CV = EV - AC Average (Mean) = Sum of all members divided by the number of items. CPI = EV / AC Median = Arrange values from lowest value to highest. Pick the middle SV = EV - PV one. If there is an even number of values, calculate the mean of the SPI = EV / PV two middle values. EAC ‘no variances’ = BAC / CPI Mode = Find the value in a data set that occurs most often. EAC ‘fundamentally flawed’ = AC + ETC EAC ‘atypical’ = AC + BAC - EV Values EAC ‘typical’ = AC + ((BAC - EV) / CPI) 1 sigma = 68.26% ETC = EAC - AC 2 sigma = 95.46% ETC ‘atypical’ = BAC - EV ETC ‘typical’ = (BAC - EV) / CPI 3 sigma = 99.73% ETC ‘flawed’ = new estimate 6 sigma = 99.99% Percent Complete = EV / BAC * 100 Control Limits = 3 sigma from mean VAC = BAC - EAC Control Specifications/ Specification Limits = Defined by EV = % complete * BAC customer; looser than the control limits PERT Order of Magnitude estimate = -25% to +75% Preliminary estimate = -15% to + 50% PERT 3-point = (Pessimistic + (4*Most Likely)+Optimistic)/6 Budget estimate = -10% to +25% PERT S.D (σ) = (Pessimistic - Optimistic) / 6 Definitive estimate = -5% to +10% PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2 Final estimate = 0% Total S.D (σ) = Square Root (Sum of All Variance) Float on the critical path = 0 days Network Diagram Pareto Diagram = 80/20 Activity Duration = EF - ES or Activity Duration = LF - LS Time a PM spends communicating = 90% Total Float = LS - ES or Total Float = LF – EF Crashing a project = Crash least expensive tasks on critical Free Float = ES of Following Activity - EF of Present Activity path. EF = ES + duration JIT inventory = 0% (or very close to 0%) ES = EF of predecessor LF = LS of successor LS = LF - duration Acronyms Project Selection AC Actual Cost PV = FV / (1+r)^n BAC Budget at Completion FV = PV * (1+r)^n BCR Benefit Cost Ratio NPV = Formula not required. Select biggest number. ROI = Formula not required. Select biggest number. CBR Cost Benefit Ratio IRR = Formula not required. Select biggest number. CPI Cost Performance Index Payback Period = Add up the projected cash inflow minus expenses CV Cost Variance until you reach the initial investment. DUR Duration BCR = Benefit / Cost EAC Estimate at Completion CBR = Cost / Benefit Opportunity Cost = The value of the project not chosen. EF Early Finish EMV Expected Monetary Value Communications ES Early Start Communication Channels = n * (n-1) / 2 ETC Estimate to Complete EV Earned Value Probability FV Future Value EMV = Probability * Impact in currency IRR Internal Rate of Return Procurement LF Late Finish PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target LS Late Start Cost NPV Net Present Value PERT Program Evaluation and Review Technique Depreciation Straight-line Depreciation: PTA Point of Total Assumption Depr. Expense = Asset Cost / Useful Life PV Planned Value Depr. Rate = 100% / Useful Life PV Present Value ROI Return on Investment Double Declining Balance Method: SPI Schedule Performance Index Depr. Rate = 2 * (100% / Useful Life) SV Schedule Variance Depr. Expense = Depreciation Rate * Book Value at Beginning of Year Book Value = Book Value at beginning of year - Depreciation Expense VAC Variance at Completion σ Sigma / Standard Deviation Sum-of-Years' Digits Method: Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc. Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)