Professional Documents
Culture Documents
PIARC Bridge Priorisation
PIARC Bridge Priorisation
org
2012R32EN
Cycle 2004-2007
PRIORITISATION
OF BRIDGE
REHABILITATION
WORKS
Technical Committee 4.4
Bridges and related structures
2 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN statements
The World Road Association (PIARC) is a nonprofit organisation established in 1909 to improve
international co-operation and to foster progress in the field of roads and road transport.
The study that is the subject of this report was defined in the PIARC Strategic Plan 2004 – 2007
approved by the Council of the World Road Association, whose members are representatives of
the member national governments. The members of the Technical Committee responsible for
this report were nominated by the member national governments for their special competences.
Any opinions, findings, conclusions and recommendations expressed in this publication are
those of the authors and do not necessarily reflect the views of their parent organizations or
agencies.
This report is available from the internet site of the World Road Association (PIARC)
http://www.piarc.org
Cover: Fotolia
3 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
This report has been prepared by the Working Group 3 of the Technical Committee 4.4 “Bridges
and related structures” of the World Road Association (PIARC).
Peter Graham (Australia), Malcolm Kerley (Virginia, US), Susanne Troive (Sweden) and Börre
Stensvold (Norway).
Peter Graham and Malcom Kerley were responsible within the Technical Committee of the
quality control for the production of this report.
The Technical Committee was chaired by Rafael Astudillo (Spain) and Florent Imberty (France),
Dimitris Konstandinidis (Greece) were respectively the French and English-speaking secretaries.
4 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
contents
SUMMARY...................................................................................................................................................5
Introduction........................................................................................................................................6
appendices.............................................................................................................................................27
Appendix A1 – Bridge Asset Management System Questionnaire....................27
Appendix A2 – B ridge Prioritisation Method Questionnaire............................28
Appendix A3 – S upplementary (Moderation of System Outputs)
Questionnaire ...................................................................................................29
Appendix B – Bridge Asset Mangement Systems: Summary of Responses....30
Appendix C – Bridge Prioritisation Methods: Summary of Responses.........43
Appendix D – Bridge Prioritisation Methods: Analysis of Responses..........49
Appendix E – Moderation of System Outputs: Summary of Responses.........57
5 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
SUMMARY
The analysis of the responses to the questionnaires that were submitted by more
than twenty countries has provided an indication of the minimum data sets and
processes that are required to prioritise bridge rehabilitation at the network level.
Although different prioritisation philosophies have been adopted by contributors
there is convergence in the data sets that are required. This is primarily in the
bridge and road inventory items but to a lesser extent in the rated deterioration of
components where there is significant divergence due to condition, damage and
repair priority philosophies that have been adopted by the surveyed countries as
measure of component deterioration. However, regardless of the favoured
philosophy, consistent, current and reliable inventory and condition data are
essential to prioritisation of bridge maintenance interventions to facilitate the
necessary data manipulation, analysis and reporting functionality.
2012R32EN
Introduction
The challenge in bridge management is to ensure that all bridges in a road network
remain fit for their intended purpose over their design life and beyond at minimum
life cycle cost. Issues of affordability in the context of “trade-offs” between
maintenance requirements for other road assets are outside of the scope of this
project. However, the bridge rehabilitation prioritisation process is part of the entire
road infrastructure management task and bridge asset managers must seek a
balance between the proposed performance targets and reasonable funding needs.
Against this background, the PIARC Bridges and Related Structures Technical
Committee identified the need to investigate the current practises in network level
prioritisation of bridge maintenance interventions that have been adopted by a
sample of member countries. The committee considered that a survey of member
countries would be of interest both to countries with developed systems and those
with systems under development. In the case of the first target audience group the
study would provide a means of benchmarking existing systems or as stimulus to
enhancements while countries that were developing systems would have access to
a reservoir of information and contacts they could draw on to build or enhance
similar capabilities.
7 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
In conclusion, there is sufficient evidence from the surveys that many owners have
embarked on multi-criteria analysis as a means of prioritising infrastructure
management actions. Additionally, those who have not developed a multi-criteria
approach consider it to be desirable. Accordingly, it would appear that an investigation
of those authorities that have indicated that they have automated prioritisation
systems would be a logical extension to the sound groundwork conducted by the C11
committee. Indeed, this was the ultimate conclusion made in the “Asset Management
in Relation to Bridge Management” report. However, it should be borne in mind that
the development of infrastructure management systems is dynamic and some of the
authorities that indicated that they did not have a methodology for prioritisation
when surveyed may have developed one in the interim.
8 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
This project has a direct link to the goal of Strategic Theme 4 Quality of Road
infrastructure (2004-2007) namely to “improve the quality of road infrastructure
through efficient management of road assets in line with user’s expectations and road
managers requirements”. The overview further defines the necessity to “implement
management systems capable of integrating all components of infrastructure, based
on indicators reflecting functionalities” to efficiently manage road assets. The need
for further works is expounded in Issue 4.4.2 where one of the listed strategies is to
“continue the work on management of structures particularly in the field of strategic
planning”. The stated output is a “guidebook on strategic planning”.
3. Scope
The goal of this project is to document the systematic processes used by some of the
member countries of PIARC to assess and prioritise bridge management. The project
deliverable will be a guideline designed to assist network managers produce a prioritised
list of investment candidates, within budget constraints and the strategic direction of
the relevant organisation. Initially this will be used to compile the bridge programme
but ultimately may be utilised to derive the wider road network programme.
4. Methodology
Two questionnaires were developed by the project team to elicit details of the Bridge
Management Systems (BMS) and the bridge rehabilitation processes operated by a
sample of PIARC member countries. Initially, the survey was restricted to the home
countries of the project team to ensure that a minimum data set would be obtained.
Additionally, this exercise was designed to detect weaknesses in the questionnaires
and make the necessary improvement before circulating it to a wider group that had
no prior involvement in the project.
Preliminary analysis of the survey results found that BMS derived priorities were
often subject to manual review and change at the programme development stage.
However details of factors that influence these changes were not sought in the
original questionnaires. Pursuant to the completion of the primary surveys the
project team agreed that supplementary information concerning the modification of
BMS derived priorities would be desirable and a further questionnaire was developed
for completion by the project team members.
9 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
The three questionnaires used in this project are listed below and included as
Appendix A:
The responses to the Bridge Asset Management System questionnaire, that is included
as Appendix A1, have been summarised in Appendix B and are discussed below.
5.1. Background
While most BMS include culverts there are examples of more extensive “Structure
Management Systems” in some countries that include other assets, such as tunnels
(Sweden, UK, Denmark, Western Australia), retaining walls (UK), gantries (example
Western Australia, UK, Vienna), high lightning masts (UK) and noise barriers
(Vienna). Several countries have indicated that additional structural asset types will
ultimately be included in their’ structural management system. While, this report
will use BMS to denote all forms of structural management system, only the content
and functionality pertaining to bridges will be analysed.
Predictably, the number of structures included in the BMS varies depending on the
extent of the road network in the respective countries. The extremes range from the
largely rural Northern Territory of Australia that manually manages 200 bridges
while the developed state of Virginia in the USA manages some 20,280 bridges and
culverts in its BMS. Additionally, the extent and sophistication of management
systems is dependant on the size and complexity of network that has to be managed.
In most countries, the principal BMS structure inclusion criterion is defined by
minimum span length however the minimum waterway area is sometimes specified
as a supplementary criterion. In the event that other structure types are included in
the BMS then specific inclusion criteria are specified in that regard.
10 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
5.2. Components
The system will normally be predicated on a detailed asset inventory containing data
pertaining to location, geometry, condition, defects, maintenance activities,
estimates, replacement costs and so on. Optimally, the BMS will be part of an
integrated Road Information System that allows access to traffic, crash, environment,
function and other road asset data to be included in the network analysis deliberations.
By modelling the present and future performance of the infrastructure system,
it enables administrations to identify infrastructure needs. Based on this information,
the system will be able to identify options or alternatives for addressing these needs.
These alternatives will usually be analysed and evaluated on the basis of their
cost-effectiveness using analytical tools and other optimisation techniques.
Constraints on budget and resource allocation are generally incorporated into the
evaluation criteria of the alternatives. Selected alternatives are then included in the
list of projects that will go into the road administrations short- and long-range plans.
The final stages of the process consist of implementation of the projects and
monitoring of the resulting performance of the infrastructure system.
However, as stated previously, the state of development of the BMS and its subsidiary
components in the responding countries varies greatly. All submitted BMS have
some kind of inventory module and condition rating system. However, there is a
significant divergence in condition, damage and repair priority philosophies that
have been adopted by the surveyed countries as measure of component deterioration.
Most keep records on inspections and management activities and the facility to plan
and rank future management activities. Documents such as reports, photographs and
plans are often stored in the systems. Some respondents indicate that they include
knowledge and/or costing databases (Sweden, Croatia, and Hungary) to assist in
planning and estimating management activities and the costs associated with these.
5.3. Outputs
Typically, the outputs from the BMS consist of detailed asset inventory reports and the
known condition of the assets. Defects and maintenance activities are also often
identified. Examples of other outputs mentioned are design and/or assessed load
capacities (UK, Sweden, Queensland and Western Australia). Reports vary from
standard to customised forms that can be produced as paper and/or spreadsheet formats.
11 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
Many BMS produce budget needs based on the condition of the assets. Some of the
submissions indicate that they run different scenarios as basis for decision-making.
In Hungary, for example, the condition of network is determined for different funding
scenarios while Ontario runs alternative program scenarios for varying budgets or
performance targets to determine prioritized investment candidates. In Finland and
Denmark optimal annual budgets are developed based on scenario runs. Network
level reports are produced by the BMS in Norway, Hungary, Sweden and Queensland.
5.4. Benefits
The benefits that can be realised from a BMS are dependant on its state of
development, friendliness and functionality. Furthermore, the degree of alignment
with the owner’s organisational structure, operational procedures, policies and
strategies also influences the efficiencies and benefits that can be realised.
Typically, respondents were of the opinion that the ready accessibility of consistent
and reliable inventory and condition/defect data as a means monitoring performance
(or asset health) and identifying priority investment candidates was a significant
benefit of the BMS. Respondents from countries with more advanced BMS state the
benefits of economic modules that deliver network level efficiencies through
budget-constrained, incremental benefit/cost analyses (Ontario, Switzerland and
Virginia). Efficient and effective management of assets, operational support of
planning and operations and objective decision making were identified as benefits
by many of the respondents as would be expected. A myriad of other benefits were
identified that included effective heavy load management, improved asset
performance, risk reduction and improved communication mechanisms for agencies,
politicians, industry and the public.
2012R32EN
This questionnaire was designed to elicit the primary factors, together with respective
weightings, that are used to derive network priorities and attendant investment
candidates for the maintenance programme. Review of Appendix C shows that more
than eighty (80) different prioritisation factors were nominated by respondents.
These would have been difficult to analyse in a meaningful manner thus they have
been grouped together under the common categories. (The rationale for the grouping
is evident in the tables presented in Appendix C.) Each bridge parameter was given
a value rating of low, medium, or high in the response and these were weighted to
determine the importance factor for the category as shown in table 2. The Importance
Factor is determined by the number of times the bridge parameter was identified in
responses weighed by the value of the rating received (L=1, M=2 and H=3). The sum
of the modified ratings represents the value of the importance factor.
Structural
Conditions 3 3 15 30 40 120 153 (1.0)
Traffic Impacts 6 6 10 20 7 21 47 (0.3)*
Design
Requirements 5 5 13 26 4 12 43 (0.3)
Bridge Function/
Geometrics 13 13 7 14 4 12 39 (0.3)
Financial Aspects 7 7 3 6 8 24 37 (0.2)
Social Aspects 6 6 5 10 1 3 19 (0.1)
Road Impacts 4 4 4 8 2 6 18 (0.1)
Environmental
Impacts 4 4 3 6 0 0 10 (0.1)
The primary data and performance measures used by responding countries for
analysing the bridge network and determining candidates for the bridge rehabilitation
program are described below. These indicate a heavy reliance on condition,
deterioration or other structural factors as would be anticipated in a bridge
engineering system. Traffic impacts are the second most dominant factor which
again is unsurprising however the relatively low weighting of financial considerations
was not expected particularly given the responses to the realised benefits in the
preceding section.
13 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
A review of the factors indicate a high preference for the engineering aspects of a
Bridge Management System. Structural conditions, traffic impacts, design
requirements, bridge function/geometrics and financial aspects are the top
parameters. Of these, traffic impacts and financial aspects are not technical
engineering aspects. Financial and social aspects and road and environmental
impacts were considered less important.
The bias for the engineering aspect of a Bridge Management System is probably
greatly influenced by the background or experience of the individuals that completed
the survey. These individuals concentrated on the important structural conditions of
the bridge in filling out the survey. Since most Bridge Management Systems are
developed within the engineering section or division of an agency, it is logical to
assume that engineering technical aspects would be emphasized.
However, while financial aspects are rated at the bottom of this grouping, it greatly
influences the ability of managers to maintain their inventory. This is covered later
in the report.
Appendix D of the report shows each parameter submitted by each county. The rating
received (L, M, H) is also shown. Table D2 shows a summary of the ratings and Table
D3 the grouping of the parameters into categories agreed to by the project team.
Structural conditions consist of 27 different parameters with the highest rating for
condition ratings and general condition rating. Component condition/results of
inspection and repair urgency also stood out as important factors. The importance
factor for structural condition of 153 (shown in table 1) greatly exceeded any of the
other categories. Traffic impacts (47) and design requirements (43) as well as bridge
functions/geometrics (39) and financial aspects (37) are closely grouped together in
importance factors. Commercial vehicle/heavy traffic volume was the most
important parameter for traffic impact while it was load capacity in design
requirements. The bridge function/geometric category highlighted weights,
clearance and obstacles crossed over. Funding (level and source) and the socio
economic marginal return/cost benefits were the most important parameters to
consider in the financial area.
The last grouping of categories: Social aspects (19), Road impact (18) and
environmental impacts (10) did not have any parameters that stood out. Accident
frequency, road classification, and environment aggressiveness were the main
parameters for these categories.
14 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
Preliminary analysis of the survey responses indicated that the network priorities
derived from the BMS were almost without exception subject to manual review and
moderation. It was considered that this moderation would generally be driven by the
following influences but that these should be tested by a supplementary questionnaire:
• BMS programming and output is not consistent with actual operational practises;
• primary data used to select bridge maintenance program candidates is not current
or reliable;
• need to package structures in jobs on a geographical and/or bridge material basis
to increase delivery efficiency through minimisation of establishment overheads;
• need to interface with other road infrastructure systems and their’ priorities to
package works that realise savings and produce greater return in terms of improved
service to users;
• cross-district or cross-region packaging to realise organisational or economic
efficiencies;
• priorities within pre-defined intervention envelopes may be re-ordered in accordance
with operational or local strategic imperatives;
• priorities re-ordered in the aftermath of a natural disaster such as flooding, fire,
earthquake or avalanche;
• priorities re-ordered in the aftermath of severe accident damage or collapse;
• structures that do not meet the target intervention levels may also be considered on
the basis of an approved business case arguing over-riding strategic or operational
imperatives. In this event it is essential that the proposal details how structures
displaced from the programme can be safely managed.
Pursuant to the completion of the primary surveys the project team agreed that
supplementary information concerning the modification of BMS derived priorities
would be desirable and a further questionnaire entitled “Moderation of System
Derived Priorities” was developed for completion by the project team members. The
pro-forma is included as Appendix A3 and the results are shown in table 2, page 16,
and discussed below. This questionnaire listed the primary moderation factors agreed
by the project team that are listed below and was designed to elicit the frequency that
they were used in the moderation processes adopted in the member countries.
15 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
b) Budgetary limits
Variations in the volume and rate of the economic growth achieved by individual
regions may trigger differences in the demand for road transport of goods. Certain
groups representing specific economic interests have frequently showed willingness
to fund construction or modernization of road sections directly related with their
activities and their contribution to such construction and modernization projects can
yield considerable additional resources. Thus, previously earmarked funds can be
released and re-assigned to other important projects.
A national initiative such as increased axle masses or the access of innovative heavy
vehicle configurations may necessitate a change of local, bridge maintenance and
16 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
The development and maintenance of the public road network has regularly become
a key subject of pre-election campaigns. However, the re-assignment of the available
funds, to meet promises of a political nature can compromise the short and long-term
bridge maintenance program.
Importance Factor
Weighted Score
Weighted Score
Weighted Score
Weighted Score
Weighted Score
(normalised)
Priority moderation
Score
Score
Score
Score
Score
factors
Aspects of operation 37
and maintenance of the 0 0 4 8 1 3 4 16 2 10
entire road network (0.8)
46
Budgetary limits 0 0 0 0 3 9 3 12 5 25
(1.0)
Recognition of 24
individual or group
interest with increase in 1 1 5 10 4 12 1 4 0 0 (0.6)
funding *
Conflict of local and 21
national interest 4 4 5 10 1 3 1 4 0 0
(0.5)
Expectations of groups 23
representing political 2 2 5 10 3 9 1 4 0 0
or other interests (0.5)
* Sample calculation: Importance Factor = 1 x 1 + 5 x 2 + 4 x 3 + 1 x 4 + 0 x 5 = 27 ;
Normalised = 27 / 46 = 0.6
17 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
The priority moderation factors selected for the survey appear to be appropriate
given that all are reasonably well represented in the results. It is clear that insufficient
budget allocations to address the system derived needs (1.0) and issues of affordability
in the context of “trade-offs” between maintenance requirements for other road
assets (0.8) are the primary change mechanisms as one would probably expect.
However, the normalized scores for the other moderation factors that range between
0.5 and 0.6 show that they are also significant mechanisms for changes to BMS
derived priorities.
It is interesting to note that the financial aspects of the priority moderation factor
clearly stands out as the leading factor when it was not considered as the major factor
in the initial survey of bridge parameters.
Within the context of the prioritisation process, the bridge rehabilitation intervention
standards in some instances may represent the minimum duty of care standard. If
funding is insufficient to meet the entire network needs then the unfunded structures
must be proactively managed to ensure the safety of road users and to mitigate the
road network authority’s duty of care and non-feasance liability. Typically structure
specific management plans can be developed and implemented as a means of
demonstrating responsible management of a network within available funding levels.
The responsible authority has a number of options within this context as itemised
below. It is essential that the condition of the structure and these plans are
continuously reviewed pending the required maintenance treatment being effected:
The findings of the various surveys together with the accumulated experience of the
project team members can best be expressed in a set of basic guidelines for the
prioritisation of bridge rehabilitation works. Although, as the surveys show, this is a
complex and iterative process it is hoped that the following sections will provide a
18 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
useful frame of reference for those administrations with advanced BMS and provide
some assistance to those administrations with BMS under development.
9.1. Overview
2012R32EN
• performance of the assets and inspection and maintenance standards are continuously
monitored through the inspection regime.
The responses to the questionnaires indicate the minimum framework required for
the development of a BMS capable of conducting network level prioritisation. The
basic outlines of the fundamental components are as follows.
Network level prioritisation is dependant on current, consistent and reliable data that
is delivered by a number of subsidiary processes. Accordingly, it is essential that
both the prioritisation system and the subsidiary systems are underpinned by
appropriate strategies, policies, accountabilities, methodologies, training
programmes and accreditation schemes. The details are outside the scope of this
report but a comprehensive, mature and robust bridge management system would
require the following support tools:
Table B2 in Appendix B documents the components that comprise the BMS in the
various countries that responded to the questionnaires. It can be seen that there is
convergence with respect to the primary components but the extent and detail of
coverage is dependant on the size and complexity of the network and the maturity of
the road authority’s network management systems. It is clear however that an
20 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
It is also apparent that the prioritisation task will generally involve consideration of
the various operational factors that have been discussed in section 1.8 and are
generally external to the BMS such as the strategic importance of the route, traffic
and accident data. Accordingly, the developer must consider the means of populating
the prioritisation tool through manual or data transfer interfaces. Alternatively, and
preferably, the BMS can be developed as an integrated module of the Roads
Information Management System.
• inventory Module with sufficient granularity to define the assets such that the
desired system functionality is achievable. However, consideration will have to
given to the cost of populating and maintaining inventory data when defining the
inventory structure and content as the labour costs for programming, population
and maintenance can be significant;
• inspection Module that is the repository of all inspection data including condition
or defect rating at the bridge and component level. The module would generally
include an inspection status and programming tool;
• maintenance Management Module that provides the mechanism for assigning
maintenance activities and estimated repair costs to defects identified by the
inspection regime. The module should also be able to record the actual costs incurred
in effecting the repairs and remove the associated defects from the structure when
the works are completed. (This is essential when current network needs have to be
determined);
• optimisation Module that includes predictive condition and economic modelling
to determine current and future network funding needs and/or to ensure that the
best network return is achieved for the available budget. Typically, this will be an
incremental cost benefit analysis capability;
• prioritisation Module that is described in the section 1.8; and
• interfaces with the Road Information Management System.
21 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
Different types of inspections are carried out during the life of a bridge and the BMS
should support all of these however prioritisation decisions are generally predicated
on the detailed and systematic condition/defect rating of components These inspections
are generally conducted at approximately five year intervals, however, this varies
between jurisdictions and the interval may also vary depending on the last rated
condition and/or structure type. Usually this inspection is a thorough visual inspection
of the whole bridge conducted within close proximity of individual components. It
may include inspection of cables, under-water components and/or electrical and
mechanical equipment. Given that crucial network management decisions are
contingent on the data collected by this level of inspection it is imperative that data
quality is ensured through the development of systematic inspection processes with
the appropriate manuals, training and accreditation structure.
2012R32EN
It is essential that the document is allowed to evolve with stakeholder feedback and
performance monitoring to eliminate sub-optimal treatments and add new or
improved treatments.
10. PROCESSES
The allocated funds for bridges in operation are normally divided into two major
programs:
2012R32EN
The various stages for identifying candidates and prioritising needs for the works
programmes can be itemised as follows:
2012R32EN
2012R32EN
11. Conclusions
13. Glossary
Capital Works – Works that improve the functionality of the structure such as
replacement, strengthening or modifications.
26 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
Steward – The owner’s delegate with responsibility for the bridge rehabilitation
programme.
C11 – PIARC Technical Committee 2004-2007 Road Bridges and Related Structures.
27 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
appendices
COUNTRY
Bridge Asset Management System (BAMS)
BACKGROUND
Should cover:
• Why developed?
• What developed?
• Size of bridge inventory?
COMPONENTS
Should cover:
• What is included in system?
• How is the system set up?
OUTPUTS
Should cover:
• What information is in system that can be used?
BENEFITS
Should cover:
• What are the benefits/goals of the system?
Note: Number of bullets in each category show for draft purposes only. Individual
systems may have more or less.
28 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
Appendix A2 – B
ridge Prioritisation Method
Questionnaire
COUNTRY
Bridge Prioritisation Method
Note: Number of bullets in each category show for draft purposes only. Individual
systems may have more or less.
29 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
Appendix A3 – S
upplementary (Moderation of System
Outputs) Questionnaire
How intensively can the five factors listed below influence the result produced by the
management system?
1. absolutely not;
2. slightly perceivably, infrequently, in case of a few projects;
3. regularly, in case of more projects but not too significantly;
4. regularly and significantly;
5. predominantly, almost in every case.
Factors 1 2 3 4 5
Aspects of operation and maintenance of the road network
(Competing priorities from other assets and effects of other
A maintenance or capital network strategies. The latter could be
strategic rehabilitation of a route that promotes assets on that route
over higher bridge priorities on other routes.)
Budgetary limits
(Optimising works within a constrained budget. Re-programming on
B
basis of whole of life costs when maintenance deferral is required
due to funding constraints.)
Appreciation of individual or group interest; increase of the
possible/available funds
(Contributions made to road authority by private, state or federal
C bodies to conduct works to maintain access levels or improve access
levels. This allows expenditure to be redirected in some instances.
Bridge strengthening for excess mass movements or perhaps federal
funding for HML initiative. )
Conflict of local and national interests
(Competing regional or federal strategies. Business case for
D accelerated maintenance to assist regional development or local
industry at expense of statewide priorities. Need to accelerate works
on interstate routes (not national highway) for HML.)
Expectations of groups representing political or other interests
E (The effects of delivering projects defined in a political manifesto or
other political initiative on the needs defined programme.)
TABLE B1 – BACKGROUND
30
2012R32EN
SRA 14,500 bridges, BaTMan is web-based, 7 regions manage national Bridge & network level Plan-opt peripheral for
19 tunnels. in-house BMS for SRA roads. decision making tool short long term planning.
Sweden (Swedish Road & long term planning.
Administration) Also used
by Rail & councils.
Bridge & culvert inventory VDOT used BMS is part of transition
Virginia records for 12,640 bridges AASHTO-PONTIS to needs-based budgeting.
(USA) & 7,640 culverts >= 36 ft 2 (COTS package) since
openings. 1995.
Appendix B – B
985 bridges with span>5m HrMos based on DANBRO St&-alone PC based Basic inventory &
total area 520,000m 2. introduced in 1997 to system with data exchange condition data collection
Croatia
provide budgeting & by external disks. 1989-1991.
prioritisation functionality.
Developed by “Pontex Integrates inventory,
Ltd” to manage operation condition, defects,
& maintenance of all structural assessment but
Czech
bridges on all types of financial optimisation
road. aims at higher level of
bridges.
1450 bridges & tunnels. DANBRO started in 1987 Initiated to provide St&-alone PC based DANBRO 2 has Windows
34 major structures. by Danish Road budgeting & prioritisation system with data exchange OS & is client server based
Denmark
Directorate & “Ramboll”. functionality to by external disks. with internet updates.
supplement inventories.
H-BMS manages the Primary network Prioritises investment Relational database for all
operation & maintenance management tool. candidates through bridge data.
Hungary of 6000 bridges on the optimisation of available
National road network funding.
Bridges with span > 2 m.
Summary of Responses
17,500 bridges with data Norwegian Public Roads NPRA responsible for System comprises
for inventory, inspection, Administration initiated national & local documentation to underpin
condition & maintenance BMS named BRUTUS in authorities’ bridges. inspection & inventory
Norway
activity, costs & 1991 to relace existing processes.
procedures. bridge inventory.
Bridge has span > 2.5 m.
7560 bridges & major Defects based BMS SANRAL formed 1998 to STRUMAN integrated
culverts total including “STRUMAN” developed in manage national roads. with the “Intelligent
concessions (6770 1998 to replace condition 15,000km, Transport Information
excluding concessions) based system. 150-190,000 AADT, System”.
ridge Asset Mangement Systems:
South
Bridge defined as span (average 3,500).
Africa
> 6m or L >= 20 m or
Opening> 36 m 2. Major
culverts have span > 2.1 m
or Opening > 5 m 2.
PRIORITISATION OF BRIDGE REHABILITATION WORKS
TABLE B1 – BACKGROUND
31
2012R32EN
Manages the operation & BMS is Sub-system of Created a corporate Addresses risk of Assists operational Provides performance
maintenance of 2,800 Road Information System inventory. overloading defective mangers develop bridge measures that are accepted
bridges & 3,600 major ARMIS. structures. maintenance & a s a means of allocating
Queensland
culverts. replacement programmes. budget.
Australia
Includes structures with
Openings>1.8 m &
Waterway Area > 3m 2.
3000 structures (bridges, Development of BMS in Currently only a bridge Inventory & Bridge
tunnels, gantries) progress. Will be register database holding Maintenance Practices
Western Structures with opening > sub-system of IRIS inventory & basic Manuals Implemented.
Australia 3 m. Integrated Road management information
Information System. on state & local
government bridges.
Manages 200 mainly short Independent bridge
Northern span modern PSC bridges. inventory with overall
Territory Includes road, pedestrian bridge condition rating
Australia & cycle bridges with a maintained.
span > 4 m.
Structure span > 3 m. OBMS initiated in 1999 & Client/server using Oracle
Ontario inventory & inspection database. Data checkout &
Canada modules released in June checking from central
2000. server to field units.
1650 “objects” in City of “BAUT” initiated 1999 for
Vienna data base. Austrian Highway
Vienna operating association to
Austria manage bridges, tunnels,
walls, gantries & noise
barriers.
“Network Quality Index SAMOA development Index of Network Quality
Development” initiated in initiated in-house in 1986 IQR from algorithm using
2000 based on data from to collect inspection data distribution of ranges of
Autostrade
“STONE” program Uses on road structures & in IQR.
Italy
“maximum ratings” that 1996 elaboration for the
indicate urgency of repair. prioritisation of
interventions.
KUBA development Data used to develop Part of overarching road KUBA 4 release in 2007.
initiated in-house in 1992 policies, optimal system MISTRA that is
Switzerland to collect inspection & intervention for each also under development.
intervention data on road structure & load rating.
structures.
18,000 bridges & culverts BMS initiated in 1986 to Object to provide a reliable Based on thorough
entered . replace the Bridge tool to determine funding inspection & condition
Finland Register. needs for maintenance, evaluation.
rehab & replacement &
project planning.
PRIORITISATION OF BRIDGE REHABILITATION WORKS
TABLE B1 – BACKGROUND
32
2012R32EN
Ultimately will hold BMS used to enact Sound asset management Still under trial.
10,000 national highway maintenance plans that requires data.
bridges. reduce life-cycle costs &
Japan
smooth future bridge
reconstruction
programmes.
Transit NZ operates a A national Bridge Asset Operate Bridge
largely manual system Management Plan outlines Descriptive Inventory
comprising policies, the staged development of (BDI) & a Bridge
New
specifications & a system. Structural Inventory (BSI)
Zealand
guidelines. Used to engage databases.
external suppliers & their
systems.
Holds inventory records A BMS has been in use Highways Agency (HA) / SMIS used for scheduling
for 9000 bridges & large since 1984 but current DoT is responsible for inspections / recording
culverts, 1500 small Structures Management & operating, maintaining, defects / planning /
United
culverts, 1705 retaining Information System improving & managing the prioritising / managing
Kingdom
walls, 11 tunnels, 2700 (SMIS) developed on motorway & trunk road maintenance.
gantries, 600 high lighting Oracle by HA & launched network.
masts. (> 20 m). in 2000.
Contains inventory & Ministry of Works has Part of MoW transition to
inspection records for used Torroja Ingenieria needs based budgeting for
16,246 bridges & 973 (COTS) Sistema de maintenance & operations.
Spain
culverts. (> 3 m opening). Gestion de Puentes (SGP)
bridge management
modules since 2000.
Ministry of Danish system bought in Bridge inventory where Based on visual inspection At this moment the system Provides performance
Communications and 1993. Provide a tool to 32 State Bridge Offices evaluation. is having a Windows based measures that are accepted
Transports uses SIPUMEX determine funding needs manage about upgrade. as a means of allocating
Mexico (Spanish Initials for for maintenance and 7300 Federal Highway budget.
Mexican Bridge System). project planning. bridges. Neither State nor
Municipal bridges are
included.
PRIORITISATION OF BRIDGE REHABILITATION WORKS
TABLE B2 – COMPONENTS
33
2012R32EN
Overall Management Bridge management Bridge databases- Knowledge databases Processing
strategy- rule sets. activities- processing of inventories- admin, -deterioration curves, unit modules-inspection, project
databases. maintenance, design, rates, technical solutions, plans, procurement,
Sweden
trafficability, damage, measuring methods. verification, result analysis,
planned actions, performed load classifications.
actions, traffic flow.
Inspection Module- Project Planning Module Programming Preservation module-cost & Results module - graphical Gateway Module-
maintain inventory & (under development) Module-develop network deterioration modelling to scenario results of cost & Interfacing with other
Virginia inspection data. Analysis of structure standards & improvements optimise investment & performance. systems.
(USA) performance under different & run multi-year budget safety. Software modified
treatment scenarios. Used simulations/scenarios. by VDOT.
for project planning.
Inventory Module- location, Principal Inspections Ranking Module - Priority Optimisation Module - Price Book Module-
admin, geometry, technical Module- condition ratings, listing based on condition & Selects optimum plans for Learning (tenders entered)
properties. damage descriptions, call AADT (automatic & each bridge based on schedule of rates for
higher level inspections, manual). applied network budget creating BoQ for estimating
Croatia
evaluation of routine constraint. Technical & cost of plans.
maintenance, photos. financial long-term strategy
alternatives have to be
developed for each bridge.
Inventory Module- location, Principal Inspections Routine Maintenance Optimisation Module - Price Book Module- Bridge Map Module- Map
admin, geometry, technical Module- condition ratings, Module- Maintains requests Selects optimum plans for Learning (tenders entered) based queries & reports.
properties, technical report damage descriptions, call & performance of activities each bridge based on schedule of rates for
archive. for higher level inspections, & produces BofQ’s. applied network budget creating BoQ for estimating
Denmark
evaluation of routine constraint. Technical & cost of plans.
maintenance, photos. financial long-term strategy
alternatives have to be
developed for each bridge.
2. Optimisation for
maximum benefit.
TABLE B2 – COMPONENTS
34
2012R32EN
Inventory Module - Inspection Module - Maintenance Module - Cost Module - Record of Administration Module -
National overview of Inspection cycle Routine maintenance & construction, replacement, Authorisations & access.
dimensions & management & costs, priority rehabilitation scheduled maintenance
characteristics-owners, id, results, material scheduled manually costs. Residual values
names, location, traffic investigations. Ratings for considering damage & calculated.
Norway limits, load capacity. consequence & degree of condition indices. Works
Storage & manipulation of damage & member orders can be produced.
photos & plans. Dynamic significance determine
interface with Road Data Element Condition Index.
Bank. Cause of damage recorded.
Preliminary repair costs.
Inventory - basic Inspection Module -Degree, Prioritisation, Budget & Inspector training & User access to nationwide
dimensions & extent & relevancy of Maintenance Modules accreditation. infrastructure inventory &
South
characteristics. defects. Bridge Condition Exposure condition.
Africa
Index calculated from
inspection data.
Bridge Information System Inspection & Condition Inspector Training & Load capacity assessment & Specifications & Prioritisation Methodology.
- Repository of all bridge Rating policy & procedures Accreditation. Heavy Load Management. Maintenance Manual
data in various modules. covered in Bridge Management of
Structure, Design, Inspection Manual. Sub-Standard Bridges.
Queensland Inspection, Maintenance,
Australia Prioritisation, Image
Browser, Excess Mass,
Historical Report Archives.
All modules have querying
& reporting functions.
Inventory supplemented Inspection Management - Heavy Load Management- Maintenance Management Bridge Maintenance Asset Valuation.
with ID’s & hydraulic data. Management of data derived policies, procedures & -programming, scope, cost, Manuals.
Western
from existing processes & records. optimisation, status,
Australia
manuals. Inspector financial tracking.
accreditation & backlog.
Northern Inventory with Overall
Territory Condition Rating.
Australia
Inventory- location, type, Inspection- Element based Analysis Module- Project & Documents Module -
age, span, components. condition ratings. network level. Incremental Designed to store photos,
Maintenance work, benefit cost analysis to documents & plans.
Ontario performance deficiencies & determine optimal project & Currently only photos.
Canada capital work network investment over a
recommendations recorded 60 y period. 1-5 & 6-10 y
in database. Inspections programmes provided.
every 2 years.
Data collection - inspection Deterioration & Budget Reporting - Detailed reports Load Rating- compares load Administrative
& intervention data at Prediction Scenarios- on any module. effect of abnormal loads Components.
structure & element level. Intervention & associated with design load effects to
unit costs are defined for support permit issue.
Switzerland
condition states of each
element. Project costs can
computed at any year &
structure BCRs calculated.
Bridge Register - data, HIBRIS-Network Level Hanke-Siha Repair & Reference Bridges-
photos, reports, parameters, BMS Long term module to reconstruction programmes Representative sample of
feedback & users. find optimal network for 6 years at project level. bridge types & locations
condition. Short-term that are frequently
module to determine how to monitored to map
Finland move current stock to performance for
optimal level at project deterioration models.
level. Includes a life-cycle
module called Bridge Life.
Markov chain condition
predictions used.
Interaction - bridge specs, Deterioration Models. Life Cycle evaluation Soundness Evaluation Standard repair method
Japan traffic volumes, inspection model. model (?? Capacity??). selection & project cost
results, repair histories. estimation model.
Inventory Module: Records Condition Module: Records Assessment Module: Works Module: Risk based Asset Valuation: Nett Future Modules: Whole Life
completed for all structures current & historic Assessed loading capacities. approach, called “Value depreciated replacement Costing, Condition
down to component level. component defects. Management”, to costs from age, type & Assessment and Future
Also holds photographs & Extent A-E, Severity 1-5. prioritising & scheduling dimensions of structures. Performance Assessment.
drawings. (A1 defect free, E5 maintenance or capital
United
non-functional). works programmes.
Kingdom
Activity Scheduler:
Progress monitoring.
Performance Indicators
PRIORITISATION OF BRIDGE REHABILITATION WORKS
(recent): Condition,
availability & Reliability.
TABLE B2 – COMPONENTS
36
2012R32EN
Inventory Module: Records Inspection Module: Records Management Module: Results Module: Reports on
completed for all structures. completed for 5,000 Classifies structures to predicted network cost &
Spain
structures. (30%). determine those in worst associated performance.
condition.
Inventory Module - Inspection Module – Visual Maintenance Module - Cost Module - Record of Administration Module - Bridge Map Module-
National overview of Inspection based module, Routine maintenance & construction, replacement, Authorisations & access Georreferenced Map based
dimensions & photos, rating based on priority rehabilitation scheduled maintenance depending on level of the queries & reports.
characteristics: id number, bridge engineer experience. scheduled manually costs. end user.
name, location, type Ratings for degree of considering damage &
structure, year of damage & member condition indices. Works
Mexico
construction, year of significance determine orders can be produced.
maintenance, Element Condition Index.
georreferenced coordinates, Cause of damage recorded.
rating form 0 to 5. Storage Preliminary repair costs.
and manipulation of photos
and plans.
PRIORITISATION OF BRIDGE REHABILITATION WORKS
TABLE B3 – OUTPUTS
37
Asset inventory. Physical & Temporal record Load capacity. Management Cost optimised Priced BofQ for CBA @ network Inspection & Information for
2012R32EN
Sweden functional of defect/ plan/activities. structure plans. each structure. level. performance operational
condition. damage. follow-ups. contractors.
Asset Inventory. Condition Performance Prioritised list
database measures of candidates
compiled by - “general based on CBA.
Virginia accredited condition”,
(USA) inspectors. “sufficiency
ratings”
“Health
Indices”.
Asset inventory. Vertical Statistical Temporal Principal Budget need Condition rating Maintenance Cost estimates
Clearances. analysis. records of inspection overview. statistics. work orders. for structure
Croatia
inspection & reports (6y plans.
maintenance. intervals).
Standard or
customised
reports from the
various modules
- inventory,
Czech condition,
capacity,
inspection,
maintenance
estimates
& so on.
Inventory Vertical Load capacities. Statistical Temporal 10 y budget List of Economic Maintenance Approved B of Q’s & Unit rate
reports. clearances. analysis records of needs. candidate scenarios for work orders. maintenance estimate records.
reporting. inspection, schemes. budget profiles. product lists. production.
Denmark
defects,
condition &
maintenance.
Detailed Optimisation Customised & Condition of Programme of
analysis of each module delivers standard query network for works for best
bridge. project needs, tools. different cost benefit for
Hungary
economic funding available
indicators & scenarios. budget.
guides policies.
Detailed Bridge Backlog Reporting Inspection & State of the Consistent
inventory. Condition estimates & options. maintenance bridge network bridge ratings
Indices. repair budgets. history & reports. using accredited
Norway
projected inspectors &
budgets. documented
methodology.
Detailed Priority Index Bridge repair Routine Repair projects Emergency Maintenance Projected
South Africa Inventory. for all estimates. maintenance & budgets. repairs history. budgets.
structures. activities. identified.
Detailed Current Defects & Critical Defensible Consistent & Development of State of network
inventory. condition maintenance structures programmes practical access maps. reports for
Queensland documented activities identified by from quantification senior
PRIORITISATION OF BRIDGE REHABILITATION WORKS
Detailed Current Defects & Work/ Defensible Load ratings Bridge needs
2012R32EN
inventory. condition maintenance expenditure maintenance that support the aligned with
Western
documented activities forecasts. programmes. heavy vehicle programme
Australia
consistently. identified. permit system. management
approach.
Inventory with Priorities Defensible
Northern
Overall determined maintenance
Territory
Condition from inventory programmes.
Australia
Rating. & ratings.
Inventory lists. Inspection Cost beneficial Scenario runs
reports & projects for year with varying
Ontario summaries. 1-5 & 6-10 budgets or BCI
Canada Bridge programmes. targets with
Condition Index corresponding
reports. programmes.
Vienna Inventory,
Austria queries.
Generally the
maintenance
budget is
applied to
Autostrade
derive the avg
Italy
programme of
works &
acceptable
target ratings.
Generally Inventory, Medium & long Working
reports from the inspections, term financial program with
report module. interventions & needs. prioritised list
Switzerland
costs. of interventions
for a given
budget.
HIBRIS- Hanke-Siha- 68 standard
optimised Repair & reports in
annual budgets reconstruction Bridge Register
based on programmes for module- basic
scenario runs. 6 years at data,
Finland project level. functionality,
Reports on inspection,
efficiency & condition,
repair follow-up repair, load
available. carrying
capacity.
Bridge specs, Present state Repair & Estimates of
traffic volumes, & future strengthening necessary repair
inspection soundness. programmes works.
Japan
results, repair based on
histories. soundness
evaluation.
PRIORITISATION OF BRIDGE REHABILITATION WORKS
TABLE B3 – OUTPUTS
39
From BDI
2012R32EN
- Single sheet
New Zealand summaries or
computer
spreadsheets.
Detailed Known Design & Standard & Value
Inventory. condition from assessed load ad-hoc management of
United
systematic capacities. reporting intervention
Kingdom
inspection capability. works.
programme.
Detailed Known Performance Prioritised list
inventory. condition of ratings: General of structures
structures using Condition & determined by
Spain systematic Bridge Benefit Cost
methodology & Importance analysis.
accredited Index.
inspectors.
Detailed Known Performance Prioritised list Inspection & State of the Consistent Approved State of network
inventory. condition of ratings: General of structures maintenance bridge network bridge ratings maintenance reports for
structures using Condition & determined by history & reports. using accredited product lists. senior
Mexico visual Bridge Benefit Cost projected inspectors & management.
inspections by Importance analysis. budgets. documented
accredited Index. methodology.
inspectors.
PRIORITISATION OF BRIDGE REHABILITATION WORKS
TABLE B4 – BENEFITS
40
2012R32EN
Asset Physical & Temporal Load capacity. Management Cost optimised Priced BofQ CBA @ Inspection & Information
Sweden inventory. functional record of plan/activities. structure for each network level. performance for operational
condition. defect/damage. plans. structure. follow-ups. contractors.
Asset Vertical Statistical Temporal Principal Budget need Condition Maintenance Cost estimates
inventory. Clearances. analysis. records of inspection overview. rating work orders. for structure
Croatia
inspection & reports (6y statistics. plans.
maintenance. intervals).
Standard or
customised
reports from
the various
modules
- inventory,
Czech
condition,
capacity,
inspection,
maintenance
estimates
& so on.
Inventory Vertical Load Statistical Temporal 10 y budget List of Economic Maintenance Approved B of Q’s & Unit rate
reports. clearances. capacities. analysis records of needs. candidate scenarios for work orders. maintenance estimate records.
reporting. inspection, schemes. budget product lists. production.
Denmark
defects, profiles.
condition &
maintenance.
Detailed Priority Index Bridge repair Routine Repair projects Emergency Maintenance Projected
South Africa Inventory. for all estimates. maintenance & budgets. repairs history. budgets.
structures. activities. identified.
TABLE B4 – BENEFITS
41
2012R32EN
Detailed Current Defects & Critical Defensible Consistent & Development State of
inventory. condition maintenance structures programmes practical of access network
Queensland documented activities identified by from quantification maps. reports for
Australia consistently. identified. prioritisation non-feasance of operational senior
tool. & risk load capacity. management.
perspectives.
Detailed Current Defects & Work/ Defensible Load ratings Bridge needs
inventory. condition maintenance expenditure maintenance that support aligned with
Western
documented activities forecasts. programmes. the heavy programme
Australia
consistently. identified. vehicle permit management
system. approach.
Vienna Inventory,
Austria queries.
Generally the
maintenance
budget is
applied to
Autostrade
derive the avg
Italy
programme of
works &
acceptable
target ratings.
From BDI
- Single sheet
New Zealand summaries or
computer
spreadsheets.
Overview of Ready access Overview of Mininimise Constrained Management All Federal MEXICO. Overview of Ready access Overview of Mininimise
inventory and to bridge data repair and safety risks budget and road and inventory and to bridge data repair and safety risks
condition. inside the budget needs and economic scenarios. documentation highway condition. inside the budget needs and economic
Mexico Ministry and for planing. shocks. of maintenance bridge Ministry and for planing. shocks.
its 32 Bridge works. structures its 32 Bridge
Offices in all covered. Offices in all
country. country.
PRIORITISATION OF BRIDGE REHABILITATION WORKS
TABLE C1 – BRIDGE RATING INDICES AND ALGORITHMS
43
2012R32EN
Priority ranking is determined
by relative socio-economic
benefits and the marginal
return. (Cost benefit analysis,
Sweden
bridge criticality, road
hierarchy, detour length, load
capacity/demand, condition of
critical components).
General Condition Rating Sufficiency Rating (SR) Condition ratings for Health Index 0-100% (best)
(GCR) 0(failed) - 9 for deck, 0(failed) - 100 for FHWA “commonly recognised calculated at element and
Appendix C – B
superstructure, substructure & funding allocations. < 80 structural elements” bridge level.
Virginia
channel. rehabilitation, < 50 1-5(worst).
(USA)
replacements. Includes load
capacity/demand, functional
obsolescence/level of service.
Bridge condition rating 0-5 Repair strategies are only
(worst) based on engineering developed for critical
judgement within available structures (important bridges
budget. and those in very poor
condition) due to lack of
Croatia
of Responses
deterioration of all elements. and considers load capacity, dependent on traffic, located.
Poland
The GCR is the lowest rating road safety, allowable speed, international corridors,
for deck, girders, abutments/ clearance adequacy, approach strategic value of road. High,
piers as a mathematical mean. alignment. medium and low ratings.
TABLE C1 – BRIDGE RATING INDICES AND ALGORITHMS
45
2012R32EN
General Condition Rating 1-5 Element ratings collected every Utilisation value under review.
(Worst) - Measure of five years. Condition and
Switzerland
deterioration and loss of value damage process are recorded.
(restoration cost).
Indicator for preservation & Project level (structure) Rehabilitation & Life Cycle Action Profiles
functionality -Sum of Damage indicator of repair needs - Reconstruction Index (UTI) - (LCAP) - Scenario analysis
Points (VPS) based on Repair Index (KTI) based on functional deficiencies at tool.
Finland
condition, damage class, repair condition, damage class and bridge level.
urgency for individual bridges repair urgency.
or collectively.
Degree of Damage A-E (worst) Counter-measures - Seven Bridge Soundness calculated
rated for each component. categories rated for each for bridge based on the above.
Japan
component. Includes elevation
to detailed investigation.
Available funding and Any components in CS 3,4,5 Strong justification for Seismic screening. Scour screening.
subjective condition ratings. are high priority. preventative maintenance is
No formal condition rating high priority.
system. Factors used are
Condition (C), Importance of
New Zealand
Component (R), Importance of
Bridge (I), Cost of delaying
Maintenance (E) Urgency = C
x R x I x E < 15 low, 15-50
medium, > 50 high priority.
Condition, availability and
reliability indicators recently
United Kingdom
developed will be used to assist
in structure management.
General Condition Rating Road Weight- dependent on Bridge Weight (BW) = Structure Weight - function of Historical Value - subjective
(MCE)= 0-5 (perfect to failed) traffic volume and % trucks. Structure Weight X Historical replacement cost 0.71, 1, 1.41. rating by manager 0.71, 1, 1.41.
for superstructure, Value 0.5-2.0.
Spain substructure, accesses &
equipments “elements” at each
inspection. MC bridge (MCB)
is the summation of elements.
General Condition Rating 1-5 Element ratings collected every Bridge Priority Index If bridge needs further
(Worst) - Measure of two years. Condition and calculated from one or more evaluation due to importance
deterioration. damage process are recorded. elements graded 3 or more: of either the bridge or the
Mexico grade 3, repair in no more than damage, special detailed
5 years; grade 4, repair in no inspections are programmed.
more than 2 years; grade 5,
repair immediately.
PRIORITISATION OF BRIDGE REHABILITATION WORKS
TABLE C2 – BRIDGE RATING METHODOLOGY
46
2012R32EN
Object (bridge level) planning module Network planning module determines
evaluates effect of maintenance deferral on bridges with the best economic return for
a bridge for various strategies and identifies various maintenance deferral strategies.
Sweden
the strategy with the best return. This
module can also handle improvements but
currently not utilised.
Prioritisation of intervention works is Level of maintenance determined from Element condition, deterioration models, Health Index is being evaluated for use in
ultimately determined manually by GCR & SR. Varies from preventative & cost/benefit analysis to rank priorities in prioritisation. It represents the fractional
considering the values of the following ordinary maintenance to replacement. PONTIS. distribution of condition states for
Virginia
indices. Preventative/Ordinary GCR 9-7, SR individual elements and collectively for the
(USA)
80-100%; Repair/Rehabilitation GCR 6-5, structure.
SR 50-80%; Rehabilitation/Replacement
GCR < 4, SR < 50%
Manual determination of priorities based on
Croatia bridge condition rating in conjunction with
AADT.
NPV’s calculated at optimum and five year
deferral. Then 1-4 years deferrals are
interpolated for say three scenarios for each
bridge. The lowest NPV is sorted for each
Denmark bridge. The optimisation algorithm finds the
strategy for each bridge with the lowest
MPV in a five-year period. That is, the
specific remedial action for a bridge with
the lowest economic consequences.
Level and urgency of maintenance defined Optimisation module of PONTIS/H can
by condition calculate total needs or show condition
Hungary outcome for investment scenarios. Current
approach is to dynamically maintain current
network condition.
Engineering judgement based on the BCIs
determined from the inspection programme
Norway and the results of special investigations.
These are sometimes supplemented with
Cost Benefit Analyses.
Manual development of program based on
PI’s into individual bridge projects or
South Africa
packages of bridges projects within budget
allocation.
Risk score intervention thresholds for Structure Management Plans have to be The maintenance strategy should be Gross allocations will be made on the basis
rehabilitation are stipulated in the State developed for any structure that exceeds the consistent across district boundaries. of the analysis but there is scope for
Queensland
Wide Planning Strategy. thresholds pending repairs being conducted. moderation of projects at the district level
Australia
provided that acceptable business cases are
submitted.
PRIORITISATION OF BRIDGE REHABILITATION WORKS
TABLE C2 – BRIDGE RATING METHODOLOGY
47
2012R32EN
Engineering judgement with reference to Investment is predicated on a whole of life
bridge inspection results, road and bridge costing approach.
Western
inventories and hierarchies, traffic, load
Australia
capacity and current works programmes. A
system “overview” tool is being planned.
Independent road and bridge inventories are
maintained including an overall bridge
Northern
condition rating. Given the small number of
Territory
relatively modern bridges with few defects,
Australia
prioritisation is straightforward and by
exception.
The proposed prioritisation system will be Selected bridges are analysed for 1-5 and Incremental Benefit Cost ratio method is
Ontario designed to assist network managers assign 6-10 year programs for each bridge and only used to select projects for available budget.
Canada priorities and will not supplant sound those projects that return a positive benefit (Bridges/projects ranked by IBC ratio.
engineering judgement. are considered in the network analysis.
Condition ratings are considered in
Vienna
prioritising works. No method or other
Austria
factors provided.
Variations include multiple bridges or
Autostrade roadworks that are “bulked” in a single
Italy contract, specific user demands or political
reasons.
Condition state 5 bridge or element rating
Poland triggers an investigation or immediate
repair.
Bridges with high GCRs are investigated. KUBA assigns treatments to elements based
on condition and damage process. A unit
Switzerland
cost (country average) is applied to each
damaged element to calculate repairs.
Project level - KTI, UTI, Makovian Chain, Network Level - Makovian linear
LCAP, cost analysis. optimisation, deterioration and repair action
Finland
models based on Makovian chain, cost
models, long term and short term analyses.
Manager of each National highway office
Japan determines priorities and program from the
damage and countermeasure records.
New Zealand Cost controls at project level.
United Refer Value Management process.
Kingdom
Prioritisation Index = BW x (max MCE x MCE, MCB. Level of maintenance or capital works
Spain
2MCB). assigned on basis of MC.
PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
Appendix D – B
ridge Prioritisation Methods:
Analysis of Responses
Austria - Vienna
Austr - Queens.
Austr - North
New Zealand
Austr - West
Parameter
Denmark
Hungary
S. Africa
Virginia
Finland
Norway
Canada
Croatia
Sweden
Mexico
Poland
Japan
Spain
Swiss
Italy
U.K.
% Defective Components in Structure
H H
Group
% in Poor for 5 Bridge Components H H
AADT/Total Traffic Volume L L M M L M M M H
Access for Pedestrians and Cyclists L
Accessibility of Heavy Traffic M
Accident Frequency M L H
Aesthetics M
Agreement with Local Authorities M
Anidro Program Parameters M
Any Hazardous Category M
Assessment of Serviceability H
Boa Program Parameters M
Bridge Age H M
Bridge Clearances/Clearances L L H M
Bridge Element Condition & Analysis M M H H H
Bridge Geometry/Weight L M M M
Bridge Structural Part H
Capacity Until Repair H
Commercial Vehicle/Heavy Traffic
H H M M H
Volume
Component Condition/Results of
M M M H H H
Inspection
Component Material M M
Component Significance M M M
Condition Rating H H H H L M H
Currency of Condition Data M M
Current Bridge Condition Index H
Defect Importance H
Deficiency Status H
Degree and Consequence of Damage H H
Depreciation L
Design Class L H L
Detour Length L H H M L M
Environment Aggressiveness L L M
Environmental L M
Excluded Components L
Expected Development of Damage H
Expected Development of Traffic Volume H
Flood Capacity M
Funding: Level and Source H H H H M M
General Condition Ratings H H H H H M H
Hazardous Materials Route L
50 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
Austria - Vienna
Austr - Queens.
Austr - North
New Zealand
Austr - West
Parameter
Denmark
Hungary
S. Africa
Virginia
Finland
Norway
Canada
Croatia
Sweden
Mexico
Poland
Japan
Spain
Swiss
Italy
U.K.
Health Index L L
Hydraulic Records M
Hydraulic Sufficiency M
Importance Factor M
Integration of Public Transport Facilities L
Intensified Monitoring H
Load Capacity H H M
Load Carrying Class H
Load Demands M
Local Industry Access L
Maintenance Estimates M
Maintenance Ranking M
Major Services Carried/Services Carried L L
Moveable Bridges H M
Navigable Waterway L L L
Number of Damages H
Obstacle Crossed/Over L L L M
Other Road Users L L L M
Partial Bridge Networks H
Present Service Load M
Present Value L
Priority Rating of Bridge Using Defects H
Repair Urgency H H M H
Replacement Value L L L L
Required Service Load M
Risk of Structural Failure H
Road Classification L L L L L L M
Road Geometry at Bridge L
Road Importance for Society H M
Road Needs for Improving Road Network H
Samoa Program Parameters M
Seismic Risk M
Significance of Damage Element H
Socio Economic Marginal Return/
H H H
Cost-Benefit
Stone Program Parameters H
Structure Type L M
Sufficiency Rating H H
Traffic Restrictions in Repair Period H
Type of Damage H
Utilization Value L
Waterway Adequacy L
51 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
TABLE D2- COLLATION OF FACTORS AND WEIGHTINGS
Parameter High Medium Low
% Defective Components in Structure Group 1 0 0
% in Poor for 5 Bridge Components 1 0 0
AADT/Total Traffic Volume 1 5 3
Access for Pedestrians and Cyclists 0 0 1
Accessibility of Heavy Traffic 0 1 0
Accident Frequency 1 1 1
Aesthetics 0 1 0
Agreement with Local Authorities 0 1 0
Anidro Program Parameters 0 1 0
Any Hazardous Category 0 1 0
Assessment of Serviceability 1 0 0
Boa Program Parameters 0 1 0
Bridge Age 1 0 0
Bridge Clearances/Clearances 1 1 2
Bridge Element Condition & Analysis 2 2 0
Bridge Geometry/Weight 0 3 1
Bridge Structural Part 1 0 0
Capacity Until Repair 1 0 0
Commercial Vehicle/Heavy Traffic Volume 3 2 0
Component Condition/Results of Inspection 2 3 0
Component Material 0 2 0
Component Significance 1 2 0
Condition Rating 4 1 1
Currency of Condition Data 0 2 0
Current Bridge Condition Index 1 0 0
Defect Importance 1 0 0
Deficiency Status 1 0 0
Degree and Consequence of Damage 2 0 0
Depreciation 0 0 1
Design Class 1 0 2
Detour Length 1 2 3
Environment Aggressiveness 0 1 2
Environmental 0 1 1
Excluded Components 0 0 1
Expected Development of Damage 1 0 0
52 PRIORITISATION OF BRIDGE REHABILITATION WORKS
2012R32EN
2012R32EN
2012R32EN
2012R32EN
2012R32EN
2012R32EN
2012R32EN
Factors Ratings Importance
Respondent 1 2 3 4 5 factor
D Conflict of local and national interests Hungary 1
(Competing regional or federal
Norway 1
strategies. Business case for accelerated
maintenance to assist regional Sweden 1
development or local industry at expense
South. Africa 1
of statewide priorities. Need to
accelerate works on interstate routes (not Virginia USA 1
national highway) for HML).
Czech
Greece
France
Croatia 1
Mexico 1
Queensland Australia 1 1
Queensland Australia 2 1
Queensland Australia 3 1
Queensland Australia 4 1
Total/11 4 5 1 1 0 21
EE
xpectations of groups representing Hungary 1
political or other interests (The effects
Norway 1
of delivering projects defined in a
political manifesto or other political Sweden 1
initiative on the needs defined
programme). South. Africa 1
Virginia USA 1
Czech
Greece
France
Croatia 1
Mexico 1
Queensland Australia 1 1
Queensland Australia 2 1
Queensland Australia 3 1
Queensland Australia 4 1
Total/11 2 5 3 1 0 25