Professional Documents
Culture Documents
Classroom Exercise
Classroom Exercise
Page 1 of 6
1. Project Vs Operation
c. What do you understand by Project constraint and give examples of the same?
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
Page 2 of 6
2. Explain the difference between a Project Expeditor and Project Coordinator in the context if
a Weak Matrix?
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
3. List down the advantages and disadvantages of the following organization structures?
Functional
Disadvantages Advantages
Weak Matrix
Disadvantages Advantages
Balanced Matrix
Disadvantages Advantages
Strong Matrix
Disadvantages Advantages
Projectized
Disadvantages Advantages
Page 3 of 6
4. Represent the Cost and Staffing Level and Stakeholders influence and Cost of Change in a
project lifecycle pictorially?
5. You are the project manager for a restaurant chain, with stores in 20 states. You are
considering opening a new outlet in Mumbai or Chennai. You have derived the following
information:
Project Mumbai City: The payback period is 27 months, and the IRR is 35 percent.
Project Chennai: The payback period is 25 months, and the IRR is 32 percent.
Which project should you recommend to the selection committee?
6. You are the project manager for Delta International. You’re considering recommending a
project that costs INR 575,000; expected inflows are INR 25,000 per quarter for the first two
years and then INR 75,000 per quarter thereafter. What is the payback period?
A. 40 months
B. 38 months
C. 39 months
D. 41 months
Page 4 of 6
7. Below is the network diagram for a project. Answer the below questions for this diagram?
a. What is the float for each activity on the critical path? ____
b. What is the total duration for path A → B → C → G? ____
c. What is the total duration for path A → B → F → G? ____
d. What is the total duration for path D → E → F → G? ____
e. What is the total duration for path D → H → I? ____
f. Which path is the critical path? ____ → ____ → ____ → ____
g. Write down the float for each activity:
Page 5 of 6
a. Construct an activity diagram to represent the above scenario.
b. Determine the critical path for the above project using forward and backward pass
c. What is the total duration of the critical path
d. What is the total float/slack available?
9. Complete the below table with PERT formula. All the estimates are in hours
Expected
Activity
Activity Activity Range Of
Activity P M O Standard
Duration Variance Estimates
Deviation
(EAD)
A 47 27 14
B 89 60 41
C 48 44 39
D 42 37 29
Calculate the Total Standard Deviation and Total Activity Variance?
10. Below is the table showing cost parameters for a project to construct building
Page 6 of 6