PROJECT: PROJECT NAME SITE NO.: COMMISSIONING CHECK SHEET FOR CHILLED WATER PUMP. Sheet No. SUBCONTRACTOR: EQUIPMENT NO. SEQUENCE NO. SERIAL NO. : DATE LOCATION : COMMISSIONED ON ‘Checked ITEM POINTS TO BE CHECKED by REMARKS 1 Chilled water distribution network pressure tested and cleared. Makeup connection made. Dosing pot connected. ‘Strainers are cleaned. Drain connections to all equipment provided, Pressure gauges and flow switches are installed Tightness of electrical connections. ‘Supply voltage and motor rating. Free rotation of impeller. Pump and motor are clean Overload setting and fuse rating. Pump and motor alignment. Pumps are interfaced with BMS. 2 3 4 3 6 7 z 9 10 | MCC is clean. 11 12 13 14 15 Pumps are in manual made. THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND 10 COMPLY WITH CONTRACT SPECIFICATIONS. CHECKED BY SUBCONTRACTOR: Signature WITNESSED BY CLIENT: Signature WITNESSED / ACCEPTED BY CONSULTANT: Signature