You are on page 1of 34

AEMS Case Study on

Energy Saving Operations


and Asset Modifications

By: John C. Whittaker


Operations Manager
+44 (0)1404 812294
Contents:
Introduction
Methodology
Case Study
System Description
Initial Investigation
Primary Recommendations
1st Verification
Review & Additional Remedial Work
2nd Verification
Further Savings

Appendix

© Advanced Energy Monitoring System Ltd. 2009


Introduction:
Who are Advanced Energy Monitoring Systems Ltd?

 AEMS Established in 1981 by Maurice Yates

 AEMS is now part of the Entity Group (3,500 employees) to further Energy
Management Services in the UK and Overseas

 Pioneers in Life Cycle Costing (1983)

 Developers of the Yatesmeter & associated software

 Experts in enhancing “Fluid Motive Units” & system performance

 Innovators in the pumping field (air & liquid) – 4 DTI Smart Awards

 Experience of testing over 10,000 pumps & blowers worldwide

 Project management and QA of new & refurbished plant

© Advanced Energy Monitoring System Ltd. 2009


Methodology:
For any investigation into targeted energy reduction in pumping systems,
an element of desktop study and field / site evaluation is required.

Investigation Approach
Desktop Study
Assessment of Cost (£)
Standard KPI (kWh/Ml)
Enhanced KPI (kWh/Ml/m pumped head)
(kWh/Ml/m static head)
Site Investigation
Pump Testing
Multi-pump Monitoring
Analysis of Data
Initial Recommendation

© Advanced Energy Monitoring System Ltd. 2009


Methodology – 2:
Individual Pump Performance Monitoring

Portable used to determine:

Pump curves
System curves
Flowmeter verification

On a periodic basis

© Advanced Energy Monitoring System Ltd. 2009


Methodology – 3:
Multi-pump Monitoring – 1

A cascade of Yatesmeters
enable the measurement of both
the individual pump
performance and the system
performance in real time.

© Advanced Energy Monitoring System Ltd. 2009


Methodology – 4:
Multi-pump Monitoring – 2
90 Pump 1 Pump 2 Pump 3 Pump 4

89 Total Pumping Cost v Flow

88 15

14 Current Pumping Cost


87
13 Optimum Solo Schedule
86

85 Multi-pump monitoring 12

11
Optimum 2// Schedule

Optimum 3// Schedule


Pump Efficiency (%)

84
enables the data analysis of 10

Pumping Cost (£/Ml)


83 9

the combined operating


8
82
7
81
6
80 effects of the pumps 5

79 4

78 operating in the system 3

2
77
1
76
0
08-May 09-May 09-May 10-May 10-May 11-May 11-May 12-May
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600 1700 1800 1900 2000
Flow Rate (l/s)

1000 2000
Pump 1 Pump 2 Pump 3 Pump 4 Total

900 1800

800 1600

700 1400

Parameters logged include:


Flow Rate Per Pump (l/s)

Total Flow Rate (l/s)


600 1200

Individual and total pump head 500 1000

Individual and combined efficiency 400 800

Individual and combined power 300 600

Individual and combined flow 200 400

100 200

0 0
08-May 09-May 10-May 11-May

© Advanced Energy Monitoring System Ltd. 2009


Methodology – 5:
Multi-pump Monitoring – 3

Multi-pump monitoring enables the summated


performance of the pumping system to be
accurately displayed.

Example of combined efficiency performance


of a non-scheduled pumping system

Example of combined efficiency performance


of a scheduled pumping system

© Advanced Energy Monitoring System Ltd. 2009


Case Study:
Contents
System Description
Initial Findings
Primary Recommendations
1st Verification & Review
Remedial Work
2nd Verification
Further Savings

© Advanced Energy Monitoring System Ltd. 2009


Case Study – System Description:

System 1 System 2 System 3


42.4% of 42.9% of 14.7% of
Total Flow Total Flow Total Flow
Pumping system transfers treated 85m Head 55m Head 15m Head
water into 3 systems – 2 systems
are pumping to reservoirs, one
system is a pressure zone.

Original Pumping plant consists of


5 rotor resistor variable speed
pumps and 2 fixed speed pumps.

A B C D E F G
System was operated as a
common manifold only from the 5
variable speed pumps (A – E).

© Advanced Energy Monitoring System Ltd. 2009


Case Study – Initial Findings:

The pumps (A – E) were operating with


efficiency shortfalls of between 3 to 13%.

At higher operational speeds the pumps


were cavitating.

Operating the pumps into a combined


manifold increased the operational cost
excessively for 2 of the 3 systems.

© Advanced Energy Monitoring System Ltd. 2009


Case Study – Initial Findings:
Kempton AWTW
Current Schedule
Combined Pump Efficiency v Flow
100

90

80

70

Combined Pump Efficiency (%)


60

The combined efficiency of the pumping 50

station was 75% 40

30

20

Current Average Pumping Efficiency = 75.5 %


10

The operational pumping costs was 0


0 200 400 600 800 1000 1200 1400 1600 1800 2000

272.4 kWh/Ml. Station Volume Flow Rate (l/s)

Kempton AWTW
Current Pumping Cost
Total Pumping Cost v Flow

The annualised energy consumption was 350

17,883 MWh. 300

250

Pumping Cost (kWh/Ml)


200

150

100

Current Average Station Pumping Cost = 272.4 kWh/Ml


50

0
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Flow Rate (l/s)

© Advanced Energy Monitoring System Ltd. 2009


Case Study – Initial Findings:
System Splits

Energy
Percentage of total
Consumption Energy Cost (£)
Flow (%)
(MWh)
42.4 7,582 492,830

42.9 7,672 498,680

14.7 2,629 170,885

TOTALS 17,883 1,162,395

Energy Cost based on 6.5p/kWh

© Advanced Energy Monitoring System Ltd. 2009


Case Study – Primary Recommendations:

1) Separate the common manifold into individual pumping mains.


System 1 – Pressure system no saving
System 2 – 55m – 1,416 MWh saving (18.4% reduction)
System 3 – 15m – 1,433 MWh saving (54.5% reduction)

2) Trim pumps (later) A to E for an additional saving of 1,144 MWh

3) Re-commission pumps F & G to operate into System 3.

© Advanced Energy Monitoring System Ltd. 2009


Case Study – 1st Verification:
PROVEN
The common manifold was separated into individual pumping mains.

System 1 – 36 MWh saving (using pump A instead of pump B)

System 2 – 425 MWh saving (System restrictions prevented full recovery)

System 3 – 1,557 MWh saving (Exceeded initial assumptions)

Total Savings – 2,018 MWh (£131K) – 2 month payback

The 1st Verification demonstrated that substantial operational savings could be achieved
through getting the pumps to operate away from a common manifold arrangement. All
savings achieved with NO capital expenditure.

However, to improve responsiveness to system 3 a decision to install VSDs to the pump


would be beneficial.

© Advanced Energy Monitoring System Ltd. 2009


Case Study – Additional Remedial Work:
Although the savings for system 3 exceeded initial assumptions, there were further energy
savings to be recovered by converting the fixed speed pumps to variable speed.

Saving through matching the pump flow to system requirement.

Saving through rehabilitation of the mechanical and electrical assets

The remedial work consisted of:

Pump Refurbishment of Pumps F & G

Replacement of the electric motors with EFF1 motors

Installation of Variable speed drives to match system requirement

© Advanced Energy Monitoring System Ltd. 2009


Case Study – 2nd Verification:
The refurbishment and installation of the
variable speed drives reduced the
energy consumption for the system from
an original

272.4 kWh/Ml (initial baseline)

To
Variable Speed Energy Saving
72.9 kWh/Ml (post scheduling and refurb.)
59 kW (43%) @ 305 l/s
Resulting in a total energy saving of;

1,927 MWh (£125K)

Or

73.3% reduction in system cost!

© Advanced Energy Monitoring System Ltd. 2009


Case Study – Further Saving Potential:
To date one of the three systems has been improved, there
are still scope to increase the savings of the site.

Convert the existing rotor resistor machines to true VSD


Improve pressure management at the site
Refurbish 3 pumps

Total additional savings 3,400 MWh (£222K)

© Advanced Energy Monitoring System Ltd. 2009


AEMS Case Study on
Energy Saving Operations
and Asset Modifications

By: John C. Whittaker


Operations Manager
+44 (0)1404 812294
Appendices:
The Appendices for the presentation contain supplemental information
relating to some of the specifics outline in the presentation brief.

Appendix 1 - Thermodynamic principle formula


Appendix 2 - Power measurement
Appendix 3 - Data Analysis Methodology

© Advanced Energy Monitoring System Ltd. 2009


Appendix 1 – Methods of Measurement:
Yatesmeter Technology – 1

Efficiency = Work Done or Work Out


Effort Work In

Work In = Work Out + Losses

hp = Wo
Wo + Losses

hp = 1
1 + Losses/ Wo

© Advanced Energy Monitoring System Ltd. 2009


Appendix 1 – Methods of Measurement:
Yatesmeter Technology – 2

Energy Dissipated as Heat may be expressed, per unit mass, as:-

Losses = Cp.dT.Q

Work Out = g.H.Q

\ Losses = Cp.dT.Q In the equation Q cancels


W.O. g.H.Q

1
Efficiency = 1 + Cp.dT
g.H

© Advanced Energy Monitoring System Ltd. 2009


Appendix 1 – Methods of Measurement:
Yatesmeter Technology – 3

Using the Efficiency Eqn. and a measured value for Power, Flow can be
Determined.

Pgr = r.g.Q.H Q = Pgr.hp.hm


hp.hm g.H

Flow measurement:

Q= Pgr.hm
g.H + dT.Cp

The accuracy of the power assessment affects the calculation of flow only.

© Advanced Energy Monitoring System Ltd. 2009


Appendix 2 – Methods of Measurement (Power):
Two Wattmeter Method – 1

© Advanced Energy Monitoring System Ltd. 2009


Appendix 2 – Methods of Measurement (Power):
Three Wattmeter Method – 2

© Advanced Energy Monitoring System Ltd. 2009


Appendix 3 – Data Analysis:
Methodology – 1
The analysis of the field performance data for both the individual pump and
system characteristics are assessed to determine the best opportunities to
reduce the operating cost of the whole pumping system, rather than limiting the
assessment to only the pump.
In order to undertake a comprehensive assessment the following considerations
should be made.
1) Variations in the flow profile for the pumping system for solo and multi-pump
parallel pumping.
2) Determine the intersection of solo and parallel pumping against the system
characteristic.
3) Predict the future performance of the pumping plant remedial work against the
system characteristic.
4) Calculate the present and future operation in kWh/ML/m, and use as basis for
performance verification.

© Advanced Energy Monitoring System Ltd. 2009


Appendix 3 – Data Analysis:
Areas Investigated for Energy Reduction Opportunities - 1
10

5
12.5

17.5

Pump Optimisation
Pump Efficiency
Variable Speed / Trim
Pipework Improvements
Correct Re-selection of Pumps
Appendix 3 – Data Analysis:
Methodology – Flow Profile Variation

Daily Flowrate Variation

300

The daily flow profile


250
shows the extent of the
variation in flow that the
pumps systems have to 200

cope with. Flowrate

150
This data is then further
analysed to determine
100
the amount of solo and
parallel pumping.
50

0
31-Mar-99 19-Jul-99 06-Nov-99 24-Feb-00 13-Jun-00 01-Oct-00 19-Jan-01 09-May-01 27-Aug-01 15-Dec-01 04-Apr-02
Date

Daily Flows System Ave

© Advanced Energy Monitoring System Ltd. 2009


Appendix 3 – Data Analysis:
Methodology – Flow Histogram
EXAMPLE WPS - Pumping System
No of Days Spent at Various Flow Rates Over the Past 3 Years
50

45

The flow histogram


40
shows the extent of solo
and parallel pumping. 35

30
Frequency (days)

25

20

15

10

0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300
Flow Rate (l/s)

© Advanced Energy Monitoring System Ltd. 2009


Appendix 3 – Data Analysis:
Pump Optimisation – 1

Pump Optimisation aims to operate


the existing pumping plant in the
most efficient mode of operation.
Improvements vary between 5% -
26%, and involve no capital
investment.
Example System
The initial trial month showed the
operation of system 1 had an
average operating efficiency of
66.9%.
The shortfall in performance was
due to the operation of the fixed and
variable speed pumps in parallel.

© Advanced Energy Monitoring System Ltd. 2009


Appendix 3 – Data Analysis:
Pump Optimisation – 2

After the initial monitoring, a new


operating schedule was recommended
and implemented. This resulted in an
initial improvement of 22.3%, or £38k /
pa.
Pump Optimisation can be implemented
onto any system which operates
combination of pumps in parallel.
Systems to be targeted are systems
which operate variable speed pumps, in
combination with fixed speed or
different pump types / sizes.

© Advanced Energy Monitoring System Ltd. 2009


Appendix 3 – Data Analysis:
Methodology – System Intersection – 1

The intersection of the pump


performance curve with the system
curve is used to determine the
present cost of operation.

© Advanced Energy Monitoring System Ltd. 2009


Appendix 3 – Data Analysis:
Methodology – System Intersection – 2

As well as determining the present cost of


operation, the intersection of the system curve is
used to predict the following effects
Pump Refurbishment improvements
Trim benefits
Variable Speed benefits
New pump selection

© Advanced Energy Monitoring System Ltd. 2009


Appendix 3 – Data Analysis:
Pump Refurbishment

Pump refurbishment should aim to


recover the performance of the pump back
to at-least the original performance

© Advanced Energy Monitoring System Ltd. 2009

You might also like