1 - Electricity Connection Date Procedure
eS iets
No. Drea! ito) Cory Tita tL
1 Private Villa Without connection date
2 Agricultural Projects Without connection date
3 Commercial / Commercial Two Years |
Residential / Industrial / Local
Government / Federal Government
4 Residential Villas located in Two Years
commercial areas or real estate
developer area
ele
For the following categories:
Commercial / Commercial Residential / Private Residential / Agricultural /
Industrial / Local Government / Federal Government. The connection date
will be as following:
toe DY Tot at Cl) Connection Date
1 250 KVA transformer Three Years
2 500 KVA transformer Three Years
3 1,000 KVA transformer Three Years
4 1,500 KVA transformer Three Years
5 More than one 1,500 KVA transformer Four Years
6 Connection from suggested or under Four Years
construction Substation
7 High Voltage Substations (33KV/132KV) Without
connection date3 - Electricity Connection Date Alteration Procedure
1- Connection date alteration application must be filled along with an
explanatory letter from the owner
2- To apply for alteration, the building completion percentage must be more
than 50%
3- Payment of Study fees to confirm the possibility of altering the
connection or not (3,000 Dirhams non-refundable)
4- Once the possibility of connection date alteration is approved, an
electricity drawing approval application must be opened along with the
1 previous application receipt (original)
5- Payment of connection date alteration fees
1- Electricity Connection Date Alteration request + explanatory letter
approved by the owner
2- To accept the application, the building completion percentage must be
at least 50%
3-__ Incase of Alteration, a final application for the approval of electricity
Drawing shall be submitted along with the original payment receipt
4- Payment of the study fees for the Possibility of Alteration and delivery or
not (AED 3000) is not refundable
5- Alteration fees will be paid to issue a new date
6- Connection date will be issued for the projects when the application for
approving electricity Drawing is opened
Table no. 6
Fees in Dirhams as per Duration
CT ary ae 1 bras re Ty ea
a er Crs
110,000
30,000 50,000A dire (-)
Table no. 7
Fees in Dirhams as per Transformer Capacity & Duration
BCU
Oar rs
6Months 1Year 1Year& 2Year 2Year& 3 Year
OU CTT ty
250 KVA 20.000 | 40.000 | 80.000 |120.000| 160.000 | 200.000
500 KVA 30.000 | 60.000 | 120.000 |180.000| 240.000 | 300.000
1,000 KVA | 40.000 | 80.000 | 160.000 240.000| 320.000 | 400.000
1,500 KVA | 50.000 |100.000| 200.000 300.000) 400.000 | 500.000
alolrnja
The following to be considered:
1- If it exceeds 2 years, 20,000 Dirhams is added for each 6 months (for LV)
2- The previous fees are calculated per transformer (for HV)
3- If it exceeds 2 years, the fees of the first year is added for each 6 months
(for HV)
4 What is less than 6 months is considered complete 6 months
5- The fees above do not apply to transformers in Private Villas