You are on page 1of 11

Electric Power Systems Research 77 (2007) 24–34

A technical evaluation framework for the connection


of DG to the distribution network
Stavros A. Papathanassiou ∗
School of Electrical and Computer Engineering, National Technical University of Athens (NTUA), 9 Iroon Polytechniou str., 157 73 Athens, Greece
Received 12 October 2005; received in revised form 4 January 2006; accepted 17 January 2006
Available online 10 March 2006

Abstract
Technical advances and institutional changes in the electric power industry have resulted in a constantly increasing penetration of distributed
generation (DG) resources in the grids. For the connection of new DG installations to the network a variety of factors are taken into account,
including technical requirements imposed by utilities to ensure that the DG station does not adversely affect the operation and safety of the
network. In this paper, fundamental issues related to the interconnection of DG installations to the grid are discussed and evaluation rules are
presented, which address power quality considerations and are suitable for application by electric utility and DG engineers. The attention is focused
on the steady-state and fast voltage variations, flicker and harmonic emissions. The simplified evaluation procedures of the paper are largely
based on the relevant IEC publications and reflect the current practice of several European utilities. A discussion of the interconnection protection
requirements is also included in the paper.
© 2006 Elsevier B.V. All rights reserved.

Keywords: Distributed generation (DG); Distribution networks; Interconnection; Power quality; Voltage variations; Flicker; Harmonics; Protection

1. Introduction utilities (e.g. [3–9]). It is also important that the interconnection


requirements (power quality considerations, fault ride-through
The penetration of distributed generation (DG) resources capability, anti-islanding detection, etc.) not only influence the
(wind turbines, photovoltaics, fuel-cells, biomass, micro- economic viability of a particular DG investment, but also act
turbines, small hydroelectric plants, etc., ranging from sub-kW as a driving force for the design of components with improved
to multi-MW sizes) in distribution grids is increasing world- operating characteristics. A typical example is the uniform adop-
wide. The drive for cleaner energy sources, the economic oppor- tion of PWM voltage-source converters at the grid side of all
tunities presented for investors in the deregulated electric indus- modern DG sources and the implementation of sophisticated
try environment and the potential benefits for utilities (peak- anti-islanding schemes in small DG sources connected to the
shaving, congestion alleviation, reduction of losses, better asset LV network (e.g. [10,11]).
utilization, etc.) are contributing to this trend [1]. In this paper, fundamental considerations are first discussed,
Although there always exist important regulatory and busi- regarding the grid-interconnection schemes used in practice.
ness issues concerning the integration of DG in the grids, techni- Then, a framework of technical criteria and requirements is
cal considerations are often viewed as a critical factor affecting presented, which permits the efficient evaluation of new DG
the development of new installations [2]. To facilitate the tech- installations. The paper deals mainly with MV installations and
nical evaluation process for the interconnection of new DG it focuses on power quality issues, namely slow and fast volt-
installations, without compromising the operating and safety age variations, flicker and harmonic emissions. Other important
requirements of the grid, suitable disturbance limits have been considerations, such as interconnection protection requirements,
adopted and simplified evaluation methodologies are applied by are briefly discussed, whereas the critical issue of the fault
level contribution of DG [12] is not dealt with in the context
of this paper. The interconnection criteria and guidelines pre-
∗ Tel.: +30 210 7723658; fax: +30 210 7723593. sented are based on the extensive set of IEC power quality
E-mail address: st@power.ece.ntua.gr. standards (part of the IEC 61000 series of EMC publications).

0378-7796/$ – see front matter © 2006 Elsevier B.V. All rights reserved.
doi:10.1016/j.epsr.2006.01.009
S.A. Papathanassiou / Electric Power Systems Research 77 (2007) 24–34 25

Fig. 1. Connection point (CP) and point of common coupling (PCC).

They reflect the evaluation practices adopted in [9], which are the basic alternatives (HV/MV substations being replaced by
similar in concept to the practices of several other European MV/LV ones).
utilities. In Scheme 1 the DG station is connected to an existing distri-
bution feeder, via an extension to the existing line. It is possible
2. Interconnection schemes that reinforcement (e.g. conductor upgrade) may be required
for the existing feeder (black line in Fig. 2). In Scheme 2, a
DG installations are connected to the distribution grid using
arrangements not essentially different from those used for con-
sumers, as it is schematically illustrated in Fig. 1. Most important
is the differentiation between the actual connection point (CP)
and the point of common coupling (PCC). The latter is defined
as the closest to the DG installation node, where other users
are (or may be) connected and it may differ from the physical
point of connection, when the installation is interconnected via
a dedicated (“direct”) line segment, as in Fig. 1.
The equipment used for the connection to the grid obvi-
ously varies, depending on the standardization applied by each
utility. Nevertheless, the coupling substation at the installation
terminals always comprises the required switching/protection
equipment and metering devices, indicatively shown in Fig. 1.
The most common schemes for the interconnection to the MV
and HV grid are illustrated in Fig. 2. The numbering of these five
schemes corresponds to increasing DG capacity, fault-level at the
PCC and cost and time of construction for the interconnection
Fig. 2. Alternative interconnection schemes for a DG installation (MV and HV
works. For smaller installations, which may be connected to the network) and associated PCCs. Grey/black line for existing/new parts of the
LV network (e.g. <100 kW), cases 1, 2, 4 and 5 of Fig. 2 are network.
26 S.A. Papathanassiou / Electric Power Systems Research 77 (2007) 24–34

dedicated (‘direct’) line connects the DG station directly to the disconnection upon detection of abnormal grid conditions. A
MV busbars of the HV/MV substation (where the PCC is now discussion on this subject is provided in Section 7 of the paper.
located). When this is not possible or acceptable, an upgrade • Effect on network signaling systems. User equipment should
of the existing substation is examined (Scheme 3), installing a not interfere with the operation of public network signaling
new HV/MV transformer. If this is not possible, a new HV/MV systems (e.g. attenuate or amplify signals of the acoustic fre-
substation has to be built, either under/near an existing HV line, quency ripple control systems).
whereupon the DG station is connected at the MV level (Scheme
4), or within the premises of the DG installation (Scheme 5). In 4. Slow voltage variations
the latter case, an extension of the HV line is needed (often a
radial single-circuit line, to keep costs down) and the station The statistical nature of voltage variations is recognized today
becomes a user of the HV network, unlike all the other schemes, and relevant norms have been issued, such as the European Norm
where the station is a MV network user. Large stations, of the EN 50160 [14], which imposes statistical limits, in the sense that
order of tens of MW and above, are connected directly to the a small probability of exceeding them is acceptable. However,
HV grid. checking the conformity against statistical limits at the plan-
Selecting the appropriate interconnection scheme is often a ning stage calls for elaborate procedures, such as probabilistic
complicated economic and technical decision, which takes into load flow techniques (e.g. [15,16]). Such an approach is rela-
account: tively difficult to apply, would require data usually unavailable
in practice and completely defies the objective of simplicity and
• the existing network infrastructure; efficiency in the evaluation. For this reason, utility directives for
• the cost of grid reinforcement and extension works; the connection of DG adopt simpler and more straightforward
• the cost of power and energy losses on the interconnecting procedures. The evaluation procedure presented in the following
network; utilizes 10-min average values of the voltage and can be applied
• possible implications in the construction of major grid works in two stages.
(e.g. environmental permits for new HV lines); At a first stage, the maximum steady-state voltage change
• technical criteria and requirements, related to power quality, ε (%) at the PCC is evaluated using the following simplified
fault level, protection, etc., which are presented in more detail relation and compared to a limit:
in the following sections. 100
ε (%) ∼
= (Rk Pn + Xk Qn ) ≤ 2% (1)
Un2
3. Overview of technical requirements
where Pn and Qn are the DG rated (or maximum continuous)
The interconnection of DG sources to the grid is often active and reactive powers, and Zk = Rk + jXk the network short-
regarded as a potential source of power quality disturbances circuit impedance at the PCC.
and appropriate requirements and evaluation methodologies are The 2% limit in Eq. (1) is typical (e.g. [8,9]) and relatively
applied. In general, they comprise two distinct stages. First, strict, since this is a “first stage” evaluation and, further, this
the expected disturbance is calculated at the Point of Common limit is allocated to a single user, whereas the voltage level is
Coupling (PCC)1 because of a specific DG installation. Then, determined by the aggregate effect of all connected consumers
suitable limits are applied to ensure that the expected distur- and generators.
bance level does not adversely affect other users of the network. In practical situations, Eq. (1) will yield a voltage increase,
Following the IEC 61000 definitions [13], planning levels are due to the active power flow on the resistive part of the network
generally used as disturbance limits. Power quality phenomena impedance, which may be significant in case of weak grids. For
taken into consideration are slow (steady-state) voltage varia- this reason, slightly inductive power factor values are usually
tions, fast voltage changes, flicker and harmonic emissions. preferred (Q < 0).
Beyond the power quality issues, additional considerations Since voltage variations are the aggregate effect of generat-
and requirements include the following: ing facilities and network loads, a second stage, more detailed
evaluation involves load flow calculations in the network, tak-
ing into account the actual network configuration and loads.
• Network capacity. Ratings of all network components must
By solving the load flow for the four combinations of max/min
be sufficient to handle the power of the DG station.
load/generation, the maximum and minimum voltages, Umax and
• Short circuit capacity. DG source contribution should not lead
Umin , are determined for each node (usually, min load/max gen
to exceeding the design fault level of the network. This issue
yields maximum voltages and max load/min gen minimum volt-
is dealt with more detail in [12].
ages). These voltages must then be appropriately bounded. In
• Switching and protection equipment. All DG installations are
[9], the following requirements are set for the steady-state volt-
equipped with suitable interconnection protection, to enforce
age of all nodes (Fig. 3, top diagram):

1 Dedicated interconnection lines are formally a part of the grid. For this
• The median voltage of any node k should lie within ±5% of
reason, disturbance limits may also be enforced for the point of connection (CP) the nominal voltage, a requirement dictated by the off-load
as well, albeit more lenient than for the PCC. tap changer of the MV/LV distribution transformers (±5%
S.A. Papathanassiou / Electric Power Systems Research 77 (2007) 24–34 27

median deviation is corrected by the fixed taps:


Umax,k − Umin,k
≤ 0.03 · Un (3)
2

The requirements expressed by Eqs. (2) and (3) determine


the region of acceptable maximum and minimum node voltages
illustrated in Fig. 3 (bottom diagram), against which the load
flow results are compared.
In the four load-flow calculations proper account must be
taken of the voltage regulating means of the network (OLTCs of
HV/MV transformers, line voltage regulators, capacitor banks),
which normally operate on time scales of 1 min or longer and
therefore affect the steady-state (10-min average) values. Fur-
ther, when dealing with sources with adjustable power fac-
tor (synchronous generators, PWM converters), this has to be
accounted for in the load flow calculations.

5. Rapid voltage changes—flicker

Rapid voltage changes occur within the 10-min averaging


interval used in the definition of slow voltage variations, typi-
cally on a time scale between half a period (10 ms at 50 Hz) and a
few seconds. They are induced either by switching operations in
the DG installation (usually start/stop operations of equipment)
or by the variability of the output power during normal operation
(e.g. for wind turbines).
In the case of rapid voltage changes, both their magnitude
and the resulting flicker emissions should be limited. Measures
of the flicker emissions are the short-term, Pst , and long-term,
Plt , flicker severity indices ([17–19]).
Regarding switching operations, the limits imposed depend
Fig. 3. Top diagram: definition of maximum/minimum and median node voltage on the voltage level (LV or MV) where the installation is con-
in steady-state. Bottom diagram: acceptable region of maximum and minimum
nected, the size of the equipment and the frequency of the
node voltages.
operations. Taking into account the requirements of the rele-
vant IEC documents [20–23], the limits of Table 1 can be set for
regulation, in steps of 2.5%): the relative (%) voltage change (see also Fig. 4).
An evaluation of the expected voltage change at the PCC at
Umin,k + Umax,k the cut-in of a DG unit is given by:
0.95 · Un ≤ ≤ 1.05 · Un (2)
2 Sn
dmax (%) = 100 · kU (ψk ) (4)
Sk
• The variation of the voltage around its median value should
not exceed ±3% of the nominal, so that the LV network volt- where kU (ψk ) is the voltage change factor, defined for wind tur-
age deviations remain within ±8% (planning limit), after the bines in IEC 61400-21 [24], and included in their test certificates

Table 1
Magnitude limits for rapid voltage changes
Frequency of switching operations, r (h−1 : per hour, d−1 : per day)

r > 1 h−1 2 d−1 < r < 1 h−1 r < 2 d−1

LV
Steady-state change, dc ≤3% ≤3% ≤3%
Maximum change, dmax ≤4% ≤5.5% ≤7%
r > 10 h−1 1 h−1 < r ≤ 10 h−1 r ≤ 1 h−1

MV
Steady-state change, dc – – –
Maximum change, dmax ≤2% ≤3% ≤4%
28 S.A. Papathanassiou / Electric Power Systems Research 77 (2007) 24–34

using the flicker coefficient, c(ψk , va ), dependent on the average


annual wind speed, va , at the WT installation site and the grid
short circuit impedance angle, ψk :
Sn
Pst = Plt = c(ψk , va ) (8)
Sk
For the total flicker emissions of a wind farm comprising N
WTs, the following relation is used:

 N
1 
Pst = Plt =  (c(ψk , va ) · Sn,i )2 (9)
Sk
i=1

Fig. 4. Fast voltage change pattern and characteristics. where the flicker summation in normal operation is performed
applying a quadratic summation rule.
as a function of the angle ψk of the short-circuit impedance Zk of Limits for flicker emissions are the same for normal operation
the grid. Suitable values of kU for installations with synchronous and switchings. At the LV level, limits stipulated in IEC 61000-
generators are discussed in [25]. For simplified calculations, kU 3-3 are Pst ≤ 1 and Plt ≤ 0.65. At the MV level, the determination
can be set equal to the ratio of the equipment starting current of limits is left to the utilities, which set the planning levels for
to its rated current, ranging from less than 1 to higher than 8, their grids. Indicative values for planning levels in MV systems,
depending on the type of equipment and the starting method according to IEC 61000-3-7, are Pst ≤ 0.9 and Plt ≤ 0.7. The
used. allocation of these global limits to individual installations is
Eq. (4) is applied for the single unit in the power station, which made according to the principles presented in the next section
creates the largest disturbance. Summation rules for simultane- for harmonics (equations similar to (10) and (12) are applied).
ous switchings of equipment need not be applied, due to the very
low probability of coincident events. 6. Harmonics
For the case of wind turbines, flicker emissions resulting from
switching operations can be calculated as ([24,27]): The increasing use of power electronics at the front end of
 N 1/3.2 many DG types (variable speed WTs, photovoltaics, micro-
18  turbines, etc.) poses harmonic control requirements for their
Pst = N10,i (kf,i (ψk ) · Sn,i )3.2
(5)
Sk connection to the grid. Several national and international stan-
i=1
dards and recommendations are available today (e.g. [30–33]), to
 N 1/3.2 elaborate appropriate evaluation procedures. In this section, an
8 
Plt = N120,i (kf,i (ψk ) · Sn,i )3.2
(6) approach based on the IEC set of standards is presented, which
Sk comprises three basic steps: first, the definition of acceptable
i=1
voltage distortion limits (planning levels), second, the allocation
where N is the number of generators operating in parallel, Sn,i
of global harmonic voltage limits to individual users (producers
the rated capacity and kf,i (ψk ) is the flicker step factor of unit
or consumers) and third, the determination of the corresponding
i (defined in [24]). N10,i and N120,i are the maximum number
current distortion limits for a specific installation.
of switching operations that can take place in a 10- and 120-
For LV systems specific compatibility levels are given in IEC
min interval for unit i. If the flicker step factor is unavailable,
61000-2-2 [34], which also serve as planning levels, and are
the flicker has to be evaluated either by the shape characteris-
included in Table 2. At higher voltage levels (MV and HV), it
tics and the frequency of the disturbance (IEC 61000-3-3 [20],
is the responsibility of the utility to determine the compatibility
provides useful guidance), or by simulation using a software
levels in its network and then define appropriate planning levels.
implementation of the flickermeter algorithm of IEC 61000-4-
For reference purposes, Table 2 summarizes indicative planning
15 [19].
levels from IEC 61000-3-6.
The following rule is commonly applied for the summation
of flicker due to switching operations (used for Plt as well):
 6.1. MV systems

Pst = 3 3
Pst,i (7)
i The coordination of harmonic emission control at the differ-
ent voltage levels (LV, MV and HV) of a power system requires
where the exponent may also be 3.2, instead of 3.0, as in Eqs.
that distortion transmitted from one level to another be taken
(5) and (6).
into account. Hence, the distortion limit GhMV , available to all
During normal operation, voltage changes resulting from
installations connected to the MV system, is ([33]):
fluctuations of the DG output power may create flicker prob-

lems, a well-known fact for WTs [26–29]. According to IEC
GhMV = a LahMV − (ThHM · LhHV )a (10)
61400-21, the expected flicker emissions of WTs can be assessed
S.A. Papathanassiou / Electric Power Systems Research 77 (2007) 24–34 29

Table 2
Planning levels for LV, MV and HV networks (IEC 61000-3-6 [33])
Odd harmonics = 3k Odd harmonics = 3k Even harmonics

Order, h Harmonic voltage (%) Order, h Harmonic voltage (%) Order, h Harmonic voltage (%)

LV MV HV LV MV HV LV MV HV

5 6 5 2 3 5 4 2 2 2 1.6 1.5
7 5 4 2 9 1.5 1.2 1 4 1 1 1
11 3.5 3 1.5 15 0.3 0.3 0.3 6 0.5 0.5 0.5
13 3 2.5 1.5 21 0.2 0.2 0.2 8 0.5 0.4 0.4
17 2 1.6 1 >21 0.2 0.2 0.2 10 0.5 0.4 0.4
19 1.5 1.2 1 12 0.2 0.2 0.2
23 1.5 1.2 0.7 >12 0.2 0.2 0.2
25 1.5
1.2
0.7

>25 0.2 + 1.3 · 25


h 0.2 + 0.5 · 25
h 0.2 + 0.5 · 25
h

THD: 8% at LV; 6.5% at MV; 3% at HV.

where LhMV and LhHV are the MV and HV planning levels for where the fundamental frequency inductive component Xk of the
harmonic order h (from Table 2) and ThHM the harmonic transfer short circuit impedance at the PCC is evaluated from:
coefficient from HV to MV level (ranging from below 1.0 to
more than 3.0); a is the exponent of the harmonic summation Un2 sin ψk
Xk = (15)
rule: Sk
 
However, since this is not a realistic assumption, a simplified
Uh = a a
Uhi or Ih = a a
Ihi (11) approach can be established [33] with reference to Fig. 5, where
i i all network capacitance is aggregated at the MV busbars and any
IEC 61000-3-6 suggests a = 1 for h < 5, a = 1.4 for 5 ≤ h ≤ 10 possible resonance in the HV system is ignored. The capacitance
and a = 2 for h > 10, since harmonics of higher orders tend to in Fig. 5 accounts for the first order parallel resonance with the
have random phase angles. upstream system (but not for possible higher order resonances).
From GhMV , the voltage distortion limit EUhi for an individual If all resistances and system loads in Fig. 5 are ignored, the
installation can then be determined, in proportion to its rated resonant frequency fr and the respective harmonic order hr (not
power, Sn,i : necessarily an integer) are given by

Sn,i √ SkS fr SkS
EUhi = GhMV a = GhMV a si (12) fr = f1 ⇒ hr = = (16)
St Qc f1 Qc

where St is the total capacity of the network (e.g. equal to the where SkS is the short circuit capacity at the MV busbars of the
rated MVA of the feeding transformer). St can also be interpreted HV/MV substation and Qc is the total capacitive reactive power
as the total capacity of the distorting equipment in the network, of the MV network. A rough and conservative estimation of Zh
to avoid over-pessimistic results. is then given by the “envelope impedance curve” of IEC 61000-
It is common practice in harmonic studies to regard the con- 3-6, shown in Fig. 6. The resonant amplification factor, kr , of the
nected equipment as a harmonic current source (although this system impedance at the PCC typically varies between 2 and 5 in
may not be correct in certain cases, e.g. voltage controlled con- public distribution networks, depending mainly on the damping
verters), whereas the limits discussed previously refer to the effect of the system load. A discussion on the application of this
harmonic distortion of the system voltage. In order to relate method is provided in [35].
these quantities, the system harmonic impedance Zh at the PCC For installations with filters or significant PFC capacitance,
is needed. Then: in more complex networks or when resonant conditions exist in
the HV network, the approach presented above is not suitable.
EUhi
Uhi = Zh · Ihi ≤ EUhi ⇒ Ihi ≤ EIhi = (13)
Zh
where Uhi and Ihi are the h-order harmonic distortion of the volt-
age and current due to installation i and EUhi , EIhi the respective
limits allocated to this installation.
For MV systems no standardized reference impedance is
available and the harmonic impedance Zh has to be evaluated
for each specific network. For a purely inductive system (no
shunt capacitance):
Zh ≈ h · Xk (14) Fig. 5. MV network equivalent for simplified harmonic analysis ([33]).
30 S.A. Papathanassiou / Electric Power Systems Research 77 (2007) 24–34

where MhLV is the harmonic current limit per MVA of Sk . ψk


is taken into account, because of the predominantly resistive
character of the LV networks. MhLV values can be derived based
on Eq. (18).

6.3. Interharmonics and higher order harmonics

The evaluation procedures outlined above cater for harmonic


orders h ≤ 40 (IEEE Std. 519 [31], provides limits up to the
50th order), which is sufficient for line-commutated converters,
Fig. 6. System harmonic impedance approximation, using the (envelope as well as for voltage-source converters with a low switching
impedance curve) [33]. frequency. However, the increasing utilization of fast switching
PWM converters has extended the harmonic frequency spectrum
Manual computation of Zh is possible in certain cases but the well beyond 2 kHz, where limits and standardized evaluation
application of harmonic load flow software is recommended. methodologies are still unavailable. Due to the lack of relevant
The procedure described, although heavily simplified by standards and experience in this range, a conservative approach
research standards, may already be complicated enough for is often adopted. In [6,7,9], a strict limit is set on the voltage
application in practical situations. To further facilitate the eval- distortion due to higher order and interharmonic components:
uation of low distortion equipment at the MV level, without
Uh ≤ 0.2%, h > 40 or h non-integer
resorting to the procedure described above, a “Stage 1” require-
ment may be formulated. Using Eqs. (13)–(15) and the definition which is in line with the interharmonics planning level suggested
of the resonant amplification factor, kr , from Fig. 6, it is derived: in IEC 61000-3-6.
An issue related to harmonics is also the possible interference
Un2 of DG installations with mains signaling, such as ripple control
Uhi ≈ kr · h · · sin ψk · Ihi ≤ EUhi (17)
Sk systems. Such systems usually operate in the range 100–500 Hz
For the “Stage 1” evaluation, a conservative approach is (up to 2–3 kHz) by injecting a voltage signal of higher frequency
adopted. The resistive part of Zk is ignored (sin ψk = 1) and the on the power frequency voltage waveform. To ensure no inter-
limit EUhi is deduced from the planning levels LhMV (or GhMV ) ference, the injection of harmonics or interharmonics from the
in proportion to the ratio si (a = 1 in Eq. (12)). Then, from Eq. DG installations should be minimized at the ripple control fre-
(17): quency and its sidebands at frequencies differing by twice the
fundamental frequency.
Ihi /si LhMV Ihi
≤ = MhMV ⇒ ≤ MhMV · Sk (18)
Sk kr · h · U n
2 si 7. Interconnection protection requirements
The limit MhMV in Eq. (18), expressed in A/MVA, is then
directly evaluated using the nominal voltage of the network and The DG-utility interface protection is primarily intended to
assuming an appropriate value for kr (kr = 5 would be a conserva- ensure the safety of other users of the network and of util-
tive approach). Such a simplified evaluation is adopted in [6,9]. ity personnel and it should be properly coordinated with other
If Eq. (18) is not satisfied, a more detailed evaluation has to be protections of the grid. The protective functions incorporated
conducted, as discussed previously. therein may differ considerably, depending on the size, voltage
level, type of DG equipment and the operation and protection
6.2. LV systems scheme of the network. A comprehensive overview for small
DG stations is provided in [37].
The principles outlined in the previous section for MV sys- The primary function of the interconnection protection
tems are also applicable to the LV level. However, for LV systems (besides fault detection via overcurrent relays) has always been
IEC 725 [36], establishes a reference system impedance, per- the detection of islanding situations and the immediate discon-
mitting thus the direct determination of harmonic current limits. nection of the generating equipment. Islanding has been exten-
IEC 61000-3-2 provides limits for equipment with rated cur- sively studied for PVs connected to the LV network and islanding
rent ≤ 16 A/phase (Class A). For DG units with rated current detection and protection schemes have been proposed, tested and
between 16 and 75 A/phase, the limits of IEC 61000-3-4 are gradually implemented in commercial products [10,11]. In case
applicable, when connected to a PCC where the short circuit of DG installations utilizing synchronous generators, islanding
ratio is higher than 33. For DG installations with rated current is a serious concern, too. If induction generators are used, the
higher than 75 A per phase, the Stage 1 evaluation procedure possibility of self-excited operation exists and such situations
used for MV installations (Eq. (18)) can be applied, using as have been encountered in practice. An example is shown in
emission limit: Fig. 7, recorded on the Greek island of Chios, where about 5 MW
of wind power are connected to a 20 kV line, which includes
Sk a 20 km section of submarine cable [38]. The opening of the
Ih ≤ MhLV · (19)
sin ψk feeder circuit breaker resulted in a voltage swell in the isolated
S.A. Papathanassiou / Electric Power Systems Research 77 (2007) 24–34 31

Table 3
Indicative settings for the interconnection protection relays
Relay Settings Type A Settings Type B

Threshold Delay (s) Threshold Delay (s)

27 0.85·Un 0.3 0.80·Un 1.2


59 1.10·Un 0.3 1.15·Un 1.2
81U 49.5 Hz 0.3 47.5 Hz 1.2
81O 50.5 Hz 0.3 51.5 Hz 1.2

as fast disconnection of DG sources in lines with fast reclosing


schemes (ensuring disconnection before reclosing, to prevent
unacceptable stresses [39]). These requirements are fulfilled by
the settings Type A in Table 3. The 0.3 s activation time is short
Fig. 7. Recorded voltage during the isolated operation of a feeder with significant enough to ensure disconnection before the first reclosing of the
wind power, following the opening of the circuit breaker at its departure [38]. feeder breaker (approximately 0.5 s after initiation of the fault).
At the same time, it is also long enough to avoid tripping by
part, sustained for about 15 s (the WT over-voltage protection voltage dips due to faults on adjacent feeders, cleared in the
was set high, due to the high normal operation voltage). first reclosing cycle (with instantaneous overcurrent relays, dips
Typical minimum protective functions of the interconnec- last approximately 0.1–0.15 s). Transfer-trip schemes can also
tion protection system are over-/under-voltage and over-/under- be used between the line and DG breakers, a solution considered
frequency, as shown in Fig. 8. Zero-sequence (residual) voltage for relatively large installations.
relays are also stipulated in many cases (depending on the MV Fast activation times, however, lead to increased “nuisance”
network neutral earthing arrangements and step-up transformer trips of the DG station, which may pose a threat to the stability
connections). In Table 3, two groups of indicative relay settings of systems with high levels of DG penetration. In such cases,
(Type A and Type B) are provided and discussed in the follow- maintaining generation capacity in operation during critical dis-
ing. turbances takes precedence over other considerations, leading
Strict settings are needed in the voltage and frequency pro- to the adoption of less sensitive protection settings. The Type B
tection, Table 3 to achieve sensitive islanding detection, as well settings in Table 3, applicable for DG stations connected to the

Fig. 8. Basic functions of the interconnection protection system.


32 S.A. Papathanassiou / Electric Power Systems Research 77 (2007) 24–34

ation resources to distribution networks. Technical require-


ments and assessment criteria are presented for power quality
related issues, including steady-state and rapid voltage varia-
tions, flicker and harmonic emissions, which are suitable for
practical application. These criteria and procedures are largely
based on the set of relevant IEC publications, as well as on cur-
rent utility practice.
It is certain that the technological advancements will call
for continuous update of the evaluation methodologies. For
instance, active front-end converters, with load balancing, flicker
cancellation and active filtering capabilities, may soon find their
way into commercial DG equipment. The operating paradigm
of distribution networks with significant DG resources will also
Fig. 9. Voltage sag immunity requirements imposed to large wind farms by a
German utility (E.ON. Netz GmbH [40]). evolve, towards an “active” network principle. Further, apart
from the core technical issues, it is also certain that other market
and regulatory factors will affect critically the degree of future
MV network of island grids, ensure adequate ride-through for DG penetration and the criteria and requirements for their inte-
voltage sags due to faults cleared by inverse-time overcurrent gration.
relays of the feeder breakers. They are also much less sensi-
tive to temporary voltage and frequency excursions, common in Appendix A. List of symbols
small isolated power systems.
Besides adopting less sensitive protection settings, to main-
tain generation capacity in operation during critical distur- a harmonics summation exponent
bances, imposes also requirements for the fault ride-through c flicker coefficient
capability of DG units. A characteristic example is the require- dc “permanent” deviation during a fast voltage change
ment first imposed by the German utility E.ON. to all large wind event (%)
farms connected to its system, that their generators should ride dmax maximum deviation during a fast voltage change event
through all voltage sags lying above the magnitude-duration (%)
characteristic of Fig. 9 [40,41]. In addition, in all countries EIhi current harmonic emission limit (order h), applicable
experiencing high DG penetrations (mainly wind power), the to installation i
grid codes now impose strict requirements on all stations con- EUhi voltage harmonic distortion limit (order h), applicable
nected to the grid (initially only for HV level installations, now to installation i
gradually for the MV level as well), in order to assure that f1 fundamental frequency
they actively assist the grid, by properly regulating their out- fr resonance frequency
put active and reactive power, both in normal operation and GhMV voltage harmonic distortion limit (order h), available to
during contingencies [42]. For such requirements to be met, all users of a MV network
the design of the DG units themselves has to be revised (fast h harmonic order
action of pitch controllers, moderate over-speed allowance, pos- hr order of harmonic resonance
sibly incorporation of storage at the DC-link, installation of Ih current harmonic (order h)
SVCs at the generator terminals for conventional induction kf flicker step factor
generators, etc.). kr resonant amplification factor
At present, this discussion is relevant for large DG instal- kU voltage change factor
lations connected to the HV and MV level. In the case of LV LhHV , LhMV , LhLV voltage harmonic distortion planning level
installations, the functional requirements for the utility inter- (order h) in HV, MV and LV systems
face concentrate mostly on the islanding detection, which in MhMV , MhLV current harmonic emission limit (order h), in
general is the responsibility of the manufacturer to provide as A/MVA, for MV and LV installations
an integrated part of the equipment. The protection functions of N number of wind turbines in a wind farm
LV DG equipment may be heavily revised in the medium- or N10 maximum number of switching operations of a WT in
long-term, due to the increasing momentum of the “Microgrid” a 10 min interval
concept, i.e. the possibility for parts of LV networks with suffi- N120 maximum number of switching operations of a WT in
cient distributed generation to intentionally isolate and operate a 120 min interval
autonomously from the main grid [43–45]. PCC Point of common coupling
Pn rated active power of a DG unit or installation
8. Conclusions Plt long-term flicker index
Pst short-term flicker index
The paper includes a presentation of important technical Qc aggregate capacitance at the MV busbars of the
considerations for the interconnection of distributed gener- HV/MV substation
S.A. Papathanassiou / Electric Power Systems Research 77 (2007) 24–34 33

Qn rated reactive power of a DG unit or installation [13] IEC 61000-1-1, Part 1: General—Section 1: Application and Interpretation
r frequency of switching operations of Fundamental Definitions and Terms, 1992.
[14] European Norm EN 50160, Voltage Characteristics of Electricity Supplied
Rk resistive component of the network short-circuit
by Public Distribution Systems, CENELEC, 1999.
impedance at the PCC [15] N. Hatziargyriou, T. Karakatsanis, M. Papadopoulos, Probabilistic load
si ratio of the rated power Sn,i of installation i to the total flow in distribution systems containing dispersed wind power generation,
capacity St of similar installations IEEE Trans. Power Syst. 8 (February (1)) (1993).
Sk network short-circuit capacity at the PCC [16] N.G. Boulaxis, S.A. Papathanassiou, M.P. Papadopoulos, Wind turbine
effect on the voltage profile of distribution networks, Renewable Energy
SkS network short-circuit capacity at the MV busbars of the
25 (March (3)) (2002) 401–415.
HV/MV substation [17] IEC 868-0, Part 0: Evaluation of Flicker Severity, 1991.
Sn rated apparent power of a DG unit or installation [18] IEC 868, Flickermeter. Functional Design and Specifications, 1986
St total capacity of “disturbing” installations in the net- (Amendment No. 1, 1990).
work [19] IEC 61000-4-15, Part 4: Testing and Measurement Techniques—Section
15: Flickermeter-Functional and Design Specifications, 1997.
ThHM coefficient for the transfer of voltage harmonic distor-
[20] IEC 61000-3-3, Part 3: Limits—Section 3: Limitation of Voltage Fluctu-
tion (order h) from HV to MV level ations and Flicker in Low-Voltage Supply Systems for Equipment with
Uh voltage harmonic (order h) Rated Current ≤ 16 A, 1994.
Umin,k , Umax,k minimum and maximum steady-state voltage of [21] IEC 61000-3-5, Part 3: Limits—Section 5: Limitation of Voltage Fluctu-
node k ations and Flicker in Low-Voltage Power Supply Systems for Equipment
with Rated Current Greater than 16 A, 1994.
Un nominal voltage of the network
[22] IEC 61000-3-11, Part 3: Limits—Section 11: Limitation of Voltage
va annual average wind speed Changes, Voltage Fluctuations and Flicker in Low Voltage Supply Sys-
Xk inductive component of the network short-circuit tems for Equipment with Rated Current <75 A and Subject to Conditional
impedance at the PCC Connection, 2000.
Zk network short-circuit impedance at the PCC [23] IEC 61000-3-7, Part 3: Limits—Section 7: Assessment of Emission Lim-
its for Fluctuating Loads in MV and HV Power Systems—Basic EMC
Zh network harmonic impedance (order h)
Publication, 1996.
Zhr network harmonic impedance at resonance frequency [24] IEC 61400-21, Wind Turbine Generator Systems—Measurement and
(order hr ) Assessment of Power Quality Characteristics of Grid Connected Wind Tur-
ψk phase angle of the network short-circuit impedance at bines, 2001.
the PCC [25] N.A. Kasmas, S.A. Papathanassiou, Evaluation of the Voltage Change Fac-
tor kU for DG Equipped with Synchronous Generators, Electric Power Syst.
ε steady-state voltage change (%)
Res., in press.
εmax steady-state voltage change limit (%) [26] A. Larsson, Flicker emission of wind turbines during continuous operation,
IEEE Trans. Energy Convers. 17 (March (1)) (2002) 114–118.
References [27] A. Larsson, Flicker emission of wind turbines caused by switching
operations, IEEE Trans. Energy Convers. 17 (March (1)) (2002) 119–
[1] W. El-Khattam, M.M.A. Salama, Distributed generation technologies, def- 123.
initions and benefits, Electric Power Syst. Res. 71 (2004) 119–128. [28] T. Thiringer, T. Petru, S. Lundberg, Flicker contribution from wind turbine
[2] R.B. Alderfer, M.M. Eldridge, T.J. Starrs, Making Connections: Case Stud- installations, IEEE Trans. Energy Convers. 19 (March (1)) (2004) 157–163.
ies of Interconnection Barriers and their Impact on Distributed Power [29] S.A. Papathanassiou, F. Santjer, Power quality measurements in an
Projects, NREL Report SR-200-28053, July 2000. autonomous island grid with high wind penetration, IEEE Trans. Power
[3] CIGRE TF C6.04.01, Connection Criteria at the Distribution Network for Deliv. 21 (1) (2006) 218–224.
Distributed Generation, Draft Version, October 2005. [30] ANSI/IEEE Std. 519, Recommended Practice and Requirements for Har-
[4] IEEE Std. 1547, Standard for Interconnecting Distributed Resources with monic Control in Electric Power Systems, 1992.
Electric Power Systems, 2003. [31] IEC 61000-3-2, Part 3: Limits—Section 2: Limits for Harmonic Current
[5] IEEE Std. 929, Recommended Practice for Utility Interface of Photovoltaic Emissions (equipment input current ≤ 16 A per phase), 2000.
Systems, 2000. [32] IEC 61000-3-4, Part 3: Limits—Section 4: Limitation of Emission of Har-
[6] Recommendation for the Connection and Parallel Operation of Generating monic Currents in Low-Voltage Power Supply Systems for Equipment with
Facilities at the MV Network, VDEW, second ed., 1998 (in German). Rated Current Greater than 16 A, 1998.
[7] Recommendation for the Parallel Operation of Generating Facilities at the [33] IEC 61000-3-6, Part 3: Limits—Section 6: Assessment of Emission Limits
LV Network of Electric Utilities, VDEW, third ed., 1991 (revised 1996) (in for Distorting Loads in MV and HV Power Systems, 1996.
German). [34] IEC 61000-2-2, Part 2: Environment—Section 2: Compatibility Levels for
[8] Specifications for Connecting Wind Farms to the Transmission Network, Low-Frequency Conducted Disturbances and Signalling in Public Supply
ELTRA (Denmark), 2000 (available at http://www.eltra.dk). Systems, 1990.
[9] Technical Requirements for the Connection of Independent Generation to [35] S.A. Papathanassiou, M.P. Papadopoulos, Harmonic Analysis in a Power
the Grid, Public Power Corporation (PPC), Greece, 2004. System with Wind Generation, IEEE Trans. Power Deliv. (paper TPWRD-
[10] A. Woyte, R. Belmans, J. Nijs, Testing the islanding protection function of 00066-2005), in press.
photovoltaic inverters, IEEE Trans. Energy Convers. 18 (March (1)) (2003) [36] IEC 725, Considerations on Reference Impedances for Use in Determin-
157–162. ing the Disturbance Characteristics of Household Appliances and Similar
[11] W. Bower, M. Ropp, Evaluation of Islanding Detection Methods for Utility- Electrical Equipment, 1981.
Interactive Inverters in Photovoltaic Systems, Report SAND2002-3591, [37] IEEE PES Power System Relaying Committee, Intertie Protection of
Sandia National Laboratories, 2002. Consumer-Owned Sources of Generation, 3 MVA or less (available at
[12] Th. Boutsika, S. Papathanassiou, N. Drossos, Calculation of the fault level http://www.pes-psrc.org).
contribution of distributed generation according to IEC Standard 60909, [38] M.P. Papadopoulos, S.A. Papathanassiou, S.T. Tentzerakis, Operating
in: Proceedings of CIGRE Symposium Power Systems with Dispersed Problems in Wind-Diesel Power Systems with Extended MV Networks,
Generation, Athens, April 2005. Proceedings of EUWEC’96, Goteborg, Sweden, May 1996.
34 S.A. Papathanassiou / Electric Power Systems Research 77 (2007) 24–34

[39] S.A. Papathanassiou, M.P. Papadopoulos, Mechanical stresses in fixed [45] D. Georgakis, S. Papathanassiou, N. Hatziargyriou, A. Engler, C. Hardt,
speed wind turbines due to network disturbances, IEEE Trans. Energy Con- Operation of a Prototype Microgrid System Based on Micro-Sources
vers. 16 (December (4)) (2001) 361–367. Equipped with Fast-Acting Power Electronics Interfaces, Proceedings of
[40] E.ON Netz GmbH, Supplementary Grid Connection Regulations for Wind PESC’04, Aachen, Germany, June 2004.
Energy Converters, December 2001.
[41] F. Santjer, R. Klosse, New Supplementary Regulations for Grid Connection Stavros A. Papathanassiou was born in Thesprotiko, Greece. He received the
by E.ON Netz GmbH, DEWI Magazin Nr. 22, February 2003, pp. 28–34. diploma in electrical engineering from the National Technical University of
[42] J. Matevosyan, T. Ackermann, S. Bolik, L. Söder, Comparison of inter- Athens (NTUA), Greece, in 1991 and the Ph.D. degree in 1997 from the same
national regulations for connection of wind turbines to the network, in: University. He worked for the Distribution Division of the Public Power Cor-
Proceedings of Nordic Wind Power Conference NWPC’04, Göteborg, Swe- poration of Greece, where he was engaged in power quality and distributed
den, March 2004. generation studies, being responsible for the elaboration of DG interconnection
[43] MICROGRIDS—Large Scale Integration of Micro-Generation to Low guidelines. In 2002, he joined the Electric Power Division of NTUA as a lec-
Voltage Grids, EU Contract ENK5-CT-2002-00610, Technical Annex, May turer. His research mainly deals with DG technology and integration issues in
2002 (also at http://microgrids.power.ece.ntua.gr). distribution networks. He is a member of the IEEE, CIGRE and of the Technical
[44] Consortium for Electric Reliability Technology Solutions (CERTS), White Chamber of Greece.
Paper on Integration of Distributed Energy Resources—The CERTS Micro-
Grid Concept, 2002 (available at http://certs.lbl.gov/).

You might also like