SOLUCIÓN A - SECCION CANAL TODA CON EMPEDRADO

BASE CANAL LONGITUD ANCHO ESPESOR TOTAL m3 PRECIO A.P.U


TRAMO ZAMBRANO 2 620 4 0.15 372 $ 202,300.00
TRAMO EXTERIOR 360 4 0.15 216 $ 202,300.00
Total m3 588 $ 202,300.00

TALUDES Y BERMA LONGITUD ANCHO ESPESOR SUBTOTAL m3 # TALUDES


TRAMO ZAMBRANO 2 620 7.15 0.15 664.95 2
TRAMO EXTERIOR 360 7.15 0.15 386.1 2
Total m3

ANALISIS DE PRECIO UNITARIO - EMPEDRADO


DESCRIPCION unidad cantidad precio unitario
Mortero de cemento CEM II/B-P 32,5 N tipo M-7,5,
confeccionado en obra con 300 kg/m³ de cemento y una m3 0.08 $ 680,000.00
proporción en volumen 1/5.

Granzon m3 0.8 $ 120,000.00

Cuadrilla AA - Obra Civil dia 0.21 $ 190,000.00


Mezcladora de Cemento 1 bulto dia 0.1 $ 120,000.00
TOTAL

SOLUCIÓN B - SECCION CANAL TODA GEOMEMBRANA POLIETILENO

BASE CANAL LONGITUD ANCHO TOTAL m2 PRECIO A.P.U


TRAMO ZAMBRANO 2 620 4 2480 $ 23,400.00
TRAMO EXTERIOR 360 4 1440 $ 23,400.00
Total m3 3920 $ 23,400.00

TALUDES Y BERMA LONGITUD ANCHO SUBTOTAL m2 # TALUDES


TRAMO ZAMBRANO 2 620 7.15 4433 2
TRAMO EXTERIOR 360 7.15 2574 2
Total m3

ANALISIS DE PRECIO UNITARIO - EMPEDRADO


DESCRIPCION unidad cantidad precio unitario
Geomembrana HDPE Polietileno - Cal 20 MILS m2 1 $ 12,000.00
Cuadrilla AA - Obra Civil dia 0.06 $ 190,000.00
TOTAL

SOLUCIÓN C - BASE EMPEDRADA Y TALUDES EN GEOMEMBRANA DE POLIETILENO

BASE CANAL LONGITUD ANCHO ESPESOR TOTAL m3 PRECIO A.P.U


TRAMO ZAMBRANO 2 620 4 0.15 372 $ 202,300.00
TRAMO EXTERIOR 360 4 0.15 216 $ 202,300.00
Total m3 588 $ 202,300.00

TALUDES Y BERMA LONGITUD ANCHO SUBTOTAL m2 # TALUDES


TRAMO ZAMBRANO 2 620 7.15 4433 2
TRAMO EXTERIOR 360 7.15 2574 2
Total m3
A CON EMPEDRADO

SUBOTAL PRECIO
$ 75,255,600.00
$ 43,696,800.00
$ 118,952,400.00

TOTAL m3 PRECIO A.P.U SUBOTAL PRECIO


1329.9 $ 202,300.00 $ 269,038,770.00
772.2 $ 202,300.00 $ 156,216,060.00
2102.1 $ 202,300.00 $ 425,254,830.00

TOTAL
$ 544,207,230.00
Subtotal

$ 54,400.00

$ 96,000.00

$ 39,900.00
$ 12,000.00
$ 202,300.00

MEMBRANA POLIETILENO

SUBOTAL PRECIO
$ 58,032,000.00
$ 33,696,000.00
$ 91,728,000.00

TOTAL m3 PRECIO A.P.U SUBOTAL PRECIO


8866 $ 23,400.00 $ 207,464,400.00
5148 $ 23,400.00 $ 120,463,200.00
14014 $ 23,400.00 $ 327,927,600.00

TOTAL
$ 419,655,600.00
Subtotal
$ 12,000.00
$ 11,400.00
$ 23,400.00

GEOMEMBRANA DE POLIETILENO

SUBOTAL PRECIO
$ 75,255,600.00
$ 43,696,800.00
$ 118,952,400.00

TOTAL m3 PRECIO A.P.U SUBOTAL PRECIO


8866 $ 23,400.00 $ 207,464,400.00
5148 $ 23,400.00 $ 120,463,200.00
14014 $ 23,400.00 $ 327,927,600.00

TOTAL
$ 446,880,000.00

SOLUCION A Toda la s
SOLUCION B Toda la seccion co
SOLUCION C Base empedrada y talu

https://www.electromanferonline.com/
ALCANCE VALOR
Toda la seccion en empedrado $ 544,207,230.00
Toda la seccion con Geomembrana de Polietileno $ 419,655,600.00
Base empedrada y taludes en Geomembrana de Polietileno $ 446,880,000.00