MECHANICAL DATA SHEET

FOR VESSEL

DOC. NO. 1416-MC-MDS-V-101 CLIENT : SELAN EXPLORATION TECHNOLOGY LTD, BAKROL, AHMEDABAD SHEET 1 OF 4

TAG NO. V-101 PROJECT : SELAN OIL FIELD DEVELOPMENT PROJECT REV 0

TWO PHASE SEPARATOR


V-101

0 29-12-2022 ISSUED FOR REVIEW NA KW RP


Checked Approved
Rev Date DESCRIPTION Prepared By
By By
FORMAT NO. MC-FR-003 EFFECTIVE FROM : 20-04-2021
MECHANICAL DETAILS AND WEIGHTS

CLIENT : SELAN EXPLORATION TECHNOLOGY LTD, BAKROL,


DOC. NO. 1416-MC-MDS-V-101 SHEET 2 OF 4
AHMEDABAD
TAG NO. V-101 PROJECT : SELAN OIL FIELD DEVELOPMENT PROJECT REV 0
DESIGN / FABRICATION CODE ASME SEC. VIII DIV.1 LATEST EDITION CODE STAMP N.A
SERVICE NON LETHAL (FLAMMABLE) IBR N.A
VESSEL SIZE 700mm I.D x 2100mm TL to TL QTY : 1 No. TYPE CYLINDRICAL + HORIZONTAL

DESCRIPTION UNIT DESIGN DATA


Gas (Methane, Ethane, Propane, Butane, Carbon dioxide, Nitrogen) /
FLUID
Liquid (Hydrocarbon oil + water)
DENSITY OF FLUID (GAS / LIQUID) kg/m3 2.25 / 897
VOLUME (OPERATING / GROSS) m3 0.6 / 0.9
OPERATING PRESSURE kg/cm2 (g) 2.07 - 2.58
OPERATING TEMPERATURE (MAX.) °C 40
DESIGN PRESSURE (INT./ EXT.) kg/cm2 (g) 5 / FV
DESIGN TEMPERATURE °C 80
MDMT °C 0
MAWP kg/cm2 (g) 5
HYDRO TEST PRESSURE kg/cm2 (g) 6.5 (AT TOP)
TEST POSITION (VERTICAL/HORIZONTAL) - HORIZONTAL
CORROSION ALLOWANCE mm 3
WELD JOINT EFFICIENCY (SHELL / HEAD) - 0.85 / 1.0
RADIOGRAPHY (SHELL / HEAD) - SPOT + ALL 'T' JOINTS / FULL
PWHT N.A
IMPACT TEST N.A
STRESS RELIEVING N.A
INSULATION TYPE / THICKNESS TYPE / mm / - HOT / 25
DEMISTER PAD DETAIL - 1416-PS-PDS-V-101 (SHEET 3 OF 4 of PDS)
WIND DESIGN CODE / BASIC WIND SPEED m/sec IS 875 (Part 3) / 39
SEISMIC DESIGN CODE / ZONE / LOCATION - IS 1893 RSM (Part 2&4) / ZONE III / BAKROL, AHMEDABAD
INSPECTION BY - CLIENT / TPIA
WEIGHTS
FABRICATED WEIGHT (WITHOUT INTERNALS) kg 815
EMPTY WEIGHT ( WITH INTERNALS) kg 855
OPERATING WEIGHT kg 1598
HYDRO TEST WEIGHT kg 1791
FOUNDATION LOAD DATA AT BASE
WIND SHEAR AT BASE kg 150
SEISMIC SHEAR AT BASE kg 125
WIND MOMENT AT BASE kg-m 105
SEISMIC MOMENT AT BASE kg-m 90
REFERENCE DOCUMENT
SR.NO. DESCRIPRION DOCUMENT NO. REV. NO.
1 PROCESS DATA SHEET 1416-PS-PDS-V-101 2
2 MECHANICAL DESIGN BASIS 1416-MC-DBS-101 1
3 ENGG. STD. FOR VESSELS REACTORS & COLUMNS MC-DCI-101 3
MATERIAL OF CONSTRUCTION
ITEMS MATERIAL ITEMS MATERIAL
SHELL SA 516 Gr.70 EARTHING CLEAT / BOSS SS 304
DISH END SA 516 Gr.70 NAME PLATE SS 304
GIRTH FLANGES (NON STD.) SA 266 Gr. 2 NAME PLATE BRACKET SA 516 Gr.70
NOZZLE FLANGES SA 105 FASTENERS (INTERNAL) SS 304
GASKET ** INTERNAL ATTACHMENT SA 516 Gr.70
NOZZLE UP TO 300NB SA 106 Gr. B DEMISTER PAD SS 316
NOZZLE ABOVE 300NB SA 516 Gr.70
R.F. PAD SA 516 Gr.70
SA-193 Gr.B7 /
FASTENERS (EXTERNAL)
SA-194 Gr.2H (HDG)
EXTERNAL ATTACHMENT SA 516 Gr.70
SADDLE SUPPORT SA 516 Gr.70 + IS:2062 E250 BR
LIFTING TRUNIONS / LIFTING LUG / TAILING LUG IS:2062 E250 BR
** SPIRAL WOUND GRAPHITE FILLED, WITH SS 304 INNER & CS OUTER RING
FORMAT NO. MC-FR-003 EFFECTIVE FROM : 20-04-2021
NOZZLE SCHEDULE & MOC

CLIENT : SELAN EXPLORATION TECHNOLOGY LTD, BAKROL,


DOC. NO. 1416-MC-MDS-V-101 SHEET 3 OF 4
AHMEDABAD
TAG NO. V-101 PROJECT : SELAN OIL FIELD DEVELOPMENT PROJECT REV 0

NOZZLE SIZE SCH. / FLANGES RF PAD PROJECTION


SERVICE QTY REMARKS
MARK NO. NB THK. CLASS TYPE FACE OD x T MIN.

F FEED INLET WITH `J' PIPE 80 80 1 150# WN RF - 200


B BOTTOM OUTLET 50 160 1 150# WN RF - 200
V VAPOR OUTLET 50 160 1 150# WN RF - 200
D DRAIN 50 160 1 150# WN RF - 200 WITH BLIND FLANGE

PT PRESSURE TRANSMITTER 50 160 1 150# WN RF - 200 DIAPHRAGM SEAL TYPE

SV PRESSURE SAFETY VALVE 50 160 1 150# WN RF - 200


TG THERMOWELL 40 XXS 1 150# WN RF - 200
LC LEVEL CONTROLLER HOLD HOLD 1 150# WN RF - - HOLD

LG1-2 LEVEL GAUGE 50 160 2 150# WN RF - 200 MAGNETIC TYPE

S1 SPARE 40 160 1 150# WN RF - 200 WITH BLIND FLANGE

S2 SPARE 50 160 1 150# WN RF - 200 WITH BLIND FLANGE

IMPORTANT NOTES
GENERAL :-
1. THE CONSTRUCTION OF EQUIPMENT SHALL BE AS PER ASME SEC VIII DIV.1, SEC II. SEC V, SEC IX & OTHER APPLICABLE CODES.
2. ALL DIMENSIONS ARE IN MM, UNLESS OTHERWISE SPECIFIED.
3. ALL FLANGES BOLT HOLES SHALL BE STRADDLE TO THE HORI./VERT. CENTER LINES OF EQUIPMENT.
4. STD. FLANGES SIZE UP TO 600NB SHALL BE AS PER ASME B16.5 & ABOVE 600NB AS PER ASME B16.47 SERIES B. UNLESS OTHERWISE AS PER DETAILS.
5. STD / NON STD FLANGES GASKET SEATING SURFACE SHALL HAVE 125 TO 250 AARH FINISH & SUITABLY PROTECTED DURING HANDLING.
6. NOZZLE PROJECTION ON SHELL/DISH SHALL BE TAKEN FROM OUTER SURFACE.
7. NOZZLES UP TO 50 NB SHALL BE STIFFENED WITH 2 GUSSETS 6T x 40W @ 90 DEG APART.
8. NOZZLE UP TO 300NB SHALL BE SEAMLESS & ABOVE CAN BE FABRICATED FROM PLATE & LONG SEAM SHALL BE 100% RT TESTED.
9. NOZZLE RF PADS, OTHER EXTERNAL PADS & SLIP ON FLANGES SHALL HAVE 1 TAPPED HOLE OF 1/4" NPT.
10. EQUIPMENT TOLERANCES SHALL BE AS PER QPS STD. MC-STD-001.
11. ALL REMOVABLE INTERNALS SHALL BE DESIGNED SO AS TO PASS THROUGH MANHOLE / BODY FLANGE.
12. SPARES- (A) 200% GASKET PER FLANGED JOINT (B) 10% OF BOLTS & NUTS (EACH SIZE) OR MIN. 2 NOS.
13. LIFTING LUGS/TRUNNIONS/TAILING LUGS AS PER QPS STD. OTHERWISE VENDOR TO DESIGN WITH IMPACT FACTOR OF 2.0
14. DEMISTER IS IN VENDOR'S SCOPE OF SUPPLY. DEMISTER DETAIL ATTACHED.

MATERIAL :-
1. ALL MATERIALS SHALL BE NEW AND UNUSED AND TOLERANCE ON THE THICKNESS OF THE PLATES SHALL BE POSITIVE ONLY.
2. THE CARBON CONTENT FOR MATERIAL SHALL NOT EXCEED 0.23%, EXCEPT FOR FORGINGS WHICH SHALL BE LIMITED TO 0.25% MAXIMUM & CEQ <=0.45%.
3. PRESSURE PARTS LIKE NOZZLE NECKS, PIPING, AND FITTINGS SHALL BE OF SEAMLESS CONDITION.
4. ALL FORGINGS/FLANGES SHALL BE IN NORMALIZED CONDITION.
5. PLATES (PRESSURE PARTS) THK. =>16mm & NON STD. FLANGES => 10" SHALL BE 100% UT TESTED.

FABRICATION ;-
1. INDICATED THICKNESS ARE MIN. ACCEPTABLE AFTER FABRICATION.
2. ALL BUTT WELD SHALL BE FULL PENETRATION WELD. THESE WELD SHALL BE BACK CHIPPED, DP CHECKED AND REWELDED.

3. ALL WELD SEAMS (LS & CS) SHALL BE ORIENTED TO CLEAR NOZZLE OPENING OR OTHER ATTACHMENTS. IF UNAVOIDABLE, 150mm RT AT BOTH SIDE OF THE SEAM SHALL BE PERFORMED.

EXAMINATION :-
1. SPOT RT MEANS 10% RT OF ALL JOINTS + ALL T-JOINTS & FULL RT MEANS 100% RT FOR ALL BUTT WELDS & NOZZLES =>10".
2. ALL PRESSURE PARTS WELD SHALL BE CHECKED BY PT/DP & DISH ENDS KNUCKLE REGION FROM INSIDE & OUTSIDE BEFORE/AFTER HYDRO TEST.

INSPECTION & TESTING :-


1. PRIOR TO FINAL INSPECTION AND HYDROSTATIC TEST, THE INSIDE AND OUTSIDE OF THE VESSEL SHALL BE THOROUGHLY CLEANED AND SHALL BE FREE FROM ALL SLAG, SCALE, DIRT,
GRIT, WELD SPATTER, AND PIECES OF METAL PAINT AND OIL.
2. GASKET, BOLTS & NUTS USED FOR TEST SHOULD BE OF SAME MATERIAL AS THAT USED IN SERVICE.
3. CLEAN POTABLE WATER SHALL BE USED FOR HYDRO TEST. HYDROSTATIC TEST SHALL BE HELD FOR ONE HOUR MIN. TEMPERATURE SHALL BE BETWEEN 15-45° C.
4. VESSELS SHALL BE DRAINED IMMEDIATELY AFTER TESTING AND ANY REMAINING POCKETS OF WATER SHALL BE SWABBED DRY. THE VESSEL SHALL BE DRIED BY BLOWING AIR FOR A
CONTROLLED LIMITED PERIOD.
SURFACE PREPARATION AND PAINTING :-
1. EQUIPMENT SHALL BE SUPPLIED IN FINISHED CONDITION AND AS PER SELAN SPECIFICATION.
2. ALL SS INT/EXT SURFACES SHALL BE PICKELED & PASSIVATED AFTER HYDRO TEST.
FORMAT NO. MC-FR-003 EFFECTIVE FROM : 20-04-2021
`A'

`A'

PROCESS SOLUTIONS PVT.LTD.


REV. 2
PROCESS DATASHEET
DEMISTER PAD

DOC. NO. CLIENT SELAN EXPLORATION TECHNOLOGY LTD, BAKROL, AHMEDABAD TAG NO.
1416-PS-PDS-V-101 ITEM TWO PHASE SEPARATOR V-101
PROCESS AND PERFORMANCE DATA (Demister Pad) Rev.
Services To prevent carry over of liquid droplets from outgoing gas leaving vessel. No. of pads 1
Process Data
Operating pressure 2.07-2.58 kg/cm2g Design pressure 5/FV kg/cm2g
Operating temperature 40 °C Design temperature 80 °C
Shell ID 700 mm Shell MOC CS
Vapour Data
Vapour / Mist Light Hydrocarbon gas (3) Vapour flowrate 179 kg/hr
Vapour density 2.3 kg/m3 Vapour molecular weight 19.1
Vapour viscosity 0.01 cP
Liquid Data
Liquid flowrate 1,605 kg/hr Liquid surface tension # dynes/cm
Liquid density 897 kg/m3 Liquid viscosity 219.4 cP
Demister Detail
Demister type Mesh Type**
Demister OD * mm Efficiency expected(4) >99** %
Overall thickness 150** mm Allowable pressure drop 150 (max)** mmWC
Demister MOC SS316** Surface area * m2/m3
Density * kg/m3 % Voids *

Scope of supply
1. Demister with support / fixing system
NOTES
* Vendor to specify
** Vendor to confirm
1 Vendor to specify installation arrangement / GA drawing.
2 Vendor to specify calculated pressure drop through the demister.
Gas Composition (%wt) : CH4 - 73.39%, C2H6 - 9.29%, C3H8 - 8.18%, C4H10 - 4%, C5H12 - 2.14%, C6H14 - 1%, N2
3
- 1%, CO2 - 1%.
4 Efficiency for removal of liquid particle size ≥ 10μm.

# SELAN to confirm/provide.

Format no: PS-FR-008/R-01 Effective Date: 18/05/2022 Page 3 / 4