BORED PILE

PROCEDURE
(1) Site Preparation

(2) Set Up location of Bored Pile

(3) Casing installation

(4) Drilling

(5) Removing Slime (Cleaning Bored Hole)

(6) Koden test (Testing by Untrasonic Drilling Mornitor)

(7) Inserting Steel Cage

(8) Tremie pipe installation

(9) Air lifting

(10) Concreting

(11) Casing removal

BHONE KO AUNG
BBORED PILE PROCEDURE

BHONE KO AUNG 1
BBORED PILE PROCEDURE

(1) Site Preparation

BHONE KO AUNG 2
BBORED PILE PROCEDURE

ပထမဦးဆုံး Projectမွာ လုပမ


္ ယ့္ Bored pile နဲ႔ပက္သတ္္တ့ဲ Data ေတြရေ
ွိ နသိေနရမွာပါ။ Structural
Dwg၊ Siteရဲ႕Area၊ Ground lvl၊ Structural dwgမွာ Detail ပါတ့ဲ Pile Center
Point/Location(Coordinate)၊ Pile cut-off lvl၊ Rebar top lvl၊ Pile toe lvl၊ Capping beam lvl၊ Pile
size၊ Pile design length၊ Pile rebar shedule detail၊ Pileထဲမွာထည့္မယ့္Inclinometer &
Untrasonic & Groutingမႈတ္ဖ႔ုိ စတဲ့Pipe၊ ေလာင္းမယ့္Concreteနဲ႔သတ္တ့ဲ Dataအေသးစိတ္၊ Bentonite
specification detail၊ Pile type(Eg..Contiguous bored pile wall; Main structure foundation
pile ;King post pile .etc) .etc စသည္ေတြအကုန္လုံးကုိ အကုန္ေလ့လာ တြက္ခ်က္ထားရပါမယ္။ ၿပီးရင္
Ground Floor lvl၊ Basementပါရင္လည္း Basement lvl၊ Pile cap lvl၊ Pile cap design detail &
Structural dwg၊ Pile capထဲဝင္ရမယ့္Development lengthေတြပါေလ့လာထားရပါတယ္။

ၾကဳိတင္ျပင္ဆင္ရမွာက ေန႔စဥ္Pileဘယ္နွလုံးတူးမယ္ (Site area အေျခအေန၊ရာသီဥတု အေျခအ


ေန၊ယႏၲရား အင္အား၊Labour အင္အား၊Material..(Steel cage & Concrete /Plumpအေျခေနစသည္တုိ႔
ေပၚမူတည္ၿပီး)၊ဘယ္pile noေတြတူးမယ္ဆုိတာ Planခ်ရပါတယ္။ ယႏၲရား ေတြသာြ းလာ လြယေ
္ အာင္ Site
အတြင္းပုိင္းက စတူးတာလည္းရွိပါတယ္။ ယႏၲရား အထုင
ိ န
္ င
ွ ့္အဝင္အထြက္ အဆင္ေျပဖုိ႔ Bored pile point
ေတြ နီးလြန္းရင္လည္း မေကာင္းပါဘူး။ ေျမျပဳိမွာဆုိးတဲ့အတြက္ အရမ္းနီးေနတဲP
့ ile နွစ္လုံးတစ္ေနထဲ
တစ္ျပဳိင္ထတ
ဲ ူးလုိ႔မရပါဘူး။ Designerသတ္မွတ္ေပးတဲ့အေပၚမူတည္ပါတယ္။ Wall pileလုိ Continuous
pileေတြဆုိ ေလာင္းၿပီး24hrၾကာမွ ကပ္ရပ္pileတူးလုိ႔ရပါတယ္(Designer သတ္မွတ္ခ်က္ေပၚမူတည္ၿပီး)။

Site areaႀကီးရင္အ့ဲPileေတြကဘယ္Zoneထဲၾကမလဲၾကဳိတင္Drawingၾကည့္ၿပီး အခ်ိန္မွီ Site


Cleaningလုပ္ထားရပါတယ္။တူးမယ့္ Bore pile locationမ်ားကုိ အၾကမ္းဖ်င္းခန္႔မွန္းၾကည့္ၿပီး(လုိအပ္လ်င္
survey pointအၾကမ္းခ်ခုိင္းၿပီး)ထုေ
ိ နရာကုိ ဘုိးစက္အထုိင္ရဖုိ႔ Back holeနဲ႔ ေျမညႇိျခင္းလုပ္ရပါတယ္။
Level ညီေအာင္၊ ေျမေပ်ာ့ေနပါက ေျမအမာခံရေအာင္၊ ေလာင္းၿပီးသားက်င္းမ်ား အျခားခ်ိဳင့္မ်ား ကုိလည္း
အမာခံရေအာင္ Soilအမာနဲ႔Refillျပန္လုပ္ ျပဳျပင္ၿပီး ဘုိးစက္ထုိင္မယ့္ေနရာမွာသံျပားမ်ား (ဘုိးစက္
changeနဲ႔ ကန္႔လန္႔)ခင္းေပးထားရပါတယ္။ ယႏၲာရားႀကီးေတြထုိင္မွာမုိ႔ ေျမသားအမာခံ
ေကာင္းဖုိ႔အထူးသတိျပဳရပါမယ္။ စက္ထုိင္မယ့္ ေဘးေတြကုိပါ Compactျဖစ္ေအာင္သတိျပဳရပါမယ္။
သုိ႔မွာသာ Drillingလုပေ
္ နစဥ္ စက္အထုိင္မပ်က္ပဲ Vertically & Horizontally stableျဖစ္ၿပီး တြင္းမ
ေကာက္ တြင္းလည္းမေစာင္း lvlလည္းမွန္မွာပါ။ ေယဘုယ်အားျဖင့္ Casing lvlက Rebar top lvlထက္ျမင့္
့္ရပါမယ္။ သု႔မ
ိ ွသာCasing lvlထက္မွာrebarမေပၚေနမွာပါ။ Casing lvlက Ground lvl ထက္ 500mm
ေလာက္ပဲ ျမင့္တာပါ (Casing stopperက Casing နႈတခ
္ မ္းကေန 500mmေလာက္မွာတတ္ထားတာပါ)။
ထုိ႔ေၾကာင့္Casing lvlကုိ Rebar top lvlထက္ျမင့္ေအာင္ ေျမကုိ ဖု႔သ
ိ င့္ရင္ဖ႔ထ
ုိ ားၿပီး Compactရ
ေအာင္လုပ္ထားရပါတယ္ (Cappig beam ပါတဲ့Wall pileေတြမွာ Ground lvlနဲ႔ Rebar top lvl တူညီလု

BHONE KO AUNG 3
BBORED PILE PROCEDURE

နီးပါးရွိတတ္လုိ႔ပါ Lvlသတိျပဳဖုိ႔လုိပါတယ္)။ စက္အထုိင္ရဖုိ႔ ေျမအမာခံရဖုိ႔ကုိ မတူးခင္တစ္ရက္


(မနက္ျဖန္တူးမယ့္pileအတြက္)အလုိထဲက ေန႔စဥ္ျပင္ဆင္ထားသင့္ပါတယ္။ ေနာက္ဆုံး Bentonite tank
ေနရာ၊ Agကားဘယ္လမ္းကဝင္မလဲ၊ ယႏၲယားေတြဘယ္လုိထုိင္မလဲ၊ Steel cage(သံျခင္းေတြ)
တျခားပစၥည္း (Eg.Casing ၊Drilling bucket၊Tremie pipe၊Pipe stand၊Agေလာင္းမယ့္ကေတာ့;etc)
ေတြဘယ္လုိထားမလဲ ထိပါSite conditon ေပၚမူတည္ၿပီး စဥ္းစားPlanခ်ရပါတယ္။ ။

(2) Set Up location of Bored Pile

မိမိတူးမည္P
့ ile No(Coordinate)ေတြကုိ SurveyerကTotal stationနဲ႔ Center Pointခ် သံငုတ္ ရုိက္ၿပီး
သံငုတ္ကုိျမင္သာေအာင္safety tapeပတ္ထားပါတယ္။ သံငုတက
္ 1
ုိ 0mm dia သုံးေလ့ရွိၿပီး ေျမျပင္
ေပၚ200mmေလာက္ေဖာ္ထားပါတယ္။ သံငုတ္ကုိမေ႐ြ႕ေအာင္အထူးသတိျပဳၿပီး အေၾကာင္းတစ္ခု၂ေၾကာင့္
ေ႐ြ႕သာြ းပါက surveyနဲ႔ျပန္checkျပဳျပင္ေပးရပါမယ္။ ၿပီးရင္ အဲ့ဒီသံငုတ္ကေန 1.5m or သတ္မွတ္ distance
တစ္ခုမွာ 90°(X;Y)ပုံစံခြာၿပီး Ref သံငုတ္စုိက္ေပးထားရပါတယ္။ Casing ခ်တဲ့အခါ ref ငုတ္နဲ႔
Casingနႈတ္ခမ္းတုိင္းၿပီး(ေစာ၂က ရတဲC
့ enter distanceကုိ Casing Radious နႈတ္လုိ႔ရတဲ့
Distanceနဲ႔တင
ုိ း္ ) ခ်ရင္ Pile eccentricity(ECC)စစ္တ့အ
ဲ ခါ အမ်ားႀကီး မျပဳျပင္ရေတာ့ပါဘူး။ Ground
lvlကုိလည္းတလက္စထဲ recordလုပ္ထားပါတယ္။ ။

BHONE KO AUNG 4
BBORED PILE PROCEDURE

BHONE KO AUNG 5
BBORED PILE PROCEDURE

(3) Casing installation

Casing installလုပ္ရာမွာ Pre boreတူးၿပီးခ်တာနဲ႔ Vibro Hammerသုံးၿပီးခ်တာ ၂မ်ိဳးရွိပါတယ္။


အသုံးမ်ားတဲ့ Casing lengthေတြက 4.5m၊ 3m၊ 1.5mစသျဖင့္အမ်ိဳး၂ရွိရာ ေျမအမ်ဳိးစားလုိက္ ေျမေပ်ာ့ရင္
Steel cage (Rebar weight)မ်ားရင္ Casing length ရွည္တာပုိေကာင္းပါတယ္။ သုိ႔မွသာ Steel cage
weight နဲ႔ Concrete pouringလုပေ
္ နစဥ္ Vibrationေၾကာင့္ တျခားအေၾကာင္းေတြေၾကာင့္ Casing ကြၽံတာ
(နဂုိlvlေအာက္က်သြားတာ) မျဖစ္မွာပါ။ တခ်ိဳ႕Test pileေတြဆC
ုိ asing length 9mထိရွိပါတယ္။ Casing
Diameterေတြက Bore pile diameterထက္ 100mmကေန 150mm ~200mm ထိပုိႀကီးပါတယ္။
ဥပမာ1000mm bore pileအတြက္ဆC
ုိ asing diaက 1150mmပါ။

Preboreတူးတဲအ
့ ခါ ေယဘုယ်အားျဖင့္ Auger or Soil bucketကုိ အသုံးျပဳတူးပါတယ္။ တူးေနစဥ္မွာ
သတ္မွတ္ Specification ရွိတ့ဲ Bentoniteကုိ ျဖည့္ေပးေနရပါတယ္ (တူးေနရင္းေျမေတြျပဳိမက်လာ
ေအာင္ပါ)။

pre boreတူးၿပီး Casingခ်တဲ့အခါေျမႀကီးထဲမွာfittingျဖစ္ေနေစဖု႔အ


ိ တြက္ Casing lengthနဲ႔
Diaကုိတက
ြ ္ခ်က္ၿပီး Operatorကုိ ေျပာၿပီး တူးခုိင္းရပါတယ္။ ေယဘုယ်အားျဖင္း Casingကုိ 0.5mကေန
1mထိ Ground levelအေပၚမွာေဖာ္ထားေလ့ရွိပါတယ္ Stopperကလည္း Casingနႈတ္ခမ္းကေန 500mm
ေလာက္မွာတပ္ထားတာပါ။ ဥပမာ Ground lvl ေပၚမွာ0.5mပဲေဖာ္ထားမယ္ဆ4
ုိ .5m length
casingအတြက္ 4mေလာက္တူးရပါတယ္။ တူးရမယ့္ Diaကေတာ့ Casing sizeအတုိင္းပါ(Casing
diaရဖု႔အ
ိ တြကB
္ ucketေဘးမွာ သံတုံး အစြယ္ထုတထ
္ ားၿပီး diaကုိလုိသလုိညႇိရပါတယ္)။ တူးၿပီးရင္ Steel

BHONE KO AUNG 6
BBORED PILE PROCEDURE

cage weight န႔ဲConcrete pouringလုပေ


္ နစဥ္ Vibrationေၾကာင့္ အေၾကာင္းအမ်ိဳးေၾကာင့္ Casingကြၽံတာ
(နဂုိlvlေအာက္က်သြားတာ)မျဖစ္ေအာင္Casing stopperေနရာေအာက္မွာ သံျပားခင္းထား (သု႔)ိ အမာခံရ
ေအာင္လုပထ
္ ားရင္ lvl တည္ၿငိမ္မႈ ပုေ
ိ ကာင္းပါတယ္။ Service Craneသုံး၍ Casingခ်ပီး Surveyနဲ႔ Total
stationသုံးၿပီး Casing ECCစစ္ရပါတယ္။ Casing နႈတ္ခမ္းေပၚကုိ အေပါင္းလကၡဏာ ဇကာတင္ၿပီးSurvey
pointေထာက္ၿပီး ေပဘူးနဲ႔Centerခြစ
ဲ စ္ပါတယ္။ သတ္မွတE
္ rror ထက္ေက်ာ္ရင္Back holeနဲ႔ျပဳျပင္
ေပးရပါတယ္။ ECCကုိ ေယဘုယ်အားျဖင့္75mm errorခြင့္ျပဳပါတယ္။ ကြၽန္ေတာ္တုိ႔siteမွာေတာ့
ေယဘုယ်အားျဖင့္20mmပဲခင
ြ ့္ျပဳပါတယ္။ ECC Ok ၿပီဆုိရင္ Casing level တုိင္းၿပီး
recordလုပ္ထားပါတယ္။ ECCနဲ႔ Lvl okၿပီဆုိ Back hoeနဲ႔ Casing ပတ္ပတ္လည္ကုိ ေျမနဲ႔အုံၿပီးသိပ္
ေပးပါတယ္။ Casingကုိ မထိခုိကေ
္ အာင္လုပ္ရပါတယ္(Casing stableျဖစ္ေအာင္နဲ႔ တူးေနခ်ိန္တင
ြ ္
Bentoniteရည္မ်ားCasingနခမ္းမွစိမ့္လွ်င္တင
ြ ္းနခမ္းကုိ တုိက္စားႏုိင္လုိ႔ ေျမနဲ႔အုံၿပီးသိပ္ေပးတာပါ)။

Vibro hammerနဲ႔ခ်ရင္ Surveyငုတက


္ ေန Casing Diaအတုင
ိ ္းစက္ဝုိငး္ ပုံစံ Markingမွတေ
္ ပးထားပါတယ္
ၿပီးရင္ ထုိစက္ဝုိငး္ ေပၚကုိCasingတည္ၿပီး Vibro Hammerနဲ႔ရုိကခ
္ ်ပါတယ္။ Vibro hammerသုံးၿပီး ခ်ေနစဥ္
ECCနဲ႔ Verticallyကုိ အၾကမ္းဖ်င္း စစ္ေပးေနရပါတယ္။ ၿပီးရင္ ECCနဲ႔ Casing Lvl စစ္ေပးရပါတယ္
Recordယူထားရပါတယ္။ ၿပီးရင္ ေစာ၂ကလုိ ေျမနဲ႔အသ
ံု ပ
ိ ္ေပးပါတယ္

Casing lvlရၿပီဆုိတာနဲ႔ Final depthတြက္လ႔ပ


ုိ ါၿပီ။ ။

BHONE KO AUNG 7
BBORED PILE PROCEDURE

BHONE KO AUNG 8
BBORED PILE PROCEDURE

BHONE KO AUNG 9
BBORED PILE PROCEDURE

BHONE KO AUNG 10
BBORED PILE PROCEDURE

BHONE KO AUNG 11
BBORED PILE PROCEDURE

(4) Drilling

Casing ECC & Lvlစစ္ပီးတာနဲ႔ ဘုိးစက္ဝင္ထုိငၿ္ ပီး Final depthထိေရာက္ေအာင္ Drilling


Bucketသုံး၍တူးပါတယ္။ ဘယ္ေလာက္အနက္တူးရမယ္ဆုိတာကုိ ဘုိးစက္ Operatorကုိတခါထဲ
ေျပာထားရပါတယ္။ Bucket sizeျပည့္မျပည့္ကုိလဲ တခါထဲစစ္ရပါတယ္။ တူးလုိ႔5mတစ္ခါေရာက္တုိင္း နဲ႔
soil အေရာင္ေျပာင္းတုိင္း soil sampleယူထားၿပီး soil classခြဲၿပီး recordလုပေ
္ ပးထားရပါတယ္။ သာမန္
ေျမမ်ိဳးဆုိရင္ ရုိး၂ Soil bucketနဲ႔တူးၿပီး မာၿပီး ေက်ာက္ဆန္တယ္ဆုိရင္ Rock bucketနဲ႔တူးပါတယ္။ တူး
ေနရင္းBucket အစြယ္က်ိဴး၍ျဖစ္ေစ ပ်က္စီးသြား၍ ျဖစ္ေစ အသစ္လဲမည္B
့ ucketကုိ ျပန္တုိင္း
စစ္ေပးရပါမယ္ (50mm ႀကီးသြားရင္ပဲ Concrete Vol အေျပာင္းလဲမ်ားလုိ႔ပါ၊ Bucket sizeမျပည့္ရင္လဲ
သံခ်င္းခ်တဲ့အခါ မက်ပဲေထာက္ေနတတ္ပါတယ္၊Design Diaလဲမရပဲေနပါမယ္)။ Final Depth
တြက္နည္းကုိေတာ့ပုံမွာျပထားပါတယ္။ Final Depthတြက္တ့အ
ဲ ခါ 300mm ထပ္ေပါင္းထည့္ပါတယ္။
လုိအပ္တာထက္ 300mmေလာက္ပုိတူးတဲ့သေဘာပါ။ တူးေနစဥ္ Final depthမေရာက္ခင္ အ
ေၾကာင္းတစ္ခုခုေၾကာင့္ ဥပမာ Rock layerေတြ႕၍ ရုိး၂bucketနဲ႔တူးလုိ႔မရရင္ Rock Bucket (သု႔)ိ Rock
Augerနဲ႔ေျပာင္းတူးပါတယ္။ Bucketအမ်ိဳးမ်ိဳးသုံးၾကည့္ေသာ္လည္း အခက္ခရ
ဲ ွိ၍ဆက္တူး၍မရရင္
Designerနဲ႔ညႇိႏုွိင္းၿပီး ခ်က္ခ်င္းေဆာင္႐ြက္ရပါတယ္။ တူးေနစဥ္အတြင္း ဘုိးစက္ အထုင
ိ ္stableျဖစ္ဖ႔ုိ
ဘုိးစက္Kelly bar verticallyျဖစ္ဖ႔ဂ
ုိ ရုစုိကရ
္ ပါတယ္။ Kelly bar ေစာင္းမေစာင္းလဲ အၾကမ္းဖ်င္းစစ္ေပး
ေနရပါတယ္။ မသကၤာရင္ Spirit lvl (သု႔)ိ Surveyျဖင့္ Kelly barကုိ Vertical Checkေပးရပါတယ္(အထုင
ိ ္
အဆင္မေျပရင္ တြငး္ ေစာင္းတာ ဆက္တူးလုိ႔အဆင္မေျပျဖစ္တာျဖစ္တတ္ပါတယ္)။တြင္းေစာင္းရင္ သံျခင္

BHONE KO AUNG 12
BBORED PILE PROCEDURE

းခ်လုိ႔လည္း မက်ပဲျဖစ္တတ္ပါတယ္ အခက္ခဲရွိရင္ ခ်က္ခ်င္းျပဳျပင္ေပးရပါတယ္။ ကြၽန္ေတာ္တုိ႔Siteထဲမွာ


ေတာ့ Rock Socketingမလုပပ
္ ါဘူး။ တခ်ိဳ႕Projectေတြမွာဆုိ Designအရ Rocket layerထိေရာက္
ေအာင္တူးရပါတယ္။ Rock layer ေရာက္တာနဲ႔စက္က (engine ဝပ္သြားၿပီး)တုနခ
္ ါေနၿပီး ေသခ်ာေအာင္
အားစုိက္တူးၾကည့္ၿပီး Rock layerကုိ အတည္ျပဳရပါတယ္။ ေက်ာက္သား နမူနာ ယူရပါတယ္။ Rock layer
ေရာက္တာနဲ႔ Socketingလုပဖ
္ ႔အ
ုိ တြက္ Core barral နဲ႔ Rock Coringလုပ(္ တူး)ပါတယ္ (
ေက်ာက္လြာထဲဝင္ရမယ့္ Rocket socketing lengthက Pile diaရဲ႕ အနည္းဆုံး1D ကေန 2Dထိ ရွိပါတယ္
)။

တူးေနတဲ့တေလ်ာက္လုံး Bentonite ကုိျဖည့္ေပးေနရပါတယ္ (တြင္းမျပဳိေအာင္)။ ကြၽန္ေတာ္တ႔ုိ


SiteမွာသုံးတဲB
့ entonite specificationက

Viscosity →32 to 35

Mud density →1.06 to 1.1

Sand Content →less than2%

PH value →8~10 ပါ။

BentoniteကုC
ိ asingနႈခမ္းကေနအနည္းဆုံး 1mေလာက္ထိေရာက္ေအာင္ျဖည့္ပါတယ္။ Bentonite lvlက
Casingေအာက္နႈတ္ခမ္းေအာက္သာြ းလု႔မ
ိ ရပါဘူး။ ေရာက္သာြ းရင္ Casingေအာက္နႈခမ္းနဲ႔ ေျမႀကီးၾကား
Gap(Bentoniteမရွိတ့ဲေနရာ) ျဖစ္ၿပီးေျမေတြပဲ့က်တတ္လုိ႔ပါ (သတ္မွတB
္ entonite specificationမွန္မမွန္
ကုိ တြငး္ ထဲမျဖည့္ခင္ Preboreမတူးခင္Bentonite tankမွာ အရင္စစ္ပါတယ္၊ ၿပီးရင္Drillingလုပၿ္ ပီးတဲ့အခါ
တြင္းထဲကယူၿပီး ထပ္စစ္ ပါတယ္၊ Air liftingၿပီးရင္ တြငး္ ထဲကBentonite တစ္ခါထပ္စစ္ပါတယ္ ) ။
ဘုိးစက္Operatorက သတ္မွတ္ F.Dေရာက္ၿပီေျပာရင္ မွန္မမွန္ Measuring tape (soundingၾကဳိး)နဲ႔
လုိခ်င္တ့ဲF.Dေရာက္မေရာက္စစ္ပါတယ္။ လုိခ်င္တ့ဲF.Dေရာက္ရင္ တြင္းထဲက အနည္နွစ္ေတြကုိ
Cleaningလုပ္ရပါေတာ့မယ္။ ။

BHONE KO AUNG 13
BBORED PILE PROCEDURE

(5) Removing Slime (Cleaning Bored Hole)

Cleaningလုပ္မယ္ဆုိတာနဲ႔ Drilling bucket ကုိျဖဳတ္ၿပီး Cleaning bucketကုိ တတ္ေပးရပါတယ္။


Cleaning bucketကDrilling bucketလုိ အစြယ္အခ်ြန္ေတြမပါပဲ လွည့္ျပီး အနယ္နွစ္ေတြကုိ သဲ့ယူတ့ပ
ဲ ုံစံပါ။
ၿပီးရင္ျဖည္း၂ခ်င္း တြင္းထဲက အနည္နွစ္ေတြ ကုနေ
္ အာင္တူးပါတယ္။

နဂုိF.Dအထိပဲ ျပန္နႈိက္(တူး)တာပါ။ Base cleaningလုပ္ၿပီးသြားရင္ Surveyျဖင့္ ECCနဲ႔ Casing Lvlကုိ As


buildအေနနဲ႔ ေနာက္တခါ ျပန္စစ္ေပးရပါတယ္။ ECCနဲ႔ Casing lvlအနည္းငယ္အေျပာင္းလဲရွိႏုိင္ၿပီး
Recordလုပ္ထားရပါတယ္။

BHONE KO AUNG 14
BBORED PILE PROCEDURE

BHONE KO AUNG 15
BBORED PILE PROCEDURE

(6) Koden test(Testing by Untrasonic Drilling Mornitor)

ကြၽန္ေတာ္တုိ႔Siteမွာေတာ့ Konden Testကုိ မသုံးပါဘူး။ ဒါေပမယ့္ ဗဟုသုတအေနနဲ႔ပါ။ Untrasonic


Drilling Mornitor မွာ Winch unitနဲ႔ Recorder unitဆုိၿပီး နွစခ
္ ုပါပါတယ္။ Winch unit ကုိ Casing
ေပၚတင္ၿပီး Winch unitက Sensor unitကုိ တြငး္ ထဲကုိ ျဖည္း၂ခ်င္းခ်ပါတယ္။ ထုိအခ်ိန္မွာ Recorder
unitကေန X-X´ ,Y-Y'ပုံစံန႔ဲ Graphေလးထြက္လာပါတယ္။ ထုG
ိ raphကေနၿပီး တြင္းေစာင္းမေစာင္း တြင္
းျပဳိမျပဳိ(ဂလုိင္ ျဖစ္မျဖစ္) Souding အနက္တုိ႔ကုိသိရွိႏုိငပ
္ ါတယ္။ အဲဒီ DataေတြကR
ုိ ecordလုပ္
ထားရပါတယ္။ Koden testတစ္ခါလုပ္ရင္1hrနီးပါၾကာပါတယ္။ Bore pileေတြက တူးၿပီးလုိ႔အခ်ိန္
ၾကာတာနဲ႔အမွ် တြင္းထဲက Bentonite Qualityက်တတ္ၿပီး တြင္းျပဳိျခင္း Settlement ထုိငျ္ ခင္း တု႔ျိ ဖစ္တတ္
လုိ႔ အျမန္ဆုံးေလာင္းရပါတယ္။ ထု႔ေ
ိ ၾကာင့္Siteအမ်ားစုမွာ Koden Testကုိမစစ္ၾကပါဘူး။ ဒါေၾကာင့္
စတူးကထဲက Kelly Barကုိ Verticallyျဖစ္ေအာင္ စက္အထုင
ိ ္ေကာင္းေအာင္ Checkေပးေနရပါတယ္။ ။

BHONE KO AUNG 16
BBORED PILE PROCEDURE

BHONE KO AUNG 17
BBORED PILE PROCEDURE

(7) Inserting Steel Cage

Koden test စစ္ၿပီးတာနဲ႔ Service Craneျဖင့္Steel Cage(သံျခင္း)စခ်လု႔ရ


ိ ပါၿပီ။

Steel Cageျပဳလုပ္ရာမွာပါဝင္တ့ဲ အဓိက အစိတပ


္ င
ုိ ္းေတြက

1.Mainbar

(သတ္မွတD
္ ia၊Number၊Length၊Lapping၊Binding၊Weldingရွိရျပည့္စုံရပါမယ္)

2.Binders (သု႔)ိ Outer Ring

(သတ္မွတ္Dia၊Spacing၊Lapping၊ Binding၊Weldingရွိရ ျပည့္စုံရပါမယ္)

3.Stiffener (သု႔)ိ Inner ring

(သတ္မွတ္Dia၊Spacing၊Lapping၊Binding၊Welding ရွိရ ျပည့္စုံရပါမယ္)

4.Spacer bar (သု႔)ိ Cover chair bar

(သတ္မွတ္Dia၊Spacing၊Number၊ Binding၊Welding ရွိရ ျပည့္စုံရပါမယ္)

5.Hanging Rod

BHONE KO AUNG 18
BBORED PILE PROCEDURE

(H.Rက သံျခင္းကုိ သတ္မွတl္ vlရရွေ


ိ နေအာင္ Casingနႈတခ
္ မ္းကေန သံျခင္းကုိလွမ္းခ်ိတ္ထားတာပါ
၊Casing lvlနဲ႔ Reabar top lvlကုိလုိက္ ၿပီး HR က အတုိးအေလ်ာ့ရွိပါတယ္)။

**H.Rတြက္တ့အ
ဲ ခါ Casing Lvlနဲ႔ Pile Design Length & Cut off lvlကုိၾကည့္ၿပီးတြက္ပါတယ္
ပုံမွာျပထားပါတယ္။

သံျခင္းမ်ားထုတ္လုပ္ေရးလုပ္(လုံးတဲ)့ အခါ သတ္မွတ္ သံျခင္းDia မွနေ


္ အာင္ ၊Main barေတြ straightျဖစ္
ေအာင္ ဂရုစုိက္ရပါတယ္။ Lappingေနရာေတြကုိ Spiralမပတ္ပခ
ဲ ်န္ထားပါတယ္။ က်င္းေပၚမွာMain bar
ေတြ Lappingလုပ္ၿပီးမွ ပတ္မွာမုိ႔ပါ။

ကြၽန္ေတာ့္တ႔ိုSiteမွာသုံးခဲ့တဲ့ Designက

Pile Capထဲဝင္ရမယ့္ Development length →45d

Main bar lapping →45d

Inner ring lapping →350mm

Spiral lapping →35d ,d=dia of spiral

Spacer bar →4nos @every pile length 3m

H.R dia →25mm

H.R Lapping →45d

Bottom cover →100mm

Side cover →75mm

သံျခင္းမ်ားခ်တဲ့အခါ တစ္ျခင္းနဲ႔တစ္ျခင္း အေပၚေအာက္ (ပ ဒု တ စ) မွားမခ်မိေအာင္ အစဥ္လုိက္


ဂရုစုိက္ရပါမယ္။ Craneနဲ႔ ပထမဆုံးျခင္းကုိ ျဖည္း၂ခ်င္းစခ်ပါတယ္။ ပထမဆုံးျခင္းရဲ႕အေပၚဆံုး Inner
ring(မိန္းကြင္း)ကုိ Casing နႈတ္ခမ္းမွာ ကန္႔လန္႔ျဖတ္ ဂလန္႔ (Steel Cage weightကုိခံႏုိင္တ့ဂ
ဲ လန္႔)2
ေခ်ာင္းထုိးၿပီးCasingေပၚ တင္ထားမွာပါ။

Inner ringရဲ႕အေပၚမွာ Main barမ်ားက Lapping lengh တစ္ခုစာ ေပၚေနမွာပါ။ ၿပီးရင္Lapping


lengthအတြက္လုိအပ္တ့ဲ spiralကြင္းကုိတြက္ခ်က္ၿပီး သံျခင္းကုိစြတ္ခ်လုိက္ပါတယ္။ Spiral okၿပီဆုိရင္
ဒုတိယေျမာက္ျခင္းကုိ Service Craneျဖင့္မထားၿပီး ပထမသံျခင္းနဲ႔ Main barေတြပူးၿပီး Welding (သု႔)ိ

BHONE KO AUNG 19
BBORED PILE PROCEDURE

Bullet clip တြဲပါတယ္ (Structual dwgမွာပါတဲ့ Designအတုင


ိ ္း)။ Weldinနဲ႔တဲြရင္ Welding length &
Thicknessကုိ Designerရဲ႕ Guidelineအတုင
ိ ္းလုိကန
္ ာရပါတယ္။ Main barေတြ တြဲၿပီးတာနဲ႔
ေစာ၂ကထည့္ထားတဲ့Spiral ကုိ Lapping zoneေနရာမွာပတ္ေပးပါတယ္။ Lapping lengthနဲ႔ Spiral
spacingလည္းမွန္ရပါမယ္။

Splice%က50% (သု႔)ိ 100%ပါ(Designေပၚမူတည္ၿပီး)။ သံျခင္းဆက္လ႔O


ုိ kၿပီဆုိတာနဲ႔
ဒုတိယခ်င္း(ပထမခ်င္းနဲ႔တဲြရက္ခ်င္း) ကုိ Craneနဲ႔ ျဖည္း၂ခ်င္းခ်ပါတယ္။ ဒုတိယခ်င္းရဲ႕အေပၚဆုံးInner ring
ေရာက္တဲ့အခါ အရင္တုင
ိ း္ ပဲ ကလန္႔ထုိး Spiral ထည့္ တတိယတစ္ျခင္း ထပ္ဆက္ပါတယ္ ေေနာက္ျခင္းေန
ေတြလည္း အလားတူပထ
ဲ ပ္၂ဆက္သြားတာပါ။

Designကေပးထားတဲ့ Steel cageေတြအစဥ္လုိက္ခ်ၿပီးရင္(Steel cage lengthရတဲ့အခါ)တြက္


ထားတဲ့သတ္မွတ္lengthရွိတ့ဲHanging Rod 2ေခ်ာင္း ကုိ ေနာက္ဆုံးသံျခင္းRebar top lvlနဲ႔
LappingပူးၿပီးWelding တြေ
ဲ ပးရပါတယ္။ Welding ကုေ
ိ သခ်ာဂရုစုိကေ
္ ပးရပါတယ္။ Steel cageအားလုံးရဲ႕
Weightကုိ H.R 2ေခ်ာင္းထဲက ထမ္းရတာမုိ႔ပါ။ H.R weldingတြဲၿပီးတာနဲ႔ Craneနဲ႔ ျဖည္း၂ခ်င္းခ်ၿပီး
H.Rက ကြင္းနွစ္ကြင္းကုိ ကလန္႔ထုိးျပီး Casingေပၚတင္ထားပါတယ္။ H.Rကုိ
Casingနႈခမ္းဆီ(ေဘး)ကပ္ၿပီးထားရပါတယ္။ Tremie pipeခ်ရလြယေ
္ အာင္ပါ။

Design ကPileထဲကုိ Pipeေတြထည့္ဖုိ႔ေပးထားရင္ တဆက္ထထ


ဲ ည့္ေပးရပါတယ္။ ဥပမာ...တည္ေဆာက္
ေရးလုပ္ေနစဥ္ Siteရဲ႕ ေျမေအာက္ Foundation အေျခေနကုC
ိ heckingလုပဖ
္ ႔ုိ Equipmentေတြအတြက္
Pileထဲမွာ Inclinometer pipe၊Untrasonic pipeေတြထပ္ထည့္ပါတယ္။ Groutingမႈတ္ဖုိ႔အတြက္ GI pipe
ေတြကုိခ်ေပးထပ္ထည့္ေပးရပါတယ္။ ေယဘုယ်အားျဖင့္ F.Dထိေရာက္ေအာင္pipeေတြဆက္၂ၿပီးခ်ပါတယ္

တခ်ဳိ႕Pojectေတြမွာဆုိ Steel cage installationၿပီးရင္ Surveyနဲ႔ ECCနဲ႔ Casing lvlထပ္စစ္ၿပီး


recordလုပ္ပါတယ္။ ။

BHONE KO AUNG 20
BBORED PILE PROCEDURE

BHONE KO AUNG 21
BBORED PILE PROCEDURE

(8) Tremie pipe installation

သံျခင္းခ်ၿပီးတာနဲ႔ Craneျဖင့္Casingေပၚ Pipe standတင္ပါတယ္။ ၿပီးရင္ ထုp


ိ ipe stand အေပါက္ကေန
Craneျဖင့္ Tremie pipeခ်ပါတယ္။

အသုံးမ်ားတဲ့ Tremmie pipe lengthေတြက 4m( ကေတာ့ခြၽန္ပုံစံပါတဲ့ ေအာက္ဆုံးပုိက္)၊ 3m၊ 2m၊ 1m၊
0.5m အမ်ိဳး၂ရွိပါတယ္။ Diaကေတာ့350mm၊250mm၊200mmစသျဖင့္ရွိပါတယ္။

Pile size 600mmDiaအတြက္ဆုိရင္ေတာ့ Tremmie pipe dia 200mmကုိပဲ သုံးသင့္ပါတယ္။

BHONE KO AUNG 22
BBORED PILE PROCEDURE

Tremie pipe tip နဲ႔ bore holeရဲ႕ ေအာက္ေျခအကြာေဝး(Gap)ဟာ200mm-300mmအတြင္းရွိရပါမယ္။


အတုဆ
ိ းံု pipe lengthက0.5mအထိပဲ ကစားရတာမုိ႔ (Lengthညႇိလ႔ရ
ုိ တာမုိ႔)အခက္ခဲရွိတဲ့အခါ
Gapက500mmျဖစ္သာြ းတတ္ပါတယ္(အဆင္ေျပပါတယ္)။ Gapမ်ားရင္ေအာက္
ေျခConcreteမသန္႔ပဲျဖစ္တတ္သလုG
ိ apနဲရင္လည္းConcreteမတုိး(ထြက)္ ႏုိင္ပဲပုိက္ဆုိ႔တတ္ပါ တယ္။
Tremie pipe length က F.Dကုိ Gap နႈတ္ေပးရုံပါပဲPipe lengthရရင္ဘယ္နွမီတာဘယ္
နွလုံးတြက္ၿပီးခ်ရပါတယ္။ Gapကုိလထ
ဲ ည့္စဥ္းစားရပါတယ္။ ပုိကေ
္ တြဆက္တ့အ
ဲ ခါ စည္းကြငး္ (သေရကြင္
း)ထည့္ၿပီးၾကပ္ေပးရပါတယ္။ Bentoniteအရည္စိမ့္လ႔မ
ုိ ရပါဘူး(Water Tightျဖစ္ရပါမယ္)။ အရစ္ကုန္
အားကုန္ၾကပ္မွသာ pipe length ရွည္လာတဲ့အခါ မႏြ႕မ
ဲ ွာပါ (Pipe အတြဲလုိက္ႀကီးႏြ႕ရ
ဲ င္ သံျခင္းနဲညိွတတ္
ပါတယ္)။

Tremie pipeတပ္ၿပီးတာနဲ႔တျပဳိင္နက္ Bore pileေဘးနား မနီးမေဝး 3mေလာက္မွာBentonite ျပန္


ေရကန္တူးၿပီး casingကေနေျမာင္းသြယေ
္ ပးထားရပါမယ္။ Concreteေလာင္းေနစဥ္ Bentoniteက
လ်ံတက္လာကာ အဲ့ကန္ထဝ
ဲ င္ရမွာပါ။ ၿပီးရင္ pumpနဲ႔စုပ္ၿပီး Bentoniteကန္ထပ
ဲ ုိက္လုိင္းနဲ႔ျပန္ပုိ႔ ပါတယ္။
Concreteေလာင္းေနစဥ္အရမ္းအေရးႀကီးတဲ့အခ်က္က Tremie pipe lapping (Concreteထဲမွာျမဳပ္
ေနရမယ့္length)ပါ။ (Concretingမွာေဖာ္ျပထားပါတယ္)

Tremie pipeတြကန
္ ည္းကုိပုံမွာျပထားပါတယ္။ ။

(9) Air lifting

Tremie pipeခ်ၿပီးတဲ့အခါ Settlement (အနည္အနွစ္)ဘယ္ေလာက္ထုိင္သာြ းလဲတုိင္းရပါတယ္ ။


Soundingတုိင္းလု႔ရ
ိ တဲF
့ .Dက နဂုF
ိ .Dနဲ႔မတူပဲ Depthေလ်ာ့သြားရင္ Settlement ထုိင္တာေသခ်ာပါတယ္။
ဥပမာ Drillinၿပီးခ်ိန္ F.Dက 43m (Design depthကလည္း43mဆုိပါေတာ့) Tremie ခ်ၿပီးခ်ိန္မွာ F.Dက
42ပဲရွိေတာ့တယ္ဆုိ Settlementက1mပါ(Design depthလည္းမရေတာ့ပါဘူး)။

BHONE KO AUNG 23
BBORED PILE PROCEDURE

Settlement 300mmထိပဆ
ဲ A
ုိ ir lift မႈတ္စရာမလုိပါဘူး Settlement 300mmထက္မ်ားတာနဲ႔ Air lift
မႈတ္ရပါတယ္ Air liftေခါင္း ကုိ Tremie pipeမွာ စြတၿ္ ပီး ၾကပ္ေပးရပါတယ္။ ေလဝင္ပုိက္ကုိ
ေအာက္F.Dထိခ်ေပးရပါတယ္။ Air lift ပုိက္ခ်ၿပီးတာနဲ႔ Compressorနဲ႔စမႈတ္ပါတယ္။ အဲဒီအခ်ိန္မွာ
bentoniteနဲ႔ settlement အနွစ္ေတြထက
ြ ္လာပါတယ္ settlementေတြကုန္တ့ထ
ဲ ိ (ထြက္တ့ဲ ဟာေတြကုိ
လက္နဲ႔စမ္းၾကည့္ရင္ အနွစ္ေတြ နည္းသြားတဲ့ထိ) မႈတေ
္ ပးရပါတယ္။ Air liftမႈတေ
္ ပးေနစဥ္ တြငး္ ထဲက ထြက္
ေနတဲ့Bentoniteေတြေနရာမွာ Bentonite အသစ္ေတြကုိ Pumpနဲ႔ အဆက္မျပတ္ျဖည့္ေပးေနရပါတယ္။
တြင္းထဲကထြက္တB
့ဲ entonite ေတြကုိ Tankဆီျပန္ပ႔ၿုိ ပီး သန္႔စင္ၿပီး ျပန္သုံးလုိ႔ရပါတယ္။ Air liftလုပတ
္ ာက
အေဝစိတင
ြ ္းထဲ က ေရကုC
ိ ompressorနဲ႔မႈတ္တင္တာနဲ႔ ပုံစံတူပါတယ္ (Bentoniteအသစ္ျပန္ျဖည့္ရင္
း)။တြင္းထဲက Bentonite specificationကုိ Air liftingၿပီးရင္ တစ္ခါထပ္စစ္ပါေသးတယ္။

Air lift ၿပီးတာနဲ႔ Agေလာင္းမယ့္ကTremie pipeမွာ Agထည့္မယ့္ကေတာ့ (Hooper)ကုိတပ္ပါတယ္။ ။

(10 ) Concreting

Concrteမေလာင္းခင္ၾကဳိတင္ျပင္ဆင္ရမွာက Agကားဘယ္လမ္းကဝင္မလဲဆုိတာပါ(တြင္းဝကုိ ကားဖင္ထုိး


ေလာင္းတဲ့အခါ Casingက ကားရဲ႕Ag ဇလားထက္ျမင့္ေနတတ္တာမု႔ိ ကားဇလားကုိ အျမင့္ေရာက္ေအာင္
Back holeနဲ႔slopeပုံစံလမ္းေဖာ္ျခင္း၊ကားတက္လ႔ရ
ုိ ေအာင္ Slope ပုံစံ သံဖရိနခ
္ င္းျခင္း ၊ကားဝင္မယ့္လမ္
းတေလ်ာက္ Compactionရေအာင္လုပျ္ ခင္း ေျမသားေကာင္းေအာင္ ကားမ ႄကြံေအာင္ သံျပားခင္းျခင္း)။
Agေလာင္းတဲ့ကေတာ့ Hooperကုိမဖု႔ိ Service craneဘယ္နားက ထုိင္မလဲ ျပင္ဆင္ထားရပါတယ္။ တြင္
းနဲ႔မနီးမေဝးမွာ Service Boom အေထာင္ေကာင္းမယ့္ေနရာမွာ Service အထုင
ိ ္ အမာခံရေအာင္
ၾကဳိတင္ျပင္ဆင္ရပါတယ္။ ကားဝင္လ႔မ
ုိ ရလ်င္ Station pumpနဲ႔ေလာင္းရပါတယ္။ Station pumpနဲ႔ေလာင္
းမယ္ဆုိ Pump pipeအတြကေ
္ ခ်ာဆီကုိပါ ထည့္မွာထားရပါတယ္။ ေလာင္းတဲ့ပုံစံကေတာ့ Craneရဲ႕Hook
သီးအႀကီးက Hopper(ကေတာ့)ကုိမထားၿပီး Hookသီးအေသးက Pumpရဲ႕ပုိကေ
္ ပ်ာ့ကုိ မထားၿပီးေလာင္
းပါတယ္။

BHONE KO AUNG 24
BBORED PILE PROCEDURE

F.Dရကတည္းက Concrete volume(m3)ကုိၾကဳိတက


ြ ္ထားလုိ႔ရပါတယ္။ Cutt off lvlအေပၚကုိအနည္
းဆုံး1mပုိေလာင္းေပးဖုိ႔ပါထည့္ေပါင္းေပးရပါတယ္(တြက္နည္းကုိပုံမွာျပထားပါတယ္)။ သုံးခဲ့တG
့ဲ radeက
ေတာ့ ေယဘုယ်အားျဖင့္35Mpaပါ(Structural dwgအတုင
ိ း္ )။ Bore pileေလာင္းရင္ Slumpေပ်ာ့ေလ
ေကာင္းေလပါ။ အသုံးျပဳတဲ့Slumpကေတာ့ 200±20mmပါ။ slumpမာရင္ျဖစ္ေစ slump okေသာ္လည္း
concreteေထြးေနလ်င္ျဖစ္ေစ ပုိက္ဆ႔တ
ုိ တ္ပါတယ္။ ဒါေၾကာင့္Agမွာရင္လုိအပ္ရင္ slumpျပင္ရေအာင္
Chemicalဘူးပါယူလာခုိင္းရပါတယ္။ သုံးခဲ့တ့C
ဲ oncrete setting timeကလည္း 3hrပါ။

ၿပီးရင္ Siteနဲ႔ Plumpအကြာအေဝး၊ Agကားေရာက္ဖ႔ၾုိ ကာခ်ိန္၊ Ag တစ္စီးတြင္းထဲေလာင္းမည့္ၾကာခ်ိန္၊


Tremie pipe ျဖဳတ္ခ်ိန္ တု႔က
ိ ုိခန္႔မွန္းတြက္ခ်က္ၿပီး Agကုိ ဆက္တုိက္မွာသင့္ရင္မွာရပါမယ္။ မိနစ္အနည္
းငယ္ျခား မွာသင့္ရင္မွာရပါတယ္။ သု႔မ
ိ ွသာ ေလာင္းေနစဥ္ Agကားကုိေစာင့္ရတာမ်ိဳး မျဖစ္ေစပဲ Agကား
ေတြၾကဳိေရာက္ၿပီးsetting time ျပည့္သာြ းမွာကုိလည္းေရွာင္ရွားႏုိင္မွာပါ။ ကားေတြStandby ရွေ
ိ နရပါမယ္။
ေလာင္းရင္း ကားမရွိလုိ႔ မိနစ္အနည္းငယ္ၾကာရင္ပဲ တြငး္ ထဲနဲ႔Tremie pipeထဲကConcrete အနည္းငယ္
မာလာၿပီးပုိက္ဆ႔တ
ုိ တ္ပါတယ္ အခန္႔မသင့္လုိ႔ေစာင့္ရရင္Service Craneနဲ႔ ပုိကက
္ ုိဆြေပးေနရပါမယ္။

မွာထားတဲ့Ag ကားေတြေရာက္တာနဲ႔ ဖင္ထုိးၿပီးစေလာင္းလုိ႔ရပါၿပီ။ စေလာင္းတာနဲ႔ တြင္းထဲမွာ Specific


Gravity မ်ားတဲ့ Concreteက Specific Gravityနည္းတဲ့ Bentonite ေနရာကုိ ယူလုိက္တ့အ
ဲ တြက္
Bentoniteအရည္က လ်ံွထက
ြ ္လာၿပီး ေစာ၂က တူးထားတဲ့ ျပန္ေရကန္ထဝ
ဲ င္ပါတယ္။ ကန္ထက

Bentoniteကုိ pumpနဲ႔ Bentonite tankထဲျပန္ပ႔ပ
ုိ ါတယ္။ ေနာက္တစ္ႀကိမျ္ ပန္သုံးရေအာင္ပါ။

Concreteေလာင္းတဲ့အခါ တက္လာတဲC
့ oncreteကုိ soundingတုိင္းၾကည့္ၿပီး Pipe lengthကုိတျဖည္း၂
ေလ်ာ့ (Pipeကုိ ျဖဳတ္)လာရပါတယ္။အရမ္းအေရးႀကီးတဲ့အခ်က္က Tremie pipe lapping
(Concreteထဲမွာျမဳပ္ေနရမယ္l့ ength)ပါ။ Concreteေလာင္းေနစဥ္မွာ Tremie pipe lappingက
ေယဘုယ်အားျဖင့္

Dia1500mm pileအတြက္ 6m (4mလဲရပါတယ္ pile sizeႀကီးလုိ႔ Agကားတစီးေလာင္းရင္ Lvl


တအားမတက္လာတဲ့အတြက္ safeျဖစ္ေအာင္6mထားတာပါ)။

Dia 1000mm (သု႔)ိ 800mm pileအတြက္ 4m

Dia 600mm pileအတြက္ 3m Concreteထဲမွာအၿမဲျမဳပ္ေနရပါမယ္။

Lappingမ်ားရင္ pipeဆု႔တ
ိ တ္သလုိ Lappingနည္းရင္လည္း Lappig လြတၿ္ ပီး (လြတ္တ့ဲေနရာကုိ
bentoniteတုိးဝင္လာၿပီး) Pileခါးျပတ္တတ္ပါတယ္။ ဒါ့ေၾကာင့္ Lappingကုိ Safeျဖစ္ေအာင္ထားရပါမယ္။

BHONE KO AUNG 25
BBORED PILE PROCEDURE

Soundingကုိ ေသခ်ာတုိင္းၿပီး Pipe ဘယ္ႏ


္ ွလုံးျဖဳတ္မလဲတက
ြ ္ခ်က္ၿပီးေသခ်ာျဖဳတ္ရပါတယ္ (မွားျဖဳတ္လ်င္
lappingလြတ္ႏုိင္လ႔ပ
ုိ ါ)။ ဥပမာ Tremie pipe lengthက 42mနဲ႔ဆင္ထားပါတယ္။ တစီးေလာင္းၿပီးလုိ႔
Sounding က33mရတယ္ဆုိပါေတာ့။ lappingက 3mထားမယ္ဆုိ pipe lengthက 36m ရွိရေတာ့မွာပါ။ ထု႔ိ
ေၾကာင့္ 3m pipe2လုံးျဖဳတ္လ႔ရ
ုိ ပါတယ္။ Concreteတအားမာလုိ႔ အက်မေကာင္းလုိ႔ Pipeဆု႔မ
ိ လုိျဖစ္လုိ႔
Lappingေလ်ာ့ရမယ္ဆုိ Lapping ကအနည္းဆုံး2m ေတာ့က်န္ကုိက်န္ရပါမယ္။ Soundig ေသခ်ာတုိင္
းရပါမယ္။ ပုိက္ကုိ ဇြတ္မ မမိေအာင္ Crane operatorကုိလဲ သတိေပးထားရပါမယ္။ concrete lvlကုိ cut-
off lvlအေပၚကုိအနည္း 1mအထိေလာင္းေပးပါတယ္။ ေလာင္းေနရင္းန႔ဲ Soundingတုိင္းၾကည့္လ႔ုိ သတ္မွတ္
Concrete lvlေရာက္ရင္ Concreting ၿပီးပါၿပီ။ ။

(11) Casing removal

Concretingၿပီးတဲ့အခါ Casing နႈတ(္ Casing Removeလုပ)္ ရေတာ့မွာပါ။ Concrete lvlက Casing


bottom lvlေအာက္ေရာက္ေနရင္ နႈတရ
္ တာ ျပႆနာမရွိေပမယ့္ Concrete lvlက Casing ထဲေရာက္
ေန(ဝင္ေန)ရင္အခ်ိနၾ္ ကာတာနဲ႔အမ်ွ Casingနဲ႔ Concrete ကုိက(္ Concreteနဲ႔Bondျဖစ္သာြ းပါတယ္
)သြားတတ္ပါတယ္။ ထုိ႔ေၾကာင့္ Casingကုိ ျမန္ျမန္နႈတေ
္ ပးရပါတယ္။ Casing ထဲဝင္မဝင္သိခ်င္ရင္Casing
Lengthနဲ႔ Sounding (Casigနႈတခ
္ မ္းကေန Concrete lvlထိတုိငး္ တဲ့Length) ကုိတက
ြ ္ရပါတယ္။
Sounding Length က Casing Lengthထက္နည္းေနရင္ Concrete Casingထဲဝင္ေနပါၿပီ။ Casingကုိ
Ag ကုိကရ
္ င္ Service Craneနဲ႔Back Hole ၂စီးေပါင္းၿပီးနႈတရ
္ င္ေတာင္မႂကြပါဘူး။ ဒါ့ေၾကာင့္
Concretingၿပီးတာနဲ႔ Casingေပၚက Steel Cageရဲ႕ H.R ကြင္းကုိ Weldingနဲ႔ျဖတ္ပစ္ၿပီး Craneနဲ႔ အျမန္

BHONE KO AUNG 26
BBORED PILE PROCEDURE

နႈတ္ရပါတယ္။ Casingနႈတၿ္ ပီးတာနဲ႔ Bore Pileလုပင


္ န္းစဥ္ၿပီးၿပီလ႔ေ
ုိ ျပာလုိ႔ရပါတယ္။ Test Pileဆုိရင္
ေတာ့Casing လ်ံွတ့ထ
ဲ ိေလာင္းၿပီး Casing မနႈတပ
္ ါဘူး (Load Testလုပဖ
္ ႔အ
ုိ တြက္ပါ)။ Structing Beam
ေတြအတြက္ King Post Pile ဆုိရင္လည္း Steel Column (H-Beam)ကုိ Casingက
ယာယီထမ္းထားရတဲ့အတြက္ Casingခ်က္ခ်င္းနႈတ္မရပါဘူး။ သတ္မွတC
္ oncrete Strength ရမွသာ နႈတ္
ရတာပါ။ King Post Pileေတြက Casing lengthတုိတာသုးံ ေလ့ရွိၿပီး Casing bottom lvl ထိေရာက္ေအာင္
ေလာင္းေလ့မရွိတ့အ
ဲ တြက္ ျပႆနာမရွိပါဘူး။ King Post Pileအေၾကာင္းကုိသတ္သတ္ေနာက္္တစ္Post
အေနနဲ႔ တင္ျပပါ့မယ္။

Casingနႈတၿ္ ပီးတာနဲ႔ အဲ့ေနရာမွာ တြငး္ ပုံစံျဖစ္က်န္ေနခဲ့မွာပါ။ အၾကမ္းဖ်င္းေတာ့ မ်က္နွာျပင္Cleaningလုပ္


ထားသင့္ပါတယ္။ Setting Time ျပည့္ေလာက္မွ Fillingလုပေ
္ ပးသင့္ပါတယ္။ တူးထားခဲ့တဲB
့ entonite ျပန္
ေရကန္ကုိပါ Filling & Compactingလုပေ
္ ပးရပါတယ္။ ထုေ
ိ နရာကုိျဖတ္ၿပီးယႏၲရားေတြသာြ းလာမွာမုိ႔ ေသ
ခ်ာရုစုိက္Filling &Compacting လုပေ
္ ပးရပါမယ္။ ။

Bore Pileလုပင
္ န္းစဥ္ၿပီးပါၿပီ။ ။

လုိအပ္ခ်က္မ်ားရွိရင္ Friတုိ႔Editလုပႏ
္ ုိငပ
္ ါတယ္။

###သင္ဆရာ၊ျမင္ဆရာ၊ၾကားဆရာ အေပါင္းကုိCreditျပဳအပ္ပါတယ္။

Photo Credit to Google

Bhone Ko Aung

Date;(Sept;2017)

BHONE KO AUNG 27