Professional Documents
Culture Documents
Damages - English Law
Damages - English Law
(LAW 61004)
ENGLISH LAW –
DAMAGES FOR BREACH OF CONTRACT
1
10/29/2023
Dr Jenita Kanapathy (School of Law & Governance)
11 Relevant case law on GBD (I)
Wrotham Park Estate Co PHL built houses in breach of a restrictive covenant it had given to WPE, the owner
v Parkside Homes Ltd of adjacent land. No diminution in value of WPE’s land; also, no reliance losses.
[1974] 1 WLR 798 (HC) Held:
(i) WPE’s claim for a mandatory injunction for the houses to be pulled down
C recovered 5% of D’s
rejected;
gains (ii) WPE awarded £2,500 as damages being 5% of PHL’s anticipated profits.
Attorney General v B wrote a book on his exploits as a spy for the Crown in breach of his secrecy
Blake [2001] 1 AC 268, agreement. Crown claimed GBD against B.
HL Held:
(i) C’s interest in performance of a contract might render it just and equitable for
the court to make an order for specific performance; or grant an injunction; or
C recovered 100% of D’s in exceptional cases, to make an order that D should retain no benefit from his
remaining gains breach of contract.
(ii) A useful general guide, though not exhaustive, was whether the claimant had a
legitimate interest in preventing the defendant’s profit-making activity and,
hence, in depriving him of his profit.
(iii) Declaration that the AG was entitled to be paid a sum equal to whatever
amount was due and owing to B from the publishers.
10/29/2023
The Hadley v Baxendale rules: time they made the contract, as the
probable result of the breach of it.”
Per Alderson B:
Students must read this case.
Losses recoverable for breach of contract
are such losses “…as may fairly and The test for remoteness is in two parts: (a)
reasonably be considered the 1st rule operates objectively,
according to what loss is a natural
i. either arising naturally, that is, according
consequence of the breach; (b) the 2nd
to the usual course of things, from such
rule operate subjectively and is based on
breach of contract
the specific knowledge of potential losses
ii. or such [losses] as may reasonably be that is in the minds of both parties when
supposed to have been in the the contract is made.
contemplation of both parties, at the
On the facts, the stoppage of production was not a “natural” consequence of D’s
delay in delivering the broken shaft to the manufacturer because P might have
had a spare shaft so as to be able to continue uninterrupted production.
The stoppage was also not within the reasonable contemplation of both parties
when the contract was made as a probable result of the breach because P had
not informed D that any delay in delivering the broken shaft would cause
stoppage of production (i.e. the special circumstances were not made known to
D).
A new test for remoteness was suggested Due to the delay, shipowners had to
by Lord Hoffmann & Lord Hope. accept a lower rate of charter from the
3rd party for the whole of the duration of
Charterers of ship redelivered the ship to
the charterparty with the 3rd party.
the shipowners 9 days late.
Issue: were the charterers liable to the
Meanwhile, unknown to charterers,
shipowners for the losses relating to (i) the
shipowners had entered into a
9-day delay or (ii) for the whole duration
charterparty with a 3rd party to take
of the charterparty with the 3rd party.
effect from the original redelivery date at
a particular rate of charter. Held: liable only for (i). Loss (ii) was too
remote.
Lord Hoffmann & Lord Hope’s test: The loss is charter that may occur if they were to
too remote if D did not assume redeliver the ship late.
responsibility (i.e. agree to be responsible),
Lord Rodger, however, applied the
when the contract was made, for the type
traditional Hadley v Baxendale rules, and
of loss that occurred. Conversely, the loss is
decided that Loss (ii) was too remote
NOT too remote if the defendant did
because it could not be said that type of
assume responsibility for that loss
loss was reasonably within the
Thus, they decided that, on the facts, Loss contemplation of the parties, since the
(ii) was too remote because it could not be charter had no knowledge that the
said that the charterers had assumed shipowners had entered into a follow-on
responsibility, when the contract was charter with a 3rd party.
made, for losses connected to a follow-on
3. C does NOT have to lead any evidence 3. Invalidity of penalty clause does NOT bar C’s
as to his actual loss; he recovers what is right to claim for his actual loss i.e. C will have to
stated in the LAD clause. lead evidence as to his actual loss.
Dunlop Pneumatic Tyre Co Ltd v New Garage 3. Rebuttable Presumption that the terms is a
& Motor Co Ltd [1915] AC 79 (HL): PENALTY when a single lump sum is made
payable by way of compensation, on the
1. If the sum stipulated (X) for is extravagant
occurrence of one or more or all of several
and unconscionable in amount in
events, some of which may occasion
comparison with the greatest loss which
serious and others but trifling damages.
could conceivably be proved to have
followed from the breach: PENALTY 4. If none of the above, X is a GENUINE PRE-
ESTIMATE of damages; this is so even if the
2. If the breach is only failing to pay a sum of
consequences of the breach are such as
money, and X is a sum greater than the
to make precise pre-estimation almost an
sum which ought to have been paid:
impossibility.
PENALTY.