Professional Documents
Culture Documents
PROCESS COSTING
Process
Where goods and services results from sequence of continuous &
repetitive operations or processes
Process costing is used when company is mass producing the same
items and the items goes through a number of different stages
PROCESS COSTING
Two key issues in process costing are losses & incomplete units
During production process, some input is loss due to evaporation or
wastage
Normal loss represent items that you expect to loss during a process.
Therefore its cost is treated as part of cost of good production
Normal loss are usually treated as percentage of input i.e. normal loss is
expected to be 5% of the input material
PROCESS COSTING
Illustration:
At the start of the heating process 1,000 Kg of material costing $16/kg
is input. During the process the conversion cost of $2,000 are incurred.
Normal loss through evaporation is expected to be 10% of the input.
During March, 1,000 Kg were the input and output was 900 Kg.
Compute the unit and total cost of the output in March?
Input Output Loss (Balancing)
1,000 Kg 900 Kg 100 Kg
PROCESS COSTING
PROCESS COSTING
Process Account
Kg $ Kg $
Input 1,000 16,000 Input 900 18,000
Conversion Cost - 2,000 Normal Loss 100 -
PROCESS COSTING
PROCESS COSTING
To be able to assigned correct amount of cost to finished and partially
completed units, we use a concept called equivalent units or EU
For example: if we had 1,000 units that are 50% complete at the end of
the period. How many finished units is this equivalent to?
PROCESS COSTING
Illustration:
EM Ltd is a manufacturer. In period 1 the following production occurred
Started = 1,400 Units
Closing Work in Progress (CWIP) = 400 Units
Degree of completion of CWIP :
Material = 100% Conversion = 50%
Cost incurred in period 1:
Material=$81,060 Conversion=$71,940
SCHOOL OF BUSINESS & MANAGEMENT MISS FATIMA KHIZAR
18
PROCESS COSTING
Finished goods are 100% complete for both material & conversion
EUs
Finished Goods (1,000×100%) 1,000
Material 1,400
CWIP (400×100%) 400
Finished Goods (1,000×100%) 1,000
Conversion 1,200
CWIP (400×50%) 200
SCHOOL OF BUSINESS & MANAGEMENT MISS FATIMA KHIZAR
19
PROCESS COSTING
PROCESS COSTING
Input $ $
Completed Units 1,000×$117.85 117,850
CWIP (Material) 400×$57.90 23,160
CWIP (Conversion) 200×$59.95 11,990
35,150
Total
SCHOOL OF BUSINESS & MANAGEMENT 153,300
MISS FATIMA KHIZAR
21
PROCESS COSTING
Process Account
$ $
Material 81,060 Finished Goods 117,850
Conversion 71,940 CWIP Material 23,160
CWIP Conversion 11,990
153,000 153,000
ACTIVITY 4
(SOLUTION)
ACTIVITY 5
(SOLUTION)
ACTIVITY 5
(SOLUTION)