ID Task Name Resource Names Duration

1 Project:- Pedestrian walkway infornt of meden


Habtamu (Proj. Mang.),Nebiyu (site 40 days
insurance from existing pedesrtian walk way to 20 Eng.),Mekdes (Surveyor),Caltu
meter to the south (Admin.),Meseret (Act.),Sintayehu
(Forman)
2 1. GREENERY AND TERRAZZO 34 days
3 1. Excavation and EarthWork 34 days
4 1.1 Site Clearing or/ Remove trees, Existing Daily laborer[1,000%] Daily 1 day
fence and other obstacles
5 1.2 Bulk Excavation in ordinary soil to a depth of laborer[1,000%] 1 day
30cm from stripped top soil
6 1.3 Demolishing Existing Fence, tree, roots hush Daily laborer[1,000%] big 1 day
stone and any obstacle existing on the site as
7 1.4 Cartaway the excavted surplus material to a Daily laborer[1,000%],Truckc 1 day
distance of 5km away Driver[200%]
8 1.5 Backfill fine selected materials and compacted Truckc Driver[200%],Daily 1 day
by roller machine well in layer not laborer[1,000%]
9 1.6 Back fill with fertile soil to make greenery area, Daily laborer[1,000%],Truckc 1 day
plant locally known grass bed on top of best soil as Driver[200%]
per given detail on drawing. The selected soil, could
be from a borrow pit or from
10 1.7 Planting "Duranta" tree from OGL 30cm Daily laborer[500%],Carpenter 1 day
height must be 30cm c/c with random
11 1.8 Planting "Picas from OGL 50-60cm height" Daily laborer[1,000%],Carpenter 1 day
must be must be 50cm c/c with random
12 1.9 Planting "Arucaria Jerusalem tree from OGL 80- Daily laborer[1,000%],Carpenter 1 day
100cm height" must be 10m c/c with random
13 1.10 Planting "Cyprus tree from OGL 50-60cm height" Daily laborer[1,000%],Carpenter 1 day
must be 10m c/c with random exchanging
14 1.11 Planting "Tuna tsidi tree from OGL 50-60cm Daily laborer[1,000%],Carpenter 1 day
height"must be 500cm c/c with random
15 1.12 Planting Bottle brush flower of dia 50cm and Daily laborer[1,000%],Carpenter from 1 day
OGL 80<m height at every corner position
16 1.13 Planting "Grass" concrete, filled into Daily
formwork and laborer[1,
17 1.14 Apply 15cm thick basaltic stone or vibrated 000%],Car
equivalent hardcore well rolled consolidated penter
blinded with hand crushed stone
18 2. CONCRETE WORK Daily
laborer[52
19 2.1 Mass Concrete, Class C-25 360Kg/m3 of 0%],Maso
n[130%],Ass. Mason[260%] 1 day

1 day

21.5
days
19.5 days
ID Task Name Resource Names Duration

20 2.1.a. Curb mass Concrete Mason[300%],Daily 1 day


laborer[1,800%],Mixer
Operator,Vibrator Operator
21 2.1.b. For RHS post of fence, shade and
Daily laborer[1,200%],Mixer 13.5 days
bench Pad, electric pole Operator[200%],Vibrator
Operator[200%],Mason[200%]
22 2.1.b.1 For RHS post of fence 2 days
23 2.1.b.2 For RHS post of shade and bench Pad 1 day
24 2.1.b.3 For RHS post of electric pole
0.5 days
25 2.2 Provide 10cm mass concrete c-25 with
cement content of 360Kg/m3 filled over hard Mason[200%],Daily 1 day
core for Terrazzo side walkway laborer[1,200%],Mixer
Operator[200%],Vibrator
2.3 Providing Fromwork Operator[200%]
26
21 days
27 2.3.a. to Curb mass Concrete
Carpenter,Ass. Carpenter,Daily 2 days
2.3.b. For RHS post of fence, shade and laborer[400%]
28
bench Pad, electric pole Ass. Carpenter,Daily 15 days
29 2.3.b.1 For RHS post of fence laborer[400%],Carpenter
2 days
30 2.3.b.2 For RHS post of shade and bench Pad
31 2.3.b.3 For RHS post of electric pole 1 day

32 3. Flooring Work 0.5 days

33 3.1 Fiber Glass bottle of dia 50-60cm and height of 3 days


50-60cm
3.2 Apply 5cm thick Terazzo tile using cement Daily laborer[600%],Tailer[300%] 0.5 days
34
screed or mortar on every pedestrian passage
Tailer[300%],Daily laborer[600%] 2 days
35 3.3 Apply River stone on every outer part curb
stone of that located internal greenery by Tailer[300%],Daily laborer[600%]
36 4. STEEL WORK 1 day

37 Supply and erect metal grill for protection of 11 days


greener part of as shown on the given
11 days
drawing. Price shall include Applying two
coats of antirust paint and super paint with
its purpose .
38 FOR FENCE
8 days
ID Task Name Resource Names Duration

39 4.1 Posting SHS dia. 40*40*2.5mm with height of Ass. Welder[400%],Daily 2 days
1.25m fence work laborer[600%],Welder[200%]
40 4.2 Welding SHS Vertical section of Daily 3 days
30*30*1.5mm with height of 60cm between top laborer[600%],Welder[200%],Ass.
and horizontal member of the fence. Welder[400%]
41 4.3 Welding SHS horizontal section of Daily 2 days
40*40*2.5mm at the top and bottom of the fence. laborer[600%],Welder[200%],Ass.
Welder[400%]
42 4.4 Circular metal copper and use sharp (spear) Ass. Welder[200%],Daily 1 day
metal on the top For SHS post laborer[400%],Welder
43 FOR DUST PARTICLE STORAGE 3 days

44 4.6 Welding SHS Vertical section of Welder[200%],Ass. 1 day


30*30*1.5mm with height of 1.30m at Welder[400%],Daily laborer[600%]
45 4.7 Welding SHS horizontal section of Welder,Ass. Welder[200%],Daily 1 day
30*30*1.5mm at the top and bottom ceircular laborer[400%]
46 4.8 Circular Metal sheet (lamera) for water Daily laborer[400%],Welder,Ass. 1 day
Storage Welder[200%]
47 5. Electrical Work 28 days
48 5.1 60*60*80cm MAN HOLE with cover Daily laborer[400%],Mason,barbender,Carp 1 day
Electrician,Daily laborer[700%] Daily e
49 5.2 Octagonal light pole of dia 120mm at base and 0.5 days
dia. 60mm at top length 3000mm above laborer,Electrician
50 5.3 POWER CABLES 0.6/1KV,3x2.5nsq.mm for 1 day
electrical 1.3m pole and 0m greenery light Daily laborer,Electrician
51 5.4 HPK 100*1*HPE,250W with lamp reflector 1 day
and accessories
52 6. Bench and Shed 6 days
Welder[200%],Ass.
53 6.1 RHS dia. 60*60*2.5mm thick vertical for leg Welder[400%],Daily laborer[600%] 1 day
post of bench as per drawing. Welder[200%],Ass.
54 6.2 RHS dia. 60*40*2.5mm thick vertical and Welder[400%],Daily laborer[600%] 1 day
horizontal member as per drawing. Welder,Ass. Welder[200%],Daily
55 6.3 SHS dia. 60*60*2.5mm thick vertical and laborer[400%],Carpenter,Ass. 1 day
horizontal of shed as per drawing. Carpenter
Daily laborer[400%],Carpenter,Ass.
56 6.4 Timber pinus 10*4cm thick pinus purlin for Carpenter 1 day
horizontal member of bench as per drawing Daily laborer[400%],Carpenter,Ass.
57 6.5 Timber pinus 10*5cm thick pinus purlin for Carpenter 1 day
horizontal member of shed as per drawing Daily laborer[400%],Carpenter,Ass.
58 6.6 Timber pinus 5*4cm thick pinus purlin for Carpenter 1 day
vertical horizontal member of bench as per
ID Task Name Resource Names Duration

59 7. Roofing 1 day
60 7.1 Translucent polycarbonate sheet bullan, bushan, Daily laborer[400%],Carpenter,Ass. 1 day
roofing fixed to 10x5cm pinus purlin and truss nailed Carpenter
by doom headed nail and plastec
61 8. Sanitary Works 1 day
62 8.1 Supply, lay and fix polypropelene pipe (PPR) Daily laborer[200%],Plumber 1 day
32mm dia and gate valve, phoset use all
63 2. DITCH COVER 40 days
64 1- CLEARING WORK 2 days
65 1.1 Clearing Drain floor to the right and Left and Daily laborer[1,000%],Chiesler[300%] 1 day
closing concrete sewerage pipe
66 1.2 Cartaway the solid or liquid waste from site. Daily laborer[1,000%] 1 day
67 2. REINFORCED CONCRETE WORK 7 days
68 2.1 Reinforced concrete in class C-25 2 days

69 2.1.a Pre-cast or in-situ ditch slab cover with steel Mason[200%],Daily laborer[1,200%],Mixer 2 days
handling fixed in mold Operator[200%],Vibrator Operator[200%]

70 2.2 Form work 2 days

71 2.2.a Under and sides of ditch slab cover Carpenter,Ass. Carpenter,Daily 2 days
laborer[400%]
72 2.3 RINFORCEMENT WORK 2 days

73 2.3.a Diameter 10mm, deformed bar Daily laborer[200%],barbender[200%] 2 days

74 3. FINISHING WORK 9 days


75 3.1 Apply three coats of plaster in cement mortar for Plasterer[200%],Daily laborer[400%] 1 day
top and outside for curb mass concrete
76 3.2 apply three coats of approved make weather Painter[200%],Daily laborer[200%] 1 day
resistant plastic zebra paint to edge external
77 4. TERAZZO TILE 1 day
78 4.1 20x20x5cm terrazzo tile or othre interlock shape Daily laborer[600%],Tailer[300%] 1 day
terazzo as soon you cast at the same time