Professional Documents
Culture Documents
Planning for bridge construction is required as it has huge impact on life of people. Social,
scientific and technological dimensions for bridge construction must be considered. The
decision of providing a bridge across any barrier is to facilitate the community residing on
either side of the project. Some major bridges bring benefits to the whole country.
There are three dimensions that are involved in the planning of any mega project like a
bridge. This is considered as an initial step towards the planning of structures, that would
finally bring up with a project that would be advantageous to the community in all aspects.
The three dimensions are:
● Scientific Dimension
● Social Dimension
● Technological Dimension
There exist certain laws for nature, based on which every structure constructed must perform.
Scientists explain these natural forms and the existence of these laws with the help of certain
inter-relations between certain elements. In one or the other form, the scientists or the
engineers make use of pre-existing technologies in nature, that the only difference is the
method they used to undergo. Various scientific developments that are made by the engineers
based on these; like bringing different alternative materials by chemical analysis, physics - to
observe and analyze the dynamic behavior of the structure; Mathematics - used to analyze
and determine the forces and the stresses. Hence efficient structures are evolved with the help
of the scientific dimension.
Social Dimension for Bridge Construction
Enhancement of quality of life of the people, are greatly facilitated by the bridge
construction. These structures improve the mobility of people as well as the material. This
dimension helps to realize the pros and cons of such construction and their related
precautions. Such a huge construction brings changes to the society and the people, but also
bring adverse changes to the environment. It is not only required for the bridges to satisfy the
need of mobility and the future demands but also must satisfy the problems related to noise,
pollution, during and after construction. As the structure is the for the welfare of the whole
community, the people are also committed and responsible for bringing their contribution to
this welfare in the form of taxes, levies or in the forms of tolls. This would help in looking
the construction as a cost benefited work and as a means of economic development. The
above considerations come under the social dimension. There are also chances for the
incorporation of political dimension with the social dimension. This arises in the situation of
choice of location or the facility, or in prioritizing the needs for the welfare of the economy.
The social dimension has a direct close connection with the scientific and the technological
dimension.
Technological Dimensions for Bridge Construction
There have been many technological developments over decades in the field of new
structures, methods of construction and materials, as an alternative for rare ones and in
bringing new machinery that works over human workers. This technology has helped in
bringing and refining alternatives in the bridge construction. Now instead of bricks, steel,
cement etc., construction are carried out by glass fibers, carbon fibers etc. Going through
such innovations in technologies, the first FRP material constructed bridge was in China in
the year 1982. It composed of five box girders with a clear span of 20.4m. The development
of carbon fiber reinforced polymer i.e. CFRP cables, that gain a strength of 3300Mpa and
modulus of elasticity of 165GPa, was also made. The Winterthur Bridge in Switzerland,
make use of such cables. Two cables out of twenty-two are made of this material. The steel is
available with higher capabilities, like high strength varying from 60MPa to 100MPa, that
have remarkable ductility and corrosion resistance. These had led to the new construction
choices in arches, cable supported structures, slender structures and longer spans. The
accurate behavior of structures is clearly analyzed with the help of new techniques of scale
models, computers for huge analysis and aerodynamic studies. With the development of new
heavy vehicles with huge capacities, the engineers are forced to construct the bridges with
higher capacity. This will influence the strength and the dimensions of the bridge and affect
the maintenance related to the same. All these bring up a higher impact on the environment,
in the form of air pollution, higher depletion of natural resources. These massive structures
make use of huge amount of concrete, which in turn make use of aggregates from nature.
When it comes to the concern of a structural engineer, the scientific dimension comes to be
the primary criteria. But he must balance with the other two dimensions i.e. the social and the
technological dimension. This concludes that he must evolve a structure that is acceptable
socially at the same time economic, durable and efficient. This depends on how he chooses
the technological dimension, which must be conducted at the conceptual stage of the project.
The planning sequence for the construction of a new highway or a railway project is a major
part of the project planning. Based on the complexity of the barrier across which the bridge
must be constructed, the detailing of the project planning increases, because more
investigation must be carried out. In general, the major steps that are involved in the planning
for the construction of a new project is mentioned below:
The major steps that are involved in the planning for bridge construction are
An assessment of the traffic type and its quantum is necessary to decide the following factors:
The data collection for this must be done carefully so that a proper idea on how the traffic
pattern, the growth strategies such as agricultural, industrial as well commercial
developments are influenced. The bridge construction has a huge investment at the initial
stages. Once completed, a small variation or renovation is not recommended. So, it is advised
to bring a design that considers the future capacity requirements and traffic factors. The
traffic assessment study should be considered the following factors into consideration. This
mainly is carried out with the help of a traffic planner or an Economist.
While having a location study and fixing the location of the bridge, it is very essential to
consider the need and the location of cross drainage works if any. The cross-drainage work is
said to have 15 to 20 % of the overall project cost if it must be implemented. Hence before
choosing the alignment for bridge construction, it is necessary to determine all the possible
CD works and its effect. The following factors are considered reliable in fixing the location
of the bridge.
● Location chosen over a stream with no bends or meanders. It will be straight in reach.
● A stream with no branches or tributaries
● The location being confined with properly defined banks
● If the bridge or the culvert is with the road approach, on either side having maximum
extent
● If the crossing is normal to the alignment of the road and angle of skew is necessary,
limit it.
Other than the above-specified conditions, the major river crossings of the bridge
construction should satisfy the following conditions:
a) River regime
The river upstream must be straight. If there is bend in the downstream, it must be avoided.
The river in the reach must be free from whirls, excess current due to eddies. The channel in
reach must is narrow and well defined. The river regime should have inerodable banks that
are firm. If there are no inerodable banks, over gorging, guide banks in dry locations also
must be provided.
b) Approaches
During floods, the approaches must be secure from flood attacks or any major spills. High
expensive approach construction must be avoided. It is recommended to pass through
built-up areas, or high hills or through major basin or religious structures. The approaches
have a reasonable proximity to the main road. It should not let construction of costly
connecting link. The ideal approach will avoid the construction under water that is highly
costly and uneconomical. They should help in a way to bring lesser maintenance to the whole
system, hence increasing the life period of the bridges.
4. Reconnaissance Survey for Bridge Construction
This is a pre-feasibility study, which studies the entire reach of the river, that must be crossed;
to find out best and suitable position for bridge location. The factors each site satisfies are
taken as lists and each is analyzed individually, from which the best consideration is chosen.
The final number of feasible sites must be refined down to three or four, this can be done only
by going in detail of each site and refining the most suitable ones. During this stage, maps are
used to locate theses feasible sites. The direct assessment of the site is made to understand the
location features (local criteria), studying the existing and growth of traffic with the help of
surveys, knowing information from the people residing, simple routes and short cuts in the
area, river flow and its spread are also studied. A feasibility study on the economy of cost, the
duration of construction, the sources of resources are also assessed. Now the whole
information is gathered and a comparison is made. Based on the discussion and refinement,
the best feasible site for implementation is chosen.
5. Preliminary Engineering for Bridge Construction
This stage of planning can be called as a techno-economic feasibility study. Here, the
technical details related to the bridge construction is studied in a detailed manner, to bring all
possible alternatives to proceed the construction. Mainly it is found that the total cost of the
project is plus or minus 15% of the cost that is estimated at this stage of planning. To process
the technical study, minimum level of field study and measurements, the location study, and
related parameters must be done.
This stage is the final stage of planning in the bridge construction, before the commencement
of the construction work. Full investigation from the roots is taken and documented. The
investigations conducted are:
● Ground survey
● Soil exploration- foundation details
● Hydrological data
● Model studies and analysis
Construction Planning:
The scheduling problem is to determine an appropriate set of activity start time, resource
allocations and completion times that will result in completion of the project in a timely and
efficient fashion. Construction planning is the necessary fore-runner to scheduling. In this
planning, defining work tasks, technology and construction method is typically done either
simultaeously or in a series of iterations. More formally, an activity is any subdivision of
project tasks. The set of activities defined for a project should be comprehensive or
completely exhaustive so that all necessary work tasks are included in one or more activities.
Typically, each design element in the planned facility will have one or more associated
project activities. Execution of an activity requires time and resources, including manpower
and equipment, as described in the next section. The time required to perform an activity is
called the duration of the activity. The beginning and the end of activities are signposts or
milestones, indicating the progress of the project.
For example, the problem of placing concrete on site would have sub-activities associated
with placing forms, installing reinforcing steel, pouring concrete, finishing the concrete,
removing forms and others. Even more specifically, sub-tasks such as removal and cleaning
of forms after concrete placement can be defined. Even further, the sub-task "clean concrete
forms" could be subdivided into the various operations:
● Transport forms from on-site storage and unload onto the cleaning station.
● Position forms on the cleaning station.
● Wash forms with water.
● Clean concrete debris from the form's surface.
● Coat the form surface with an oil release agent for the next use.
● Unload the form from the cleaning station and transport to the storage location.
Sub-division yields no benefit if reasonably accurate estimates of activity durations and the
required resources cannot be made at the detailed work breakdown level. On the other hand,
if the specified activities are too coarse, it is impossible to develop realistic schedules and
details of resource requirements during the project. More detailed task definitions permit
better control and more realistic scheduling. It is useful to define separate work tasks for:
repare and check shop drawings" should be divided into a task for preparation and a task for
checking since different individuals are involved in the two tasks and there may be a time lag
between preparation and checking.
In practice, the proper level of detail will depend upon the size, importance and difficulty of
the project as well as the specific scheduling and accounting procedures which are adopted.
However, it is generally the case that most schedules are prepared with too little detail than
too much. It is important to keep in mind that task definition will serve as the basis for
scheduling, for communicating the construction plan and for construction monitoring.
Within these subdivisions, we identify clearing, excavation, filling and finishing (including
seeding and sodding) associated with earthwork, and we define watering, compaction and
paving sub-activities associated with pavement. Finally, we note that the roadway segment is
fairly long, and so individual activities can be defined for different physical segments along
the roadway path. In Figure 9-2, we divide each paving and earthwork activity into activities
specific to each of two roadway segments. For the culvert construction, we define the
sub-divisions of structural excavation, concreting, and reinforcing. Even more specifically,
structural excavation is divided into excavation itself and the required backfill and
compaction. Similarly, concreting is divided into placing concrete forms, pouring concrete,
stripping forms, and curing the concrete.
Fig: Illustrative Hierarchical Activity Divisions for a Roadway Project
Once work activities have been defined, the relationships among the activities can be
specified. Precedence relations between activities signify that the activities must take place in
a particular sequence. Numerous natural sequences exist for construction activities due to
requirements for structural integrity, regulations, and other technical requirements. For
example, design drawings cannot be checked before they are drawn.
Suppose that a site preparation and concrete slab foundation construction project
consists of nine different activities:
A. Site clearing (of brush and minor debris),
B. Removal of trees,
C. General excavation,
D. Grading general area,
E. Excavation for utility trenches,
F. Placing formwork and reinforcement for concrete,
G. Installing sewer lines,
H. Installing other utilities,
I. Pouring concrete.
With this information, the next problem is to represent the activities in a network diagram and
to determine all the precedence relationships among the activities. One network
representation of these nine activities is shown in Figure.
Alternatively, the nine activities could be represented by nodes and predecessor relationships
by branches or links, as in Figure 9-6. The result is an activity-on-node diagram. In Figure
9-6, new activity nodes representing the beginning and the end of construction have been
added to mark these important milestones.
Estimating Activity Durations
In most scheduling procedures, each work activity has an associated time duration. These
durations are used extensively in preparing a schedule. For example, suppose that the
durations shown in Table 9-3 were estimated for the project diagrammed in Figure 9-0. The
entire set of activities would then require at least 3 days, since the activities follow one
another directly and require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3 days.
In many cases, the number or amount of resources applied to particular activities may be
modified in light of the resulting project plan and schedule. The calculation of a duration as
in Equation is only an approximation to the actual activity duration for a number of reasons.
First, it is usually the case that peculiarities of the project make the accomplishment of a
particular activity more or less difficult
Illustration of Productivity Changes Due to Learning
Random factors will also influence productivity rates and make estimation of activity
durations uncertain. For example, a scheduler will typically not know at the time of making
the initial schedule how skillful the crew and manager will be that are assigned to a particular
project. The productivity of a skilled designer may be many times that of an unskilled
engineer. In the absence of specific knowledge, the estimator can only use average values of
productivity.
In addition to the problem of estimating the expected duration of an activity, some scheduling
procedures explicitly consider the uncertainty in activity duration estimates by using the
probabilistic distribution of activity durations. That is, the duration of a particular activity is
assu med to be a random variable that is distributed in a particular fashion. For example, an
activity duration might be assumed to be distributed as a normal or a beta distributed random
variable as illustrated in Figure 9-9. This figure shows the probability or chance of
experiencing a particular activity duration based on a probabilistic distribution.
The estimation problem is increased considerably since more than one parameter is required
to characterize most of the probabilistic distribution used to represent activity durations. For
the beta distribution, three or four parameters are required depending on its generality,
whereas the normal distribution requires two parameters.
Potential bottlenecks can thus be identified, and schedule, resource allocation or technology
changes made to avoid problems.More detailed definitions of required resources would
include the number and type of both workers and equipment required by an activity as well as
the amount and types of materials. Standard resource requirements for particular activities
can be recorded and adjusted for the special conditions of particular projects. As a result, the
resources types required for particular activities may already be defined. Reliance on
historical or standard activity definitions of this type requires a standard coding system for
activities.
Resource Requirements for Block Foundations
In placing concrete block foundation walls, a typical crew would consist of three bricklayers
and two bricklayer helpers. If sufficient space was available on the site, several crews could
work on the same job at the same time, thereby speeding up completion of the activity in
proportion to the number of crews. In more restricted sites, multiple crews might interfere
with one another. For special considerations such as complicated scaffolding or large blocks
(such as twelve inch block), a bricklayer helper for each bricklayer might be required to
insure smooth and productive work.
Coding Systems
One objective in many construction planning efforts is to define the plan within the
constraints of a universal coding system for identifying activities. Each activity defined for a
project would be identified by a pre-defined code specific to that activity. The use of a
common nomenclature or identification system is basically motivated by the desire for better
integration of organizational efforts and improved information flow. In particular, coding
systems are adopted to provide a numbering system to replace verbal descriptions of items.
These codes reduce the length or complexity of the information to be recorded.
MASTERFORMAT involves a hierarchical coding system with multiple levels plus keyword
text descriptions of each item. In the numerical coding system, the first two digits represent
one of the sixteen divisions for work; a seventeenth division is used to code conditions of the
contract for a constructor. In the latest version of the MASTERFORMAT, a third digit is
added to indicate a subdivision within each division. Each division is further specified by a
three digit extension indicating another level of subdivisions.
The first four digits indicate the project for this activity; this code refers to an activity on
project number 0534. The next five digits refer to the MASTERFORMAT secondary
division. Note that a number of additional activities would be associated with column footing
34, including formwork and concreting. Additional fields in the coding systems might also be
added to indicate the responsible crew for this activity or to identify the specific location of
the activity on the site (defined, for example, as x, y and z coordinates with respect to a base
point).