S.E (E) IESCO CIRCLE CHAKWAL () jiuGE LOSS TO IESCO DUE TO DAMAGE OF 142 NO.S TRANSFORMERS OF DIFFERENT CAPICITIES. During audit of for above noted period, it was observed that 142 No. of transformers of different capacity were burnt which caused heavy loss to IESCO. Name of Division | No. of Cases Chakwal 38 Talagnag 31 P.D.Khan 28 . Dhudial 45 | Total 142 It is also impossible to ascertain either these transformers were related to distribution/public transformers or private individual independent transformers. It was astonished to note that not a single independent transformer was shown burnt during the year or cost there of recovered from respective consumers. This situation transpire that no check and balance being carried out by higher management to prevent such alarming situation. It is a matter of great concern that neither this situation was investigated nor any responsibility was fixed against persons ou wed tl® we 7 Rely. Efferbs are beng a pasitioe will dlamage TILL bet chet i : thy We! Dy gamedd Alco" ing (ue Nd At Produce (ee agecew to “e wo Scanned with CamScanner a a | lore | seve | ot | suotis | zo i | ql aioe zoae | vet | wt | sezor | zw | ozorres | tsoor | ZNO. \ |= o0s'e vy SOLozL | ‘v0ve Ves [= SLE | oy Och'6zL | Ose Wwidnka v 1 z ee osez ez | ooozor | sor | zr | ost | ovoz | a | saveo | esut | NYE ara > 2 |= see | ce | seen | con | ove |» ooze | we | seein | vse | avn | 2 ses'6tl | oole 960 Ole wn |e ozo rrL vee ONVOVIVL L wow oN wre 1 Thor 50 08 90° 0E NO SV adownva | Tpozarrarozzo | HOTSOOE NOSV | Gaoywya | BrOzI90-ZFOZILO Svc gO snoisinia | 6, Suawuoasnvul| aagywva esi tan SuaWNOISNYUL| —aaovIwvG puaiicdenca 40 33 soaev% | suamioasnvan | Sslnasi 4oa0v% | suawdossnveL aWVN Gordad sSnoiwdd 40 "SON W1OL gordad LNaeeuND “URVOZISO= LVOZIZ0) ANOVAVSGSTIVISNT JO SOVINGOWSa ~ GHOVNVO SUSWYOISNVEL “WNAAVHS STONID NOILVaadO ODS Scanned with CamScanner PARA no._O— S.E (E) IESCO CIRCLE CHAKWAL 4) ©) yon RECOVERY OF COST OF TRANSFORMER DAMAGED BY LOCAL NON RECOVERY peRSON MALIK MUHAMMAD KHAN OF DHOKE HAIDER AMOUNTING TO During checking of record it is pointed out that a Transformer of 50 KVA was damaged due to Tree trimming and causing loss to IESCO by a local person Malik Muhammad Khan of Dhoke Haider. It is further noted that cost of above said T/F was not recovered from concerned person. S.E/XEN (E) IESCO is requested to please look into the matter and direct all the officers/officials concerned to ensure the compliance and save IESCO from loss under report to audit. Rell: After serediig “f record Reali? cael be informed Oy aitfal accolifi7 AL = Pecover Wee Qos is \Ecco yom Concerned “Wwkimede We ; oli avayk accae ) wy ay a aa Scanned with CamScanner NINN W943- 413935, © f° 329 Qe i beet Leb res | O)_ 2B ome 26/62 ow pyr superinending Poti, . | / alagane- a sub LODGING OF FI R_AGAINST MAUK Mt IUHAMMAD KHAN S/O YOUSAF_DHOKE HAIDER TALAGANG BEARING ACEOUNY Nee 145130868701 AND MOBILE NO. oon pets ACCOUNT_NO._05- ). 0301-5: TRANSFORMER DUE TO TREETRIMMING REGARDING DAMAGING OF | SDO (E) IESCO City Talagang reported that above named person have j fallen tree at the LT line of Transformer on 11.03.2018 without | intimation/approval from said office due to which 50 KVA Transformer has been damaged and Authority has sustained huge loss amounting to Rs. 70616/- SDO IESCO City Talagang reported to SHO Police Station Taalagang to lodge proper FIR ainst above named person and recovery from said person be made to recover the loss of ESCO but said SHO has not lodged FIR up till now. In view of above, it is requested that the said SHO may be advised to lodge FIRs as per report of SDO IESCO City Talsgang, 5° that the loss sustained by ESCO could be recovered and could be informed to IESCO Higher Authority yer accordingly. ‘yak wy -XECUTIVE ENGINEER (E) ie, \ p- 165CO OPERATION DIVISION i q . 3 TALAGANG. | Yaw © C tor, 1. S.E. IESCO Circle Chakwal please | 2 S00(E) 1esco Sub Division City Talagang for vigilant pursuance, \ \ { Scanned by CamScanner aN Scanned with CamScanner FF ACTION FOR THEFT OF. MATERIAL VALUING ule "gq nECOVERYOWRITE OFF ACTION FOR THEFT OF M gs, 342000/-APPROX. General scrutiny of the record revealed that theft of material valuing Rs. 342,000/- was took place in Lilla Town Sub Division under P.D. Khan Division as per detail below mentioned. However, despite the lapse of considerable period neither of the recovery of stolen material could be affected nor the thieves could be controlled. This indicated that the chances of recovery of stolen material from the thieves were very remote and ultimately the loss was required to be got written off from the competent authority. But it appeared that no steps seemed to have been taken for getting the loss written off. Further the financial adjustment of theft of material against head of account meant for stock losses was also required to be carried out which was also not done. MATERIAL QUANTITY COST (RS.) Conductor 7/.186 3780 meters 342,000 3 SE/XEN may please look into the matter and get the loss written off from the competent authority after observing departmental formalities and insure the financial effect of this loss against stock losses under head of u account. Progress achieved in the matter may please be intimate to audit. : wile eff Case cil be Cuibedeed Luder ‘| Momation G edit. C flag Veo (veas Or Gam unete Ly quilt Va clue Qanet- a Scanned with CamScanner osze |= “AW - [= son zoozve | 0 | o | 0 | ose] - |- viol TSaSL SIR HBOS ATA) wo ey] ve Tau) ‘SNOISIAIG BN . a wen | poumiene [HEL OE swoisyoor 30 on ~ FWNSYHS S1OwID NOMvuadO OOS3I pn Scanned with CamScanner para no 00 S.E (E) IESCO CIRCLE CHAKWAL @) GE: AMOUNT’AGAINST ARREARS Is. jjuGe AMOUNT AGAINST ARREARS Is. 2. OUTSTANDING ‘AS PER CP-61 AND During scrutiny of record, it has been noticed that heavy arrears of fs. 27.12 Million against 1021 No. consumers is lying out standing in CP-61 & CP-62 up till now which is serious irregularity and financial loss to IESCO, The detail is as under: Name of Division congintrs Amount (Rs.) Chakwal 40 14.40 Talagnag 644 8.08 P.D.Khan 105 2.21 Dhudial 232 2.43 Total 1021 27.12 SE is requested to look into the matter and efforts may please be made for the recovery of amount from consumers as early as possible a een will be made and Audit evil be 4 ety . vnforoned acsoclnlf Che elf welt hecovey eo Kev wre Scanned with CamScanner e141 teez | 29°05 I 9¥9 | yemeuo reipnug eux Od Bueberey remyeug uoIsIAId JO 2weN quawhed peppy MeN souejeg Buuedo 8102/90 OL LL0Z/20 Wosy (oA1Sses601d) 29 'B 19-dd Buy AWMYVHO 31919 OOSAl OUS JOWIES Scanned with CamScanner F para no._ C= S.E (E) IESCO CIRCLE CHAKWAL (°) i “yUGE NO OF PENDING NEW CONNECTION APPLICATIONS During checking of record it is pointed out that as per CP-13 for 06/2018, a huge number of New Connections were laying pending. It is desired that the pendency may be cleared as soon as possible. Detail is as under:- GENERAL | COMMERCIAL | INDUSTRIAL TUBE WELL | TOTAL RIPE 970 14 2 18 1114 UN-RIPE 2050 274 6 5 2335 TOTAL 3020 388 18 23 3449 SE is requested to look into the matter and direct the concerned to clear the above noted pendency to save the IESCO from revenue loss. 6 clear all Rely. Efferls ave being mae lms et deny new commection ellen clue te which huge se E Rue commeclions Poudeyg . i to aun A Woduce Tuc Yecod wh Wt ey a $ g We Scanned with CamScanner TL aseaivag / aseasoul abe % i) aseaiseg / aseesoul abe % : 9s691 Lb0z/90- 940z/Z0 104 2691 2y0z/90 40d ; y206Z 8102/90 - 2102/20 404 ZOLb @107/90 404 (uenig suogoauucg man ) (uenig suoqzauuog MeN ) NOSIYVdWOD SAISSSYDOUd NosravdNOD ATHLNOW T - bre 6281 alt ZOLb 9zes S822 evoe 8102/90 LLe8 6012 Zly L694 9870l 68s! L688 LL0z/90 HLNOW SHL HLNOW SHL ONvTY! BONVIWE | 4y101 | aaloarza | oNRINGNaND | TV 4 oL onrand al ONISOTD SNOILOSNNOD a3Alz03u SHLNOIN G3AIgZ03N ~SNOILVOIIdd¥ SNOILVOIIddv 40 wsodsia 810/90 JO-HINOW SHI ONTENG SNOILSANNO: MEN JO SSa¥SOUd asa AWMMVHO Sloulo NOILVvaadO Oosal Scanned with CamScanner

You might also like