ID % Task Task Name Duration Est. Start Est.

Finish Predecessors
Resource
Complete Mode Names
1
2 95% UTAP Data Cleaning Project 75.9 days Wed 12/06/19Thu 19/09/19
3 100% [0] Pre-Project 38 days Wed 12/06/19 Wed 31/07/19
4 100% Sign-Off: Contract 0 days Wed 12/06/19 Wed 12/06/19 IH,KPMC
5 100% Recruitment and Staffing: Phase 1 8 days Wed 12/06/19 Fri 21/06/19 4 KPMC
6 100% Recruitment and Staffing: Phase 2 27 days Tue 25/06/19 Wed 31/07/19 4 KPMC
7 100% Pre-Project Complete 0 days Fri 21/06/19 Fri 21/06/19 5
8 100% [1] Project Initiation 8.5 days Tue 25/06/19 Fri 05/07/19
9 100% Kick-Off Meeting 1 day Tue 25/06/19 Tue 25/06/19 4 IH,KPMC
10 100% Develop PID 2 days Wed 26/06/19 Thu 27/06/19 9 KPMC
11 100% Review of PID 16 hrs Wed 03/07/19 Thu 04/07/19 10 IH
12 100% Approve Sign-off PID 4 hrs Fri 05/07/19 Fri 05/07/19 11 IH
13 100% Workshop: Activity Planning 1 day Fri 28/06/19 Fri 28/06/19 4 IH,KPMC
14 100% Workshop: Data Cleaning Process Review 2 days Mon 01/07/19 Tue 02/07/19 13 IH,KPMC
15 100% Training: Team Leads 2 days Tue 02/07/19 Wed 03/07/19 14 KPMC
16 100% Project Initiation Complete 0 days Fri 05/07/19 Fri 05/07/19 12

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 1
ID % Task Task Name Duration Est. Start Est. Finish Predecessors
Resource
Complete Mode Names
17 95% [2] Delivery 56.2 days Fri 05/07/19 Tue 17/09/19
18 95% [2.1] Data Cleaning Execution (KPMC) 56.2 days Fri 05/07/19 Tue 17/09/19
19 96% [2.1.1] Phase 1 56.2 days Fri 05/07/19 Tue 17/09/19
20 97% Phase1: Team 1 (Hardap + Otjozondjupa) 56.2 days Fri 05/07/19 Tue 17/09/19
21 98% Hardap Region 55.8 days Fri 05/07/19 Mon 16/09/19
22 100% Training: Review Team 1 4 days Fri 05/07/19 Tue 09/07/19 KPMC
23 100% Rehoboth District 22 days Wed 10/07/19 Tue 06/08/19
24 100% Travel Rehoboth District 4 hrs Wed 10/07/19 Wed 10/07/19 22
25 100% Rehoboth District hospital 10.5 days Wed 10/07/19 Wed 24/07/19 24 TEAM 1
26 100% Rehoboth Health centre 1 day Thu 11/07/19 Thu 11/07/19 25 TEAM 1
27 100% Rehoboth Clinic 1 day Thu 11/07/19 Thu 11/07/19 26 TEAM 1
28 100% Rietoog Clinic 1 day Thu 25/07/19 Thu 25/07/19 25 TEAM 1
29 100% Schlip Clinic 1 day Thu 25/07/19 Thu 25/07/19 25 TEAM 1
30 100% M&E Control 1 day Mon 29/07/19 Mon 29/07/19 27,26,28,25TL1
31 100% Complete: Rehoboth District 8 days Mon 29/07/19 Tue 06/08/19 25,27,26,28,30
32 99% Mariental District 17 days Wed 07/08/19 Thu 29/08/19

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 2
ID % Task Task Name Duration Est. Start Est. Finish Predecessors
Resource
Complete Mode Names
33 100% Travel Mariental District 3 hrs Wed 07/08/19 Wed 07/08/19 31 TEAM 1
34 100% Mariental District Hospital 7.63 days Wed 07/08/19 Fri 16/08/19 33 TEAM 1
35 100% Stampriet Clinic 1 day Mon 12/08/19 Mon 12/08/19 TEAM 1
36 100% Gibeon Clinic 2 days Tue 13/08/19 Wed 14/08/19 35 TEAM 1
37 100% Hoachanas Clinic 1 day Mon 12/08/19 Mon 12/08/19 33 TEAM 1
38 100% Maltahohe Health Centre 1 day Thu 15/08/19 Thu 15/08/19 36 TEAM 1
39 100% Kalkrand Clinic 1 day Tue 27/08/19 Tue 27/08/19 38 TEAM 1
40 100% Mariental Clinic 1 day Fri 09/08/19 Fri 09/08/19 33 TEAM 1
41 90% M&E Control 2 days Wed 28/08/19 Thu 29/08/19 31,34,35,36,37,38,39,40
42 90% Complete: Mariental District 0 days Thu 29/08/19 Thu 29/08/19 41
43 90% Aranos District 6 days Mon 19/08/19 Tue 27/08/19
44 67% Travel Aranos District 3 hrs Mon 19/08/19 Mon 19/08/19 TEAM 1
45 100% Aranos Health Centre 2 days Thu 22/08/19 Mon 26/08/19 47 TEAM 1
46 100% Aranos Clinic 0.75 days Mon 19/08/19 Mon 19/08/19 44 TEAM 1
47 100% Gochas Clinic 1 day Wed 21/08/19 Wed 21/08/19 44 TEAM 1
48 60% M&E Control 1 day Tue 27/08/19 Tue 27/08/19 46,45,47 TEAM 1

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 3
ID % Task Task Name Duration Est. Start Est. Finish Predecessors
Resource
Complete Mode Names
49 60% Complete: Aranos 0 days Tue 27/08/19 Tue 27/08/19 48
50 60% Complete: Hardap Region 0 days Thu 29/08/19 Thu 29/08/19 49,42,31
51 94% Grootfontein District 11.8 days Sun 01/09/19 Mon 16/09/19
52 100% Travel Grootfontein District 1 day Sun 01/09/19 Sun 01/09/19 50
53 100% Grootfontein DH 7 days Mon 02/09/19 Tue 10/09/19 52 TEAM 1
54 100% Grootfontein Clinic 3 days Wed 11/09/19 Fri 13/09/19 53 TEAM 1
55 60% M&E Control 1 day Wed 11/09/19 Mon 16/09/19 54 TL1
56 0% Complete: Grootfontein District 0.4 days Wed 11/09/19 Mon 16/09/19 54,53,55
57 0% Complete: Phase1: Team 1 0.4 days Wed 11/09/19 Tue 17/09/19 50,56
58 96% Phase 1: Team 2 (Omusati) 25 days Sun 07/07/19 Tue 06/08/19
59 96% Oshikuku District 25 days Sun 07/07/19 Tue 06/08/19
60 100% Travel Oshikuku District 1 day Sun 07/07/19 Sun 07/07/19
61 100% Training: Review Team 2 3 days Mon 08/07/19 Wed 10/07/19
62 100% Okalongo 10 days Thu 11/07/19 Wed 24/07/19 61 TEAM 2A
63 100% Onheleiwa 2 days Thu 25/07/19 Fri 26/07/19 62 TEAM 2B
64 100% Onaanda 2 days Thu 25/07/19 Fri 26/07/19 62 TEAM 2B

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 4
ID % Task Task Name Duration Est. Start Est. Finish Predecessors
Resource
Complete Mode Names
65 100% Odimbwa 2 days Thu 25/07/19 Fri 26/07/19 62 TEAM 2A
66 100% Omutundungu 3 days Fri 26/07/19 Mon 29/07/19 64 TEAM 2B
67 100% Epoko 2 days Mon 29/07/19 Tue 30/07/19 65 TEAM 2A
68 100% Okando 1 day Mon 29/07/19 Mon 29/07/19 65 TEAM 2C
69 100% Sheetekela 2 days Tue 30/07/19 Wed 31/07/19 64 TEAM 2B
70 100% Elim 1 day Thu 01/08/19 Thu 01/08/19 69 TEAM 2A
71 100% Lipandayamiti 1 day Wed 31/07/19 Wed 31/07/19 67 TEAM 2A
72 100% Ogongo 1 day Fri 02/08/19 Fri 02/08/19 68 TEAM 2C
73 100% Okathitu 1 day Thu 01/08/19 Thu 01/08/19 69 TEAM 2B
74 100% Olupandu 1 day Wed 31/07/19 Wed 31/07/19 67 TEAM 2A
75 100% Olutsiidhi 1 day Thu 01/08/19 Thu 01/08/19 74 TEAM 2A
76 100% Omagalanga 1 day Mon 29/07/19 Mon 29/07/19 68 TEAM 2B
77 100% Omuthitugwonyama 1 day Fri 02/08/19 Fri 02/08/19 72 TEAM 2C
78 100% Onkani 1 day Thu 01/08/19 Fri 02/08/19 75 TEAM 2A
79 100% Othika 1 day Thu 01/08/19 Thu 01/08/19 76 TEAM 2B
80 100% St. Benedict/Oshitumuma 8 hrs Fri 02/08/19 Fri 02/08/19 78 TEAM 2B

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 5
ID % Task Task Name Duration Est. Start Est. Finish Predecessors
Resource
Complete Mode Names
81 20% M&E Control 2 days Mon 05/08/19 Tue 06/08/19 80 TL2
82 20% Complete: Oshikuku District 0 days Tue 06/08/19 Tue 06/08/19 80,70,67,71,65,72,62,68,73,74,75,76,77,66,
83 93% Phase 1: Team 3 (Ohangwena) 27 days Sun 07/07/19 Thu 08/08/19
84 93% Odibo District 27 days Sun 07/07/19 Thu 08/08/19
85 100% Travel Odibo District 1 day Sun 07/07/19 Sun 07/07/19
86 100% Training: Review Team 3 3 days Mon 08/07/19 Wed 10/07/19 KPMC
87 100% Odibo HC 11 days Thu 11/07/19 Thu 25/07/19 86 TEAM 3A
88 100% Edundja 2 days Thu 25/07/19 Fri 26/07/19 87 TEAM 3B
89 100% Hamukoto 1.5 days Wed 24/07/19 Sat 27/07/19 87 TEAM 3C
90 100% Ohangwena 3 days Fri 26/07/19 Mon 29/07/19 87 TEAM 3A
91 100% Okatope 3 days Mon 29/07/19 Wed 31/07/19 88 TEAM 3B
92 100% Ohaukelo 2 days Thu 01/08/19 Fri 02/08/19 89 TEAM 3C
93 100% Onamukulo 3 days Fri 02/08/19 Mon 05/08/19 90 TEAM 3A
94 100% Ondobe 2 days Tue 30/07/19 Sat 03/08/19 91 TEAM 3B
95 20% M&E Control 3 days Tue 06/08/19 Thu 08/08/19 94,88,89,87,90,92,91,93
TL3
96 20% Complete: Odibo District 0 days Thu 08/08/19 Thu 08/08/19 92,86,88,89,87,90,91,93,94,95

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 6
ID % Task Task Name Duration Est. Start Est. Finish Predecessors
Resource
Complete Mode Names
97 93% [2.1.2] Phase 2 19 days Sun 04/08/19 Wed 28/08/19
98 94% Phase 2: Team 4 (Nyangana) 14 days Sun 04/08/19 Tue 20/08/19
99 94% Kavango East (Nyangana District) 14 days Sun 04/08/19 Tue 20/08/19
100 100% Travel to Nyangana and within District 1 day Sun 04/08/19 Sun 04/08/19 80 TL2
101 100% Training: Review Team 4 2 days Mon 05/08/19 Tue 06/08/19 100 KPMC
102 100% Nyangana DH 7 days Wed 07/08/19 Thu 15/08/19 101 TEAM 4
103 100% Kapupahedi 2 days Tue 13/08/19 Wed 14/08/19 101 TEAM 5A
104 100% Karukuta 1 day Tue 13/08/19 Tue 13/08/19 101 TEAM 5A
105 100% Katere 2 days Fri 09/08/19 Mon 12/08/19 101 TEAM 5A
106 100% Mabushe 1 day Mon 12/08/19 Tue 13/08/19 105 TEAM 5A
107 100% Mbambi 3 days Wed 07/08/19 Fri 09/08/19 101 TEAM 5A
108 100% Ndonga 2 days Wed 14/08/19 Thu 15/08/19 104 TEAM 5A
109 100% Shinyungwe 2 days Thu 08/08/19 Fri 09/08/19 101 TEAM 5A
110 100% Kandjara 2 days Wed 14/08/19 Thu 15/08/19 109 TEAM 5A
111 20% M&E Control 2 days Mon 19/08/19 Tue 20/08/19 102,103,104,105,106,107,108,109,110,101
TL2,TL3
112 20% Complete: Kavango West (Nyangana) 0 days Tue 20/08/19 Tue 20/08/19 110,101,103,104,105,106,107,108,102,109,

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 7
ID % Task Task Name Duration Est. Start Est. Finish Predecessors
Resource
Complete Mode Names
113 91% Phase 2: Team 5 (Andara) 9 days Fri 16/08/19 Wed 28/08/19
114 91% Kavango East (Andara District) 9 days Fri 16/08/19 Wed 28/08/19
115 100% Travel Andara District 1 day Fri 16/08/19 Fri 16/08/19 102
116 100% Andara Hospital 5 days Mon 19/08/19 Fri 23/08/19 115 TEAM 4
117 100% Divundu 2 days Tue 20/08/19 Wed 21/08/19 115 TEAM 5
118 100% Kangongo 1 day Mon 19/08/19 Mon 19/08/19 117 TEAM 5
119 100% Mayara 1 day Tue 20/08/19 Tue 20/08/19 118 TEAM 5
120 100% Mutjiku 1 day Thu 22/08/19 Thu 22/08/19 119 TEAM 5
121 100% Old bagani 2 days Wed 21/08/19 Thu 22/08/19 119 TEAM 5
122 100% Omega 1 day Thu 22/08/19 Thu 22/08/19 119 TEAM 5
123 100% Shandikongoro 1 day Mon 19/08/19 Mon 19/08/19 115 TEAM 5
124 20% M&E Control 2 days Tue 27/08/19 Wed 28/08/19 116,117,118,119,120,121,122,123
TL3,TL2
125 20% Complete: Kavango West (Andara) 0 days Wed 28/08/19 Wed 28/08/19 124
126 100% [2.2] Data Migration (IHN) 9 days Fri 19/07/19 Tue 30/07/19
127 100% Phase 1 Rollout: Rehoboth District 9 days Fri 19/07/19 Tue 30/07/19
128 100% Travel to Rehoboth Dsitrict 8 hrs Fri 19/07/19 Fri 19/07/19 27 IH TEAM2

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 8
ID % Task Task Name Duration Est. Start Est. Finish Predecessors
Resource
Complete Mode Names
129 100% Quantum Upgrade to v 14: Rehoboth Clinic 8 hrs Fri 19/07/19 Fri 19/07/19 27 IH TEAM2
130 100% Quantum Upgrade to v 14: Rehoboth HC 8 hrs Fri 19/07/19 Fri 19/07/19 27 IH TEAM2
131 100% Quantum Upgrade to v 14: Rehoboth District Hospital 0 hrs Fri 19/07/19 Fri 19/07/19 25 IH TEAM2
132 100% Quantum Upgrade to v 14: Rietoog Clinic 1 day Tue 30/07/19 Tue 30/07/19 28 IH TEAM2
133 100% Quantum Upgrade to v 14: Schlip Clinic 1 day Mon 29/07/19 Mon 29/07/19 29 IH TEAM2
134 100% Complete: Upgrade Rehoboth District 1 day Tue 30/07/19 Tue 30/07/19 129,130,131,132,133
135 30% [3] Project Closure 5.9 days Thu 12/09/19 Thu 19/09/19
136 30% [3.1] Data Cleaning 5.9 days Thu 12/09/19 Thu 19/09/19
137 30% Handover: Final Project Documentation 5 days Thu 12/09/19 Thu 19/09/19 30,41,48,55,81,95,111,124
KPMC
138 0% Project Closure Accpeted 0 days Thu 19/09/19 Thu 19/09/19 137 IH

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 9
Actual Start Actual Finish Baseline Start Baseline
Tue Finish
11/06 Wed 12/06 Thu 13/06 Fri 14/06 Sat 15/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Wed 12/06/19 NA Wed 12/06/19


Mon 16/09/19
Wed 12/06/19 Wed 31/07/19 Wed 12/06/19Wed 31/07/19
Wed 12/06/19 Wed 12/06/19 Wed 12/06/19 Wed 12/06/19 12/06
Wed 12/06/19 Fri 21/06/19 Wed 12/06/19 Fri 21/06/19 K
Tue 25/06/19 Wed 31/07/19 Tue 25/06/19 Wed 31/07/19
Fri 21/06/19 Fri 21/06/19 Fri 21/06/19 Fri 21/06/19
Tue 25/06/19 Fri 05/07/19 Tue 25/06/19 Thu 04/07/19
Tue 25/06/19 Tue 25/06/19 Tue 25/06/19 Tue 25/06/19
Wed 26/06/19 Thu 27/06/19 Wed 26/06/19 Thu 27/06/19
Wed 03/07/19 Thu 04/07/19 Fri 28/06/19 Fri 28/06/19
Fri 05/07/19 Fri 05/07/19 Fri 28/06/19 Fri 28/06/19
Fri 28/06/19 Fri 28/06/19 Fri 28/06/19 Fri 28/06/19
Mon 01/07/19 Tue 02/07/19 Mon 01/07/19 Mon 01/07/19
Tue 02/07/19 Wed 03/07/19 Tue 02/07/19 Thu 04/07/19
Fri 05/07/19 Fri 05/07/19 Fri 28/06/19 Fri 28/06/19

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 10
Actual Start Actual Finish Baseline Start Baseline
Tue Finish
11/06 Wed 12/06 Thu 13/06 Fri 14/06 Sat 15/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
Fri 05/07/19 NA Fri 05/07/19 Mon 16/09/19
Fri 05/07/19 NA Fri 05/07/19 Mon 02/09/19
Fri 05/07/19 NA Fri 05/07/19 Tue 27/08/19
Fri 05/07/19 NA Fri 05/07/19 Tue 27/08/19
Fri 05/07/19 NA Fri 05/07/19 Tue 27/08/19
Fri 05/07/19 Tue 09/07/19 Fri 05/07/19 Tue 09/07/19
Wed 10/07/19 Tue 06/08/19 Wed 10/07/19Wed 24/07/19
Wed 10/07/19 Wed 10/07/19 Wed 10/07/19 Wed 10/07/19
Wed 10/07/19 Wed 24/07/19 Tue 16/07/19 Tue 23/07/19
Thu 11/07/19 Thu 11/07/19 Wed 10/07/19 Fri 12/07/19
Thu 11/07/19 Thu 11/07/19 Wed 10/07/19 Wed 10/07/19
Thu 25/07/19 Thu 25/07/19 Mon 15/07/19 Tue 16/07/19
Thu 25/07/19 Thu 25/07/19 Thu 25/07/19 Thu 25/07/19
Mon 29/07/19 Mon 29/07/19 Tue 23/07/19 Wed 24/07/19
Mon 29/07/19 Tue 06/08/19 Wed 24/07/19 Wed 24/07/19
Wed 07/08/19 NA Wed 24/07/19Mon 05/08/19

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 11
Actual Start Actual Finish Baseline Start Baseline
Tue Finish
11/06 Wed 12/06 Thu 13/06 Fri 14/06 Sat 15/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
Wed 07/08/19 Wed 07/08/19 Wed 24/07/19 Wed 24/07/19
Wed 07/08/19 Fri 16/08/19 Wed 24/07/19 Mon 29/07/19
Mon 12/08/19 Mon 12/08/19 Mon 29/07/19 Mon 29/07/19
Tue 13/08/19 Wed 14/08/19 Mon 29/07/19 Tue 30/07/19
Mon 12/08/19 Mon 12/08/19 Tue 30/07/19 Wed 31/07/19
Thu 15/08/19 Thu 15/08/19 Wed 31/07/19 Thu 01/08/19
Tue 27/08/19 Tue 27/08/19 Thu 01/08/19 Fri 02/08/19
Fri 09/08/19 Fri 09/08/19 Fri 02/08/19 Sun 04/08/19
Wed 28/08/19 NA Sun 04/08/19 Mon 05/08/19
Thu 29/08/19 NA Mon 05/08/19 Mon 05/08/19
Mon 19/08/19 NA Mon 05/08/19Fri 09/08/19
Mon 19/08/19 NA Mon 05/08/19 Mon 05/08/19
Thu 22/08/19 Mon 26/08/19 Mon 05/08/19 Thu 08/08/19
Mon 19/08/19 Mon 19/08/19 Mon 05/08/19 Mon 05/08/19
Wed 21/08/19 Wed 21/08/19 Thu 08/08/19 Fri 09/08/19
Tue 27/08/19 NA Thu 08/08/19 Fri 09/08/19

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 12
Actual Start Actual Finish Baseline Start Baseline
Tue Finish
11/06 Wed 12/06 Thu 13/06 Fri 14/06 Sat 15/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
Tue 27/08/19 NA Fri 09/08/19 Fri 09/08/19
Thu 29/08/19 NA Fri 09/08/19 Fri 09/08/19
Sun 01/09/19 NA Thu 15/08/19 Tue 27/08/19
Sun 01/09/19 Sun 01/09/19 Thu 15/08/19 Thu 15/08/19
Mon 02/09/19 Tue 10/09/19 Fri 16/08/19 Thu 22/08/19
Wed 11/09/19 Fri 13/09/19 Fri 23/08/19 Fri 23/08/19
Wed 11/09/19 NA Tue 27/08/19 Tue 27/08/19
Wed 11/09/19 NA Tue 27/08/19 Tue 27/08/19
Wed 11/09/19 NA Tue 27/08/19 Tue 27/08/19
Sun 07/07/19 NA Mon 08/07/19Wed 31/07/19
Sun 07/07/19 NA Mon 08/07/19Wed 31/07/19
Sun 07/07/19 Sun 07/07/19 Mon 08/07/19 Mon 08/07/19
Mon 08/07/19 Wed 10/07/19 Mon 08/07/19 Wed 10/07/19
Thu 11/07/19 Wed 24/07/19 Thu 18/07/19 Thu 25/07/19
Thu 25/07/19 Fri 26/07/19 Thu 18/07/19 Thu 18/07/19
Thu 25/07/19 Fri 26/07/19 Tue 16/07/19 Wed 17/07/19

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 13
Actual Start Actual Finish Baseline Start Baseline
Tue Finish
11/06 Wed 12/06 Thu 13/06 Fri 14/06 Sat 15/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
Thu 25/07/19 Fri 26/07/19 Tue 16/07/19 Tue 16/07/19
Fri 26/07/19 Mon 29/07/19 Mon 15/07/19 Mon 15/07/19
Mon 29/07/19 Tue 30/07/19 Fri 12/07/19 Fri 12/07/19
Mon 29/07/19 Mon 29/07/19 Fri 26/07/19 Fri 26/07/19
Tue 30/07/19 Wed 31/07/19 Tue 23/07/19 Tue 23/07/19
Thu 01/08/19 Thu 01/08/19 Thu 11/07/19 Thu 11/07/19
Wed 31/07/19 Wed 31/07/19 Mon 15/07/19 Mon 15/07/19
Fri 02/08/19 Fri 02/08/19 Wed 17/07/19 Wed 17/07/19
Thu 01/08/19 Thu 01/08/19 Mon 29/07/19 Mon 29/07/19
Wed 31/07/19 Wed 31/07/19 Tue 30/07/19 Tue 30/07/19
Thu 01/08/19 Thu 01/08/19 Wed 31/07/19 Wed 31/07/19
Mon 29/07/19 Mon 29/07/19 Thu 11/07/19 Thu 11/07/19
Fri 02/08/19 Fri 02/08/19 Fri 12/07/19 Fri 12/07/19
Thu 01/08/19 Fri 02/08/19 Fri 19/07/19 Fri 19/07/19
Thu 01/08/19 Thu 01/08/19 Mon 22/07/19 Mon 22/07/19
Fri 02/08/19 Fri 02/08/19 Wed 24/07/19 Thu 25/07/19

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 14
Actual Start Actual Finish Baseline Start Baseline
Tue Finish
11/06 Wed 12/06 Thu 13/06 Fri 14/06 Sat 15/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
Mon 05/08/19 NA Fri 26/07/19 Tue 30/07/19
Tue 06/08/19 NA Wed 31/07/19 Wed 31/07/19
Sun 07/07/19 NA Mon 08/07/19Mon 29/07/19
Sun 07/07/19 NA Mon 08/07/19Mon 29/07/19
Sun 07/07/19 Sun 07/07/19 Mon 08/07/19 Mon 08/07/19
Mon 08/07/19 Wed 10/07/19 Mon 08/07/19 Wed 10/07/19
Thu 11/07/19 Thu 25/07/19 Fri 12/07/19 Fri 19/07/19
Thu 25/07/19 Fri 26/07/19 Thu 11/07/19 Thu 11/07/19
Wed 24/07/19 Sat 27/07/19 Thu 11/07/19 Thu 11/07/19
Fri 26/07/19 Mon 29/07/19 Mon 22/07/19 Mon 22/07/19
Mon 29/07/19 Wed 31/07/19 Tue 23/07/19 Tue 23/07/19
Thu 01/08/19 Fri 02/08/19 Mon 22/07/19 Mon 22/07/19
Fri 02/08/19 Mon 05/08/19 Wed 24/07/19 Wed 24/07/19
Tue 30/07/19 Sat 03/08/19 Thu 25/07/19 Fri 26/07/19
Tue 06/08/19 NA Fri 26/07/19 Mon 29/07/19
Thu 08/08/19 NA Fri 26/07/19 Fri 26/07/19

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 15
Actual Start Actual Finish Baseline Start Baseline
Tue Finish
11/06 Wed 12/06 Thu 13/06 Fri 14/06 Sat 15/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
Sun 04/08/19 NA Mon 29/07/19Mon 02/09/19
Sun 04/08/19 NA Sun 04/08/19 Thu 22/08/19
Sun 04/08/19 NA Sun 04/08/19 Thu 22/08/19
Sun 04/08/19 Sun 04/08/19 Sun 04/08/19 Sun 04/08/19
Mon 05/08/19 Tue 06/08/19 Mon 05/08/19 Wed 07/08/19
Wed 07/08/19 Thu 15/08/19 Thu 08/08/19 Fri 16/08/19
Tue 13/08/19 Wed 14/08/19 Sun 18/08/19 Sun 18/08/19
Tue 13/08/19 Tue 13/08/19 Sun 18/08/19 Sun 18/08/19
Fri 09/08/19 Mon 12/08/19 Mon 19/08/19 Mon 19/08/19
Mon 12/08/19 Tue 13/08/19 Mon 19/08/19 Mon 19/08/19
Wed 07/08/19 Fri 09/08/19 Tue 20/08/19 Tue 20/08/19
Wed 14/08/19 Thu 15/08/19 Tue 20/08/19 Tue 20/08/19
Thu 08/08/19 Fri 09/08/19 Wed 21/08/19 Wed 21/08/19
Wed 14/08/19 Thu 15/08/19 Wed 21/08/19 Wed 21/08/19
Mon 19/08/19 NA Thu 22/08/19 Thu 22/08/19
Tue 20/08/19 NA Thu 22/08/19 Thu 22/08/19

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 16
Actual Start Actual Finish Baseline Start Baseline
Tue Finish
11/06 Wed 12/06 Thu 13/06 Fri 14/06 Sat 15/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
Fri 16/08/19 NA Mon 29/07/19Fri 16/08/19
Fri 16/08/19 NA Mon 29/07/19Fri 16/08/19
Fri 16/08/19 Fri 16/08/19 Mon 29/07/19 Mon 29/07/19
Mon 19/08/19 Fri 23/08/19 Fri 02/08/19 Fri 09/08/19
Tue 20/08/19 Wed 21/08/19 Mon 12/08/19 Mon 12/08/19
Mon 19/08/19 Mon 19/08/19 Tue 13/08/19 Tue 13/08/19
Tue 20/08/19 Tue 20/08/19 Tue 13/08/19 Tue 13/08/19
Thu 22/08/19 Thu 22/08/19 Wed 14/08/19 Wed 14/08/19
Wed 21/08/19 Thu 22/08/19 Wed 14/08/19 Wed 14/08/19
Thu 22/08/19 Thu 22/08/19 Thu 15/08/19 Thu 15/08/19
Mon 19/08/19 Mon 19/08/19 Thu 15/08/19 Thu 15/08/19
Tue 27/08/19 NA Fri 16/08/19 Fri 16/08/19
Wed 28/08/19 NA Fri 16/08/19 Fri 16/08/19
Fri 19/07/19 Tue 30/07/19 Thu 01/08/19 Mon 16/09/19
Fri 19/07/19 Tue 30/07/19 Fri 19/07/19 Fri 26/07/19
Fri 19/07/19 Fri 19/07/19 Fri 12/07/19 Fri 12/07/19

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 17
Actual Start Actual Finish Baseline Start Baseline
Tue Finish
11/06 Wed 12/06 Thu 13/06 Fri 14/06 Sat 15/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
Fri 19/07/19 Fri 19/07/19 Fri 12/07/19 Fri 12/07/19
Fri 19/07/19 Fri 19/07/19 Fri 12/07/19 Fri 12/07/19
Fri 19/07/19 Fri 19/07/19 Wed 24/07/19 Wed 24/07/19
Tue 30/07/19 Tue 30/07/19 Thu 25/07/19 Fri 26/07/19
Mon 29/07/19 Mon 29/07/19 Thu 25/07/19 Thu 25/07/19
Tue 30/07/19 Tue 30/07/19 NA NA
Thu 12/09/19 NA Tue 03/09/19 Mon 09/09/19
Thu 12/09/19 NA Tue 03/09/19 Mon 09/09/19
Thu 12/09/19 NA Tue 03/09/19 Mon 09/09/19
NA NA Mon 09/09/19 Mon 09/09/19

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 18
Sun 16/06 Mon 17/06 Tue 18/06 Wed 19/06 Thu 20/06 Fri 21/06 Sat 22/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

KPMC
K
21/06

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 19
Sun 16/06 Mon 17/06 Tue 18/06 Wed 19/06 Thu 20/06 Fri 21/06 Sat 22/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 20
Sun 16/06 Mon 17/06 Tue 18/06 Wed 19/06 Thu 20/06 Fri 21/06 Sat 22/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 21
Sun 16/06 Mon 17/06 Tue 18/06 Wed 19/06 Thu 20/06 Fri 21/06 Sat 22/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 22
Sun 16/06 Mon 17/06 Tue 18/06 Wed 19/06 Thu 20/06 Fri 21/06 Sat 22/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 23
Sun 16/06 Mon 17/06 Tue 18/06 Wed 19/06 Thu 20/06 Fri 21/06 Sat 22/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 24
Sun 16/06 Mon 17/06 Tue 18/06 Wed 19/06 Thu 20/06 Fri 21/06 Sat 22/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 25
Sun 16/06 Mon 17/06 Tue 18/06 Wed 19/06 Thu 20/06 Fri 21/06 Sat 22/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 26
Sun 16/06 Mon 17/06 Tue 18/06 Wed 19/06 Thu 20/06 Fri 21/06 Sat 22/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 27
Sun 23/06 Mon 24/06 Tue 25/06 Wed 26/06 Thu 27/06 Fri 28/06 Sat 29/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

IH,KPMC
KPMC

IH,KPMC

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 28
Sun 23/06 Mon 24/06 Tue 25/06 Wed 26/06 Thu 27/06 Fri 28/06 Sat 29/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 29
Sun 23/06 Mon 24/06 Tue 25/06 Wed 26/06 Thu 27/06 Fri 28/06 Sat 29/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 30
Sun 23/06 Mon 24/06 Tue 25/06 Wed 26/06 Thu 27/06 Fri 28/06 Sat 29/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 31
Sun 23/06 Mon 24/06 Tue 25/06 Wed 26/06 Thu 27/06 Fri 28/06 Sat 29/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 32
Sun 23/06 Mon 24/06 Tue 25/06 Wed 26/06 Thu 27/06 Fri 28/06 Sat 29/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 33
Sun 23/06 Mon 24/06 Tue 25/06 Wed 26/06 Thu 27/06 Fri 28/06 Sat 29/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 34
Sun 23/06 Mon 24/06 Tue 25/06 Wed 26/06 Thu 27/06 Fri 28/06 Sat 29/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 35
Sun 23/06 Mon 24/06 Tue 25/06 Wed 26/06 Thu 27/06 Fri 28/06 Sat 29/06
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 36
Sun 30/06 Mon 01/07 Tue 02/07 Wed 03/07 Thu 04/07 Fri 05/07 Sat 06/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

IH
IH

IH,KPMC
KPMC
05/07

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 37
Sun 30/06 Mon 01/07 Tue 02/07 Wed 03/07 Thu 04/07 Fri 05/07 Sat 06/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 38
Sun 30/06 Mon 01/07 Tue 02/07 Wed 03/07 Thu 04/07 Fri 05/07 Sat 06/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 39
Sun 30/06 Mon 01/07 Tue 02/07 Wed 03/07 Thu 04/07 Fri 05/07 Sat 06/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 40
Sun 30/06 Mon 01/07 Tue 02/07 Wed 03/07 Thu 04/07 Fri 05/07 Sat 06/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 41
Sun 30/06 Mon 01/07 Tue 02/07 Wed 03/07 Thu 04/07 Fri 05/07 Sat 06/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 42
Sun 30/06 Mon 01/07 Tue 02/07 Wed 03/07 Thu 04/07 Fri 05/07 Sat 06/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 43
Sun 30/06 Mon 01/07 Tue 02/07 Wed 03/07 Thu 04/07 Fri 05/07 Sat 06/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 44
Sun 30/06 Mon 01/07 Tue 02/07 Wed 03/07 Thu 04/07 Fri 05/07 Sat 06/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 45
Sun 07/07 Mon 08/07 Tue 09/07 Wed 10/07 Thu 11/07 Fri 12/07 Sat 13/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 46
Sun 07/07 Mon 08/07 Tue 09/07 Wed 10/07 Thu 11/07 Fri 12/07 Sat 13/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

KPMC

T
TEAM 1
TEAM 1

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 47
Sun 07/07 Mon 08/07 Tue 09/07 Wed 10/07 Thu 11/07 Fri 12/07 Sat 13/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 48
Sun 07/07 Mon 08/07 Tue 09/07 Wed 10/07 Thu 11/07 Fri 12/07 Sat 13/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 49
Sun 07/07 Mon 08/07 Tue 09/07 Wed 10/07 Thu 11/07 Fri 12/07 Sat 13/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 50
Sun 07/07 Mon 08/07 Tue 09/07 Wed 10/07 Thu 11/07 Fri 12/07 Sat 13/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

KPMC
T

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 51
Sun 07/07 Mon 08/07 Tue 09/07 Wed 10/07 Thu 11/07 Fri 12/07 Sat 13/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 52
Sun 07/07 Mon 08/07 Tue 09/07 Wed 10/07 Thu 11/07 Fri 12/07 Sat 13/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 53
Sun 07/07 Mon 08/07 Tue 09/07 Wed 10/07 Thu 11/07 Fri 12/07 Sat 13/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 54
Sun 14/07 Mon 15/07 Tue 16/07 Wed 17/07 Thu 18/07 Fri 19/07 Sat 20/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 55
Sun 14/07 Mon 15/07 Tue 16/07 Wed 17/07 Thu 18/07 Fri 19/07 Sat 20/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 56
Sun 14/07 Mon 15/07 Tue 16/07 Wed 17/07 Thu 18/07 Fri 19/07 Sat 20/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 57
Sun 14/07 Mon 15/07 Tue 16/07 Wed 17/07 Thu 18/07 Fri 19/07 Sat 20/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 58
Sun 14/07 Mon 15/07 Tue 16/07 Wed 17/07 Thu 18/07 Fri 19/07 Sat 20/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 59
Sun 14/07 Mon 15/07 Tue 16/07 Wed 17/07 Thu 18/07 Fri 19/07 Sat 20/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 60
Sun 14/07 Mon 15/07 Tue 16/07 Wed 17/07 Thu 18/07 Fri 19/07 Sat 20/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 61
Sun 14/07 Mon 15/07 Tue 16/07 Wed 17/07 Thu 18/07 Fri 19/07 Sat 20/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

IH TEAM2

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 62
Sun 14/07 Mon 15/07 Tue 16/07 Wed 17/07 Thu 18/07 Fri 19/07 Sat 20/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
IH TEAM2
IH TEAM2
19/07

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 63
Sun 21/07 Mon 22/07 Tue 23/07 Wed 24/07 Thu 25/07 Fri 26/07 Sat 27/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 64
Sun 21/07 Mon 22/07 Tue 23/07 Wed 24/07 Thu 25/07 Fri 26/07 Sat 27/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TEAM 1

TEAM 1
TEAM 1

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 65
Sun 21/07 Mon 22/07 Tue 23/07 Wed 24/07 Thu 25/07 Fri 26/07 Sat 27/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 66
Sun 21/07 Mon 22/07 Tue 23/07 Wed 24/07 Thu 25/07 Fri 26/07 Sat 27/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TEAM 2A
TEAM 2B
TEAM 2B

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 67
Sun 21/07 Mon 22/07 Tue 23/07 Wed 24/07 Thu 25/07 Fri 26/07 Sat 27/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
TEAM 2A

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 68
Sun 21/07 Mon 22/07 Tue 23/07 Wed 24/07 Thu 25/07 Fri 26/07 Sat 27/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TEAM 3A
TEAM 3B
TEAM

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 69
Sun 21/07 Mon 22/07 Tue 23/07 Wed 24/07 Thu 25/07 Fri 26/07 Sat 27/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 70
Sun 21/07 Mon 22/07 Tue 23/07 Wed 24/07 Thu 25/07 Fri 26/07 Sat 27/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 71
Sun 21/07 Mon 22/07 Tue 23/07 Wed 24/07 Thu 25/07 Fri 26/07 Sat 27/07
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 72
Sun 28/07 Mon 29/07 Tue 30/07 Wed 31/07 Thu 01/08 Fri 02/08 Sat 03/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

KPMC

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 73
Sun 28/07 Mon 29/07 Tue 30/07 Wed 31/07 Thu 01/08 Fri 02/08 Sat 03/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TL1

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 74
Sun 28/07 Mon 29/07 Tue 30/07 Wed 31/07 Thu 01/08 Fri 02/08 Sat 03/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 75
Sun 28/07 Mon 29/07 Tue 30/07 Wed 31/07 Thu 01/08 Fri 02/08 Sat 03/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 76
Sun 28/07 Mon 29/07 Tue 30/07 Wed 31/07 Thu 01/08 Fri 02/08 Sat 03/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TEAM 2B
TEAM 2A
TEAM 2C
TEAM 2B
TEAM 2A
TEAM 2A
TEAM 2C
TEAM 2B
TEAM 2A
TEAM 2A
TEAM 2B
TEAM 2C
TEAM 2A
TEAM 2B
TEAM 2B

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 77
Sun 28/07 Mon 29/07 Tue 30/07 Wed 31/07 Thu 01/08 Fri 02/08 Sat 03/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TEAM 3C
TEAM 3A
TEAM 3B
TEAM 3C

TEAM

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 78
Sun 28/07 Mon 29/07 Tue 30/07 Wed 31/07 Thu 01/08 Fri 02/08 Sat 03/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 79
Sun 28/07 Mon 29/07 Tue 30/07 Wed 31/07 Thu 01/08 Fri 02/08 Sat 03/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 80
Sun 28/07 Mon 29/07 Tue 30/07 Wed 31/07 Thu 01/08 Fri 02/08 Sat 03/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

IH TEAM2
IH TEAM2

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 81
Sun 04/08 Mon 05/08 Tue 06/08 Wed 07/08 Thu 08/08 Fri 09/08 Sat 10/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 82
Sun 04/08 Mon 05/08 Tue 06/08 Wed 07/08 Thu 08/08 Fri 09/08 Sat 10/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 83
Sun 04/08 Mon 05/08 Tue 06/08 Wed 07/08 Thu 08/08 Fri 09/08 Sat 10/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
TEAM 1

TEAM 1

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 84
Sun 04/08 Mon 05/08 Tue 06/08 Wed 07/08 Thu 08/08 Fri 09/08 Sat 10/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 85
Sun 04/08 Mon 05/08 Tue 06/08 Wed 07/08 Thu 08/08 Fri 09/08 Sat 10/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 86
Sun 04/08 Mon 05/08 Tue 06/08 Wed 07/08 Thu 08/08 Fri 09/08 Sat 10/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
TL2
06/08

TEAM 3A
TEAM 3B
TL3
08/08

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 87
Sun 04/08 Mon 05/08 Tue 06/08 Wed 07/08 Thu 08/08 Fri 09/08 Sat 10/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TL2
KPMC

TEAM 5A

TEAM 5A

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 88
Sun 04/08 Mon 05/08 Tue 06/08 Wed 07/08 Thu 08/08 Fri 09/08 Sat 10/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 89
Sun 04/08 Mon 05/08 Tue 06/08 Wed 07/08 Thu 08/08 Fri 09/08 Sat 10/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 90
Sun 11/08 Mon 12/08 Tue 13/08 Wed 14/08 Thu 15/08 Fri 16/08 Sat 17/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 91
Sun 11/08 Mon 12/08 Tue 13/08 Wed 14/08 Thu 15/08 Fri 16/08 Sat 17/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 92
Sun 11/08 Mon 12/08 Tue 13/08 Wed 14/08 Thu 15/08 Fri 16/08 Sat 17/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TEAM 1
TEAM 1
TEAM 1
TEAM 1
TEAM 1

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 93
Sun 11/08 Mon 12/08 Tue 13/08 Wed 14/08 Thu 15/08 Fri 16/08 Sat 17/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 94
Sun 11/08 Mon 12/08 Tue 13/08 Wed 14/08 Thu 15/08 Fri 16/08 Sat 17/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 95
Sun 11/08 Mon 12/08 Tue 13/08 Wed 14/08 Thu 15/08 Fri 16/08 Sat 17/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 96
Sun 11/08 Mon 12/08 Tue 13/08 Wed 14/08 Thu 15/08 Fri 16/08 Sat 17/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TEAM 4
TEAM 5A
TEAM 5A
TEAM 5A
TEAM 5A

TEAM 5A

TEAM 5A

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 97
Sun 11/08 Mon 12/08 Tue 13/08 Wed 14/08 Thu 15/08 Fri 16/08 Sat 17/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 98
Sun 11/08 Mon 12/08 Tue 13/08 Wed 14/08 Thu 15/08 Fri 16/08 Sat 17/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 99
Sun 18/08 Mon 19/08 Tue 20/08 Wed 21/08 Thu 22/08 Fri 23/08 Sat 24/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 100
Sun 18/08 Mon 19/08 Tue 20/08 Wed 21/08 Thu 22/08 Fri 23/08 Sat 24/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 101
Sun 18/08 Mon 19/08 Tue 20/08 Wed 21/08 Thu 22/08 Fri 23/08 Sat 24/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TEAM 1

TEAM 1
TEAM 1

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 102
Sun 18/08 Mon 19/08 Tue 20/08 Wed 21/08 Thu 22/08 Fri 23/08 Sat 24/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 103
Sun 18/08 Mon 19/08 Tue 20/08 Wed 21/08 Thu 22/08 Fri 23/08 Sat 24/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 104
Sun 18/08 Mon 19/08 Tue 20/08 Wed 21/08 Thu 22/08 Fri 23/08 Sat 24/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 105
Sun 18/08 Mon 19/08 Tue 20/08 Wed 21/08 Thu 22/08 Fri 23/08 Sat 24/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TL2,TL3
20/08

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 106
Sun 18/08 Mon 19/08 Tue 20/08 Wed 21/08 Thu 22/08 Fri 23/08 Sat 24/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TEAM 4
TEAM 5
TEAM 5
TEAM 5
TEAM 5
TEAM 5
TEAM 5
TEAM 5

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 107
Sun 18/08 Mon 19/08 Tue 20/08 Wed 21/08 Thu 22/08 Fri 23/08 Sat 24/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 108
Sun 25/08 Mon 26/08 Tue 27/08 Wed 28/08 Thu 29/08 Fri 30/08 Sat 31/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 109
Sun 25/08 Mon 26/08 Tue 27/08 Wed 28/08 Thu 29/08 Fri 30/08 Sat 31/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 110
Sun 25/08 Mon 26/08 Tue 27/08 Wed 28/08 Thu 29/08 Fri 30/08 Sat 31/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TEAM 1

29/08

TEAM 1

TEAM 1

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 111
Sun 25/08 Mon 26/08 Tue 27/08 Wed 28/08 Thu 29/08 Fri 30/08 Sat 31/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
27/08
29/08

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 112
Sun 25/08 Mon 26/08 Tue 27/08 Wed 28/08 Thu 29/08 Fri 30/08 Sat 31/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 113
Sun 25/08 Mon 26/08 Tue 27/08 Wed 28/08 Thu 29/08 Fri 30/08 Sat 31/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 114
Sun 25/08 Mon 26/08 Tue 27/08 Wed 28/08 Thu 29/08 Fri 30/08 Sat 31/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 115
Sun 25/08 Mon 26/08 Tue 27/08 Wed 28/08 Thu 29/08 Fri 30/08 Sat 31/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TL3,TL2
28/08

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 116
Sun 25/08 Mon 26/08 Tue 27/08 Wed 28/08 Thu 29/08 Fri 30/08 Sat 31/08
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 117
Sun 01/09 Mon 02/09 Tue 03/09 Wed 04/09 Thu 05/09 Fri 06/09 Sat 07/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 118
Sun 01/09 Mon 02/09 Tue 03/09 Wed 04/09 Thu 05/09 Fri 06/09 Sat 07/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 119
Sun 01/09 Mon 02/09 Tue 03/09 Wed 04/09 Thu 05/09 Fri 06/09 Sat 07/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 120
Sun 01/09 Mon 02/09 Tue 03/09 Wed 04/09 Thu 05/09 Fri 06/09 Sat 07/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 121
Sun 01/09 Mon 02/09 Tue 03/09 Wed 04/09 Thu 05/09 Fri 06/09 Sat 07/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 122
Sun 01/09 Mon 02/09 Tue 03/09 Wed 04/09 Thu 05/09 Fri 06/09 Sat 07/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 123
Sun 01/09 Mon 02/09 Tue 03/09 Wed 04/09 Thu 05/09 Fri 06/09 Sat 07/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 124
Sun 01/09 Mon 02/09 Tue 03/09 Wed 04/09 Thu 05/09 Fri 06/09 Sat 07/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 125
Sun 01/09 Mon 02/09 Tue 03/09 Wed 04/09 Thu 05/09 Fri 06/09 Sat 07/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 126
Sun 08/09 Mon 09/09 Tue 10/09 Wed 11/09 Thu 12/09 Fri 13/09 Sat 14/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 127
Sun 08/09 Mon 09/09 Tue 10/09 Wed 11/09 Thu 12/09 Fri 13/09 Sat 14/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 128
Sun 08/09 Mon 09/09 Tue 10/09 Wed 11/09 Thu 12/09 Fri 13/09 Sat 14/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 129
Sun 08/09 Mon 09/09 Tue 10/09 Wed 11/09 Thu 12/09 Fri 13/09 Sat 14/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TEAM 1
TEAM 1

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 130
Sun 08/09 Mon 09/09 Tue 10/09 Wed 11/09 Thu 12/09 Fri 13/09 Sat 14/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 131
Sun 08/09 Mon 09/09 Tue 10/09 Wed 11/09 Thu 12/09 Fri 13/09 Sat 14/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 132
Sun 08/09 Mon 09/09 Tue 10/09 Wed 11/09 Thu 12/09 Fri 13/09 Sat 14/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 133
Sun 08/09 Mon 09/09 Tue 10/09 Wed 11/09 Thu 12/09 Fri 13/09 Sat 14/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 134
Sun 08/09 Mon 09/09 Tue 10/09 Wed 11/09 Thu 12/09 Fri 13/09 Sat 14/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 135
Sun 15/09 Mon 16/09 Tue 17/09 Wed 18/09 Thu 19/09 Fri 20/09 Sat 21/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 136
Sun 15/09 Mon 16/09 Tue 17/09 Wed 18/09 Thu 19/09 Fri 20/09 Sat 21/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 137
Sun 15/09 Mon 16/09 Tue 17/09 Wed 18/09 Thu 19/09 Fri 20/09 Sat 21/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 138
Sun 15/09 Mon 16/09 Tue 17/09 Wed 18/09 Thu 19/09 Fri 20/09 Sat 21/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

TL1

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 139
Sun 15/09 Mon 16/09 Tue 17/09 Wed 18/09 Thu 19/09 Fri 20/09 Sat 21/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 140
Sun 15/09 Mon 16/09 Tue 17/09 Wed 18/09 Thu 19/09 Fri 20/09 Sat 21/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 141
Sun 15/09 Mon 16/09 Tue 17/09 Wed 18/09 Thu 19/09 Fri 20/09 Sat 21/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 142
Sun 15/09 Mon 16/09 Tue 17/09 Wed 18/09 Thu 19/09 Fri 20/09 Sat 21/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup

Page 143
Sun 15/09 Mon 16/09 Tue 17/09 Wed 18/09 Thu 19/09 Fri 20/09 Sat 21/09
18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18

KPMC
19/09

Task Manual Summary


Split Start-only
Milestone Finish-only
Summary Deadline
Project Summary Path Driving Predecessor Milestone Task
External Tasks Path Driving Predecessor Summary Task
Project: UTAP Data Cleaning Proje
External Milestone Path Driving Predecessor Normal Task
Date: Fri 08/12/23
Inactive Task Critical
Inactive Milestone Critical Split
Inactive Summary Progress
Manual Task Manual Progress
Duration-only Slippage
Manual Summary Rollup