Professional Documents
Culture Documents
... Deep Sea Offshore Wind
... Deep Sea Offshore Wind
February 2010
2
TABLE OF CONTENTS
Page
1 PROGRAMME ....................................................................................................................... 4
2 LIST OF PARTICIPANTS ..................................................................................................... 6
PRESENTASJONER
Grid connection
From power markets to voltages and currents, Prof Kjetil Uhlen, NTNU………………………………………… 71
Sub-stations for offshore wind farms, Steve Aughton, Siemens T&D Limited…………………………………… 76
New converter topologies for offshore wind farms, Prof Marta Molinas, NTNU………………………………… 79
Power quality measurements from wind farms, Trond Toftevaag and Tarjei Solvang, SINTEF………………… 83
12X650 TR A6920
3
Hydrodynamic effects on bottom-fixed offshore wind turbines, Karl O. Merz, PhD student NTNU, …………. 121
Prof G Moe, NTNU, Prof Ove T. Gudmestad, Univ. of Stavanger
Supply of jackets to the Alpha-Ventus wind farm, Jørgen Jorde, NorWind……………………………………. 123
Cost comparison of sub-structures, Daniel Zwick and Haiyan Long, PhD students NTNU…………………… 126
Closing session – expert panel on R&D needs for developing offshore wind farms
The European research agenda on offshore wind, Beate Kristiansen, Research Council of Norway…………. 131
State-of-the-art design practices for offshore wind farms, Peter Hauge Madsen, Risø DTU…………………. 134
Panel debate on R&D needs for developing offshore wind farms, Dr habil Hans-Gerd Busmann,
Head of Fraunhofer IWES
12X650 TR A6920
4
19.00 Dinner
5
Final programme
The need for a Norwegian test and demonstration programme on offshore wind
John Olav Giæver Tande, SINTEF / NOWITECH
11
Area
Thomas Trötscher
Magnus Korpås
John Olav Tande
SINTEF Energy Research
1 2
40
GW
-20
30
-40
20
-60
10 Wind power "deficit"
Wind power surplus
-80
0
40 60 80 100 120 140 160 1000 2000 3000 4000 5000 6000 7000 8000
Installed wind power (GW) Hours
5 6
12
0.9 0.9
5
0.8 0.8
GW
0.7 0.7
0
0.6 0.6
0.4 0.4
-10
0.3 0.3
+1000MW pumping
21 5. BC + 4500MW exchange capacity
0.4
6. BC + 3500MW exchange capacity +
20 10TWh wind
7. BC + 3500MW exchange capacity +
0.2 10TWh run-of-river hydro
19
18
0 1 2 3 4 5 6 7
0 10 20 30 40 50 60 70 80 90 100
Simulation case #
Percent of time
9 10
2000
Simulation cases
1
1. Base Case (BC) 1500
500
4. BC +3500MW exchange capacity
0.6
+1000MW pumping 0
5. BC + 4500MW exchange capacity
-500
6. BC + 3500MW exchange capacity +
0.4
10TWh wind -1000
7. BC + 3500MW exchange capacity +
10TWh run-of-river hydro -1500
0.2 Base Case
-2000 Base Case +3500MW
Base Case +3500MW +10TWh
0
1 2 3 4 5 6 7 -2500
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Simulation case #
11 12
13
4000 8
6
98% utilization
Exchange NO->EU (MW)
2000 4
Exchange (GW)
2
0 0
-2
-2000 -4
-6
-4000 Base Case -8
Base Case +3500MW
Base Case +3500MW +10TWh -10
-6000
1000 2000 3000 4000 5000 6000 7000 8000 1000 2000 3000 4000 5000 6000 7000 8000
Hours Hours
13 14
Discussion Conclusions
► Internal grid bottlenecks ► Norway can act both as a net exporter of renewable electricity
and as a ”battery” for Europe
► Limitations on water flow Provided the exchange capacity is suitably expanded
► Capacity upgrade and reserve requirements ► Norway can help Europe meet its balancing needs
► Norwegian hydro reservoirs have sufficient capacity
Down-regulation capability is limited by little pumping capacity during
the spring thaw
Up-regulation capability is less of an issue, but is somewhat limited in
the winter time
► We should not fear to ”import” European prices
As long as the planned amount of wind power is built in the North Sea
region, prices in Norway will likely fall slightly and stabilize
Prices will be less influenced by the annual changes in inflow
15 16
14
CONTENT
Statkraft in brief
Development of Round 3 – UK
Challenges
Expectations
Bjørn Drangsholt, Vice President
Wind Power R&D Seminar R&D
Royal Garden, Trondheim, 21st January 2010
Opportunities
90% RENEWABLE
Continue onshore development
ENERGY Technology and expand into offshore
Wind power
264
POWER STATIONS
AND DISTRICT
HEATING PLANTS
35%
OF NORWEGIAN
POWER
PRODUCTION
Geographic focus on the North
3200 20
Geography
...IN OVER Sea Area
EMPLOYEES.. COUNTRIES
side 4
3
Page 9
Equivalent in size to North Yorkshire or Vest Agder in Norway Forewind has agreed with The Crown Estate a target installed capacity of
9GW, though the zone has a potential for approximately 13GW, which
This is the largest zone in Round 3 equates to around 10 per cent of the total projected UK electricity
requirements.
The water depth ranges from 18–63 metres
Our 25% share is estimated to cost Statkraft 350 MNOK up to 2014 / 2015
The owners are building a project organization through the Forewind Ltd
company
side 11 12
16
Water depth
Wave climate
Limiting installation
Page 14
Page 15
Aker Verdal AS
3 4
1
18
HyWind 2,3 MW
floating wind turbine
(owned & operated
Re. Energy Sys Lab Material testing by Statoil)
GE (ScanWind)
0.2 MW
9 10
► Arena NOW, Arena Vindenergi, Norcowe, and Nowitech have ► The above will be achieved through the realisation of a
agreed to take a common approach as to define a national plan coordinated national offshore wind test and demonstration
for an offshore wind demonstration programme. programme.
11 12
2
19
► Suggestion: A NOK 5 billion test & demo programme ► Small scale (200 kW) test turbine for open
a necessary step between R&D and large scale deployment experimental research (infrastructure application due
30/1-2010 by NORCOWE, NOWITECH and CEDREN)
6000
► Test and Demonstrate ► Prototypes, possibly in scale, of various new turbine
Accumulated investment (MNOK)
5000
4 demo parks deep sea technology
(bottom fixed & floaters)
concepts and technologies (bottom-fixed and floaters)
4000
► Utilize R&D results & ► Demonstration wind farms of semi-commercial nature,
3000 gain new knowledge showcasing planning, installation, new technology,
2000 4 test turbines ► Qualify suppliers operation, access, grid connection, ..
1000
► Kick-off offshore wind ► Open programme; significant state funding; locations
farm development
0
and applications for test and demo are decided by
► Create new industry and
2009 2010 2011 2012 2014 2016 2018 2020
employment
developers; funding based on rational criteria
Year
13 14
3
20
3 4
1
21
HyWind 2,3 MW
floating wind turbine
(owned & operated
Re. Energy Sys Lab Material testing by Statoil)
GE (ScanWind)
0.2 MW
9 10
► Arena NOW, Arena Vindenergi, Norcowe, and Nowitech have ► The above will be achieved through the realisation of a
agreed to take a common approach as to define a national plan coordinated national offshore wind test and demonstration
for an offshore wind demonstration programme. programme.
11 12
2
22
► Suggestion: A NOK 5 billion test & demo programme ► Small scale (200 kW) test turbine for open
a necessary step between R&D and large scale deployment experimental research (infrastructure application due
30/1-2010 by NORCOWE, NOWITECH and CEDREN)
6000
► Test and Demonstrate ► Prototypes, possibly in scale, of various new turbine
Accumulated investment (MNOK)
5000
4 demo parks deep sea technology
(bottom fixed & floaters)
concepts and technologies (bottom-fixed and floaters)
4000
► Utilize R&D results & ► Demonstration wind farms of semi-commercial nature,
3000 gain new knowledge showcasing planning, installation, new technology,
2000 4 test turbines ► Qualify suppliers operation, access, grid connection, ..
1000
► Kick-off offshore wind ► Open programme; significant state funding; locations
farm development
0
and applications for test and demo are decided by
► Create new industry and
2009 2010 2011 2012 2014 2016 2018 2020
employment
developers; funding based on rational criteria
Year
13 14
3
23
Long blades for offshore turbines, Jørg Høyland, PhD student NTNU
A Quantitative Comparison
of Three Floating Wind Turbines
NOWITECH Deep Sea Offshore Wind Power Seminar 9 National Renewable Energy Laboratory NOWITECH Deep Sea Offshore Wind Power Seminar 10 National Renewable Energy Laboratory
4.4
2.0
+ Only slight increase in ultimate & fatigue loads
− Expensive anchor system
1.5
OC3-Hywind Spar Buoy
+ Only slight increase in blade loads
1.0
0 Moderate increase in tower loads; needs strengthening
0.5 − Difficult manufacturing & installation at many sites
ITI Enery Barge
0.0
t nt ft nt ng nt e ent − High increase in loads; needs strengthening
oo me ha me ari me as
d e R Mo e d S Mo Be Mo e r B Mom
a
Bl ding e
Sp ndin
g w
Ya ding
w
To ding − Likely applicable only at sheltered sites
n w- n n
Be Lo Be Be Be + Simple & inexpensive installation
NOWITECH Deep Sea Offshore Wind Power Seminar 11 National Renewable Energy Laboratory NOWITECH Deep Sea Offshore Wind Power Seminar 12 National Renewable Energy Laboratory
26
Ongoing Work & Future Plans Model Verification through IEA OC3
• The IEA “Offshore Code Comparison Collaboration” (OC3)
• Assess role of advanced control is as an international forum for OWT dynamics model
• Resolve system instabilities verification
• Optimize system designs • OC3 ran from 2005 to 2009:
– Phase I – Monopile + Rigid Foundation
• Evaluate system economics
– Phase II – Monopile + Flexible Foundation
• Analyze other floating concepts: – Phase III – Tripod
– Platform configuration – Phase IV – Floating Spar Buoy
– Vary turbine size, weight, & configuration • Follow-on project to be started in April, 2010:
• Verify under IEA OC3 – Phase V – Jacket
• Validate simulations with test data – Phase VI – Floating semi submersible
NOWITECH Deep Sea Offshore Wind Power Seminar 13 National Renewable Energy Laboratory NOWITECH Deep Sea Offshore Wind Power Seminar 14 National Renewable Energy Laboratory
• Training new analysts how to run & apply codes Jason Jonkman, Ph.D.
correctly +1 (303) 384 – 7026
• Investigating the capabilities / limitations of jason.jonkman@nrel.gov
implemented theories
• Refining applied analysis methodologies
• Identifying further R&D needs
Operated for the U.S. Department of Energy Office of Energy Efficiency and Renewable Energy by Midwest Research Institute • Battelle
NOWITECH Deep Sea Offshore Wind Power Seminar 15 National Renewable Energy Laboratory
4-5 7-8
– Idling + loss of grid; all blades = 90º; nacelle yaw error = ±(20º to 40º)
2.0 Side- Fore
– Instability diminished in barge by wave radiation
to-Side -Aft
1.5
• Possible solutions:
In- Out-of- Side- Fore
0° 90° to-Side -Aft – Modify airfoils to reduce energy absorption
Plane Plane
1.0
– Allow slip of yaw drive
– Apply brake to keep rotor away from critical azimuths No Brake
4 Brake
0.5
S-S T-T Defl,
Brake Engaged
2
m
0
0.0
t ts aft nts ng ts e
as ent
s
ari en
-2
oo en Sh ome
e R Mom Be om rB m
a d e
e g
d M w M w e g Mo -4
Bl ing p
S d in Ya
ing To
in 0 100 200 300 400 500 600
nd w- nd nd
Be Lo Ben Be Be Time, s
NOWITECH Deep Sea Offshore Wind Power Seminar 17 National Renewable Energy Laboratory NOWITECH Deep Sea Offshore Wind Power Seminar 18 National Renewable Energy Laboratory
27
Idling:
DLC 2.1 & 7.1a Yaw Instability
• Aero-elastic interaction causes negative damping in a mode
that couples rotor azimuth with platform yaw
• Conditions:
– Normal or 1-yr wind & wave events
– Idling + fault; blade pitch = 0º (seized), 90º, 90º
– Instability in TLP & barge, not in spar or land-based turbine
• Possible solutions:
– Reduce fully feathered pitch to allow slow roll while idling
– Apply brake to stop rotor
No Brake
180 Brake
Platform Yaw,
90
deg
0
-90
Brake Engaged
-180
0 100 200 300 400 500 600
Time, s
NOWITECH Deep Sea Offshore Wind Power Seminar 19 National Renewable Energy Laboratory
28
PhD-stud
Start: April 2004
Jörg Höyland
Finish: April 2010
jorg@smartmotor.no
Mobile: +47 971 52 477
Wind Power R&D seminar 2010 Wind Power R&D seminar 2010 1
• Customized
• Compact
• High torque
• High efficiency
• Suitable for demanding environments
Wind Power R&D seminar 2010 2 Wind Power R&D seminar 2010 3
Wind Power R&D seminar 2010 4 Wind Power R&D seminar 2010 5
29
Wind Power R&D seminar 2010 6 Wind Power R&D seminar 2010 7
Wind Power R&D seminar 2010 8 Wind Power R&D seminar 2010 9
• Glass fiber
• Carbon fiber
• Carbon and glass
Wind Power R&D seminar 2010 10 Wind Power R&D seminar 2010 11
30
Non‐linear
method
Linear
method
Wind Power R&D seminar 2010 12 Wind Power R&D seminar 2010 13
FEM model
Material Weight Price
[tonn] [Euro]
Carbon 40.2 932 000 =
Carbon/glass 65.5 476 000
Glass 75.6 171 000
Reality?
Wind Power R&D seminar 2010 14 Wind Power R&D seminar 2010 15
Wind Power R&D seminar 2010 16 Wind Power R&D seminar 2010 17
31
F F
Wind Power R&D seminar 2010 18 Wind Power R&D seminar 2010 19
Strain gages and optical measuring points Test of 6m beam at IPM/SINTEF fatigue
laboratory
Wind Power R&D seminar 2010 20 Wind Power R&D seminar 2010 21
Wind Power R&D seminar 2010 22 Wind Power R&D seminar 2010 23
32
Wind Power R&D seminar 2010 24 Wind Power R&D seminar 2010 25
Questions?
Outline
Bill Leithead
Olimpo Anaya-Lara
Development of
machines based on lift
The earliest VAWTs force started by
were drag devices. Darrieus in the
1920’s. Further
Their direct developed in the US,
descendent is the but today common
Savonius rotor. consensus is that they
are not economical for
large machines.
3 4
3 27/01/2010 4
5 6
5 6
34
Costs
VAWTs for offshore
Cost of sub-system as %age of total 5MW HAWT cost:
7 8
9 10
9 10
11 12
35
13 14
13 14
Low Cp-max and low max tip Rotor diameter is large and
speed ratio rotor speed low
15 16
16
150
-50
Azimuth β (°)
17 18
36
torque Q (MNm)
25
12.55
12
20 11
10
9
15
8
7
10 6
5
4
5
3
max power
0 capped power
0.0 0.5 1.0 1.5 2.0 2.5 4 zone
3.0
rotor speed U (rpm) const. speed
• Due to dynamic stall effects, power can not be limited by stalling • Need to keep close to stall region, when stall regulated
19 20
19
22
37
HYWIND
Diameter at water line: 6m
Diam. submerged body: 8,3 m
DYNAMIC
DYNAMIC CHALLENGES
CHALLENGES ANALYSIS TOOLS
- Simo-Riflex-Hawc2 (Marintek / Risø)
- Hawc2 Offshore (Risø)
- Bhawc (Siemens Wind Power)
- Flex5 (Stig Øye / Statoil)
- Simo-Riflex-TDHMill (Marintek / Statoil)
Reference 1
15 Case: Waves
Only
Conventional 16,7
10 Control
Strategy
Estimator 2,4
5 Based Control
Strategy
0
0 100 200 300 400 500 600
time [s]
1
38
2
39
•Main Objective:
– Verify the overall behaviour of the Hywind concept in harsh
environment.
– Identify areas of improvements, either with respect to cost reduction
or improved functionality
•Test Cases
– A variety of test cases has been defined to observe the behaviour of
Hywind Demo under various environmental loadings and control
strategies.
3
40
•Since December 23rd 2009, Hywind Demo has been on automatic operating
mode at its rated power (2.3 MW) for average wind speeds up to 18 m/s. 2
1.01
0.99
mode for all wind speeds.
1
0.98
0.5
0.97
0
0.96
-0.5
0.95
-1
0 200 400 600 800 1000 1200 1400 1600 1800 0.94
0 200 400 600 800 1000 1200 1400 1600 1800
time [s]
time [s]
1.04
corresponding dynamic simulations.
blade pitch angle / mean(blade pitch angle) [-]
1.03
•Testing and analysis of different floater motion controllers.
rotor speed / mean(rotor speed) [-]
1.02 1
1.01
• Optimization of the Hywind substructure.
1
0.99 0.5
0.98
0.97
0.96 0
0 200 400 600 800 1000 1200 1400 1600 1800 0 200 400 600 800 1000 1200 1400 1600 1800
time [s] time [s]
Thank you !
Contributors: Bjørn Skaare, Tor David Hanson, Rune Yttervik, Finn Gunnar Nielsen, and Andreas Knauer.
4
41
Table 2 Spar buoy platform data. • Mechanical forces: Mooring line forces, a range of body-to-
Depth to platform base m 120
body coupling force models, control forces (DP system),
variable mass.
Water plane diameter m 6.5
Diameter of main part m 9.4
• Inertia- and gravity forces.
Volume m3 8030
Position of mass centre m -89.92
Position of buoyancy centre m -62.14 • User specified arbitrary ‘External Force’.
Platform mass, including ballast t 7303
Platform radius of gyration in pitch m 24
• The applied BEM code will give correct time-series results for
rotor and blade loads under conditions of changing
blade pitch angle, wind speed and direction, and tower
motion.
5000 1300
Thrust kN
Rotor power (kW) 4000
3000 800
0
0 100 200 300 400 500 600 700 800 900 1000 s 2000
Time
1000 300
0
-200 5 10 15 20 25
4 6 8 10 12 14
Spar heave (m)
0.0
Force, kN
4000
6
3000
5
500
4
2000
3
0 4 6 8 10 12 14
0
5 10 15 20 -500
0 100 200 300 400 500 600 700 800 900 1000 s
Time
Mean wind speed, m/s Significant wave height, m
Max Mean Min St.Dev. Max Mean Min St.Dev.
Conclusions
Parameter variation analysis results for the test case indicate that
Tower base moment vs seastate Tower base moment vs wind
Mean wind 8 m/s 6 m Hs waves
250 250 • The power production is weakly dependent on the seastate, except that
200 power fluctuation increases with increasing wave height.
Moment, MNm
200
Moment, MNm
150
150
100 • The maximum bearing forces and tower support forces are mainly
100
50 governed by wave induced pitch motions of the tower.
0 50
-50 0
-100 -50 • The wave induced motions will have a dominating effect on rotor
-150 -100 bearing forces and on tower support forces, but relatively small effect
4 6 8 10 12 14
on the wind power absorption performance.
5 10 15 20 25
Significant wave height Mean wind speed, m/s • It is the pitch motion of the spar buoy that appears to be the greatest
Max Mean Min St.Dev. Max Mean Min St.Dev. challenge to the turbine bearing- and support structure design in this
case. Accelerations in the range 0.3 -0.4 g, angles up to 8 deg in
extreme waves.
43
optinp
reoptfi
• Finalising implementation of turbine model in RIFLEX, to facilitate
sparini
elastic response analyses of mooring lines, tower and rotor blades. remifi
(Final part of KMB-project Deepsea Offshore Wind)
moorini
storeb
• WINDOPT – Optimization tool for minimum cost specification of floating NLPQL repldat
support structure and mooring system for a wind turbine (NOWITECH sparopt
activity for completing of pilot project initiated as part of KMB Deepsea
Offshore Wind.) nlfunc run WAMOF
vesmos
mooropt
nlgrad
run MIMOSA
MIMMAC
mimrep
mimextr
21‐
21‐22 January 2010
Prof. Robert Nilssen, NTNU Elkraft
1 2
3 4
5 6
46
Why not:
‐‐ High
High Investment
Investment costs
costs and
and weight
weight
9 10
11 12
47
13 14
Rotor Rotor
Shaft
Unique mobility
Aktivt volum
Active volume
17 18
48
19 20
21 22
Omformere og Styring
Additionally: Future requirements for ”improved work place environment” may become favourable for AW technology
Wind Power R&D Seminar, Trondheim, 21. January 2010
in
d
es
te
is
cc
ar
om
Su
St
Pr
Field test of gearbox in IRIS 225 kW turbine Phase 2: Multi-MW gearbox (RENERGI)
9 10
3 MW demonstration with strategic industrial partner Animation of eccentric gearbox in 225 kW turbine
Lyse Energy
Utsira demo site
• Energy company in Rogaland
– Revenue 2008, NOKm 4 395
– Operating profit 2008, NOKm 2 445
• Planned wind projects: Kvitsøy demo site
– Kvitsøy, Utsira and other demo sites
Bjerkreim,
– Partner in Skinansfjellet (90 MW) and Bjerkreim 150 MW
(150 MW)
– Utsira, 280 MW deep offshore Skinansfjellet,
– South North-Sea, 1000 MW, offshore 90 MW
3 MW turbine demo
• Lyse Energy is applying NVE
• AW to submit application to Enova
• 3 MW gearbox field test planned for Q3 South North-Sea, 1000 MW
11 12
11 www.anglewind.no
52
1 2 3
400
Top‐mass [ton]
By
Ole Gunnar Dahlhaug 300
The Norwegian University of Science and Technology
200
4 5 6
Top weight,
> 350 ton > 500 ton 310 ton - < 200 ton • Hydraulic brake Boost
5MW pump
Eliminates
gearbox
No Yes Partly No Yes Transformer • Control system
Generator Induction Synchronous Synchronous Synchronous Synchronous
Vestas, GE,
Leading Gamesa,
Enercon Multibrid DeWind ChapDrive
Suppliers Suzlon,
Siemen
53
7 8 9
H = 100 m
mg
10 11 12
13 14
Top-Mass Reduction
RePower ChapDrive
Item
5 MW 5 MW
Rotor 120 ton No change
Rotor main shaft 27 ton No change
Yaw 16 ton No change
Main frame 89 ton Reduced weight
Gearbox 63 ton Not present
Generator 17 ton Not present
Power output 0,3 W
Converter 5.5 ton Not present
Transformer 13 ton Not present
Nacelle housing 11 ton Reduced weight
Other 68.5 ton Reduced weight
Total top mass 410 ton ca. 200 ton
The weights of the RePower turbine are approximate figures.
The total weight are given at: www.repower.de
55
Power fluctuations from offshore wind farms, Prof Poul Sørensen, Risø DTU
A
A Vision
a Possible offshore
development
Prospects for new cross- 2020 -2040
border connectors
Hydro power
Storage Sydvest linken
Balancing
SK 1,2,3 SK
NO ??Windpark SK 4 Vindpark SK 4 1,2,3
NorNed 1+2
Ekofisk Ekofisk
DK 1,5GW
GB 33GW Increasing the
NORD.LINK / NorGer
exchange capacities
by approx.
Doggerbank 5000MW
NORD.LINK / NorGer
NL 6,5GW
NorNed GE 22GW
57
Sources: DG-TREN,3E/Greenpeace, TradeWind & Office of Metropolitan Architects (OMA), Imera, Mainstream Renewable Power, Adamowitsch,
Supersmartgrid.net,
2010-01-27Desertec 7 2010-01-27 8
Development of interconnectors and a possible future grid Offshore development in Norway as seen from the TSO
• TSO cooperation thru ENTSO-E, flexible regulators and political willingness
• Legal framework for offshore wind not yet approved, seems promising
•A possible grid will emerge as modules from national wind clusters and or new
• Dedicated areas to be selected for wind production offshore
interconnectors
• Interconnector routing may be located close to selected areas
• Interconnector technology
• Stepwise development
• VSC HVDC, recommended solution, supplier interface needed
• Voltage level, to be agreed • Technology and standards need development
• CIGRE to develop standards
• R&D development needed
• Offshore wind, very limited development before 2020 in Norwegian sector
• Multi-terminals, DC breakers
• Increased capacity and reduced losses • Electrification of offshore oil and gas installations may be a driver
Main message
• Statnett has knowledge and experience to take an active role in
development of interconnectors and a possible future offshore grid in the
A Th Vision
North Sea A
an
• VSC HVDC gives flexibility for the future, but more R&D is needed
a
ks Offshore 2020 -2040
• Offshore wind is not a driving force for a grid in Norwegian sector
for
• The value of flexible Norwegian hydropower for balancing and storage lis
will increase with more interconnectors
ten
• Norway has a large potential for onshore and offshore renewables if the
market is willing to pay the cost, subsidies included
• Develop wind and small hydro onshore first
ing
Statnett will by 2020 have the 5 planned interconnectors in
operation
Optimal design of a
~
? How to connect nodes with
transmission lines to achieve
optimal social benefit?
~
subsea power grid in
the North Sea Problem: Connect off-shore wind farms to the on-shore grid and build
interconnectors between countries
T. Trötscher, M. Korpås Objective: Maximize social economic benefit
SINTEF Energy Research AS Exogenous Capacity and location of offshore wind power clusters, possible land
variables: connection points, statistical description of wind and power prices,
onshore grid equivalent, cost scenarios for grid infrastructure.
Unknowns: Where to build cables and with what power rating
Problem This is a mixed integer problem which can be solved with a branch
type: and bound algorithm
AC-side
~
~ ~ ~
~ = = =
=
~
DC-side
~ ~ ~
= = =
30
Reanalysis wind velocity is used as basis
Input data assumptions 25 Adjustment factors as described in the
TradeWind project are applied to better
Wind velocity [m/s]
20
represent onshore and offshore wind conditions
A sample is drawn using empirical latin
15 hypercube sampling
Land connection nodes in relevant countries as latitude-longitude pairs Correlation in velocity is captured
Selected relevant connection points from the TradeWind project 10 The sample size can be kept relatively small
Marginal cost of generation, generation capacities and time series of load. Wind velocity is converted to power generation
5 by applying a power curve
Official ENTSO-E scenarios, same as in TradeWind
Capacity and location of offshore wind power clusters Power curves are made to represent large
0 20 40 60 80 100 clusters
Selected a few large clusters as identified in the TradeWind project
Percent of time Individual power curves are used for onshore
Existing exchange capacity between nodes and offshore wind turbines
Used the net transfer capacities as published by ENTSO-E
1
Cost scenarios for cables, converter stations, switchgear, and offshore 1
Normalized wind farm power output
platforms
Sum wind power generation
Adapted from the EU-IEE project WindSpeed. Work in progress. 0.8 0.8
Wind data
Interpolated reanalysis data with added variations
Power [p.u.]
0.6 0.6
Sources
TradeWind http://www.trade-wind.eu/ 0.4
0.4
WindSpeed http://www.windspeed.eu/
0.2 0.2
0 0
0 5 10 15 20 25 30 35 0 20 40 60 80 100
Wind velocity [m/s] Percent of time
SINTEF Energy Research 5 SINTEF Energy Research 6
59
Optimized grid
60oN 60oN
Optimized grid
60oN
Locked to radial
connections only...
Conclusions
Meshed grids give better economic benefit for the EU as a whole than
7000
58oN
950 do radial connections
2800
890
Steps should be taken to reduce regulatory barriers
2800
Potential of savings of around 25% of investment cost
2800
o
56 N 2800 Meshed grid have a higher utilization rate than do radial wind farm
connections (~70% vs ~45%)
Cost of VSC HVDC T-offs/circuit breakers as opposed to distance to
7120
Investement in grid infrastructure shore will influence optimal grid structure
700 1500 6.5 – 13.5 billion. €
54oN 7832
Depending on cost scenario Higher costs short distance radial + bilateral interconnectors
Savings by allowing a meshed Lower costs long distance meshed grid
grid: ~2 billion €
9662
7000
4200
Better reliability for wind farms Meshed grids also...
52oN
3560
9800
3850 with a meshed grid ... Improves reliability of grid connection for wind farms
Meshed grid is more complex to
... Makes it viable to connect wind farms further offshore
445
1056
3382 2400 operate
1066
2738 Uncertain costs of t-offs/circuit
breakers
~
~
~
~
50oN
0o 3oE 6oE 9oE
Outline
(for years 2007, 2010, 2015, 2020, Parameter updating Time dependent
- Wind series
2030 combined with +3 wind variants) - Wind and load by hour - Load series
- Cost of hydro production - Inflow (hydro)
Input time series of wind speed & load - Watervalues
demand (1 hour resolution)
External LP/QP solvers for DC and PTDF
Market model to compute power hour +1 Solve Optimal power flow
- bpmpd
balances and prices. Simple marginal DC/PTDF/AC - Clp
Scenario L M H Scenario L M H
sum (GW) 15.00 23.04 32.23 sum (GW) 21.25 42.86 55.67
SE:1.80 SE:3.80
SF:0.55 SF:1.35
NO:0.13 NO:0.48
GB:4.82 GB:6.32
DK:1.04 DK:1.59
NI:0.15 NI:0.15
DE:9.80 DE:20.35
IE:0.25 IE:0.25
NL:2.00 NL:3.45
BE:0.50 BE:1.25
FR:2.00 FR:4.00
1
61
2
62
Hydro power generation is influenced by Grid modelling detail level influence the
the new interconnectors simulated utilization of offshore cables
4
x 10 NO Hydro (Optimal grid) NO Hydro (Radial grid) NO Load North Sea Offshore wind
2
(a)
DE offshore – NL offshore DE offshore – GB offshore
1.5
Power (MW)
0.5
0
5000 5100 5200 5300 5400 5500 5600
hour
4
2
x 10 DE offshore – NO offshore DE mainland – DE offshore
(b)
PSST incl. internal
1.5
Power (MW)
grid constraints in DE
1
PSST without internal
0.5 grid constraints in DE
0
6000 6100 6200 6300 6400 6500 6600
hour
Grid Optimization tool (transport model)
SINTEF Energy Research 15 SINTEF Energy Research 16
Summary
Building an offshore grid instead of radial wind farm connections and point-to-
point interconnectors have positive effects on the power market:
Facilitates export of offshore wind directly to the most optimal market area -> lower
total power system operating costs
Bottlenecks in the mainland grid can be avoided
Higher utilization of installed subsea cables
Facilitates trade between countries when wind generation is low
Onshore grid modelling detail influences the simulated utilization of the
subsea cables
An offshore grid building strategy must reflect the plans and opportunities for
onshore grid upgrades
Must also take into account the expected continued growth in onshore wind
development
Norwegian hydro power will not only be used as buffer for offshore wind
The power exchange to/from Norway is also determined by variations in demand
and onshore wind generation at the continent
3
63
Poul Sørensen
Nicolaos Cutululis
Søren Larsen
Risø DTU - Wind Energy Division
2 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 January 2010
1.5
1.0
Equivalent wind speed
0.5
amp
0.0 -amp
harmonic
-0.5
-1.0
-1.5
0 5 10 15 20
Time
3 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 January 2010 4 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 January 2010
P,Q U
1 1.05
P U1
0.5 Q U2
Voltage (p.u.)
Power (p.u.)
U3
continuous 0 1
−0.5
−1 0.95
0 10 20 30 40 50 60 0 10 20 30 40 50 60
Time (s) Time (s)
1 1.05
P U1
0.5 Q U2
Voltage (p.u.)
Power (p.u.)
U3
0 1
startup
−0.5
−1 0.95
0 10 20 30 40 50 60 0 10 20 30 40 50 60
Time (s) Time (s)
5 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 January 2010 6 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22
January 2010
64
Horns Rev
7 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 8 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 January 2010
January 2010
1 min period
9 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 January 2010 10 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 January 2010
11 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 12 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22
January 2010 January 2010
65
20
14
12
10
00:00 02:00 04:00 06:00 08:00 10:00 12:00
Time
13 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 January 2010 14 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 January 2010
Djursland Anholt O
Djursland Anholt P
Horns Rev B
Horns Rev A
Horns Rev 2
Horns Rev
15 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 January 2010 16 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 January 2010
Power [pu]
0.3 0.3
(time scales from 0.1 s and larger)
0.2 0.2 • Variable speed (time scales from 5-10 s and larger)
0.1 0.1 – Large offshore wind farms have an impact on the area control at
0
0 50 100 150
0
0 20 40 60 80
power system level, only little dependency on technology (time scales
Time [hours] Time [hours] from minutes and larger)
30 min – Simulation tool developed and validated on wind farm level (Horns
Scenario 1 Scenario 2
1
HST
0.7
HST
Rev and Nysted data)
0.8
SST 0.6 SST
– Wind farm power fluctuations can be quantified in terms of reserve
0.5 requirement to balance the fluctuations
– Wind farm power fluctuations can also be seen as reliability issue
Power [pu]
Power [pu]
0.6
0.4
0.4
0.3 (e.g. reliability indeces like frequency and duration of storms)
0.2 – Planned large scale offshore development will require new solutions
0.2
0.1
to handle storms in a secure way (to be demonstrated in TWENTIES).
0 0
0 50 100 150 0 20 40 60 80
Time [hours] Time [hours]
17 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 January 2010 18 Risø DTU, Technical University of Denmark Wind Power R&D seminar Trondheim 21-22 January 2010
66
1 2
Example
Wind power – basics - 1
• Nordic hydro inflow
• The production in wind power varies
can vary 86 TWh
continuously:
between different
years (1996, 2001)
• Transport from north
Load
Sweden to south
Sweden 10000
MW
3 4
1000
Deviation
800
4,00%
600
nominal power)
3,00% 400
200
2,00% 0
00:00
03:00
06:00
09:00
12:00
15:00
18:00
21:00
5 6
1
67
MWh/h
500
250
0
-250
Transm. DK1 -> NO1
-500
Balance Norw. (NO1)
-750
Wind P. DK1
-1000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hour Source: ELTRA / NORDPOOL
7 8
Possibilities of
Balancing summary
external balancing
• Not only one part (region, country)
of the system should be considered An illustration
• A system wide balancing is
economically efficient Region Wind Share Maximal
power of local share of
• A system wide balancing is what load wind
we will get in a future with large energy power
Näsudden 50 MW 169 % 48%
amount of wind power
Gotland 90 MW 19 % 40 %
Sweden 339 MW 0.4 % 1.5 %
Consider the whole power system
9 10
Source:
• IEA Annex 25
• Final report,
Region Wind Share of local Maximal share of Phase one
power load energy wind power 2006-08
Näsudden 50 MW 169 % 48% • “Design and
(on Gotland) operation of
power
Gotland 90 MW 19 % 40 % systems
West 2380 MW 21 % 58 % with large
Denmark amounts of
Schleswig- 2275 MW 33 % 44 % wind power”
Holstein
11 12
2
68
13 14
03:00
06:00
09:00
12:00
15:00
18:00
21:00
-200
-400
• Higher ramp rates and fast start-up may become -600
15 16
03:00
06:00
09:00
12:00
15:00
18:00
21:00
-200
-400 • If an up-regulating bid from
-600 northern Finland is the cheapest
-800
-1000 and transmission limits are not
Requires flexible intraday markets!
-1200 violated, then this one is used!
-1400
• Distance: ~1400 km
= “Balancing service”?
17 18
3
69
19 20
21 22
General wind power and integration Registered wind power projects under
and balancing challenges development in Sweden.
Total: 24 400 MW 5340 MW (*)
22 %
• Low wind power production
Corresponding to ~
questions of wind power capacity credit,
import possibilities, dimensioning load 60 TWh 6400 MW
26 %
levels, etc
• High wind power production One of these
questions of transmission, flexible projects is 5580 MW
23 %
demand (very low prices!), pumped 4000 MW Snitt 1
4
70
B2 Grid connection
From power markets to voltages and currents, Prof Kjetil Uhlen, NTNU
Sub-stations for offshore wind farms, Steve Aughton, Siemens T&D Limited
New converter topologies for offshore wind farms, Prof Marta Molinas, NTNU
1 2
3 4
5 6
72
2
P
Tr D Tr D Tr D
V,I,f Tr D Tr D Tr D
Energy
1
Properties:
Fast dynamic control of active and reactive power
Fast dynamic control of current, voltage and
frequency
Very fast (close to instantaneous) current limitations
11
during faults 12
Source: SINTEF Energy Research
73
13 14
Frequency (Hz)
PSCAD 49.9
49.8
49.9
49.8
Grid-2
49.7 49.7
35MW 49.6 49.6
49.5 49.5
Model adjustments: 68 MW 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9
• 2 isolated AC grids 40 40
Grid-1
simple equivalents 8 MW
20 20
load 60MW 0 0
-10 -10
• New control loops 0 1 2 3 4 5
Time (s)
6 7 8 9 0 1 2 3 4 5
Time (s)
6 7 8 9
17 18 a. Before b. After
74
Concluding remarks
Control strategy attributes o Great possibilities and challenges with an offshore
transmission grid based on VSC HVDC
o Robust control of MTDC was achieved by DC
voltage droop characteristics o Market solutions must be adapted to the new possibilities
(to make optimal use of the controllability of HVDC and
o No need for fast communication between the increased complexity of the grid)
terminals o Technical and market based solutions must be developed
to realise the potential for exchanging balancing power
o The system can also contribute to primary
(in particular to utilise the flexibility of Norwegian hydro
frequency support power)
o Technical solutions can be developed for exchanging
primary reserves between different synchronous systems
(and contribute to primary frequency support)
19 20
Thank you.
21 22
23 24
75
Sub-stations for
offshore wind farms
Technology and issues for offshore wind
projects
Steve Aughton, Business Development Mgr. 24th September 2009 07:00 near Hartlepool
Siemens Transmission and Distribution Ltd. IG SUB 500MW, 2,100 tonnes, C£50M
The worlds first interconnected offshore substation sails out
Wind Power R&D seminar – deep sea offshore wind
21-22 January 2010, Royal Garden Hotel, Trondheim ..Only another 299 like this to go by 2030 (in Europe alone)
Page 1 January 2010 Steve Aughton Copyright Siemens all rights reserved Page 2 January 2010 Steve Aughton Copyright Siemens all rights reserved
Europe needs renewable energy Elements of an offshore wind farm & grid connection
Norway, (Ireland), & UK own the windy parts of the sea
Substations 10%
WTGs
47%
Cables 10%
Standardisation,
Supply Chain economies of scale
– lower costs
Costs Steady ramp up of Rodsand DK Horns Rev DK Barrow GB Princes Amalia (Q7) NL 2007 Lillegrund SW 2007
1
77
500
end, not suitable for offshore wind AC
DC
500
1,000MW
VSC
Siemens HVDCplus launched 2008 Supply chain will adapt to the market
Unique conversion system Assume the right market conditions will be created
AC
DC
Many benefits for offshore wind Remains a challenge for the supply chain
1,000MW
HVDC Plus from Siemens Part of a converter arm
VSC
Concept for offshore HVDC converter 2,000MW
Classic HVDC
Page 11 January 2010 Steve Aughton Copyright Siemens all rights reserved Page 12 January 2010 Steve Aughton Copyright Siemens all rights reserved
2
78
Siemens Energy
Solutions for off shore wind farms There are two futures for offshore wind
Page 13 January 2010 Steve Aughton Copyright Siemens all rights reserved Page 14 January 2010 Steve Aughton Copyright Siemens all rights reserved
79
Offshore Challenges
Reliability and efficiency
Reduced number of components and conversion stages
Modularity of the conversion system
S. Lundberg, Wind farm configuration and energy efficiency studies - series dc versus ac layouts. Lic. of
C. Meyer, ”Key components for future offshore DC grids,” PhD dissertation, Rheinisch-Westfallischen Eng. thesis, Chalmers University of technology, Goteborg, Sweden, 2006.
Technischen Hochschule Aachen, Germany, 2007
Marta Molinas Marta Molinas
NTNU – Jan 21, 2010 NTNU – Jan. 21,
2009
80
Marta Molinas
NTNU – Nov. 19,
2010
High efficiency,
Long-life time, 1 Back to Back Converter Reference for comparison
Down sizing,
2 Reduced Matrix Converter with Full Bridge
disadvantages:
Today’s available technology does not
block more than a few kilovolts
No capability for power decoupling
Snubber losses
IG or PM
AC AC
AC DC
S. Lundberg, Wind farm configuration and energy efficiency studies - series dc versus ac layouts.
Lic. of Eng. thesis, Chalmers University of technology, Goteborg, Sweden, 2006.
R. L. Steigerwald, R. W. De Doncker, M. H . Kheraluwala, “A Comparison of High-Power DC-DC A. Mogstad, M. Molinas, ”Power collection and integration on the electric grid from offshore wind parks,”
Soft-Switched Converter Topologies,” IEEE Trans. on Industry Aplications, vol. 32, no. 5, Sept. 1996 In proc. NORPIE 2008, June 2008, pp. 21062112.
81
0.7
0.6
Topolog Tot HF- RMC-FB
Components Switches
y al Trafo
Normalized losses
0.5
0
Marta Molinas 5 6 7
Frequency [kHz]
8 9 10
Conversion stages
Converter losses
Capacitor
Transformer
Several barriers
remain
High voltage blocking
Snubber losses
Not self energized
Losses comparison in the studied topologies Protective devices (DC circuit breaker, bypass,
impact of modulation and operation principle insulation)
loss model extraction
Electronic transformers
Transient studies:
On-shore three phase fault: use of kinetic energy in the turbine Collection and conversion plaforms
Loss of one wind turbine (by pass, reconfiguration)
HVDC line fault High frequency transformers
Operation at reduced AC voltage
MW scale converters
Implementation of Bi-directional switches with higher voltage blocking
capability for MW units or multi-generator turbine (modular approach)
Multi-domain design approach for high power density and high efficiency
Common denominator:
Laboratory tests of RMC Utilization of power electronics…
Marta Molinas
NTNU – Jan. 21,
2010
Concluding Remarks
Wind power encompasses several disciplines
For further details
within electrical engineering
http://www.elkraft.ntnu.no/eno/
Follow the link to “Publications”
In each of them the challenges related to
marta.molinas@elkraft.ntnu.no
integration are different…..and can be
conflictive Speak to me for more recent work…
Contents
Ongoing measurement campaign (SINTEF Energy Research)
About the measurements
Motivation for PQ-measurements in wind farms
Power Quality Measurements from
Case 1 Description/Overview
Wind Farms Case 1 Results
Case 2 Grid Topology
Wind Power R&D seminar – Deep Sea Offshore Wind Case 2 Description/Overview
21-22 January 2010, Royal Garden Hotel, Trondheim, NORWAY
Case 2 Results
Trond Toftevaag Tarjei Solvang
trond.toftevaag@sintef.no tarjei.solvang@sintef.no Conclusions
SINTEF Energy Research
1
84
THD
7 sec
Wind farm 2
24 wind turbines rated 2,3 MW
Induction generator with local reactive compensation
Main transformer 56 MVA
Measurements
On one wind turbine (2.3 MW, 0.69 kV level)
On main feeder to wind farm (66 kV level)
2
85
3
86
Reduced Matric Converter for Off-shore Wind Farm Applications, Alejandro Garces
Full Scale Wind Measurements Relevant for Offshore Wind Power, Gursu Tasar
Grid Integration of Offshore Wind Farms and Offshore Loads using Multiterminal
HVDC, Temesgen Haileselassie
Individual Pitch Control for Horizontal Axis Wind Turbines, Fredrik Sandquist
Introduction Figure 3: Block diagram of the proposed controller for the VSC
There are two different HVDC transmission technologies, i.e. Voltage vSd r
iSd*
Source Converter (VSC), using controllable switches like Insulated-gate ki1 k
bipolar transistors (IGBT), and Current Source Converter (CSC) or s + p1
iSd
Line-Commutated Converter (LCC), using controllable switches like d u
thyristors. L 123 Modulation To
dq scheme gates
The Hybrid HVDC option is aimed at combining advantages of both HVDC L q
technologies and compensating their drawbacks.
iSq ki1 k
Figure 1: Hybrid HVDC for Offshore Wind Farms Applications s + p1
r
VSC1 iSq*
vSq r vC1
LCC
p*1 q*1
ki2 kp2 ki2 kp2
AC s + *
iRd s + iSq*
GRID p1 q1
VSCn
VSCs, connected at the wind turbine, regulate the active and reactive power
r
Vd
using a d-q synchronous reference frame controller while the LCC,connected
ki
to the main grid, maintains the DC voltage using a PI controller.(In Figure k
s+ p
v C2
3 and Figure 4 is shown the proposed controller)
1
Hybrid Combining advantages Power flow in 0
0 0.5 1 1.5 2 2.5 3
of both HVDC one direction 2
(d) DC Voltages
V [pu]
1
0
0 0.5 1 1.5 2 2.5 3
Figure 2: Equivalent Scheme of the Hybrid HVDC 2
(e) AC voltage VSC
V [pu]
i DC1 i DC2 0
-2
R1 L1 R2 L2 Rcr 0 0.5 1 1.5 2 2.5 3
VSC1 (f) Active and Reactive Power in the VSC
2
Active power
L
VA [pu]
1 2 3 1
Reactive power
v S1 + 0
i
v S2 S1 L C + + 0 0.5 1 1.5 2 2.5 3
Vdircos
E1 time [s]
n E2 C2
i S2 _ vC1 VC2 _ (a)Start up hybrid HVDC
E3
v S3 L 1 2 3
i C1 i C2 _
i S3 (a) AC Voltage LCC
2
V [pu]
-2
2 2.05 2.1 2.15 2.2 2.25 2.3
(b) Active and Reactive Power LCC
System Description of the Hybrid HVDC 2
VA [pu]
d
A [pu]
dt
V [pu]
where iSdq = [iSd , iSq ] , vSdq = [vSd , vSq ] , ϑdq = [ϑd , ϑq ] represent the
0
2 2.05 2.1 2.15 2.2 2.25 2.3
(e) AC voltage VSC
line current, AC voltage and duty vector in dq coordinates. vC 1 is the DC 2
V [pu]
voltage in the DC link and iDC 1 is the DC current in the DC link. The 0
2
√
VA [pu]
1
3 2 3
vLLcosβ − iDC 2 ωLc
0
vC 2 = (3)
π π
2 2.05 2.1 2.15 2.2 2.25 2.3
time [s]
where vC 2 is the DC voltage in the DC link, β is the ignition advance angle, (b)Steady State up hybrid HVDC
iDC 2 is the DC current in the DC link, vLL represents the line-to-line voltage (From top to bottom) AC voltage in the rectifier, Active and reactive
in the AC side, Lc is the inductance in the AC side and ω is the angular power in the rectifier, DC current, DC voltage, AC voltage in the inverter,
frequency in the AC side. Active and Reactive power in the inverter.
http://www.ntnu.no/elkraft/energiomforming/ raymundo@elkraft.ntnu.no
88
The trend has been shifting from Onshore to Offshore due to social and political reasons. Due to this change of trend, new
challenges have been emerged which are coupled with Offshore Wind Farms like installation, transportation, operation, and
maintenance.
In the operation of Wind farms, main challenges are related with sudden failures and downtimes. Due to difficulties involved in
the accessibility, remote location of these farms from onshore and depot, high production losses due to far locations from onshore
due to sudden breakdown, high costs of corrective maintenance, and tough maritime environment are playing crucial role in the
formulation of maintenance strategies for Offshore Wind Farms.
Among the maintenance strategies, preventive and predictive ones are suitable for implementation in offshore wind turbines. The
primary focus of this research is to optimize the maintenance intervals for preventive and predictive maintenance choices.
Artificial Intelligence (AI) approaches like Artificial Neural Network, Genetic Algorithm, and Support Vector Machines could be
used for having an optimum maintenance interval for such kind of maintenance tools.
Condition monitoring (CM) based technologies, such as dynamic load characteristics, oil analysis, strain measurements, physical
condition of the materials, acoustic monitoring, performance monitoring etc, are quite helpful for monitoring of wind turbines. In
this research we will also focus on the condition monitoring of wind turbine and CM data will be used for deciding about the
maintenance. To define the deterioration models by using CM data and then formulation of the mathematical models based on that
data is also one of the core objectives this research.
Operational and Maintenance (O&M) cost reduction coupled with less downtimes is the underpinning of this research. Due to
Offshore Wind Farm locations, new challenges will emerge which may pose hindrances in reducing the O &M costs. Another
core objective of this research will be to overcome such challenges to minimize the O& M expenditure.
It is highly expected that Optimization of maintenance interval using AI techniques coupled with Condition Based Maintenance
strategies will give promising results.
89
Fatigue reliability analysis of Jacket-type offshore
wind turbine considering inspection and repair
Wenbin Dong , Zhen Gao , Torgeir Moan
Centre for Ships and Ocean Structures (CeSOS), NTNU, Norway
Abstract
Abstract Results
Results
Offshore wind turbines (OWTS) are subjected to the severe environmental loads and are less
in accessible than land-based turbines. Generally, the operation of OWTS is above five to ten
times more expensive than work on land. Considering these issues, reliability of OWTS is
crucial. Methods for reliability of OWTS are therefore needed.
The present paper focuses on fatigue reliability prediction analysis of tubular joints of a fixed
jacket offshore wind turbine designed for a North Sea site in a water depth of 70 m. For fatigue
analysis, one of the most important parts is the calculation of long term statistical response of
structures. The response analysis of OWTS must take account for the dynamic coupling
between the support structure platform motions and turbine motions, and this is a challenge Fig.1 Reliability index for welded joints in jackets as a function of time. Fig. 2 Reliability index for welded joints in jackets as a function of time.
now. The present paper uses a simplified method to model the Jacket-type offshore wind No inspection and repair The target level is given by Δd = 0.2 and no use of inspection and repair,
corresponding to a0=0.11 mm.The inspection and repair scheme is
turbine and calculates the load effect. Wind load is obtained in HAWC2 well known software for characterized by 4 inspections, aD=2.0 mm and aR=0.11 mm.
simulation of wind turbine response in time domain, and dynamic response of whole structure is
obtained in USFOS well known software for dynamic response analysis of space frame
structures.
In order to quantify the effect fo inspection depending upon its quality for a given inspection
strategy and optimize the inspection scheme at the design stage, a reliability based fracture
mechanics (FM) which depends on the quality of inspection in terms of probability of crack
detection curves is presented in this paper . The long term statistical distribution of stress
ranges of tubular joints is obtained by combination of time domain simulation for representative
sea states and SN-Miner-Palmgren approach. Target safety levels are taken from SN-Miner-
Fig. 3 Reliability index for welded joints in jackets as a function of time. Fig. 4 Reliability index for welded joints in jackets as a function of time.
Palmgren approach with no effect of inspection. The target level is given by Δd = 0.3 and no use of inspection and repair, The target level is given by Δd = 0.4 and no use of inspection and repair,
corresponding to a0=0.11 mm.The inspection and repair scheme is corresponding to a0=0.11 mm.The inspection and repair scheme is
characterized by 4 inspections, aD=2.0 mm and aR=0.11 mm. characterized by 3 inspections for Δd = 0.5 and 4 inspections for Δd =
0.6, aD=2.0 mm and aR=0.11 mm.
Objectives
Objectives
Determine the fatigue reliability of tubular joints at the design stage based on
design information
Quantify the effect of inspection for a given inspection strategy at the design
stage
Optimize the inspection scheme for tubular joints at the design stage Fig. 5 Reliability index for welded joints in jackets as a function of time.
The target level is given by Δd = 0.5 and no use of inspection and repair,
Fig. 6 Reliability index for welded joints in jackets as a function of time.
The target level is given by Δd = 0.7 and no use of inspection and repair,
corresponding to a0=0.11 mm.The inspection and repair scheme is corresponding to a0=0.11 mm.The inspection and repair scheme is
Decide on the allowable cumulative damage Δd (Δd is the design Miner’s sum characterized by 3 inspections for Δd = 0.6 and 4 inspections for Δd =
0.7, aD=2.0 mm and aR=0.11 mm.
characterized by 2 inspections, aD=2.0 mm and aR=0.11 mm.
at failure) depending upon the inspection scheme ( Note: β is reliability index ( t 1 ( PF t ) , Φ is standard normal probability distribution function) ; a0 is the initial crack size; aD is the
detectable crack size which is assumed given by the POD curve; aR is the initial crack size after repair; a/c is the crack aspect ratio ; Mred is
a parameter representing effects due to local weld toe smoothing, which is used in the local stress intensity magnification factor. )
Methods
Methods Conclusions
Conclusions
In present paper the effect of inspection depending upon its quality for a given inspection strategy for
Design information
welded tubular joints in jacket-type offshore wind turbine structures has been quantified by using probabilistic
methods. The conclusions are taken from the following assumptions: welded joints in North Sea structures, 4
• Jacket structure (partly based on information • Wind turbine year inspection interval, mean crack size after repair aR 0.11 mm and mean detectable crack size aD 2.0
from Aker Solution) – 5MW NREL wind turbine mm .
– Water depth: 70 m – Tower height:67 m; Weight:210 tonnes
Based on the OWTS model used in present paper, for tubular joints, loaded by bending and tensile stresses
– Jacket height: 92 m – Nacelle weight: 295 tonnes
with a bending-tension stress ratio of 4.0, the allowable cumulative damage ,when no inspection and repair is
– Soil data (Ekofisk) – Blade weight: 115 tonnes; Diameter: 126 m
implemented, is assumed to be 0.2,0.3,0.4,0.5 and 0.7 respectively. For the case of Δd=0.2, it may not be
– V: rated=12m/s, cutin=5m/s, cutout=25m/s
relaxed, when inspection scheme as described above is considered, as shown in Fig. 2 ; for the case of
– Automatic controller: Risø Nat. Lab.
Δd=0.3, it may be relaxed to 0.4, as shown in Fig. 3; for the case of Δd=0.4, it may be relaxed to 0.5-0.6,as
shown in Fig. 4; for the case of Δd=0.5, it may be relaxed to 0.6-0.7, as shown in Fig. 5; for the case of
Δd=0.7, it may be relaxed to 0.8, and only 2 inspections may be implemented, as shown in Fig. 6 .
Simplified method to model the Jacket-type M Based on the experience in offshore oil and gas industry in North sea, the inspection reliability is rather
K ambitious, especially for tubular joints in jackets, therefore, the relaxation in design criteria shown represents
offshore wind turbine
Cd a maximum effect of inspection on design criteria.
• HAWC2
– Beam, simple structure (monopile) Cm
– Wind force (dominating) References
References
– Operational / parked conditions
• USFOS [1].Mathisen Jan, O.Ronold Knut, Sigurdssion Gudfinnur. “PROBABILISTIC MODELLING FOR RELIABILITY ANALYSIS OF JACKETS”. Proc. the 23th OMAE
Conference,Vancouver, Canada,1 January,2004
– Imported nodal force from HAWC2
[2].Tong,K.C. “Technical and economic aspects of a floating offshore wind farm”, Journal of Wind Engineering and Industrial Aerodynamics,74-76(1998),399-410
– Wave and current forces [3].Moan, T. 2005. “Reliability-based management of inspection, maintenance and repair of offshore structures”. Journal of Structure and Infrastructure engineering
1(1): 33-62
– More complicated response analysis (jacket) [4].Vårdal, O.T. & Moan, T. 1997. ”Predicted versus Observed fatigue Crack Growth. Validation of Probabilistic Fracture Mechanics Analysis of Fatigue in North Sea
Jacket Equivalent HAWC2 USFOS
structure monopile analysis analysis Jackets”. Proc. 16th OMAE Conference, Yokohama, 13-18 April 1997
[5].Moan,T.& Hovde,G.O. Jiao, G.Y. 1994. “Fatigue reliability analysis of offshore structures considering the effect of inspection and repair”. Proc. the 6th ICOSSAR
structure Conference, Innsbruck, Austria. 9-13 August 1993
[6].Newman,J.C. and I.S. Raju 1981. “An empirical stress-intensity factor equation for the surface crack”. Engineering Fracture Mechanics: Vol. 15, No. 1-2, 185-192
[7].Marine Technology Directorate Limited 1992. Probability-based fatigue inspection planning. MTD Ltd Publication 92/100, London, England
[8].Vosikovsky et al. 1985. “Fracture mechanics Assessment of Fatigue Life of Welded Plate T-Joints Including Thickness Effect”. Proc. of 4th BOSS:453-464.
Wind-induced quasi-static response Dynamic response analysis Amsterdam: Elsevier, Amsterdam
[9].Moan T.,G.O. Hovde and A.M. Blanker 1993. “Reliability-Based Fatigue Design Criteria for Offshore Structures Considering the Effect of Inspection and Repair”.
Wave-induced quasi-static response
• Excited second global mode contributes to fatigue damage most Proc. 25th OTC:Vol. ,591-599, OTC 7189. Houston: Offshore Technology Conference
Wind-induced dynamic response of the [10].Burns, D.J., S.B.Lambert and U.H.Mohaupt 1987. “Crack Growth Behaviour and Fracture Mechanics Approach”. Proc. of Conference on Steel in Marine
first global mode • Long-term response analysis : wind response + wave response Structures: Paper PS 6. Delft: Delft University of Technology
Wind-induced dynamic response of the • Long-term statistical distribution of stress ranges of turbular joints fits weibull distribution [11].Madsen, H.O. and J.D.Sorensen 1990. “Probability-based optimization of fatigue design, inspection and maintenance”. Proc. 4th Integrity of Offshore Structures:
second global mode 421-438. London: Elsevier Applied Science
[12].Olesen, R. 1992. PROBAN General Purpose Probabilistic Analysis Program User’s Manual. Veritas Sesam Systems, Report No. 92-7049,Høvik, Norway
[13].Almar-Næss, A.(Ed.), Fatigue Handbook for Offshore Steel Structures,1985 (Tapir Publisher Trondheim)
[14].TSCF, Guidance Manual for Tankers Structures. Tanker Structure Cooperative Forum and IACS,1997 (Whitherby Publishers: London)
[15].Olufsen A.,Leira B.J. ,Moan T. etal. “UNCERTAINTY AND RELIABILITY ANALYSIS OF JACKET PLATFORM”, Journal of Structural Engineering, Vol. 118, No.
t T1 T2 T3 T4 10. 1992
Overturning moment in the operational condition 1 [16].Heredia-Zavoni,E; Silva-Gonzalez, F; Montes-Iturrizaga, R: “Reliability Analysis of Marine Platforms Subject to Fatigue Damage for Risk Based Inspection
1 = repair 1 Planning”, Journal of Offshore Mechanics and Arctic Engineering, Vol.130, 2008
0 = no repair 0
[17].Jonkman J.M. “Development of Fully Coupled Aeroelastic and Hydrodynamic Models for Offshore Wind Turbines”, proceeding of 2006 ASME Wind Energy
Fatigue reliability calculation considering the effect of inspection and repair 0 1
1 Symposium, 2006
• Safety margin for failure before time t 0 [18].Madhavan Pillai,T.M. Meher Prasad, A. “Fatigue reliability analysis in time domain for inspection strategy of fixed offshore structures”, Ocean Engineering,
ac
27(2000) 167-186
M t
da m
C t T A (1 ) m
M(t) > 0, safety; M(t) < 0, failure 0 1
m 0 0
a0 Y a B
1
Y
1 0
• Event margin for inspection 1
aD 0
da m
H C 0 T1 T0 A m 1 H > 0, crack is not detected,no repair; H < 0, crack is detected, repair 0
B Torgeir Moan
m
Y a
a0
Y
0 1 Wenbin Dong Zhen Gao
• Fatigue reliability calculation 1 0 dong.wenbin@ntnu.no zhen.gao@ntnu.no
torgeir.moan@ntnu.no
1 1 Supervisor and
– Failure probability considering inspection and repair : P f P M 0 | H 0 o r H 0 0 PhD candidate , Post. Doc ,
director , CeSOS,
1 Pf 0 CeSOS, NTNU,
– Reliability calculation : 1 CeSOS, NTNU, NTNU, Norway.
0 Norway.
• Method 1 0 Norway. Research
– FORM method (First Order Reliability Method) 1 topic: Reliability of
0
offshore wind
– software: DNV Proban 0
Inspection scheme turbines .
RESULTS
0.50 0.50 1.20
Single turbine (a) Low (a) (a)
S/D = 3 Optimum 1.00
0.40 S/D = 6 0.40 High
S/D = 9
Relative maximum CP
0.80
0.30 0.30
0.60
CP
CP
0.20 0.20
0.40
0.20
0.10 0.10
0.00
0.00 0.00 Single turbine S/D = 3 S/D = 6 S/D = 9
0.0 2.0 4.0 6.0 8.0 10.0 12.0 0.0 2.0 4.0 6.0 8.0 10.0 12.0
1.80 1.80 1.20
Single turbine (b) Low (b) (b)
1.60 1.60
S/D = 3 Optimum 1.00
1.40 S/D = 3 1.40 High
S/D = 3
Relative maximum CP
1.20 0.80
1.20
CT
0.80 0.80
0.60 0.40
0.60
0.40
0.40 0.20
0.20
0.20
0.00
0.00 Single turbine Low Optimum High
0.0 2.0 4.0 6.0 8.0 10.0 12.0 0.00
0.0 2.0 4.0 6.0 8.0 10.0 12.0
Figure 4: The relative maximum power coefficient (a)
downstream distance effect and (b) upstream
Figure 2: Wake interference effect on the Figure 3: Wake interference effect on the turbine operating at different tip speed ratios.
downstream model turbine performance at downstream turbine performance at different
different S/D locations (a) power coefficient and upstream operating condition (a) power
(b) thrust coefficient. coefficient and (b) thrust coefficient.
Conclusions
The results presented in this poster shows that the power losses for a turbine operating in the wake of another is significant. In
this study, it was observed that the loss in maximum power coefficient varies between about 29 and 45% depending on the
distance between the turbines and the operating tip speed ratio of the upstream turbine. Compared with the unobstructed
turbine, the thrust of the downstream turbine is generally lower. The reduction in power coefficient and thrust coefficient from
the downstream turbine is as a result of the velocity deficit in the wake so that the downstream turbine sees a considerably
lower freestream velocity than the upstream turbine and thus, less energy is available in the air stream.
However, by adjusting the operating condition of the upstream turbine, the power output from the downstream turbine can
be substantially enhanced. When the upstream turbine was operating at different tip speed ratios, the highest and lowest loss in
maximum power coefficient occured when the upstream turbine was operating at low tip speed and optimum tip speed ratios,
respectively. This is because at low and high tip speed ratios, less energy is extracted from the air stream by the upstream
turbine compared with when it is operating at optimum tip speed ratio and this leads to relatively higher wind speed in the
wake of the upstream turbine. This results in increased power and thrust coeffcients of the downstream turbine.
PRESENTED AT: WIND POWER R&D SEMINAR – DEEP SEA OFFSHORE WIND POWER, 21-22 JANUARY 2010, TRONDHEIM, NORWAY
Reduced Matrix Converter for 91
Off-Shore Wind Farm Applications
A. Garcés, M. Molinas
Norwegian University of Science and Technology
Faculty of Information Technology, Mathematics and Electrical Engineering
Department of Electric Power Engineering
Turbine
AC
weight of the converter. Matrix converter fulfills these requirements. RMC
DC
Figure 1: Propose energy conversion system hft
AC
RMC
DC
Generators
50 Hz Medium or High Frequency
DC
AC Square AC
Nancelle
Modular approach
The proposed topology can be used also as a modular solution with
multiple generator per turbine as shown in Fig 3. The concept of this
type configuration has been studied by Cotrell [1] from the mechanical
point of view. This kind of topology presents some advantages over
Generator
High Freq. the conventional one, like increasing of reliability and efficiency as well
RMC AC/DC as decreasing of gear box mass.
Transformer
(AC3/AC1) Converter
Figure 4: Simulation results
0.6
matrix converter. A high frequency high power transformer is
suggested to electrically isolate the generator and to raise the voltage. 0.4
High frequency is used to reduced the weight of the transformer and to
0.2
reduce the harmonic distortion. It is specially important for offshore
wind farms since the investment costs could be reduced. Electrolytic
0
capacitor is not required, therefore, reliability is increased. Efficiency is 5 6 7
f [kHz]
8 9 10
AN BN CN XN YP
Discussion
In all cases, losses in the reduced matrix converter are almost 20% less
than the losses in the conventional one. This inprovment in the
= Bidirectional switch = Two RB-IGBT efficienty is caused by the topology itselft and not by the semicondutor
used, since in both cases, parameters in the IGBTs are equivalent. On
the other hand, the green plot, shows the relation of losses between
the two converterts using an IGBT in the conventional one (SEMiX
151GD066HDs) and a RB-IGBT in the reduced matrix converter. In
Reduced matrix converter and RB-IGBT this case, the losses are decreased in almost 40%. This relation shows
The Reduced Matrix converter (RMC) requires bi-directional switches how the efficiency is improved not only due to the topology itself but
which can be built using reverse-blocking IGBTs. These RB-IGBTs can also due to the use of reverse blocking IGBTs.
form a bidirectional switch without the use of additional diodes,
resulting in an efficiency increase compared to a conventional devices. References
In spite that conventional IGBTs are theoretically able to block reverse J. Cotrell, Preliminary evaluation of a multiple-generator drive-train configuration
voltages, in practice, due to construction constrains,it is necessary an for wind turbines, in 21st American Society of Mechanical Engineers (ASME)
external diode. However, the new reverse-blocking IGBT has an Wind Energy Symposium, 2002.
intrinsic diode that leads to a reduction of the forward conduction state A. Odaka, J. Itoh, I. Sato, H. Ohguchi, H. Kodachi, N. Eguchi, and H. Umida,
voltage drop of the switch. Figure 2 shows in detail the converter. Analysis of loss and junction temperature in power semiconductors of the matrix
converter using simple simulation methods, in Industry Applications Conference,
2004. 39th IAS Annual Meeting. Conference Record of the 2004 IEEE, vol. 2,
Oct. 2004, pp. 850-855 vol.2.
A. Garces and M. Molinas, Investigation and losses comparison of a reduced
matrix converter for off-shore turbines, accepted in 5th IET International
Conference on Power Electronics, Machines and Drives, PEMD, April 2010.
http://www.ntnu.no/elkraft/energiomforming/ alejandro.garces@elkraft.ntnu.no
92
0,08 20
g / kWh
0,06 15
Methods 10
0,04
At its core, our research method is based on life-cycle 0,02 5
assessment (LCA) and economic input-output analysis 0,00 0
(IOA). Combining LCA and IOA in a common framework Onshore Offshore All sites Onshore Offshore All sites
serves two purposes. First, it ensures complete system sites sites sites sites
coverage. Second, it facilitates the simultaneous
modeling of environmental and economic impacts. By comparison, life-cycle emissions of a modern natural
gas combined cycle power plant is about 420 g CO2/kWh
(Ecoinvent database).
80 % Construction
Skipheia
1. SKIPHEIA
Skipheia is wind measuring station in Titran, Frøya, run by NTNU which is
Trondheim
located on the south west tip of Frøya (Sør Trøndelag). The station is 200 km
away from Trondheim and NTNU. It is highly exposed to ocean winds.
2. OBJECTIVES
•Analyzing Wind Characteristics: Full scale measurements: wind mean
… ?
and turbulent characteristics; temperature of Atmospheric Boundary Layer.
•Data for Wind Energy industry: estimation of dynamic loads, wind farm
producibility.
3. FACILITIES
• Three masts: 2 x 100m , 1 x 45m
• 400 kW test Wind Turbine
•Additional Mast (45m) in nearby island
• Measurement cottage
• Ultrasonic Gill Anemometers
•Range 0 – 65 m/s
Instrumentation Cottage
•Accuracy ±2 % @ 12 m/s Anemometers The two 100m masts
•Resolution 0.01 m/s
•Offset ±0.01 m/s
4. CURRENT ACTIVITY
• Dec 2009: Mast 2 equipped with 12
sonic anemometers and 7 RTDs.
• 6 Levels with Log height distribution
Prevailing • Acquiring Data with a sampling rate
Winds
of 1 Hz.
Gale force maritime wind. The Froya data base. Part 1: Sites and instrumentation.
Review of the data base, Odd Jan Andersen, Jørgen Lovseth.
1
16
Background
Significant wave height H1/3 (m)
14
0.8
To facilitate safe and economic design of floating wind turbines (FWT) it is
necessary to have a good description of the physical environment that the
12
wind turbine is subject to. This includes knowledge of which loads and load
10 0.6 combinations are relevant for design of the different components of the
wind turbine.
8
0.4 For land based and bottom fixed wind turbines there exist standards that
6
define these load cases, but none exist at the present for floating wind tur-
4
bines. It is believed that the existing standards are not sufficient, as the in-
0.2
fluence of waves and current will have relatively larger influence on the
2 floating turbine.
0
2 4 6 8 10 12 14 16 18 20 22 For calculations of the fatigue loading, it is customary to use aero-elastic
Wave period T (s)
simulation codes. For wind turbines, the averaging time is 10 min, whereas
Possible research areas of interest the mean sea-state period usually is 1-3 hours. Is there a need for different
approaches to keep calculation cost at a reasonable level?
• Investigation of relevant load cases (LC’s) for FWT:
Onshore wind fatigue LC’s use 600 s turbulent simulations. Still they are quite Figure 3: Illustration of joint wind and wave spectra
time consuming. For FWT’s, the number of possibly relevant LC’s are much
larger: Combined wind, wave height, wave frequency and current. What about
wind, wave and current directions? Can you always be sure that aligned loads
are more severe than misaligned loads? To reduce the numbers of LC’s one
Wind speed
This presentation illustrates the integration of RAMS aspects with the development of offshore wind power production system, by the
Propose & application of the life cycle model of Murthy et al. [3], which includes all phases from “cradle to grave”. It is shown to be an efficient
Implement approach for obtaining a holistic development process of the systems, especially focussing on the essential attributes for the
corrections successful exploitation offshore wind power.
Abstract
Abstract Results
Results
Bending moment Shear force
Proper performance of structures requires among other things that its 7.E+05 1.0E+04
6.E+05
failure probability is sufficiently small. This would imply design for survival
Moment (KNm)
5.E+05 0.0E+00
Shear (KN)
in extreme conditions. The failure of a system can occur when the 4.E+05 -120 -90 -60 -30 0 30 60 90
3.E+05
ultimate strength is exceeded (Ultimate Limit State) or fatigue limit 2.E+05
-1.0E+04
(Fatigue Limit State) is passed. The focus in this paper is on the 1.E+05
-2.0E+04
0.E+00
determination of extreme responses for ULS design checks. The present -120 -90 -60 -30 0 30 60 90
paper deals with coupled wave and wind induced motion and structural Elevation (m) -3.0E+04
Elevation (m)
response in harsh condition up to 14.4 (m) significant wave height and 49 Maximum bending moment in each
section along the structure in 1-hour analysis Maximum shear force in each
(m/sec) 10-min average wind speed (at top of tower, 90 m) for a parked 5
x 10 section along the structure in 1-hour analysis
floating wind turbine. In survival condition the wind induced resonant 6
x 10
10
Moment (kNm)
4
dynamic structural responses show that the process is wide banded. The
2
3
time domain simulation. Based on different simulations (20 1-hour, 20 2-
2
hours, 20 3-hours and 20 5-hours) the mean up-crossing rate has been 2
probable maximum and bending moment for up-crossing level of 0.0001 0 500 1000 1500 2000
time (sec)
2500 3000 3500
0
0 0.5 1 1.5 2 2.5
for present study are very close. The minimum total simulation time in Bending moment time history at z= -60 m
Frequency [rad/s]
order to get accurate results is highly correlated to the needed up- Dynamic response Statistics (1-hour simulation) Bending moment spectrum at z= -60 m
crossing level. The 1-hour and 2-hours original values cannot provide any Response Mean STD Skewness Kurtosis
information for 0.0001 up-crossing level. Comparison of different Nacelle Surge 78.64 10.69 0.002 2.63
simulation periods shows that the 20 1-hour simulations can be used in (m)
-1 Series1
order to investigate the 3-hours extreme bending moment if the proper Pitch (deg) 12.35 3.23 -0.116 2.32 Series2
-1.5 Series3
BM at 2.18e+5 6.14e+4 -0.026 2.98 Series4
extrapolation of up-crossing rate used.
into account the regularity of the tail region of the mean up-crossing rate. top (kN)
Normalized BM Average
The mean up-crossing rate is instrumental in obtaining statistics of Shear at blade 436.53 78.29 0.260 3.20 Up-crossing rate for 20 2-hours simulations
root (kN) and the average up-crossing rate (40 hours)
extremes. As the up-crossing of high levels are statistically independent
event, we can assume a Poisson distribution for extreme bending
moment. Conclusions
Conclusions
To limit the computational efforts to
determine the 100-year extreme response Extreme values for severe environmental conditions have been obtained based
value a contour surface method is applied on 20 1-hour, 20 2-hours, 20 3-hours and 20 5-hours simulations. Since the
based on a joint distribution of wind speed, response is governed by resonance the response is close to Gaussian. The
significant wave height and wave period. process is wide banded. The up-crossing rates based on time series have been
The 100-years return period environmental obtained.
condition has been set in order to get 100- The minimum total simulation time (number of simulations multiply by
years response of the floating wind turbine simulations period) in order to get accurate results is highly correlated to the
in harsh environmental condition. A needed up-crossing level. The 1-hour and 2-hours original values cannot
systematic study for choosing the turbulent provide any information at the 0.0001 up-crossing level. The extrapolation of 1-
wind intensity and scaling the mean wind hour period in order to capture the up-crossing level of 0.0001 can be used.
velocity has been carried out. The Naess approach gives more reasonable results. If up-crossing of higher
levels is needed the total simulation time should be increased. The most
Model
Model probable maximum and bending moment for up-crossing level of 0.0001 for
present study are very close. Comparison of different simulation periods show
Floating Wind Turbine Properties (CMS) that the 20 1-hour simulations are sufficient for predicting the 3-hours extreme
Total Draft 120 m
bending moment if the up-crossing rate is based on reasonable extrapolation.
Diameter Above Taper 6.5 m
Diameter Below Taper 9.4 m Acknowledgement
Acknowledgement
Spar Mass, Including Ballast 7593,000 kg
Total Mass 8329,230 kg The first author would like to thank Drs. Zhen Gao and Nilanjan Saha from
Centre of Gravity, CG -78.61 m CeSOS/ NTNU for discussion about hydrodynamic and stochastic analysis, Profs.
Pitch Inertia about CG 2.20E+10 kg•m^2 Sverre Haver and Finn Gunnar Nielsen from Statoil for discussion about
Yaw Inertia about Centerline 1.68E+08 kg•m^2 environmental conditions and floating wind turbine concepts. We also thank Prof.
Rating 5 MW Jakob Mann, Torben J. Larsen and Dr. Anders Melchior Hansen regarding
Rotor Configuration 3 Blades discussion about the HAWC2 code developed at Risø DTU. Finally we would like
Rotor, Hub Diameter 126 m, 3 m to acknowledge the financial support from the Norwegian Research Council which
Hub Height 90 m
has been granted through the Center for Ships and Ocean Structures (CeSOS).
Cut-In, Rated, 3 m/s, 11.4 m/s,
Cut-Out Wind Speed 25 m/s
Rotor Mass 110,000 kg Authors
Authors
Nacelle Mass 240,000 kg
Tower Mass 347,460 kg
Catenary Moored Deep Spar Madjid Karimirad, Torgeir Moan,
Floating Wind Turbine PhD Candidate Professor and Director
97
Introduction
The monotower is the dominating substructure concept used for offshore wind The fatigue limit state is generally assumed to be very important for
turbines. Offshore wind farms have so far been built at a depth of up to 24m. offshore wind turbines. Here, wave loading on a monotower is discussed
As the importance of wave loads increase when deeper waters (30-60m) are in the context of fatigue loading.
considered for wind farms, it becomes increasingly important to correctly and Typically, wind loading will dominate over wave loading, and must, of
efficiently include wave loading in structural analysis. Also, for deeper waters course, be taken into account in design of a real structure. However, wind
monotowers are expected to gradually become less economical compared to loading is ignored to allow a broader discussion of wave loading. Likewise,
alternative substructure concepts (e.g. truss towers), and wave loading is dynamic effects are ignored.
important to rate different alternatives.
Storm duration
For several reasons it is of interest to make a simplified A (Rational) Scatter Diagram Fetch (Børresen, 1987)
evaluation of the wave climate and the accompanying
wave forces, e.g.: 50km / 500km Wind Mean
Speed [m/s] Duration
•Wind turbine substructure concepts can be evaluated SMB curve Scatter diagram
and compared independent of a specific site 10.8-13.8 20-25h
E.g. Carter (1982): Hs[m] 0.5 1.0 1.5 2.0 2.5
13.9-17.1 ca.15h
•In situ wave measurements in particular, but also Tp[s]
computer simulations are resource demanding. Thus, a Duration limited: 2.5 8.3/0 17.2-20.7 ca. 12h
simplified approach is very useful in an initial phase of •Hs=0.0146D[h]5/7U109/7 3.0
a project 3.5 8.3/0 1.2/0
•Tp=0.540D[h]3/7U104/7 4.0 Wind Distribution
•Using a simplified method gives an improved
4.5 0/14.5
understanding of the nature and influence of wave Fetch limited: •Weibull (2-param.)
5.0 24.8/0 1.2/0
climate and loading.
•Hs=0.0163F[km]1/2U10 5.5 9.6/10 •Shape: 1.9, scale: 10.0
Thus, a scatter diagram based on a limited number of 6.0 0/15 2.0/0
key parameters that is both easy to construct and not •Tp=0.566F[km]0.3U 10
0.4
6.5
•50-year: 35 m/s
directly connected to a specific site can be useful in 7.0 0/10.3 •1-year: 28 m/s
Fully developed:
structural design as a (partial) description of the wave 7.5 0/5.7
climate. •Hs=0.0246U102 •U10,mean= 8.9 m/s
Ref: Carter, D.,1982.”Prediction of wave height and period for a constant wind •Tp=0.785U10
Effect of Shallow water
velocity using JONSWAP results”. Ocean Engineering, 9(1), pp. 17-33
d=30m / 50m U10 = 7.5m/s - 22.5m/s
Børresen, J. A., 1987. “Vindatlas for Nordsjøen og Norskehavet”.
Wave Loads
The Keuligan-Carpenter KC number and the
slenderness relationship are typically used to classify
Scatter diagram Keulegan-
wave loading on a vertical bottom mounted cylinder. Carpenter
As the KC number is small, drag can be neglected H •Inertia dominated (no drag)
Monotower: D=6 m KC 1.3
and the mudline moment amplitude can be found D •Potential theory, CM=2
analytically by integrating the wave load over the
depth: Potential theory •(Possibly diffraction)
Slenderness
1 d (1 e kd ) 1 e kd kde kd
M Mudline D 2 2 H λ/D=2 - 13
4 k k2
Morison’s eq.
r L 𝑖𝐶
C 𝑈𝐷𝐶
𝑖𝑎𝑏𝑐 Gate
signals
𝑉𝑋,𝑎𝑏𝑐 PLL PWM
𝑉𝑎𝑏𝑐 ,𝑟𝑒𝑓 Figure 6: DC voltage droop control responses
𝛳 abc
ssdq
𝛳 𝑉 𝑉𝑐𝑑 ,𝑟𝑒𝑓 𝑉𝑐𝑞 ,𝑟𝑒𝑓
𝑋𝑑
abc
ssdq Inner
𝑉𝑋𝑞
current
abc 𝑖𝑑
𝑖𝑋,𝑎𝑏𝑐 controller
ssdq
𝑖𝑞
𝛳 𝑖𝑑,𝑟𝑒𝑓 𝑖𝑞,𝑟𝑒𝑓
𝑈𝐷𝐶,𝑟𝑒𝑓
+
𝑃𝑟𝑒𝑓 + +
𝜌𝐷𝐶 𝑃𝐼
Figure 1: Early stage scenario of multiterminal − −
HVDC in the North Sea 𝑃𝑚𝑒𝑎𝑠 𝑈𝐷𝐶,𝑚𝑒𝑎𝑠
𝑉𝑋,𝑟𝑒𝑓
+
𝑄𝑟𝑒𝑓 +
𝐾 +
𝑃𝐼
− − Figure 7: Impact of three phase short circuit fault
𝑄𝑚𝑒𝑎𝑠
𝑉𝑋,𝑚𝑒𝑎𝑠 occurring at oil/gas platform load
d id 1 0 L r id md VXd
U DC
dt iq L L r iq mq 0
Figure 2: A four terminal HVDC model used for Line frequency(rad / s)
simulation
L, r Line inductance (H) & resistance ( )
The four HVDC converter terminals were assigned VXd Measured voltage at PCC
the dc droop characteristics as shown in Figure 2. Figure 8: Loss of generation from the offshore
m modulation index wind farm
𝑈𝐷𝐶 𝑈𝐷𝐶 𝑈𝐷𝐶 𝑈𝐷𝐶 Conclusions
𝑈𝐷𝐶,𝑟𝑒𝑓
𝑖𝑑,𝑟𝑒𝑓 +
𝑃𝐼 + o Robust control of MTDC was achieved
INV REC − − by DC voltage droop characteristics
+ 𝑉𝑐𝑑 ,𝑟𝑒𝑓
0 T𝑃 0 0 𝑃 0 𝜔𝐿 o No need of fast communication between
𝑃 𝑃 𝑖𝑑 𝑉𝑑
Offshore Oil&gas terminals for operation under disturbances
Grid-1 Grid-2 𝑉𝑞
windfarm 𝜔𝐿 o System is little affected by short duration
𝑖𝑞
Platform + AC fault occurrences
load characteristics for 𝑖𝑞,𝑟𝑒𝑓 − +
o Readily expandable without any change
Figure 3: Assigned DC droop 𝑃𝐼 𝑉𝑐𝑞 ,𝑟𝑒𝑓
+
the HVDC terminals + of the existing system needed
Figure 5 : Inner current control loop
99
Modelling and control of floating
wind turbines
Thomas Fuglseth
PhD-student, Dept. of Electrical Power Engineering, NTNU
-1
Mooring
stiffness
Damping term Radiation Wave 11.5
0 100 200 300 400 500 600 700 800 900 1000
forces
time [s]
forces
Example
Radiation forces are computed by linear state space models
running in parallel. State space models found from frequency- •17 m/s constant wind speed
dependent WAMIT data using system identification techniques. •2.26 m wave height, period of 9.57 seconds
•Standard blade pitch controller for the NREL offshore
Wave excitation calculated by numerical convolution of wave
amplitude times series and wave excitation response function baseline compared with constant torque and blade
pitch
f i wave (t ) Hi (t ) (t ) Wave amplitude time series
Changing controller type can significantly damp out
Wave excitation transfer function platform pitch movement. However, this requires
(found from WAMIT) knowledge of true windspeed, unaffected by platform
movements. Anemometers at the rear of the nacelle
Model are problematic, as the measurement is delayed as
•Platform model based on HyWind 5 well as affected by the rotor.
MW design •Observer/state estimator can be used to filter out
•Cylindrical platform, 120 m wave motions and estimate true wind speed →
draft and 9.4 m diameter solution used by Statoil.
tapered towards the top. •New wind speed measurement such as spinner-
•7500 ton mass mounted pitot tubes or forward-looking LIDAR can be
•Platform modeled in WAMIT advantageous.
•Turbine model: NREL offshore
baseline
•5MW reference design based
on several industrial designs
100
Started PhD in 2009 Supervisor: Professor Jørn Vatn Cooperating business: Statcraft
Renewable energy has a vital role in the future of energy industry. Wind farms are one of the main
sources for producing electric power. As offshorewind farms are more advantageous, so these are
commonly used now‐a‐days.
Main challenges in operation of wind farms are maintenance, sudden failures and downtimes. Difficult
accessibility, too far from onshore and depot, high production losses, significant cost of corrective
maintenance, hard maritime environment are playing vital role in maintenance affaires of offshore
wind farms.
Among the maintenance strategies, preventive and predictive ones are suitable for implementation in
offshore wind turbines. Condition monitoring (CM) technologies, such as vibration analysis, oil
analysis, thermography, crack measurement … are very useful for monitoring of wind turbines. In this
research we focus on the condition monitoring of wind turbine and use of CM data for making
decision of maintenance. To define the deterioration models by using CM data and match them with
mathematical models is one of the main objectives of this research.
High availability and reliability with low cost are our ideal.
101
– Region1, 2 and 3 Coleman, enclosed by time (azimuth) varying Coleman transfor- 100
mations
10−1
Generator Region Region Region ∙ The Coleman turbine can be approximated by a linear system
torque I II III
∙ It is good representation of the turbine 10−2
0
0
10−1 100 101 102
Frequency (rad/sec)
Wind speed
𝐺
∙ Region 2: Maximum power Figure 6: Vertical flap from Collective, Horizontal and Vertical pitch
𝑢 𝑢𝑐 𝑦𝑐 𝑦
– Constant tip speed ratio -
Φ−1
𝑢
-
𝐺𝑐 - Φ𝑦 -
20
some extent. 10
0
4
0
10
0
0
The Linear Model 50
Pitch, Coleman
80 50
Blade flap, Coleman
80
50 80 50 80 20
4
Blade edge, m Generator speed, rpm
10
1
10
1 14.3 0 0
50 80 50 80
−1 14 0
10 Pitch rate Generator speed, rpm
50 80 50 80
10
14.3
10 −1
0
Figure 1: Simulation in a steady wind field with a vertical wind shear −10 14
0
Figure 2: Simulation in a steady wind field with a vertical wind shear ∙ The peak at 22.9 rad/s is due to resonance in the drive train and
0
50 80 50 80
with individual pitch blade edge motion. Pitch rate Generator speed, rpm
10
14.3
∙ It is possibly to get rid of the flap motion with individual pitch. Bode magnitude plots for the linear sys- 0
14
tem −10
50 80 50 80
Method
Col
101
Hor Figure 8: Individual pitch with the diagonal controller
∙ Nonlinear aero elastic dynamic model of the entire turbine Ver
– FAST, Bladed, HAWK2, flex5 and others 100 Pitch, degrees Blade flap, m
20
∙ Determine an operation trajectory for a given wind speed, genera- 10 −1
4
10
tor speed and generator torque 0
0
– Constant pitch angle 10−2 50 80 50 80
Pitch, Coleman Blade flap, Coleman
10−1 100 101 102
– An azimuth depending trajectory for blade motions Frequency (rad/sec)
20
4
∙ Linearize the model around the trajectory Figure 4: Generator speed from Collective, Horizontal and Vertical
10
0 0
– A linear system for each azimuth angle pitch 50 80 50 80
Pitch rate Generator speed, rpm
∙ Change the states, inputs and outputs for each system with the
10
Coleman transformation 101
Col
0
14.3
Hor
– (Almost) the same linear model for all azimuth angles Ver −10 14
100 50 80 50 80
∙ Take the mean of all system matrixes and call the corresponding
system the Coleman turbine. 10−1
Figure 9: Individual pitch with a more advance controller
∙ The Coleman turbine “almost” time (azimuth) invariant
10−2
Academic motivation:
Synthesis (development) of models for cable / transformer/ VCB for transient studies in offshore wind park.
References
[1] Madsen BT. , Emerging offshore wind power markets—conditions, quantities and timetable. Copenhagen Offshore Wind Conference, Copenhagen, 26–28 October 2005.
[2] L. Liljestrand, A. Sannino, H.Breder and S. Thorburn, “Transients in Collection Grids of Large Offshore Wind Parks”, Wiley Interscience , Wind Energ. 2008; 11:45–61.
[3] List of projects in planning, from UK Wind Energy Database UKWED. [Online]. Available: http://www.bwea.org. (accessed 18 December 2005)
[4] D. Chapman, “The Cost of Poor Power Quality”, Power Quality Application Guide, Section 2.1, Copper Development Association of UK, November 2001.
[5] Abey Daniel & Samson Gebre, “Analysis of Transients in Wind Parks: Modeling of System Components and Experimental Verification”, MSc. Thesis, Chalmers University of Technology, Sweden, 2008.
[6] S. M. H. Hosseini, M. Vakilian, and G. B. Gharehpetian, “ Comparison of Transformer Detailed Models for Fast and Very Fast Transient Studies”, IEEE Trans. On Power Delivery , Vol. 23,pp. 733-741, No. 2, April 2008.
[7] B. Gustavsen, “Wide band modeling of power transformers,” IEEE Trans. Power Del., vol. 19, no. 1, pp. 414–422, Jan. 2004.
[8] G. B. Gharehpetian, H. Mohseni, and K. Möller, “Hybrid modeling of inhomogeneous transformer windings for very fast transient overvoltage studies,” IEEE Trans. Power Delivery, Vol. 13, pp. 157–163, Jan. 1998.
[9] B. Gustavsen, A.Bruaset, J. J. Bremnes, and Arild Hassel, “A Finite-Element Approach for Calculating Electrical Parameters of Umbilical Cables” , IEEE Trans. On Power Delivery, Vol. 24, No. 4, October 2009.
[10] B. Gustavsen, A. Semlyen, “Rational Approximation of Frequency Domain Responses by Vector Fitting”, IEEE Trans. On Power Delivery, Vol. 14, No. 3, July 1999.
[11] I. Arana Aristi, “Modeling of Switching Transients in Nysted Offshore Wind Farm and a Comparison with Measurements ” , MSc. Thesis, Technical University of Denmark, June 2008.
102
103
What is NORSEWiND?
by
Erik Berge
Oldbaum
DanishTechnical Deliver high quality offshore wind atlases at hub-height for the Irish
Services
(coordinator)
University IMM Sea, the North Sea and the Baltic Sea
Develop an offshore wind database and the associated wind atlases
Garrad Hassan based on real data acquired offshore
INETI
& Partners
Develop a set of techniques to provide cost effective data anywhere
ISET
Kjeller offshore
Vindteknikk
Promotion and acceptance of remote sensing within the wind
University of
RISOE DTU
Strathclyde industry
Validate the wind atlas methodology
WINDTEST
Scottish
Kaiser Wilhelm
Enterprise
Koog
Nautilus
DONG Energy
Associates
Statoil 3E
CLS
Geographical areas covered are the Irish Sea, the Wind atlas methodology
North Sea and the Baltic Sea
Set up measurement points and collect wind data
Collect and process satellite data wind data
Develop vertical profile modeling to “lift” satellite data from 10m up to hub-
height
Generate meso-scale model data to complement and validate satellite
data, and to fill inn gaps of missing data.
Combine the data sources to an optimal wind atlas.
Apply long-term corrections to the wind atlas quantities
105
Task leader for the aggregation of the data sources into the wind atlases Annual average wind speed maps (long-term corrected)
Meso-scale modelling Monthly average wind speed maps (long-term corrected)
Verical profile analysis and modelling Standard deviation of annual averages
Long-term data analysis and correction Weibull-distribution
Operate, maintain and analyse the data from the Statoil wind cube at Wind direction distributions
Utsira. Turbulence intensity
Wind shear (maps of the wind shear coefficient)
Temperature and static stability
Mixing height
Uncertainty level of each physical parameter
12 Lidars
7 Meteorological masts
Meso-scale model – WRF Weather Research and Meso-scale model set-up (continued):
forecast model set-up:
6 km resolution
• Data stored hourly in
every grid-point for all
18 km resolution
model layers
FINO1
Large wind variability and low wind shear at FINO 1 – Low wind variability and high wind shear at FINO 1 –
convective case (10 min averages): stable case:
α~0 α ~ 0.15-0.35
19.11.2004 04.04.2004
107
Ocean roughness
Controlling factors for the Planetary
Boundary Layer (PBL)
height:100m,
287.5 2200
2000
287.5 287.5 2000
wind speed /
287.5
287.5 287.5
287.5
287.5
.0 1600
285
1600
isentropes
1400 285.0
285.0
285.0
285.0
285.0
1400 1200
.0
285 285.0
1000
1200
285.0
800 1.30
285.0 282.5 1.25
282.5
282.5 1.20
1000 600
282.5
1.15
282.5
1.10
1.05
282.5
400 1.00
800 0.95
2.5 0.90
28 0.85
200 0.80
0.75
600 0.70
0
282.5 55 50 45 40 35 30 25 20
400
200
282.5
N S
W E
0
10 15 20 25 30
2200
2000
287.5
287.5
287.5
287.5
TKE /
1800 287.5
1600 isentropes
1400 285.0
285.0
285.0
285.0
1200
285.0
1000
800 1.30
282.5 1.25
282.5
282.5 1.20
600 282.5 1.15
1.10
1.05
282.5
400 1.00
0.95
0.90
0.85
200 0.80
N S
0.75
0.70
N S
0
55 50 45 40 35 30 25 20
1
109
55:70
dub dp
40:55 Ub Cbub Ct ub Fx
Pressure perturb. of inversion: dx dx
25:40
i | U | g
pˆ
10:25 N 0
−5:10
< −5
horizontal view:
Height=100m Height=300m
Model simulations
U Zoom:
Smith (2009)
Thanks!
Email: Idar.Barstad@uni.no
2
110
Summary of paper
► Operations of the International Space Station ► Remote systems and remote operations
► Accessibility problems
Example:
Questions to answer Offshore subsea remote area operations
► How have they adapted to their respective rough environments and ► Challenges for operation and maintenance
lack of accessibility? Access to infrastructure, i.e. supply bases
Intervention logistics
► How do they manage O&M? Long lead-times for interventions
Safety issues may require use of multiple vessels in remote areas
► What are best practices?
► Solutions
► What are the major differences between O&M of shallow and deep Extensive use of redundancy in critical components and systems
water offshore wind farms?
Systems designed for reduced intervention opportunities
• Take advantage of reservoir characteristics to allow shutdown of
► What are typical mistakes and startup problems? producers without loss of total production
Automated monitoring of systems
► How can these experiences be used and adapted for the deep sea
offshore wind industry?
5 6
1
111
Example:
Electric power networks (overhead lines)
Lessons learned from FPSO
► Typical O&M methods and strategies
Risk based methods (RCM and variations on this)
► How to unite a whole industry in doing things differently
Shift from Time based to Condition based maintenance
“Safety based” maintenance
(safety is often the triggering factor for maintenance and renewal) ► The importance of viewing maintenance as an enabler
► Industry unique operational measures
and not as a cost
Inspection from helicopter and drones (unmanned micro helicopters)
11
2
112
Hywind – www.statoil.com
Mooring
www.statoil.com
www.statoil.com
Materials and Chemistry 3 Materials and Chemistry 4
Protective coatings –
Rules and regulations offshore oil & gas experience
International standards NORSOK M-501 specifies
Pre-treatment quality
IEC 61400 developed Standards/Guidelines Year
IEC 61400-1 Wind Turbines, Part 1 Design 1999/
to ensure safety for Generic type of coatings
requirements:
systems and IEC 61400-3 Wind Turbines, Part 3: Design 1999/ Film thickness and number of coats
requirements for offshore wind 2005
components turbines Inspection during construction and service
Germanische Lloyd - GL Rules and Part 1 Metallic Materials 1998
DNV DNV-OS-J101 is Regulations, II Materials and Experience indicates shorter lifetime of coatings recommended for the
based on existing oil & Welding. atmospheric zone than the 20 years designed life for offshore wind turbines
Germanische Lloyd - GL Rules for Guideline for Certification of 2003/
gas standards/ Classification and Construction, III Offshore Wind Turbines 2005
Offshore Technology Exposure conditions Typical coating system Lifetime expectancy
experience; The Danish Energy Agency’s Recommendations for Technical 2001
Zinc epoxy 60 µm Time to first major
synchronised with IEC Approval Scheme for Wind Turbine Approval of Offshore Wind Turbines
DNV-OS-J101 Design of Offshore Wind Turbine 2004/ Atmospheric zone Epoxy barrier coat 150 µm maintenance is normally
National standards (Det Norske Veritas) Structure
EU-Project RECOFF. Contract No. Recommendations for Design of
2007 UV resistant topcoat 70 µm about 10 years
According to design life.
Denmark ENK-CT-2000-00322 Offshore Wind Turbines 2-coats epoxy
Degradation of the coating
Germany Submerged zone Mean dry film thickness 350
is compensated by
µm
sacrificial anodes.
2-coats polyester
Lifetime of 20 years or
Splash zone Mean dry film thickness >
more is usually achieved
1000 µm
Materials and Chemistry 5 Materials and Chemistry 6
1
113
Are extended coating lifetimes possible? Challenges for offshore wind turbines
To ensure a lifetime corresponding to design life with a minimum
maintenance requirement, DNV recommends Keep costs low
Use coating systems with documented performance Higher energy output
Operational experience Improved foundation
Prequalification (NORSOK M-501) technology
Control that specified surface preparation and application conditions are Enlarged wind turbines
followed
Exposure Dry film thickness
Steel foundations seem to be
Typical coating system
conditions (DFT) competitive to concrete
A coating system according to ISO 12944-5, Minimum 320 µm
category C5-M (very high corrosivity): 50 years design lifetime is
Atmospheric - zinc rich epoxy primer
zone - intermediate epoxy
possible for steel structures
- epoxy or polyurethane topcoat, polyurethane
if a colour or gloss retention is required
- Glass flake reinforced epoxy or Minimum 1.5 mm
What about the corrosion
Splash zone
polyurethane or protection?
- Thermally sprayed aluminium with a silicon Minimum 200 µm
sealer
- Multilayer two component epoxy and Minimum 450 µm
Submerged
cathodic protection
www.energy.siemens.com
zone
- Alternatively cathodic protection only No coating
Materials and Chemistry 7 Materials and Chemistry 8
2
114
3
115
Location
Repower 5M
Met
Mast
Multibrid M5000
1
117
RAVE – thematic research topics (1) RAVE – thematic research topics (1)
2
118
Targets:
Reduction of the cost for OWEC support
structures (tower, substructure and
foundation)
coordination
deputy coordination lighter support structures (material cost)
optimised design process (personnel cost)
Cooperation Partners:
Integration of separate computational
tools into an easy operable simulation
and design package with common
Franzius-Institut interfaces
für Wasserbau und
Küsteningenieurwesen holistic design concept
Cooperation with industry
research according to need
associated project in: funded by:
Validation with measurement data from
the test site “alpha ventus”
Physical testing
Analysis of specific parameters and effects under labour conditions,
Franzius Institute, January to March 2010 in “large wave flume”
measurement of
water pressure World biggest wave flume in
Measurement data from alpha ventus Hannover (324m x 7m x 5m)
Comparison of measurement data of water
pressure in circumferential direction labour
with data from alpha ventus (February 2010).
Numerical simulation
Calibration of CFD Models with
labour data and alpha ventus data for
simulation of non-breaking and breaking
waves.
CFD-Model
steel
a) laser scanner with results at a b) tachymeter - results tubes in store,
three-dim. fabric
X-node – scatter-plot out-of-roundness (raised)
© Software Cyclone, Leica Geosystems mineral corrosion
protection
Installed coupons on the jacket
Relative displacement at Grouted Joint textile formwork
3
119
rope
Example: Reduction of rope force 1: ca. 13%
2
rop
Method: Multi-parameter eigenvalue problem, with
e1
“scanning” parameter
scour protection
Detected: Stiffness change of 4% in rope 1
means change of rope force of 17%.
N=10000
25 kN load
1
force sensor
frame
ADAMS WaveLoads Poseidon ANSYS
external displ.
thrust plate sensor
3 u 3 WP8
internal displ.
sensor GIGAwAVe OWEAcorr Abaqus ValiTool
sensor for pore crack state
water pressure • Cyclic loads
in- and outflow of
up to 10 Hz WP1 WP2 WP3 WP4 WP5 WP6 WP7
satiation fluid in- and outflow of wave load fatigue corrosion monitoring scour soil models model
• Cell pressure
cell pressure fluid models resistance protection system protection validation
up to 1000 kPa
load estimation FE / MKS Software modul des GIGAWIND alpha ventus
programs GIGAWIND Tools WP8 work packages
Conclusion
4
120
5
121
Karl Merz
Department of Civil Engineering
Norwegian University of Science and Technology (NTNU)
January 22, 2010
The loads on the structure are a function of several flow processes (waves, It is convenient to think about the hydrodynamic loading in
current, structural motion) which act simultaneously and interact nonlinearly. terms of flow processes. Multiple processes wind-
generated waves, remote swell, current, and structural
Calculation of loads is heavily empirical. There is a lot of laboratory data at motion are active simultaneously, and their (nonlinear)
flow parameters (like Reynolds number) that are not representative of full-scale interaction results in the fluid force on the structure.
structures. There have been field measurements on full-scale structures, but here
the flow parameters are somewhat uncertain. Connecting the two is not easy; (For the present discussion, we shall assume that each
design values should not be considered "final" or broadly applicable. process can be described by a single dominant trigonometric
term; in reality, multiple harmonics are involved.)
The value used for fluid damping should be calibrated independently of the
primary drag coefficient CD, and should be guided by full-scale data. The net flow velocity vector may
exhibit large fluctuations in both
There are several important, outstanding issues that are not considered in this direction and magnitude. If the
presentation: flow separates, forming a wake
- free surface effects, run-up, draw-down, impact (slamming), and ringing ("burst of shed vortices, then there is a
motions") ``memory effect''; the pressure
- negative damping, "lock-in", the interaction of vortex shedding and structural about the structure is a function
vibration not only of the instantaneous
- forces on members at an angle to the oncoming flow, or parallel to the free flow velocity vector, but also its
surface time history.
The Morison equation states that the fluid force is a superposition of a term in
phase with the acceleration of the flow (inertia), and a term whose dominant
component is in phase with the velocity of the flow (drag). It accounts for some
flow nonlinearity, by way of the drag term.
The Morison equation is deterministic. In itself it does not account for the history
of the flow (the state of the wake), the frequency with which the flow oscillates
back and forth, nor the fact that the instantaneous velocity vector V arises as a
superposition of several flow processes.
122
But, each process is acting with its own amplitude, frequency, and phase. Why
should we be able to describe the effects of the simultaneous wave, current, and
structural motion processes through just one drag coefficient and one added mass
coefficient? Propose:
This equation says that the processes interact, but they do so with different strengths.
(1): Swell and wind-generated waves have been combined into one "wave" term.
Company overview
Installations NorWind AS
TMP
72SLOT
124
Jack‐up operations
Rapid sequencing shorter ops period than weather changes!
1 2
Overview
• Development of offshore wind energy
• Cost comparison
Wind Power R&D Seminar – Deep sea offshore wind power, 21.-22.01.2010, Trondheim
3 4
5 6
known
known
127
7 8
• Costs
- material
- fabrication
- transport
- installation
9 10
11 12
13 14
• Not considered...
- complexity of fabrication of the whole structure
- tubes are more expensive than plates
15 16
17 18
wind direction
influence of tower wake effects to the blades access for service and maintenance
129
19 20
21
...questions?
daniel.zwick@ntnu.no
130
State-of-the-art design practices for offshore wind farms, Peter Hauge Madsen,
Risø DTU
The European research agenda on offshore wind The climate and energy targets for 2020:
20 % renewable energy
20 % energy efficiency/saving
20 % GHG reduction
Beate Kristiansen, Special Adviser / EU NCP Energy
Three pillars:
Competitiveness
Energy security
GHG
1
132
2) Offshore technology: structures for large-scale turbines 3) Grid integration, large-scale penetration of variable
and deep waters (>30 m). electricity supply.
Dev. and demo. programme: A programme on wind farms management as “virtual
new structures; power plants”, demonstrate at industrial-scale:
distant from shore;
Offshore wind farms interconnected
different water depths. to at least two countries and
At least 4 structure concepts use of different grid interconnection
techniques.
developed & tested under
different conditions. Long distance High
Voltage Direct Current.
Demonstration programme:
advanced mass-manufacturing Controllable multi-terminal
processes of offshore structures. offshore solutions with multiple
converters and cable suppliers.
R&D Programme focused on new turbines designs and use of new materials
A R&D programme for forecasting distribution of wind components and demo for new turbines,
components, manufacturing Implementation of
Beate Kristiansen
Mobil: +47 99572077
Office: +47 22037230
bki@rcn.no
SET-plan:
ec.europa.eu/energy/technology/
2
133
3
134
Presented at the
Wind Power R&D seminar – deeep sea offshore wind
21-22 Jan 2010 – Trondheim Norway
4%
Risø DTU, Technical University of Denmark 4 Risø DTU, Technical University of Denmark Title of the presentation 21-aug-2008
water level
p ile
sub-st ructure sub-structure
• Passive in their load response
sea floor • 100-year wave load dominated
• Built-in structural redundancy
p ile
seabed
foundation
Risø DTU, Technical University of Denmark Risø DTU, Technical University of Denmark
135
Risø DTU, Technical University of Denmark Risø DTU, Technical University of Denmark Slide 10
General concept based on lower roughness offshore Complexity of winds in the coastal zone
160
• Higher wind
(~50 km)
speeds/lower 1.5 Rødsand
Offshore
Land turbulence/lower wind (measurements)
120 shear
1.4
Wind speed ratio (U50/U10)
T,Q 1.3
80
profiles/further wake Equilibrium
propagation layer
1.2
40
• Higher wind speeds,
more frequent, persist for
1.1
longer periods offshore Stable
Average
• Statistically, coastal
Unstable
0
1
0.2 0.4 0.6
Normalised wind speed
0.8 1
zone >20 km 0 20 40 60 80 100
www.risoe.dk www.risoe.dk
Risø DTU, Technical University of Denmark Risø DTU, Technical University of Denmark
136
Turbulence
Lines show mixing-length profile U
Lines show logarithmic wind T .I .
using boundary layer height. Rødsand U
profile. Average
Symbols show data.
Symbols show data.
100.00
0.16
Turbulence intensity
60.00
Height (m)
0.12
40.00
0.08
20.00
0.04
0 5 10 15 20 25 30 0.00
Wind speed (m/s) 0.06 0.07 0.08 0.09 0.10 0.11
Turbulence Intensity
•Marine conditions
• Waves
• Currents
• Water level
• Sea ice
In case of wakes: • Marine growth
• Scour and seabed movement
•Normal conditions – occur frequently during
normal operation of wind turbine
•Extreme conditions – 1 year and 50 year
recurrence period
Risø DTU, Technical University of Denmark Risø DTU, Technical University of Denmark
Risø DTU, Technical University of Denmark Risø DTU, Technical University of Denmark
137
• Sources of load as for • Normal design situations with 1) Power 1.1a NTM NSS COD, UNI NCM MSL For extrapolation of U N
• Boat (+helicopter) impact appropriate external 1.2 NTM NSS Joint prob. COD, MUL No currents NWLR or ≥ F *
• Weak effect conditions 1.5 EWS NSS (or NWH) COD, UNI NCM MSL U N
Vin < Vhub < Vout Hs=E[Hs| Vhub]
• Offshore turbines may 1.6a NTM SSS COD, UNI NCM NWLR U N
experience long periods of Vin < Vhub < Vout Hs= Hs,SSS
19 Risø DTU, Technical University of Denmark Title of the presentation 21-aug-2008 Risø DTU, Technical University of Denmark
• Condition Monitoring developments (highest • Enhanced offshore transmission models for fast
reliability and lower OPEX) switching transients and harmonics analyses in
power systems
Significant developments are required in CM for
transformers (e.g. DGA of oil, tap-changers), cables Over-voltages from switching transients and
(Partial Discharge?, located where?), switchgear phenomena of this type may be very damaging on
(gas pressure?), power electronic converter very extensive EHV submarine cable circuits. The
equipment (?). insulation co-ordination requirements of the offshore
substations needs to be evaluated.
1 2
3
139
1
140