ID Task Task Name Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024

Mode Sep Oct Nov Dec Jan Feb Mar


1 Production Lighting System 105 days Mon 02/10/23 Fri 23/02/24
2 Obtain Purchase Order 0 days Mon 02/10/23 Mon 02/10/23 02/10
3 Incoming Equipment & Material 84 days Wed 11/10/23 Mon 05/02/24
4 Approval 17 days Wed 11/10/23 Thu 02/11/23
5 Hellukable 3 days Mon 16/10/23 Wed 18/10/23 2FS+2 wks
6 Control Panel 9 days Mon 23/10/23 Thu 02/11/23
7 Rittal Dryer TS8 3 days Mon 23/10/23 Wed 25/10/23 2FS+3 wks
8 Rittal Slurry AE 3 days Mon 23/10/23 Wed 25/10/23 7SS
9 Rittal JB 3 days Thu 26/10/23 Mon 30/10/23 8
10 Siemens BSM SIMBOX 3 days Tue 31/10/23 Thu 02/11/23 9
11 Siemens CGL SIMBOX 3 days Tue 31/10/23 Thu 02/11/23 10SS
12 Lightings 2 days Wed 11/10/23 Thu 12/10/23
13 LED Lightings 2 days Wed 11/10/23 Thu 12/10/23 2FS+7 days
14 Emergency LED 2 days Wed 11/10/23 Thu 12/10/23 13SS
15 Wiremesh Cable tray 3 days Mon 16/10/23 Wed 18/10/23 2FS+2 wks
16 Switches & Sockets 3 days Mon 16/10/23 Wed 18/10/23 2FS+2 wks
17 Material Onsite 82 days Fri 13/10/23 Mon 05/02/24
18 Power Cables 15 days Thu 19/10/23 Wed 08/11/23
19 Hellukable 15 days Thu 19/10/23 Wed 08/11/23 5
20 Electrical Control Panel 73 days Thu 26/10/23 Mon 05/02/24
21 Rittal Dryer TS8 12 wks Thu 26/10/23 Wed 17/01/24 7
22 Rittal Slurry AE 12 wks Thu 26/10/23 Wed 17/01/24 8

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Production Lighting Sy
Summary Manual Summary Rollup Progress
Date: Tue 31/10/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024
Mode Sep Oct Nov Dec Jan Feb Mar
23 Rittal JB 14 wks Tue 31/10/23 Mon 05/02/24 9
24 Siemens BSM SIMBOX 12 wks Fri 03/11/23 Thu 25/01/24 10
25 Siemens CGL SIMBOX 12 wks Fri 03/11/23 Thu 25/01/24 11
26 Lightings 75 days Fri 13/10/23 Thu 25/01/24
27 LED Lightings 75 days Fri 13/10/23 Thu 25/01/24 13
28 Nicad Battery 30 days Fri 13/10/23 Thu 23/11/23 14
29 Wiremesh Cable tray 15 days Thu 19/10/23 Wed 08/11/23 15
30 Switches & Sockets 20 days Thu 19/10/23 Wed 15/11/23 16
31 Installation 77 days Thu 09/11/23 Fri 23/02/24
32 Marking & Support Instal 27 days Thu 09/11/23 Fri 15/12/23
33 Cable Tray 20 days Thu 09/11/23 Wed 06/12/23
34 BSM 1,5 wks Thu 09/11/23 Mon 20/11/23 29
35 COARSE GRINDING 1,5 wks Thu 16/11/23 Mon 27/11/23 34SS+5 days
36 DRYER 2 wks Thu 23/11/23 Wed 06/12/23 35SS+5 days
37 SLURRY 1 wk Thu 30/11/23 Wed 06/12/23 36FF
38 Panel & JB Position 8 days Mon 20/11/23 Wed 29/11/23
39 BSM 1 day Mon 20/11/23 Mon 20/11/23 34SS+7 days
40 COARSE GRINDING 1 day Mon 27/11/23 Mon 27/11/23 39;35SS+7 days
41 DRYER 1 day Tue 28/11/23 Tue 28/11/23 40
42 SLURRY 1 day Wed 29/11/23 Wed 29/11/23 41
43 General LED & Emergency LED 19 days Tue 21/11/23 Fri 15/12/23
44 BSM 5 days Tue 21/11/23 Mon 27/11/23 39

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Production Lighting Sy
Summary Manual Summary Rollup Progress
Date: Tue 31/10/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024
Mode Sep Oct Nov Dec Jan Feb Mar
45 COARSE GRINDING 4 days Tue 28/11/23 Fri 01/12/23 44;40
46 DRYER 1 wk Mon 04/12/23 Fri 08/12/23 45;41
47 SLURRY 1 wk Mon 11/12/23 Fri 15/12/23 46;42
48 Switches & Sockets 5 days Thu 16/11/23 Wed 22/11/23
49 BSM 3 days Thu 16/11/23 Mon 20/11/23 30
50 COARSE GRINDING 4 days Thu 16/11/23 Tue 21/11/23 30
51 DRYER 5 days Thu 16/11/23 Wed 22/11/23 30
52 SLURRY 4 days Thu 16/11/23 Tue 21/11/23 30
53 Unit Install 68,5 days Mon 20/11/23 Thu 22/02/24
54 Cable Tray 58,5 days Mon 20/11/23 Thu 08/02/24
55 BSM 5 days Mon 20/11/23 Mon 27/11/23 29;34;15
56 COARSE GRINDING 5 days Mon 27/11/23 Mon 04/12/23 35;29;15
57 DRYER 10 days Fri 26/01/24 Thu 08/02/24 26;29;15
58 SLURRY 7 days Thu 07/12/23 Fri 15/12/23 37;29;15
59 Panels & JBs 8 days Tue 21/11/23 Thu 30/11/23
60 BSM 1 day Tue 21/11/23 Tue 21/11/23 39
61 COARSE GRINDING 1 day Tue 28/11/23 Tue 28/11/23 40
62 DRYER 1 day Wed 29/11/23 Wed 29/11/23 41
63 SLURRY 1 day Thu 30/11/23 Thu 30/11/23 42
64 Wiring 24,5 days Tue 21/11/23 Mon 25/12/23
65 BSM 1 wk Tue 21/11/23 Mon 27/11/23 19;34;39
66 COARSE GRINDING 1 wk Tue 28/11/23 Mon 04/12/23 65;19;35;40

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Production Lighting Sy
Summary Manual Summary Rollup Progress
Date: Tue 31/10/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Task Name Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024
Mode Sep Oct Nov Dec Jan Feb Mar
67 DRYER 1,5 wks Thu 07/12/23 Mon 18/12/23 66;19;36;41
68 SLURRY 1 wk Mon 18/12/23 Mon 25/12/23 67;19;37;42
69 General & Emergencies LED 20 days Fri 26/01/24 Thu 22/02/24
70 BSM 5 days Fri 26/01/24 Thu 01/02/24 65;26
71 COARSE GRINDING 5 days Fri 02/02/24 Thu 08/02/24 66;70
72 DRYER 5 days Fri 09/02/24 Thu 15/02/24 67;71
73 SLURRY 5 days Fri 16/02/24 Thu 22/02/24 68;72
74 Switches & Sockets 7 days Tue 21/11/23 Wed 29/11/23
75 BSM 3 days Tue 21/11/23 Thu 23/11/23 49
76 COARSE GRINDING 3 days Wed 22/11/23 Fri 24/11/23 50
77 DRYER 5 days Thu 23/11/23 Wed 29/11/23 51
78 SLURRY 4 days Wed 22/11/23 Mon 27/11/23 52
79 Test & Comm 16 days Fri 02/02/24 Fri 23/02/24
80 BSM 1 day Fri 02/02/24 Fri 02/02/24 70;75
81 COARSE GRINDING 1 day Fri 09/02/24 Fri 09/02/24 71;80;76
82 DRYER 1 day Fri 16/02/24 Fri 16/02/24 72;81;77
83 SLURRY 1 day Fri 23/02/24 Fri 23/02/24 73;82;78
84 Handover Control to Operation 0 days Fri 23/02/24 Fri 23/02/24 79 23/02

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Production Lighting Sy
Summary Manual Summary Rollup Progress
Date: Tue 31/10/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4