Weekly Dashboard-13
Weekly Dashboard-13
C1 – New HQ Offices
SPI SPI SPI
1 1
ENGINEERING PROCUREMENT CONSTRUCTION -1
WEEKLY PROGRESS DASHBOARD NO: 13 PLANNED: 90% PLANNED: 85% PLANNED: 77.3%
PROGRESS AS OF: 2-Nov-23 ACTUAL: 90% ACTUAL:
85% ACTUAL: 76.8%
10%
PROCUREMENT PROGRESS OVER ALL PROGRESS PAYMENT STATUS
● MATERIAL ● ACTUAL PROGRESS Project S-Curve 100%
CUMULATIVE PLANNED %
ORIGINAL CONTRACT ACCUMULATIVE
6%
WEEKLY PLANNED %
60%
● PURCHASE ORDER ● REMAINING PROGRESS 24,790,000.00 -
Actual 85.00%
85.00%
Remaining 23.20% 23.20% NET TOTAL PAYMENT
4%
PO REMAINING 40% CURRENT REVISED RELEASED
Remaining 15.00%
2% 20%
24,790,000.00
● FABRICATION & SITE DELIVERY ● VARIANCE PROGRESS OUTSTANDING INVOICE
13/M
20/M
27/M
7/Oc
6/Ma
14/O
21/O
28/O
10/Ju
17/Ju
24/Ju
1/Jul
8/Jul
15/Ju
22/Ju
29/Ju
12/A
19/A
26/A
16/S
23/S
30/S
11/N
22/N
3/Jun
5/Au
2/Se
9/Se
4/No
OVERALL COST STATUS PAYMENT STATUS
ep
ep
ep
ug
ug
ug
ov
ov
ct
ct
ct
ay
ay
ay
p
g
v
t
n
n
y
l
CASH FLOW (AED Milions) MAJOR MILESTONES
Plan Earned VARIANCE
ITEMS PLAN Actual
20.00 PROGRESS
18.30
18.00
16.88 1 Installation of firefighting main line and branches i 95.0% 90.0% -5%
16.06
16.00 15.17
2 Steel Structure 100.0% 100.0% 0%
14.00
13.09
12.52 4 Wall Partition in all building 100.0% 100.0% 0%
11.95
12.00 11.43
10.49 5 Installation of FCU installation 80.0% 76.0% -4%
9.55 9.72
10.00
8.75 6 Installation of tray and trunking for power 62.0% 58.0% -4%
7.96
8.00 7.60
7.08
5.93
6.53 7 Installation of tray and trunking for power 95.0% 90.0% -5%
6.00 5.20
4.68
4.16
4.00 3.58 8 Installation of HVAC ducting work in High level 90.0% 88.0% -2%
2.82
2.23
1.73
2.00 1.29 9 Chilled water pipe installation 75.0% 75.0% 0%
0.72
ENGINEERING NO DESCRIPTION STATUS REF DESCRIPTION ACTION TAKEN / DESCRIPTION DUE DATE OWNER
- 1 Installation of tray and trunking for power 1 Chilled water pipe installation
- 2 Installation of firefighting main line 2 Steel Structure
- 3 Finishing Works - Tiling 3
Planned 77.30%
Acutal 75.20%
REMAINING 24.80%
Remaining
24.80%
Planned 77.3%
Acutal 75.20%