ORDER OF CONSTRUCTION PROCESS - CAMPEAU MASTER BATH - 2950 CEYLON DRIVE, COSTA MESA

Order of Construction Process Time Expected


to Complete

1 Demolition 1 Day Laird

2 Rough Electrical 1 Day Jonathan

3 Framing 1 Day Laird

4 Rough Plumbing 2 Days Laird

5 Hot Mop 1 Day Laird

6 Drywall install 3 Days Jonathan & JP

7 Float/Prep Walls 2 Days Laird

8 Make sure all prep work complete 1 Day All

9 Tile 4 Day Laird

10 Shower Glass Measure 1 Hour Jim / Clearview Glass 1 -2 Weeks for Chrome Hardware
glass to arrive

11 Grout 1 Day Laird

12 Install Vanity & Start Finished 2 Days Jonathan & JP


Carpentry

13 Painting 2 Days Jonathan & JP

14 Finished Plumbing 1 Day Laird

15 Finished Electrical 1 Day Jonathan & JP

16 Install Glass Shower Enclosure 1 Day Jim / Clearview Glass

Install Accessories (Art/Mirror, etc) & 1 Day Jonathan & Gina


Walkthrough