You are on page 1of 8

1

Design and Application of SVC units in the Texas


CREZ System
Anders Boström, Member IEEE Ben Mehraban, Senior Member IEEE
ABB AB American Electric Power
Västerås, Sweden Columbus, OH, USA
anders.x.bostrom@se.abb.com bmehraban@aep.com

Abstract— This paper describes the design and SVC systems, one at Tesla Substation at 345 kV and the other
implementation of the Static Var Compensator (SVC) at Hamilton Road Substation at 138 kV. Both locations have
Systems in the Tesla and Hamilton Road Substation, part two SVC units operating in parallel where the dynamic range
of the Texas CREZ transmission system. The SVC of the Tesla units are 66 Mvar inductive to 150 Mvar
systems were taken into operation by American Electric capacitive reactive power and the Hamilton Road units range
Power (AEP) in late August 2013. The paper describes from 25 Mvar inductive to 100 Mvar capacitive reactive
some of the more important SVC design criteria such as power.
filter design and performance, control and reliability. It II. THE CREZ TRANSMISSION SYSTEM
also handles the generation and transmission system
characteristics of the CREZ transmission system, The five CREZ areas designated by PUCT encompass
providing the requirements for dynamic support. Also large areas of West Texas. The system, shown in figure 1,
included are discussions on control verification and stretch as far as 400 miles from the northern Texas panhandle
testing. and south McCamey close to the Mexican border to the load
centers of Dallas/Ft. Worth, San Antonio and Austin in east
Index Terms — Competitive Renewable Energy Zones (CREZ), Texas. To integrate the proposed wind generation capacity
Dynamic Voltage Support, Electric Reliability Council of Texas additional right of way of approximately 2300 miles were
(ERCOT), Harmonic Impedance, Public Utility commission of required. Several of the 345 kV circuits are designed solely
Texas (PUCT) , Static Var Compensator (SVC), for the purpose of integrating asynchronous generation, with
no connection to thermal generation or load centers [1], [2].
I. INTRODUCTION
In 2009 the Public Utility Commission of Texas (PUCT)
ordered several existing and future Transmission Service
Providers (TSP) in Texas to implement transmission
improvements to connect 12 GW of wind generation with a
possible future maximum generation estimated to roughly 24
GW. This includes five Competitive Renewable Energy
Zones (CREZ) connected to load centers within the Texas
Interconnection. Electric Transmission Texas (ETT) was
awarded seven line segments and four switching stations for
this purpose in cooperation with American Electric Power
(AEP), responsible for engineering and operation. Subsequent
studies performed through ERCOT on how to facilitate the
transmission capability necessary identified the need and
locations for dynamic reactive shunt and series compensation
throughout the system. As a result ETT/AEP is responsible
Figure 1. The Texas CREZ transmission system (source ERCOT). Solid
for implementing dynamic reactive power compensation at lines indicate double and dashed lines single circuit 345 kV transmission.
two locations in the system, Hamilton Road Substation west
of San Antonio and Tesla Substation in the south east of the The fact that this system is practically devoid of
Texas panhandle. The choice of dynamic device on the two conventional synchronous generation, except at the load
sites fell on the classical Static Var Compensator. Since centers located hundreds of miles away imply that reactive
August 2013 AEP has for this purpose been operating two support is imperative to facilitate high active power transfers.

978-1-4799-3656-4/14/$31.00 ©2014OFIEEE
Authorized licensed use limited to: UNIVERSITY WESTERN ONTARIO. Downloaded on July 18,2023 at 03:23:39 UTC from IEEE Xplore. Restrictions apply.
2

This is particularly the case during contingencies where The initial build dynamic range of each of the Tesla units is
critical important double circuit 345 kV lines are involved. -66 to +150 Mvar at 345 kV, consistent with the requirements
The outstretched radial nature of the transmission system will of the CREZ initial build scenario. Figure 3 shows the single
make it bound by power angle criterion limitations. Studies line diagram of one Tesla SVC unit and its connection to the
[1], [2] have indicated that angles between the wind turbine 345 kV bus. The topology of these SVC units is composed of
generator terminals and receiving end buses transiently reach one Thyristor Switched Capacitor (TSC) branch rated at 94
angles well over 90 degrees following contingencies. This is Mvar, one Thyristor Controlled Reactor (TCR) branch rated
shown even though series compensation at significant levels at 122 Mvar and 56 Mvar of fixed filters, distributed over two
is used and despite the fact that type 3 and 4 wind generators banks tuned to the 3rd and 5th harmonic respectively. The SVC
are immune to power angle limitations. Under these is connected to the 345 kV system through three phase step
circumstances the system will be subject to fast voltage down transformers, including a common spare unit.
collapse unless strategically located dynamic reactive power
is injected. It is important that these dynamic sources remain 345 kV

controllable, meaning that they are not all allowed to go into 300 MVA 300 MVA

limit. Sizing is therefore crucial to system security as are 345 /20.5 kV 345/20.5 kV

controllability and location of these devices.


It is perhaps easy to refer to the dynamic reactive
requirements as valid for the capacitive range only. However,
this type of transmission system is highly sensitive to over
voltages related to fault clearing in the vicinity of the wind
farms. In particular, this becomes an issue when generation
trips and this runs the risk of becoming a cascading situation. TCR TSC 3rd Harmonic 5 th Harmonic 3rd Harmonic 5th Harmonic
TCR TSC
Therefore, inductive range in dynamic devices is of high 122 Mvar 94 Mvar Filter
42 Mvar
Filter
14 Mvar
122 Mvar 94 Mvar
Filter
42 Mvar
Filter
14 Mvar

importance as is the ability to rapidly remove capacitive Figure 3. Single Line Diagram of the Tesla SVC units, Initial Build.
elements. Thyristor Controlled Reactor/Thyristor Switched
Capacitor (TCR/TSC) based SVC units are therefore The Tesla units are prepared for future expansion to meet
preferred over simpler topologies when operating under this the CREZ system intermediate or ultimate build scenarios,
type of system properties. where the ultimate build scenario calls for -150 to +300
In combination with the above issues, system behavior at Mvar. This range would be met by adding an identical TCR,
faults at the sending or receiving end, load composition upgrade the existing TSC to 122 Mvar and add an identical
including a significant degree of low inertia induction motors TSC. The transformer low side voltage is selected to
and the low system short circuit ratio level at the point of accommodate the full ultimate build SVC rating. A viable
interconnection, make it clear that the requirements on intermediate build requirement would be to add an additional
dynamic reactive power compensation become significant. TSC branch and/or TCR as applicable. Figure 4 illustrates the
All these phenomena are described in references [1] and [2]. SVC Voltage vs. Current characteristics for the initial and
ultimate build scenario SVC units. The filters are designed
III. TESLA AND HAMILTON RD SVC DESIGN
and rated to meet any of these CREZ expansion scenarios [2].
The Hamilton Road and Tesla Substations both house two The transformer is rated to meet the ultimate build scenario
vernier controlled SVC units operating in parallel. A site thermally as well as with respect to the core flux limit. This is
view of one of the Tesla SVC units is shown in figure 2. valid also for the initial build thyristor valves.
AEP CREZ - TESLA SVC, 345 kV side VI-diagram
1.4

1.2

1 C A B D
P r im a ry v o lta g e [p u ]

0.8

0.6

0.4
A - Nominal Initial Build Capacitive Rating

B - Nominal Initial Build Inductive Rating


0.2
C - Nominal Ultimate Build Capacitive Rating

D - Nominal Ultimate Build Inductive Rating


0
-3.5 -3 -2.5 -2 -1.5 -1 -0.5 0 0.5 1 1.5 2 2.5
<=================== Capacitive =============== SVC current [pu] =================== Inductive ==============>

Figure 2. Site view of Tesla SVC, unit #1 Figure 4. Tesla SVC Initial Build Voltage vs. Current characteristic.

Authorized licensed use limited to: UNIVERSITY OF WESTERN ONTARIO. Downloaded on July 18,2023 at 03:23:39 UTC from IEEE Xplore. Restrictions apply.
3

The dynamic range of each of the Hamilton Rd units is -25 outages of double circuits, i.e. N-1-1 are required to be
to +100 Mvar at 138 kV. They have a similar topology as the treated as N-1 outages with regard to harmonic performance.
Tesla units with one TSC branch rated at 60 Mvar, one TCR This causes the network resonances to shift around to a
branch rated at 65 Mvar and 35 Mvar of fixed filters, significantly higher degree when evaluating performance than
distributed in three banks tuned to the 3 rd ,5th and 7 th harmonic would be the case for single outage conditions. By the same
frequencies respectively. Similarly to Tesla, there is one 100 definition double outages, used for SVC component rating
MVA three phase transformer connecting each SVC unit to will involve the loss of four single 345 kV lines. This will of
the 138 kV bus including one de-energized spare. Hamilton course have significant impact on the filter design and rating.
Road does not have any expandability requirements driven by The harmonic impedance scans are based on the peak load
future system changes. The explanation is found examining powerflow cases. This is useful for harmonic evaluation
the locations of the SVC sites in relation to wind generation purposes because peak load cases tend to have the largest
and load centers. Tesla Substation is located in the number of generators, capacitor banks and other pieces of
transmission path close to the generation whereas Hamilton transmission equipment in service. These can then be readily
Road is closer to the load, somewhat outside the actual CREZ removed to evaluate multiple system conditions. However,
transmission system. higher loads tend to add more damping of the system
resonances, which is generally not conservative enough for
IV. SVC DESIGN CRITERIA the purpose of filter design. For an added level of
conservatism in the design the loads were therefore reduced
Static Var Compensators are designed to operate safely and by 50%. Even with this approach the choice of load
reliably in the transmission or distribution system to which representation is important. For the harmonic frequencies
they are connected. This can be quantified in a number of simplified load models were selected, typically series and
specific requirements in terms of dynamic range, system parallel representation is used, where the latter has the real
operating voltage conditions, contingency scenarios etc. One and reactive power represented by appropriately selected RL
important aspect of this is to select the SVC sizing and or RC components in parallel. For the series representation
topology such that undesired resonant conditions, internally the same is valid with series connected RL or RC
to the SVC and between the SVC and the AC system are combinations. Unless information on other more specific load
avoided. However, it shall be made clear that by nature, models are provided the series representation is preferred. It
resonances will always exist when inductive and capacitive provides conservative levels of damping to higher frequency
elements are combined. It is where in the frequency range system resonances. This is illustrated in figure 5, where an
they appear that has to be controlled. For an SVC this is example harmonic impedance scan is compared for series and
basically determined by how the capacitive branch size and parallel RL load representation.
transformer reactance are selected in relation to the network
impedance. For a design engineer this process can be more or
less complex depending on the system impedance data
available and its properties in relation to the susceptance over
the SVC range.

Harmonic Impedance Data and System Modelling


The filter design was performed using scans of the positive
sequence network driving point harmonic impedance for all
viable system development scenarios, including initial,
intermediate and ultimate build CREZ system conditions.
Impedance scans were performed for N-0, N-1, and N-2
system contingency cases up to and including the 50th order
harmonic for said system scenarios. A unit positive sequence
current is injected at the SVC point of connection into the
system. The resulting voltage calculated at the SVC bus is
Figure 5. Impedance Frequency Scan, Comparison of Load model Impact
proportional to the network impedance at the frequency
subject to evaluation. Calculations were performed for As seen in figure 5, the resonances occur at the same
different wind scenarios based on the different stages of frequencies for both representations, but the damping differs
system development scenarios. The wind levels considered significantly between the two.
were 0 %, 33 %, 66 % and 100 %. To further account for Transmission line modeling is also of high importance. To
variations the CREZ wind was grouped in a manner dividing correctly model the nature of the distributed losses,
it into Panhandle, McCamey and Central groups were each inductance and charging capacitance is crucial in order to
possible combination was considered for the 33 % and 66 % capture the resonances at the proper frequencies. The
scenarios. standard P-models are therefore avoided at the benefit of the
An important note regarding the CREZ system and its Bergeron representation, which has been found to capture the
harmonic impedance characteristic is that several important resonant behavior. More detailed representation is generally
345 kV double-circuit lines share common transmission not required. One shortcoming of the standard Bergeron
towers. This effectively means that contingencies involving models available is that they lack representation of frequency

Authorized licensed use limited to: UNIVERSITY OF WESTERN ONTARIO. Downloaded on July 18,2023 at 03:23:39 UTC from IEEE Xplore. Restrictions apply.
4

dependent line resistance, i.e. the conductor skin effect. To shunt elements have the purpose of relieving the SVCs
capture this, a modified Bergeron model is used that alters the throughout the system from steady state voltage control to
resistance of the line at each evaluated frequency [3], in preserve SVC dynamic range, the SVCs were removed from
particular for larger cross section area conductors used at 345 service to force the long term behavior of the shunt elements
kV and higher. Series capacitors were modeled as either in or to be evaluated. No instance was found in either the initial or
out of service. intermediate build conditions were the shunt reactors
Since it is positive sequence harmonic impedance that is of switched out or where shunt capacitors switched in. The need
interest, transformers can be modeled using standard star for shunt capacitors occurs under heavily loaded line
connection, with simple resistors and reactors representing conditions for ultimate build conditions. For SVCs only the
the losses and leakage inductance of the windings. The units expected to influence the harmonic impedance scans
transformer losses, i.e. winding and eddy current losses, were included by representation of the SVC filter banks. The
which also are frequency dependent, are captured with the impact of the Oklaunion HVDC station was evaluated in a
same method used for the transmission lines [3] to correctly similar way. The impact of the HVDC converter was shown
represent the damping at higher frequencies. to be minimal and modeled as out of service for simplicity.
The wind turbine generators throughout the CREZ system To give an idea of the sensitivity related to the various
was assumed to be composed of 80 % Type 3 (double fed system conditions and wind turbine models used a few select
induction generators) and 20 % Type 4 (full converter impedance diagrams are examined. Figure 7 shows the
generators). The harmonic impedance looking into the impact of choice of WTG model on harmonics of order 5 and
terminals of these devices can be of importance to the 7 and figure 8 illustrates the influence from different wind
impedance presented to the system seen from the SVC point levels.
of connection. This, in particular, is the case for the Tesla
units, located close to the Panhandle wind farm clusters. For
both types of wind turbines, the anticipated harmonic
impedance was determined using generic PSCAD models.
These models do not necessarily represent the equipment of
any given manufacturer but will give a reference point for
possible impedances. The Type 3 impedance characteristic is
shown in figure 6.

Figure 7. HIS result comparison of WTG models, harmonic order 7.

Figure 6. Impedance characteristics of Type 3 WTG.

In addition to load, transmission lines and wind turbines


also additional transmission equipment, such as transformers
and shunt banks are modeled to capture the system frequency
response. Transformers are modeled as resistors and reactors
representing the transformer losses (load and stray losses) and
the leakage reactance of the windings. Losses are represented
Figure 8. HIS result comparison of system wind levels, harmonic order 7.
as frequency dependent in the same manner as the
transmission lines [3]. Shunt elements will, depending on the The SVC harmonic performance requirements are based on
power flow, be either in or out of service. It is fair to assume IEEE 519 [4], which provides guidance of steady state
that for the initial build scenario the system will be lightly planning levels at transmission voltage. For 345 kV these
loaded compared to the ultimate build. Therefore it has been levels are 1.0 % for individual voltage harmonics and 1.5 %
assumed that mostly reactors will be present in the initial for the total harmonic distortion. For 138 kV the
stage and capacitors for the ultimate build stage. Because the corresponding limits are 1.5 % and 2.5 % respectively.

Authorized licensed use limited to: UNIVERSITY OF WESTERN ONTARIO. Downloaded on July 18,2023 at 03:23:39 UTC from IEEE Xplore. Restrictions apply.
5

The SVCs are designed to account for less than half of these important for the valve cooling pumps and fans. These are
levels during N-1 system conditions. N-2 conditions serve as turned off at a set minimum voltage level, e.g. during a low
base for the rating of the SVC components together with voltage contingency, waiting for the voltage to recover to
other viable short time system phenomena that may impact restart the cooling pumps. Running the SVC without cooling
the SVC main circuit components. is allowed for a limited time at low voltages as the valve
current and consequently the required cooling, reduces with
V. SVC RELIABILITY CONSIDERATIONS the voltage squared. Also fans and control enclosure air
conditioners are handled this way. Note that these different
The primary purpose of transmission SVCs is to provide systems have different voltage requirements and hence
dynamic support during system contingencies. The Hamilton require separate undervoltage detection and operational
Rd and Tesla SVC units are no exception to this. To strategies. Auxiliary systems other than the abovementioned,
maximize SVC readiness for these events it is important to vital for SVC operation are supplied from redundant dc
have a well-adapted concept to maximize the SVC uptime, systems.
which translates to availability and minimize the number of
Main Circuit
forced outages, which translates to reliability. This needs to
involve all parts of the SVC installation. Based on experience To meet the SVC availability requirements a sufficient
and previous work in this area [5] it is well known that the amount of spare parts is required. These are statistically
majority of SVC reliability issues are related to the auxiliary determined based on component failure rates and delivery
systems, such as auxiliary power supply, valve cooling, air time. Main circuit components used in SVCs are in general
conditioning and control system. In comparison main circuit mature products with a large installed base over a long period
equipment is subject to a low failure rate when properly rated. of time. This, adding long experience in SVC design, provide
The availability requirements for the SVCs in question are for low statistical failure rates. However, some of these
99% Forced Outage Availability (FOA) and 97.5% Total components, should they fail, have a significant lead time and
Availability, i.e. including forced and scheduled outages. The would render the SVC inoperable over a long time. By way
reliability requirements are specified at less than two (< 2) of example this can be illustrated by the transformer, which
forced outages per year. These values are guaranteed by the has an extremely low statistical failure rate but a very long
vendor while the statistically expected availability of the SVC production or repair lead time for failures related to the active
units delivered is 99.5% (FOA) and 99.1% totally, including part. Looking from a purely statistical perspective a spare
one scheduled 37 hour long outage for yearly maintenance. SVC transformer would provide very limited contribution to
The annual forced outage frequency is calculated to 0.55 the availability of an SVC. However, transmission SVCs are
faults per year. by nature an insurance against power system failures and an
SVC spare transformer can similarly be regarded as an
Auxiliary Power Supply
insurance policy for the SVC. The Hamilton Rd and Tesla
Many problems experienced in SVC installations are SVCs therefore have a spare transformer unit at each site
caused by unreliable auxiliary ac supplies. Issues that initially common to the two SVCs (figure 3). In addition there is a
show up as cooling system failures, fan or air conditioner spare of each type of capacitor unit, reactor etc.
problems often turn out to be related to the ac supply. To meet the reliability requirement there are several
Therefore it is important to carefully coordinate performance measures of redundancy applied. Note that this redundancy is
of the auxiliary ac supply with the equipment connected. For either in operation or in hot stand-by mode as the SVC is not
the SVC units handled in this paper the ac supply comes off allowed to go off line for failures related to this equipment.
the SVC MV bus. This is not uncommon for SVCs but the Examples of reliability driven components are thyristor
situation in this case is somewhat special since there is no valves, valve cooling system and the SVC control system.
backup source available from outside the SVC. The backup The latter is handled separately below. Each phase of the
source for the individual SVC comes from the parallel thyristor valves has two redundant levels. At failure the
operating SVC. Taking the auxiliary power off the SVC MV thyristor immediately goes into short circuit mode, a failure
bus in itself calls for a well-coordinated design to properly alarm is sent to the control system and the valve phase
handle the fluctuating voltage. Going from full capacitive to position of the failed thyristor is indicated in the HMI. No
full inductive operation the voltage swing on the auxiliary interruption in SVC operation occurs and replacement of the
system may be significant, in particular this gets more failed unit can be deferred to the next scheduled outage or
pronounced the wider the SVC operating range is. whenever convenient. The cooling system has redundancy
Vernier controlled SVCs operate with secondary voltage applied for pumps and fans. The SVCs are able to run in
limitation facilitated by the TCR. This provides for a well- reduced mode with the TSC branch out of operation.
defined maximum continuous MV bus voltage. With this as a
Control and Protection
starting point the auxiliary transformer turns ratio is chosen
such that the ac auxiliary equipment continuous voltage range The SVC main control system is redundant from the main
is met for the voltage range of the SVC continuous operating computers out through the I/O units, divided into an A and B
area. Equipment like pump motors are over-rated to allow for system with one system active and the other in standby. The
a lower than normal operating voltage. For voltage dips standby system operates in parallel with the active system
reaching lower than the minimum continuous operating although with the output interface inactive. This provides for
voltage selected equipment is turned off in a controlled a seamless transition from one system to the other when
manner to avoid tripping the SVC. In particular this is necessary. Maintenance and repair such as replacement of

Authorized licensed use limited to: UNIVERSITY OF WESTERN ONTARIO. Downloaded on July 18,2023 at 03:23:39 UTC from IEEE Xplore. Restrictions apply.
6

circuit boards can be done on the inactive system with the based protection, such as TSC valve and capacitor protection
SVC remaining in operation to avoid unnecessary down time. is implemented in the VCU while thyristor based protection
The system is self-diagnostic in the sense that any failed or such as recovery protection and protective firing is
faulty parts of the control, e.g. circuit boards generate an implemented at thyristor level.
alarm and are indicated on the local HMI by position. The SVC includes a number of control modes and features
Beside the protective functions realized in the control necessary to perform the task of dynamic voltage support
system the protection of the SVC main circuit relies on during difficult system contingency situations. Among the
conventional protective relays. The system is fully redundant more important functions are the TCR current and secondary
including dedicated current and voltage transformer cores. voltage limitations, the purpose of which is to protect the
The redundant protective relay systems utilize relay units of SVC by keeping operation within the equipment continuous
different manufacturers to minimize systematic failures in rating. The SVCs have a limited overload capability in the
relay units and settings. inductive range to handle system overvoltage. In addition to
the obvious task of automatic voltage control of the
VI. SVC CONTROL S YSTEM AND CONTROL FEATURES connecting HV bus, performed by an integrator based closed
loop regulator, some of the more important control functions
The SVC controller is a MACH2® system, built with state and operational modes include regulator gain supervision and
of the art computers, micro controllers and digital signal optimization, slow susceptance control and system
processors interconnected by high performance industry undervoltage strategy.
standard bus and fiber optic communication links. The
Gain Control
control system, depicted in figure 9 includes features like
internal supervision, Sequence of Event Recorders (SER) and Gain supervision is a tool for reducing the closed loop
Transient Fault Recorders (TFR), where the latter generates voltage regulator gain to the system conditions following
Comtrade® files triggered by HMI selectable quantities or reductions in the network fault level. This will secure the
events. All events are time tagged with a 1ms resolution. This SVC response to be as fast as possible without excessive
means that events brought into the control system through the overshoot or lingering oscillations with instability in the
I/O rack is time stamped when entering the I/O. voltage control as a result. The function acts on the number of
swings in the susceptance reference signal of the SVC
response. At a preset number of swings exceeding a preset
level the relative gain will be reduced in appropriately sized
steps, all of which are set from the local HMI. The gain is
reset from the local HMI, from remote via SCADA or
through the gain optimizing function if activated.
Gain optimization acts to adapt the gain to the prevailing
network conditions in that it can bring the gain back towards
the initial setting subsequently to a reduction, network
conditions allowing or making sure that it is kept at a lower
level if necessary. The gain optimizer works by generating
small step disturbances in the regulator input signal and
depending on the response, the relative gain is changed, as
illustrated in figure 10. Gain optimization can be disabled
independently from the gain supervisory function.
Figure 9. SVC control system, including protection and station control.

With this setup real time control and HMI/Gateway are


separated by design, utilizing industry standard embedded
software for user interaction and Local Area Network (LAN)
connection. Depending on the computing performance
required, different applications in the SVC control is located
in different parts of the control system. High speed
applications such as voltage synchronization, thyristor firing
orders, valve protection and high resolution TFR recording
are DSP based, while less demanding applications such as the
closed loop voltage control, various sequence control
schemes and low resolution TFR recording are main Figure 10. Relative gain in percent vs. time. Example of gain optimizer
computer based. Sampling of measured quantities such as action over 5 hours.
voltage and current is handled in the I/O boards.
Thyristor firing and monitoring are handled in the Valve Parallel SVC Operation
Control Unit (VCU). The VCU communicates with each
individual thyristor via two sets of fibers, one for each For SVCs operating in parallel or located electrically close
conduction direction. A fiber set contains two fibers, one for it is of obvious importance to handle control settings such
firing orders and the other for thyristor monitoring. Valve that the SVCs avoid hunting or counteracting each other.
These SVCs, like SVCs in general are designed to operate

Authorized licensed use limited to: UNIVERSITY OF WESTERN ONTARIO. Downloaded on July 18,2023 at 03:23:39 UTC from IEEE Xplore. Restrictions apply.
7

individually, with separate control, protection and auxiliary digital power system simulator used for a wide range of real
systems. Parallel operation of SVCs therefore requires means time studies. It performs electromagnetic power system
of coordinated control settings to be implemented [7]. The transient simulations with typical time steps of 50-75
most straightforward way of accommodating this is by a microseconds, utilizing a combination of custom software
Master-Slave scheme, designed to apply a common set of (RSCAD) and hardware.
control settings between the SVC units. The settings in the
Master will then automatically be applied in the unit acting as
slave. This typically applies to voltage reference, slope and
gain. Functions such as gain control and control of external
capacitors have to be treated with care in parallel SVC
operation. Gain adjustments can only be initiated by the
Master unit. The same is true for control of external shunt
banks and slow susceptance control.
Slow Susceptance Control
The slow susceptance control is an SVC susceptance
regulator implemented to keep the SVC output close to idle
or any desired set point during steady state network
conditions. The purpose is to preserve the SVC dynamic
range for contingency situations. The controller is designed to
slowly bring the SVC to the desired long term operating point
by slowly, over several minutes, adjusting the voltage Figure 11. RTDS setup
reference set point within a narrow window to reduce SVC
output. This enables slower operating system voltage The concept is to model pertinent parts of the system
controlling devices such as tap changers and breaker switched including the SVC, shown in figure 12, in the simulator and
capacitor banks to operate to cater for compensating long connect the control to the simulator through a signal interface
term voltage variations due to daily load changes etc. indicated in Fig. 11. The control, which is the actual MACH2
Undervoltage Strategies hardware and software installed at site, have access to exactly
the same current and voltage signals as when operating
The SVC is not allowed to trip for any type of undervoltage
installed at site. It will interact with the RSCAD based SVC
conditions. Depending on the severity of the undervoltage
model with the relevant signal exchange, sending back firing
condition the SVC will act in different ways. For transitory
pulses to the TCR and TSC branches modeled in the
undervoltages caused by system contingencies down to 0.3
simulator, emulating actual operation. This is done in real
p.u. the normal voltage control will handle the SVC output to
time during viable system contingencies staged in the
support the system, provided that the system fault clearance
simulator. With this method correct SVC behavior related to
works as intended. For voltages below 0.3 p.u. the thyristor
step response requirements, undervoltage strategies, etc. can
valves will be blocked, awaiting fault clearance and voltage
be verified for the actual power system in real time, internal
recovery to a selectable level, in this case 0.8 p.u. at which
SVC control system-based protective functions included.
the thyristor valves are de-blocked. The de-blocking level is
determined by the voltage level at which the cooling pumps
can be restarted. This depends on the type of auxiliary source
used, in this case the SVC MV bus is making the auxiliary
voltage basically follow the HV side. A thyristor level can
handle rated current for approximately 10 seconds without a
running cooling system. During undervoltage conditions the
valve current is considerably lower due to its voltage squared
dependence. By properly utilizing this characteristic the SVC
can handle undervoltage operation without introducing
auxiliary power equipment such as large UPS units, which in
the past have been found to add to complexity and adversely
affect reliability of SVC units. To release the control the
synchronizing supervision requires the PLL phase error to be
less than 10 degrees and the voltage level to be above 0.3 p.u.

VII. CONTROL VERIFICATION AND TESTING


An important aspect when implementing Var support
control schemes is to verify correct compensator behavior Figure 12. RSCAD model of one of the SVCs at Hamilton Rd substation.
depending on system properties such as fault level and
dynamic load properties before implementing the device in The definition of the simulator models used and the wind
the field. In this case this was done using a Real Time Digital scenarios and contingencies were agreed on during the initial
Simulator (RTDS®) [6], [7]. The RTDS is a modular, fully stages of the project. The actual controller that will be

Authorized licensed use limited to: UNIVERSITY OF WESTERN ONTARIO. Downloaded on July 18,2023 at 03:23:39 UTC from IEEE Xplore. Restrictions apply.
8

connected to the RTDS has access to the same VT and CT Local as well as remote faults were studied covering all
signals as implemented when installed and returns the firing types’ line to ground and line to line faults during a number
pulses to the RTDS. The ±10 V analogue output signals of of different wind and load scenarios. This was done for the
the RTDS are amplified to 110 V going in to the actual different CREZ system development scenarios. An example
MACH 2 control. SVC conventional relay protection can also plot from the RTDS study of a three phase fault one bus
be tested. This however generally requires RTDS interfacing removed from the Tesla SVC site is shown in figure 13. At
through amplifiers, which may practically limit the number of the initiation of the fault the SVC rapidly goes to full
relay units possible to test simultaneously. The RTDS system capacitive output. As the voltage drops below 0.4 p.u. the
itself was used for monitoring and recording of signals in the undervoltage strategy blocks the TSC branch. The TCR
power system as well as for recording of signals inside the branch is still in operation as the 345 kV bus voltage remains
control system. The internal built in MACH2 TFR was used above 0.3 p.u. and controls the SVC susceptance to zero. At
for recording and analyzing the results. On line monitoring fault clearance the SVC resumes normal operation. Note the
and operation of the SVC is done graphically from the HMI. intervention of gain reduction due to oscillations in the
The full PSSE network provided by AEP was used to susceptance reference signal.
develop appropriate network equivalents; one for each site.
The RTDS implemented network had explicitly modeled VIII. CONCLUSIONS
representation for approximately 20 buses surrounding the
SVC point of connection. The rest of the network was The CREZ system is built to transfer high amounts of
represented by equivalents bound with transfer impedances. asynchronously generated power over large distances. Since
The explicitly modeled parts included lines, series capacitors the system is more or less devoid of synchronous generation
with bypass included, shunt devices, transformers, loads etc. the system has a low short circuit ratio and high dV/dQ
Transmission lines were represented by Bergeron models to sensitivity. Thus, the system will require a significant amount
capture the frequency dependence. Any necessary of dynamic reactive power support, of which the Hamilton
modification to shunt devices to correctly represent their Rd and Tesla SVC units are part. To meet the reliability as
tuning was also done. Power flow and fault levels based on well as the system performance requirements the SVCs are
the PSSE cases were used to validate the equivalents. built combining a robust main circuit with an equally robust
A large number of load switching and system fault cases control system, using well proven and thoroughly tested
were studied for both sites at different critical system control functions.
locations, identified in dynamic performance studies Extensive effort have been given to analyzing the network
performed for the complete system in PSSE. All these cases harmonic impedance for viable contingencies taking system
were also run in PSCAD using the reduced system prior to structure properties, such as 345 kV double circuits on
the RTDS study for the purpose of comparison and common transmission towers into account. Of equal
verification. importance to correctly evaluate SVC impact on system
stability has been to properly represent the CREZ system
2
File: CNT M2FA_S2P1CNTA1 1 20121121 03;38;32_252000.CFG pertinent to the SVC installations in respect to variations in
1
wind generation and system fault level.
UP1_A [pu]
UP1_B [pu]
UP1_C [pu]

-1 IX. REFERENCES
-2
0.1
4
0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1 [1] Analysis of Reactive Compensation Design for the Competitive
Renewable Energy Zones Transmission Plan in Texas.
2
International Workshop on Large-Scale Integration of Wind Power
IP1_C [pu ]
IP1_A [pu]
IP1_B [pu]

0 into Power Systems. October 2010 Canada. W. Lasher, C. Carter,


-2 J. Daniel, R. Koessler, D. Martin, W. Wong
-4
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1 [2] Voltage Control Challenges on Weak Grids with High Penetration
1.2
of Wind Generation: ERCOT Experience. IEEE Power and Energy
1
Society General Meeting 2012, San Diego, CA.
VRESP [pu]

0.8
S-H Huang, J. Schmall, J. Conto, J. Adams, Y. Chang, C. Carter.
0.6

0.4 [3] The calculation of Switching Surges, Electra No. 32, January 1974
0.2
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1
1 [4] IEEE Std. 519-1992, IEEE Recommended Practices and
0.95 Requirements for Harmonic Control in Electrical Power Systems
REL_GAIN [pu]

0.9

0.85
[5] SVC Operation & Reliability Experiences. IEEE Power and
0.8
Energy Society General Meeting 2010, Minneapolis, MN.
0.75
A. Janke, J. Mouatt, R. Sharp, H. Bilodeau, B. Nilsson, M.
0.1
2
0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1
Halonen, A. Bostrom.
1 [6] Auas SVC, performance verification by RTDS and field tests,
BREF [p u]

2001 IEE Conference, London, UK. S. Boshoff, C. Van Dyk, L.


0
Becker, M. Halonen. S. Rudin, J. Lindholm, T. Maguire.
-1
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1 [7] Design, studies and implementation of two parallel large Static Var
Time [s]
Compensators in the Hydro-Québec 735 kV system, 2012 Cigré
Figure 13. TFR plot of three phase fault one bus removed from the SVC. Canada Conference, Montréal. L. Houle, F. Rochon, O. Turcotte,
Traces from the top: 345 kV bus voltage, SVC primary current, V. Morisette, A. Palesjo, J. Rasmussen.
voltage response, relative gain and SVC susceptance reference.

Authorized licensed use limited to: UNIVERSITY OF WESTERN ONTARIO. Downloaded on July 18,2023 at 03:23:39 UTC from IEEE Xplore. Restrictions apply.

You might also like