ATTENDEES
Note:- Ratification of minutes of the last meeting in the first subsequent meeting after that
legitimizes the minutes of meeting for all contractual purposes
SL TARGET
POINTS DISCUSSED ACTION BY
No DATE
A QUALITY
CPS was asked to submit the pending quality documents are method 28-12-23
statement for Inspection, testing and commissioning and items related 19-12-23
check. 08-12-23
As per advised SCL-MEP, the CPS will be submitted on or before 04- 04-12-23
11-23.
24-11-23
Also, CPS informed that whatever additional test which is not in their
17-11-23
scope as per contracts, requested to submit the additional claim as
actual. 15-11-23
1 PTK
SCL-MEP advised CPS to provide the list of test which is not your scope 06-11-23
and the same will be validated and confirmed. 30-10-23
20-10-23
CPS informed TCE / SCL-MEP that except the IR test remaining all test 12-10-23
wil be conducted with additional cost. 05-10-23
15-09-23
TCE requested PTK to advise in this regard to move forward 31-08-23
CONTINUATION SHEET
B ENGINEERING
TCE / CPS highlighted that the hold for 14 drawing has become the
bottle neck to complete the project within stipulated time and requested
TCE expedite to release the DID drawing to enable commence the shop
drawing approval followed by execute at site.
To be
SCL-Civil / released
TCE also highlighted that as the architect and interior was freeze and
5 SCL-MEP / by
releasing of DID drawing should be expedited to arrest further delay
PTK immediate
which already 120 days
ly.
PTK informed TCE /CPS that all the drawings pertaining to the admin
building, canteen building, visitors lounge and security cabin which are
yet to approval the from SCL-Civil
CONTINUATION SHEET
C PROCUREMENT
Cresceon was done the mock-up and approved the same by PTK
on 27-10-23.
TCE asked CPS to expedite the fabrication and install the sub structure
at machine shop area(Work in progress at fabrication Yard). 15-01-24
15-11-23
CPS assured TCE to complete the works on or before 15-01-24 and 09-11-23
complete the bus duct laying and commissioning 25-01-23. 20-10-23
16-10-23
CPS informed TCE / SCL-MEP that 1250A bus duct will be get delivered SCL-PED 12-10-23
2 03-10-23
within 8 weeks. SCL-MEP 23-09-23
19-09-23
SCL-MEP ignored their commitment and asked CPS to supply within 4 28-08-23
weeks. 24-07-23
30-06-23
As per the machine cells marking done at machine shop dated 20-11- 12-05-23
23,in which 13 out 35 rows of lighting fixtures which already erected the
supports was encountered with substructure proposed for bus duct.
1) Clearance need at high bay pipe rack at juncture of high and low
bay pipe rack (CPS assured to complete all 7 bays
interconnection on or before 04-12-23 by doing each per day) –
5 bays completed.
2) Cable tray fabrication started, installation started on 20-12-23.
3) For respective column dropping by ladder from pipe rack
clearance need to be provided by SCL, Marking already done by 26-12-23
2 CPS
CPS 10-12-23
After had discussion cable tray can be commenced at grid along V17
and subsequently cable laying will be commenced 10-12-23 24-11-23 at
Along H2-V35 to V17 and V17-H2 to H30
Revised drawing received from PTK On 15-12-23
CPS shall start the cable tray supports works in Mezanine floor by 26-
12-23 and completion of cable tray and earthingstrips by 20-01-23 15-
12-23 04-12-23 and cable laying shall start by 30-01-23 20-12-23.
2.Machine shop:-
1) Waiting for pipe rack erection (Only for few cable tray and most
of the power carrying by bus duct)
TCE added that as per the panel vendor commitment the 1st lot of panel
will be reached on or before 30-12-23 30-11-23,20-12-2023 meanwhile
the aforesaid the balance pipe rack work will be completed to enable
commence the cable tray and cable laying
29-12-23
CPS was asked to commence the HT cable laying. 18-12-23
06-12-23
CPS has started the earth work excavation in hard strata on 02-11-23 to 02-12-23
complete the work within 15 days. And CPS was asked to mobilise the 20-11-23
3 following materials for cable laying(Cable tags,route markers.Sand,truff CPS 30-10-23
and 33KV cable below mentioing warning tape shall be procured on 20-10-23
urgent basis). 16-10-23
CPS assured to complete the cable laying and related activities by 06- 29-09-23
12-23 22-09-23
11-09-23
CONTINUATION SHEET
CPS has completed all substructure, looping cable laying has been
To be
5 commenced on 24-11-23, and CPS needs to complete the SCL-MEP
confirmed
termination,ferruel number etc, SCL need to confirm 4 light fixtures
location due to no provision for light fixture exertion.
TCE highlighted and express their concern regarding the important of all
service coordinated drawings to enable execute the works without any
clashes during execution
TCE informed Crescon that the following work front are readly available
to commence the work immediately at site
SCL MEP/TCE informed CPS to expedite the earthing strip laying works 26-12-23
12 in cable trays in all the building, completion schedule to be submitted on CPS 15-12-23
15-12-23 04-12-23 revised schedule submission by 26-12-23. 04-12-23
27-12-23
SCL MEP/TCE informed to CPS regarding the earthing pits marking of 21-12-23
13 CPS
138 nos 11-12-23
04-12-23
12-01-24
SCL MEP/TCE informed to CPS regarding street light pole errection (Till
14 CPS 21-12-23
date over all 42/73 nos completed)
11-12-23