You are on page 1of 5

Pembesian Sloof

Jenis dan
Nama Jumlah Panjang
No. Ukuran Panjang Tulangan (m)
Pekerjaan (bh) Total (m)
Besi
L = (2(panjang sloof) - (2.tebal
selimut)) + (2(lebar sloof) - (2.tebal Lt = L.n
selimut)) + (2.6db)
1 Sengkang ∅10 L = (2*(0.25-(2*0.02)))+(2*(0.15- 34 bh
Lt = 0.76*34
(2*0.02)))+(2*6*0.01)

L = 0.76 m Lt = 25.84 m
Lt = L.n
Tulangan Utama D13 L= 4 m 4 bh Lt = 4.4
Lt = 16 m
L = (2(1/4.L tulangan utama + (12db)
+ (2.6db)))+(1/2.L tulangan utama + Lt = L.n
(2.12db) + (2.6db))

2 L=
Tulangan (2*(1/4*4+(12*0.013)+(6*0.013))) Lt = 4.94*1
Tumpuan dan D13 +(1/2*4+(2*12*0.013)+(2*6*0.013)) 1 bh
Lapangan
L = 4.94 m Lt = 4.94 m

Pembesian Kolom Praktis


Jenis dan
Nama Jumlah Panjang
No. Ukuran Panjang Tulangan (m)
Pekerjaan (bh) Total (m)
Besi
L = (4(panjang sloof) - (2.tebal
Lt = L.n
selimut)) + (2.6db)
1 Sengkang ∅6 19 bh
L = (4(0.12-(2*0.02))+(2*6*0.006) Lt = 0.4*19
L = 0.4 m Lt = 7.6 m
Lt = L.n
2 Tulangan Utama ∅12 L= 3 m 4 bh
Lt = 3.4
Lt = 12 m

Pembesian Pelat Pondasi Telapak


Jenis dan
Nama Jumlah Panjang
No. Ukuran Panjang Tulangan (m)
Pekerjaan (bh) Total (m)
Besi
n arah x =
L = panjang + (2.tebal) + (2.6db) Lt = L.n total
12 bh
n arah y =
1 Tulangan Utama ∅12 L = 0.60+(2*0.15)+(2*6*0.012) Lt = 1.04*24
12 bh
n total = 24
L = 1.04 m Lt = 24.96 m
bh

Pembesian Pelat Telajakan


Jenis dan
Nama Jumlah Panjang
No. Ukuran Panjang Tulangan (m)
Pekerjaan (bh) Total (m)
Besi

L arah x = (panjang telajakan -


n arah x = 4
(2.tebal selimut)) + (2(tebal telajakan Lt = L.n total
bh
- (2.tebal selimut))) + (2.6db)

L arah x = (0.60-(2*0.025))+(2*(0.10- n arah y = 5


Lt = 1.24*9
(2*0.025)))+(2*6*0.006) bh

L arah x = 0.72 m n total = 9 Lt = 11.16 m


1 Tulangan Utama ∅6
L arah y = (lebar telajakan - (2.tebal
selimut)) + (2(tebal telajakan -
(2.tebal selimut))) + (2.6db)

L arah y = (0.40-(2*0.025))+(2*(0.10-
(2*0.025)))+(2*6*0.006)

L arah y = 0.52 m
L = 0.72 + 0.52 = 1.24 m
Kebutuhan Besi
(lonjor)

x ∅10 = Lt/L 1 lonjor


besi

x ∅10 = 25.84/12

x ∅10 = 2.15 ~ 3 lonjor


x1 = Lt/L 1 lonjor besi
x1 = 16/12 = 1.33
x1 = 1.33

x2 = Lt/L 1 lonjor besi

x2 = 4.94/12

x2 = 0.41
x D13 = x1+x2
x D13 = 1.33 + 0.41
x D13 = 1.74 ~ 2 lonjor

Kebutuhan Besi
(lonjor)

x ∅6 = Lt/L 1 lonjor
besi
x ∅6 = 7.6/12
x ∅6 = 0.63 ~ 1 lonjor
x ∅12 = Lt/L 1 lonjor
besi
x ∅12 = 12/12
x ∅12 = 1 lonjor
Kebutuhan Besi
(lonjor)

x ∅12 = Lt/L 1 lonjor


besi

x ∅12 = 24.96/12

x ∅12 = 2.08 ~ 3 lonjor

Kebutuhan Besi
(lonjor)

x ∅6 = Lt/L 1 lonjor
besi

x ∅6 = 11.16/12

x ∅6 = 0.93 ~ 1 lonjor
Jenis dan Panjang
Jumlah Panjang Kebutuhan
No. Nama Item Nama Pekerjaan Ukuran Tulangan
(bh) Total (m) Besi (lonjor)
Besi (m)
Sengkang ∅10 0.76 34 25.84 3
Tulangan Utama D13 4 4 16
1 Sloof
Tulangan Tumpuan 2
4.94 1 4.94
dan Lapangan
Sengkang ∅6 0.4 19 7.6 1
2 Kolom Praktis
Tulangan Utama ∅12 3 4 12 1
Pelat Pondasi
3 Tulangan Utama ∅12 1.04 24 24.96 3
Telapak
4 Pelat Telajakan Tulangan Utama ∅6 1.24 9 11.16 1