINTALA HPS 2 1 30.00 30.00 2017
PULICHINTALA HPS 3 1 30.00 30.00 2017
2835.60
JOG HPS 1 1 13.20 13.20 1947
JOG HPS 2 1 13.20 13.20 1949
JOG HPS 3 1 13.20 13.20 1949
JOG HPS 4 1 13.20 13.20 1950
JOG HPS 5 1 21.60 21.60 1952
JOG HPS 6 1 21.60 21.60 1952
JOG HPS 7 1 21.60 21.60 1952
JOG HPS 8 1 21.60 21.60 1952
MUNIRABAD HPS 1 1 9.00 9.00 1962
MUNIRABAD HPS 2 1 9.00 9.00 1962
MUNIRABAD HPS 3 1 10.00 10.00 1965
SIVASAMUNDRUM HPS 1 1 3.00 3.00 1922
SIVASAMUNDRUM HPS 2 1 3.00 3.00 1924
SIVASAMUNDRUM HPS 3 1 3.00 3.00 1924
SIVASAMUNDRUM HPS 4 1 3.00 3.00 1925
SIVASAMUNDRUM HPS 5 1 3.00 3.00 1923
SIVASAMUNDRUM HPS 6 1 3.00 3.00 1924
SIVASAMUNDRUM HPS 7 1 6.00 6.00 1928
SIVASAMUNDRUM HPS 8 1 6.00 6.00 1934
SIVASAMUNDRUM HPS 9 1 6.00 6.00 1928
SIVASAMUNDRUM HPS 10 1 6.00 6.00 1928
ALMATTI DPH HPS 1 1 15.00 15.00 2004
ALMATTI DPH HPS 2 1 55.00 55.00 2004
ALMATTI DPH HPS 3 1 55.00 55.00 2005
ALMATTI DPH HPS 4 1 55.00 55.00 2004
ALMATTI DPH HPS 5 1 55.00 55.00 2005
ALMATTI DPH HPS 6 1 55.00 55.00 2005
GHAT PRABHA HPS 1 1 16.00 16.00 1992
GHAT PRABHA HPS 2 1 16.00 16.00 1992
KADRA HPS 1 1 50.00 50.00 1997
KADRA HPS 2 1 50.00 50.00 1999
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

KADRA HPS 3 1 50.00 50.00 1999


KALINADI HPS 1 1 135.00 135.00 1979
KALINADI HPS 2 1 135.00 135.00 1980
KALINADI HPS 3 1 135.00 135.00 1981
KALINADI HPS 4 1 150.00 150.00 1982
KALINADI HPS 5 1 150.00 150.00 1983
KALINADI HPS 6 1 150.00 150.00 1984
KODASALI HPS 1 1 40.00 40.00 1998
KODASALI HPS 2 1 40.00 40.00 1999
KODASALI HPS 3 1 40.00 40.00 1999
LIGANAMAKKI HPS 1 1 27.50 27.50 1979
LIGANAMAKKI HPS 2 1 27.50 27.50 1980
SHARAVATHI HPS 1 1 103.50 103.50 1965
SHARAVATHI HPS 2 1 103.50 103.50 1965
SHARAVATHI HPS 3 1 103.50 103.50 1967
SHARAVATHI HPS 4 1 103.50 103.50 1967
SHARAVATHI HPS 5 1 103.50 103.50 1968
SHARAVATHI HPS 6 1 103.50 103.50 1968
SHARAVATHI HPS 7 1 103.50 103.50 1968
SHARAVATHI HPS 8 1 103.50 103.50 1971
SHARAVATHI HPS 9 1 103.50 103.50 1976
SHARAVATHI HPS 10 1 103.50 103.50 1977
GERUSUPPA HPS 1 1 60.00 60.00 2001
GERUSUPPA HPS 2 1 60.00 60.00 2001
GERUSUPPA HPS 3 1 60.00 60.00 2001
GERUSUPPA HPS 4 1 60.00 60.00 2002
BHADRA HPS 1 1 2.00 2.00 1962
BHADRA HPS 2 1 12.00 12.00 1963
BHADRA HPS 3 1 12.00 12.00 1963
BHADRA HPS 4 1 7.20 7.20 1963
BHADRA HPS 5 1 6.00 6.00 1998
KALINADI SUPA HPS 1 1 50.00 50.00 1985
KALINADI SUPA HPS 2 1 50.00 50.00 1985
VARAHI HPS 1 1 115.00 115.00 1989
VARAHI HPS 2 1 115.00 115.00 1990
VARAHI HPS 3 1 115.00 115.00 2009
VARAHI HPS 4 1 115.00 115.00 2009
T B DAM HPS 1 1 9.00 9.00 1957
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

T B DAM HPS 2 1 9.00 9.00 1957


T B DAM HPS 3 1 9.00 9.00 1964
T B DAM HPS 4 1 9.00 9.00 1964
HAMPI HPS 1 1 9.00 9.00 1958
HAMPI HPS 2 1 9.00 9.00 1958
HAMPI HPS 3 1 9.00 9.00 1964
HAMPI HPS 4 1 9.00 9.00 1964
3657.40
IDAMALAYAR HPS 1 1 37.50 37.50 1987
IDAMALAYAR HPS 2 1 37.50 37.50 1987
IDUKKI HPS 1 1 130.00 130.00 1976
IDUKKI HPS 2 1 130.00 130.00 1976
IDUKKI HPS 3 1 130.00 130.00 1976
IDUKKI HPS 4 1 130.00 130.00 1985
IDUKKI HPS 5 1 130.00 130.00 1986
IDUKKI HPS 6 1 130.00 130.00 1986
KAKKAD HPS 1 1 25.00 25.00 1999
KAKKAD HPS 2 1 25.00 25.00 1999
KUTTIYADI HPS 1 1 25.00 25.00 1972
KUTTIYADI HPS 2 1 25.00 25.00 1972
KUTTIYADI HPS 3 1 25.00 25.00 1972
KUTTIYADI HPS 4 1 50.00 50.00 2001
KUTTIYADI ADDL. EXTN. HPS 1 1 50.00 50.00 2010
KUTTIYADI ADDL. EXTN. HPS 2 1 50.00 50.00 2010
LOWER PERIYAR HPS 1 1 60.00 60.00 1997
LOWER PERIYAR HPS 2 1 60.00 60.00 1997
LOWER PERIYAR HPS 3 1 60.00 60.00 1997
NARIAMANGLAM HPS 1 1 15.00 15.00 1961
NARIAMANGLAM HPS 2 1 15.00 15.00 1961
NARIAMANGLAM HPS 3 1 15.00 15.00 1963
NARIAMANGLAM HPS 4 1 25.00 25.00 1928
PALLIVASAL HPS 1 1 5.00 5.00 1940
PALLIVASAL HPS 2 1 5.00 5.00 1941
PALLIVASAL HPS 3 1 5.00 5.00 1942
PALLIVASAL HPS 4 1 7.50 7.50 1948
PALLIVASAL HPS 5 1 7.50 7.50 1949
PALLIVASAL HPS 6 1 7.50 7.50 1951
PANNIAR HPS 1 1 15.00 15.00 1963
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

PANNIAR HPS 2 1 15.00 15.00 1964


PORINGALKUTTU HPS 1 1 8.00 8.00 1957
PORINGALKUTTU HPS 2 1 8.00 8.00 1958
PORINGALKUTTU HPS 3 1 8.00 8.00 1959
PORINGALKUTTU HPS 4 1 8.00 8.00 1960
SABARIGIRI HPS 1 1 50.00 50.00 1966
SABARIGIRI HPS 2 1 50.00 50.00 1966
SABARIGIRI HPS 3 1 50.00 50.00 1967
SABARIGIRI HPS 4 1 50.00 50.00 1967
SABARIGIRI HPS 5 1 50.00 50.00 1967
SABARIGIRI HPS 6 1 50.00 50.00 1967
SENGULAM HPS 1 1 12.00 12.00 1954
SENGULAM HPS 2 1 12.00 12.00 1954
SENGULAM HPS 3 1 12.00 12.00 1954
SENGULAM HPS 4 1 12.00 12.00 1955
SHOLAYAR HPS 1 1 18.00 18.00 1966
SHOLAYAR HPS 2 1 18.00 18.00 1968
SHOLAYAR HPS 3 1 18.00 18.00 1968
1881.50
ALIYAR HPS 1 1 60.00 60.00 1970
BHAWANI KATTAL HPS 1 1 15.00 15.00 2006
BHAWANI KATTAL HPS 2 1 15.00 15.00 2006
BHAWANI BARRAGE II HPS 1 1 15.00 15.00 2013
BHAWANI BARRAGE II HPS 2 1 15.00 15.00 2013
BHAWANI BARRAGE III HPS 1 2 15.00 15.00 2012
BHAWANI BARRAGE III HPS 2 2 15.00 15.00 2013
KADAMPARI HPS 1 1 100.00 100.00 1987
KADAMPARI HPS 2 1 100.00 100.00 1988
KADAMPARI HPS 3 1 100.00 100.00 1988
KADAMPARI HPS 4 1 100.00 100.00 1988
KODAYAR HPS 1 1 60.00 60.00 1970
KODAYAR HPS 2 1 40.00 40.00 1971
KUNDAH HPS 1 1 20.00 20.00 1960
KUNDAH HPS 2 1 20.00 20.00 1960
KUNDAH HPS 3 1 20.00 20.00 1964
KUNDAH HPS 4 1 35.00 35.00 1960
KUNDAH HPS 5 1 35.00 35.00 1961
KUNDAH HPS 6 1 35.00 35.00 1961
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

KUNDAH HPS 7 1 35.00 35.00 1961


KUNDAH HPS 8 1 35.00 35.00 1964
KUNDAH HPS 9 1 60.00 60.00 1965
KUNDAH HPS 10 1 60.00 60.00 1964
KUNDAH HPS 11 1 60.00 60.00 1978
KUNDAH HPS 12 1 50.00 50.00 1966
KUNDAH HPS 13 1 50.00 50.00 1978
KUNDAH HPS 14 1 20.00 20.00 1964
KUNDAH HPS 15 1 20.00 20.00 1988
LOWER METTUR HPS 1 1 15.00 15.00 1988
LOWER METTUR HPS 2 1 15.00 15.00 1988
LOWER METTUR HPS 3 1 15.00 15.00 1988
LOWER METTUR HPS 4 1 15.00 15.00 1988
LOWER METTUR HPS 5 1 15.00 15.00 1988
LOWER METTUR HPS 6 1 15.00 15.00 1987
LOWER METTUR HPS 7 1 15.00 15.00 1989
LOWER METTUR HPS 8 1 15.00 15.00 1988
METTUR DAM HPS 1 1 12.50 12.50 1937
METTUR DAM HPS 2 1 12.50 12.50 1937
METTUR DAM HPS 3 1 12.50 12.50 1938
METTUR DAM HPS 4 1 12.50 12.50 1946
METTUR TUNNEL HPS 1 1 50.00 50.00 1965
METTUR TUNNEL HPS 2 1 50.00 50.00 1966
METTUR TUNNEL HPS 3 1 50.00 50.00 1966
METTUR TUNNEL HPS 4 1 50.00 50.00 1966
MOYAR HPS 1 1 12.00 12.00 1952
MOYAR HPS 2 1 12.00 12.00 1952
MOYAR HPS 3 1 12.00 12.00 1953
PAPANASAM HPS 1 1 8.00 8.00 1944
PAPANASAM HPS 2 1 8.00 8.00 1944
PAPANASAM HPS 3 1 8.00 8.00 1945
PAPANASAM HPS 4 1 8.00 8.00 1951
PARSON`S VALLEY HPS 1 1 30.00 30.00 2000
PERIYAR HPS 1 1 42.00 42.00 1958
PERIYAR HPS 2 1 42.00 42.00 1959
PERIYAR HPS 3 1 42.00 42.00 1959
PERIYAR HPS 4 1 35.00 35.00 1965
PYKARA HPS 1 1 7.00 7.00 1932
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

PYKARA HPS 2 1 7.00 7.00 1932


PYKARA HPS 3 1 7.00 7.00 1932
PYKARA HPS 4 1 13.60 13.60 1954
PYKARA HPS 5 1 13.60 13.60 1954
PYKARA HPS 6 1 11.00 11.00 1939
PYKARA ULTMATE HPS 1 1 50.00 50.00 2005
PYKARA ULTMATE HPS 2 1 50.00 50.00 2005
PYKARA ULTMATE HPS 3 1 50.00 50.00 2005
SARKARPATHY HPS 1 1 30.00 30.00 1966
SHOLAYAR HPS (TN) 1 1 35.00 35.00 1971
SHOLAYAR HPS (TN) 2 1 35.00 35.00 1971
SHOLAYAR HPS (TN) 3 1 25.00 25.00 1971
SURULIYAR HPS 1 1 35.00 35.00 1978
2203.20
11727.70

SUBERNREKHA HPS 1 1 65.00 65.00 1977


SUBERNREKHA HPS 2 1 65.00 65.00 1980
130.00
BALIMELA HPS 1 1 60.00 60.00 1973
BALIMELA HPS 2 1 60.00 60.00 1974
BALIMELA HPS 3 1 60.00 60.00 1974
BALIMELA HPS 4 1 60.00 60.00 1975
BALIMELA HPS 5 1 60.00 60.00 1976
BALIMELA HPS 6 1 60.00 60.00 1970
BALIMELA HPS 7 1 75.00 75.00 2008
BALIMELA HPS 8 1 75.00 75.00 2008
HIRAKUD HPS 1 1 32.00 32.00 1956
HIRAKUD HPS 2 1 32.00 32.00 1957
HIRAKUD HPS 3 1 37.50 37.50 1956
HIRAKUD HPS 4 1 37.50 37.50 1957
HIRAKUD HPS 5 1 49.50 49.50 1962
HIRAKUD HPS 6 1 49.50 49.50 1963
HIRAKUD HPS 7 1 37.50 37.50 1990
CHIPLIMA HPS 1 1 24.00 24.00 1962
CHIPLIMA HPS 2 1 24.00 24.00 1962
CHIPLIMA HPS 3 1 24.00 24.00 1964
RENGALI HPS 1 1 50.00 50.00 1985
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

RENGALI HPS 2 1 50.00 50.00 1986


RENGALI HPS 3 1 50.00 50.00 1989
RENGALI HPS 4 1 50.00 50.00 1990
RENGALI HPS 5 1 50.00 50.00 1992
UPPER INDRAVATI HPS 1 1 150.00 150.00 1999
UPPER INDRAVATI HPS 2 1 150.00 150.00 1999
UPPER INDRAVATI HPS 3 1 150.00 150.00 2000
UPPER INDRAVATI HPS 4 1 150.00 150.00 2001
UPPER KOLAB HPS 1 1 80.00 80.00 1988
UPPER KOLAB HPS 2 1 80.00 80.00 1989
UPPER KOLAB HPS 3 1 80.00 80.00 1990
UPPER KOLAB HPS 4 1 80.00 80.00 1993
MACHKUND HPS 1 1 21.25 21.25 1959
MACHKUND HPS 2 1 21.25 21.25 1959
MACHKUND HPS 3 1 21.25 21.25 1959
MACHKUND HPS 4 1 17.00 17.00 1959
MACHKUND HPS 5 1 17.00 17.00 1959
MACHKUND HPS 6 1 17.00 17.00 1959
2142.25
JALDHAKA HPS ST-I 1 1 9.00 9.00 1967
JALDHAKA HPS ST-I 2 1 9.00 9.00 1967
JALDHAKA HPS ST-I 3 1 9.00 9.00 1972
JALDHAKA HPS ST-I 4 1 9.00 9.00 2012
RAMMAM HPS 1 1 12.50 12.50 1995
RAMMAM HPS 2 1 12.50 12.50 1995
RAMMAM HPS 3 1 12.50 12.50 1996
RAMMAM HPS 4 1 12.50 12.50 1996
PURULIA PSS HPS 1 1 225.00 225.00 2007
PURULIA PSS HPS 2 1 225.00 225.00 2007
PURULIA PSS HPS 3 1 225.00 225.00 2007
PURULIA PSS HPS 4 1 225.00 225.00 2007
986.00
TEESTA-III HPS 1 1 200.00 200.00 2017
TEESTA-III HPS 2 1 200.00 200.00 2017
TEESTA-III HPS 3 1 200.00 200.00 2017
TEESTA-III HPS 4 1 200.00 200.00 2017
TEESTA-III HPS 5 1 200.00 200.00 2017
TEESTA-III HPS 6 1 200.00 200.00 2017
Appendix-B
WER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

CHUZACHEN HPS 1 1 55.00 55.00 2013


CHUZACHEN HPS 2 1 55.00 55.00 2013
JORETHANG LOOP HPS 1 1 48.00 48.00 2015
JORETHANG LOOP HPS 2 1 48.00 48.00 2015
TASHIDING HPS 1 1 48.50 48.50 2017
TASHIDING HPS 2 1 48.50 48.50 2017
DIKCHU HPS 1 1 48.00 48.00 2017
DIKCHU HPS 2 1 48.00 48.00 2017
1599.00
MAITHON HPS 1 1 20.00 20.00 1958
MAITHON HPS 2 1 20.00 20.00 1958
MAITHON HPS 3 1 23.20 23.20 1957
PANCHET HPS 1 1 40.00 40.00 1959
PANCHET HPS 2 1 40.00 40.00 1990
TEESTA LOW DAM-III HPS 1 1 33.00 33.00 2013
TEESTA LOW DAM-III HPS 2 1 33.00 33.00 2013
TEESTA LOW DAM-III HPS 3 1 33.00 33.00 2013
TEESTA LOW DAM-III HPS 4 1 33.00 33.00 2013
TEESTA LOW DAM-IV HPS 1 1 40.00 40.00 2016
TEESTA LOW DAM-IV HPS 2 1 40.00 40.00 2016
TEESTA LOW DAM-IV HPS 3 1 40.00 40.00 2016
TEESTA LOW DAM-IV HPS 4 1 40.00 40.00 2016
RANGIT HPS 1 1 20.00 20.00 2000
RANGIT HPS 2 1 20.00 20.00 2000
RANGIT HPS 3 1 20.00 20.00 2000
TEESTA V HPS 1 1 170.00 170.00 2008
TEESTA V HPS 2 1 170.00 170.00 2008
TEESTA V HPS 3 1 170.00 170.00 2008
143.20
862.00
1005.20
5862.45

KARBI LANGPI HPS 1 1 50.00 50.00 2007


KARBI LANGPI HPS 2 1 50.00 50.00 2007
100.00
KYRDEMKULAI HPS 1 1 30.00 30.00 1979
KYRDEMKULAI HPS 2 1 30.00 30.00 1979
LIST OF HYDRO POWER STATIONS AS ON 31.03.2018
Appendix-B
Total Central Sector (North Eastern Region)
North Eastern Region Total
Total All India Hydro
920.00
1342.00
45293.42
LIST OF NUCLEAR POWER STATIONS AS ON 31.03.2018
Sl. No. State Sector Owner

1 Rajasthan Central Sector NPCIL


2 Rajasthan Central Sector NPCIL
Rajasthan Central Sector NPCIL
Rajasthan Central Sector NPCIL
Rajasthan Central Sector NPCIL
Rajasthan Central Sector NPCIL
3 Uttar Pradesh Central Sector NPCIL
Uttar Pradesh Central Sector NPCIL
4 Gujarat Central Sector NPCIL
Gujarat Central Sector NPCIL
5 Maharashtra Central Sector NPCIL
Maharashtra Central Sector NPCIL
Maharashtra Central Sector NPCIL
Maharashtra Central Sector NPCIL
6 Karnataka Central Sector NPCIL
Karnataka Central Sector NPCIL
Karnataka Central Sector NPCIL
Karnataka Central Sector NPCIL
7 Tamil Nadu Central Sector NPCIL
Tamil Nadu Central Sector NPCIL
8 Tamil Nadu Central Sector NPCIL
Tamil Nadu Central Sector NPCIL
Total All India Nuclear
Appendix-C
OWER STATIONS AS ON 31.03.2018
Name of Project Unit No. No. of Units Capacity Total Capacity Year of Comm.

MW MW
DAE (RAJASTHAN) 1 1 100 100 1972
RAJASTHAN A.P.S. 2 1 200 200 1980
RAJASTHAN A.P.S. 3 1 220 220 2000
RAJASTHAN A.P.S. 4 1 220 220 2000
RAJASTHAN A.P.S. 5 1 220 220 2010
RAJASTHAN A.P.S. 6 1 220 220 2010
NARORA A.P.S. 1 1 220 220 1989
NARORA A.P.S. 2 1 220 220 1992
KAKRAPARA A.P.S. 1 1 220 220 1992
KAKRAPARA A.P.S. 2 1 220 220 1995
TARAPUR A.P.S. 1 1 160 160 1960
TARAPUR A.P.S. 2 1 160 160 1969
TARAPUR A.P.S. 3 1 540 540 2005
TARAPUR A.P.S. 4 1 540 540 2006
KAIGA A.P.S. 1 1 220 220 2000
KAIGA A.P.S. 2 1 220 220 1999
KAIGA A.P.S. 3 1 220 220 2007
KAIGA A.P.S. 4 1 220 220 2011
MADRAS A.P.S. 1 1 220 220 1983
MADRAS A.P.S. 2 1 220 220 1985
KUDANKULAM 1 1 1000 1000 2014
KUDANKULAM 2 1 1000 1000 2017
6780