Customers in the whole world work with our high quality machines from EIMA which have
a very long expectancy of life.
We prepare for our customers the project planning for complete lines of our French
Fries,Potato Flakes, Hash Browns and Peeled Potatoes lines. From washing up to the
packaging.
The machines are produced by our trained staff in our modern company in Edewecht,
Germany.
We produce with modern fabrication mediums.
Our precision guarantees our quality.
Pos. 1.0
Productdescription
Pos. 1.10
1 Description of processing: French Fries 1.000 kg/h
Type: Pommes 1.000 kg/h
Product: French Fries
Capacity: 1.000 kg/h
Raw 2.000 kg h
Material:
Sortation: share in dust max. 2%, share in stones max. 3%, dimensions
ofpotatoes max. 100 mm length
With the belt conveyor the potatoes, which are free of earth and
cabbage,will be given up in a dosing way to a washing and destoning
line.
The first section is for the separating of dry dust, after this the potatoes
areseparated from stones. The last section is for washing the potatoes
with minimal water use.
From the cutting machine the sticks go to a special sort belt. By this
special sort belt the thin sticks will be separated. It is possible to adjust
thehigh of the quantity of the waste.
In the first blanching machine the potatoes will be heating in a short time
(high short blanching machine) and in the second blanching machine
there
is a long heating by lower temperatures (long low blanching machine)
product.In the continuous fryer the potatoes will be fried to get a fat holding of 5.5
– 7,5.
The fryer work automatically and fills self- dependent oil of the oil tank.
After frying the sticks will be cooled in the air cooling system to + 8° to
10°Cover room temperature. Air ventilators blow with cool air from
outside,
so that the French Fries loses the high temperature.
After the cooling there is the last time an inspection belt for controlling.
In the freezing tunnel the French Fries will be cooled to a temperature of -18 C.
In the packing machine is in the first step a scale, which separates the
product in four parts. Under it there is the packaging machine for
packaginginto hosepipe bags.
Pos. 2.0
Machinedescription
Pos. 2.10
Washing, peeling, inspection
Pos. 2.1.10
Function:
Washing machine with a pre- dry
cleaningwithin the 1st drum. Destoner
with automatic stone outlet above
conveyor.
Product is washed in the 2nd
drum.Mud is collected in the
outlet with manually emptying.
Corrosion protection:
stainless steel parts are pickled and
passivated.Drive components 1 basic, 1 top
coat with synthetic enamel RAL 5002,
ultramarine blue
Pos. 2.1.20
1 Belt conveyor in hygienic design
Corrosion protection:
Stainless steel parts pickled and
passivated.Bearing and drive parts
varnished,
Colour RAL 5002, ultramarine blue
Pos. 2.1.30
1 Carborundum peeling machine
Type: WS 08-25 L
Product: washed potatoes
Main measurements: 3200 mm x 1200 mm x 2100 mm (L x B x H)
Material: Stainless steel, material No 304 (1.4301)
Function: peels potatoes mechanically
Energy: Engine Power/ current: approx. 6,8
kW Water: approx. 0,5
m³/h
ware)Implementation
Corrosion protection:
stainless steel parts are pickled and
passivated.Drive components 1 basic, 1 top
coat with synthetic enamel, RAL 5002,
ultramarine blue
Pos. 2.1.40
1 Inspection table
Corrosion protection:
stainless steel parts are pickled and
passivated.Drive components 1 basic, 1 top
coat with synthetic enamel, RAL 5002,
ultramarine blue
Pos. 2.20
Cutting, blanching
Offer-No. 26941 of 28.05.2020 Page 11 of 46
VC No.: 2067
Pos. 2.2.10
Corrosion protection:
Stainless steel parts pickled and
passivated.Bearing and drive parts
varnished,
Colour RAL 5002, ultramarine blue
Pos. 2.2.20
1 Cutting maschine
Pos. 2.2.30
1 Nubbin grader
Type: LS 08-20
Product: Potato sticks
Main measurements: 2490 x 1400 x 2200 mm (L x B x H)
Material: stainless steel, material No. 304 (1.4301)
Function: sorting out small pieces
Energy: Engine Power/ current: approx. 1,5 kW
Implemenation:
elements.
Two unbalance motors: 0,75 KW, efficiency class IE3, 230 / 440 V, 50 Hz, IP 65
Exchangable whole punches sieves held by spring compressors.
corrosion protection
stainless steel parts are pickled and passivated.
Drive components 1 basic, 1 top coat with synthetic
enamel,RAL 5002, ultramarine blue.
Pos. 2.2.40
1 Sliver remover
Corrosion protection:
stainless steel parts are pickled and
passivated.Drive components 1 basic, 1 top
coat with synthetic enamel, RAL 5002,
ultramarine blue
Pos. 2.2.50
OPTION: Support with platform
Type: Bühne I
Material: stainless steel, material No. 304 (1.4301)
Function: as support and maintenance construction
Implementation:
Implementation:
Side cheek made of laser blank with stiffening.
Corrosion protection:
stainless steel parts are pickled and passivated.
Pos. 2.2.60
1 Belt conveyor in hygienic design
Corrosion protection:
Stainless steel parts pickled and
passivated.Bearing and drive parts
varnished,
Colour RAL 5002, ultramarine blue
Pos. 2.2.70
1 Slant blanching machine
Corrosion protection:
stainless steel parts are pickled and
passivated.Drive components 1 basic, 1 top
coat with synthetic enamel, RAL 5002,
ultramarine blue
Pos. 2.2.80
1 Slant blanching machine
Spigot with rotary unions, water leaving through drills in the screw
axis.Screw spiral 800 mm Ø, half raising in inlet area, punched
vanes, double-sided continuous welded, bearing outside.
Sealant at waved passage with ring packing
Corrosion protection:
stainless steel parts are pickled and
passivated.Drive components 1 basic, 1 top
coat with synthetic enamel, RAL 5002,
ultramarine blue
Pos. 2.2.90
OPTION: Support with platform
Type: Bühne I
Material: stainless steel, material No. 304 (1.4301)
Function: as support and maintenance construction
Implementation:
Corrosion protection:
stainless steel parts are pickled and passivated.
Pos.
2.30
Drying, frying, freezing
Pos. 2.3.10
Corrosion protection:
stainless steel parts are pickled and
passivated.Drive components 1 basic, 1 top
coat with synthetic enamel, RAL 5002,
ultramarine blue.
Pos. 2.3.20
Type: BT EBT-150-9
3 Heat
exchangers4
Door elements
Measuring
pieces
Discharge Device
plantfor each:
Cleaning devices
unitEMR
technique
Documentation
Pos. 2.3.30
1 Wire netting band
Type: DB 10-30
Product: French Fries
Main measurements: 1000 mm breadth, 3000 mm length
Material: stainless steel, material No 304 (1.4301)
Function: transport and cooling of deep-fried french fries
Energy: Engine Power/ current: approx. 0,6 kW
Implementation:
Corrosion protection:
stainless steel parts are pickled and
passivated.Drive components 1 basic, 1 top
coat with Synthetic enamel, RAL 5002,
ultramarine blue
Pos. 2.3.40
1 Belt conveyor in hygienic design
Corrosion protection:
Stainless steel parts pickled and
passivated.Bearing and drive parts
varnished,
Colour RAL 5002, ultramarine blue
Pos. 2.3.50
1 Continuous Fryer
Pos. 2.3.60
1 Fat separator
Corrosion protection:
stainless steel parts are pickled and
passivated.Drive components 1 basic, 1 top
coat with synthetic enamel, RAL 5002,
ultramarine blue.
Corrosion protection:
Stainless steel parts pickled and
passivated.Bearing and drive parts
varnished,
Colour RAL 5002, ultramarine blue
Pos. 2.3.80
OPTION: Precooler
Type: SF P-3-2
Product: French fries, sliced 10 x 10 mm
Main measurements: 4900 x 3620 x 3000 mm (L x B x H)
Material: Stainless steel, material No 304 (1.4301), top and barrier
madeof polyurethane, sandwich panels
Function: shock freezing of the product
Input temperature: 30° C
Output temperature: -18 ° C
Corrosion protection:
manufacturer's specification
Provision:
A cooling machine must be locally provided by the client.
Pos. 2.40
OPTION: Weighing, packaging
Pos. 2.4.10
Pos. 2.4.20
Weighing and packaging machines for French Fries
Implementation:
Design characteristics:
Cone with underlying dosing and weighing containers.
Sealed construction with built-in load cell
housingand vibration drives. Easy disassembly
of all with
the products in touched parts. Disassembly of product contudcting
components without tools. Wear-resistant container without
return springs, low noise. Container control detects and
signaled the flap movement disorders.
Electrical is integrated in the weigher frame.
Controller:
Computercontrolling in multi process.
Control over color display with 200 program memory.
Menu-driven program input Automatic zero point taring,
Averaging control, integrated statistical analysis,
1 Platform accessible
Implementation:
Construction of tube frame profile with stairs and railings all around.
Cover with tread plates.
Implementation:
Bracket for thermal transfer printers to integrate into the bagging machine
with a printing software to print images for a VIDEOJET thermal transfer
printer, based on windows, including thermal transfer printer VIDEOJET
DATA FLEX +for intermittent operation with max. Intermittent pressure area:
53 x 75mm.
Corrosion protection:
Cabinet, frame and screws made of stainless steel
1.4301Body parts made of anodized aluminum
Pos. 2.50
OPTION: Energy
Pos. 2.5.10
Location: indoors
Assembly and operating conditions:
free of Frost, dust as well as dripping
water Erection altitude max. about sea
level: 50 mAmbient temperature min.
20°C
Ambient temperature max.
40°CVoltage: 400V
Voltage fluctuations max. +/-
5%Neutral conditions: yes
Earth connection: yes
Medium: Saturated
steamFuel: Gas/ Natural
gas
all details ref. to the O2-contents
inthe dry smoke gas of 2.1%
Fuel standard DVGW G260
Net calorific value (rated to 0°C / 1013
mbar)(gas): 8.83 kWh/nm3
Gas flow pressure: 100 mbar
Firing equipment
Pumpmodule PM
Type of the control feed pump On/
DQ
Totalhardness: 10.0°d
Carbon Hardness:
3.0°dMax.capacity: 8
m³/h
Type Water Softening Module: WTM-DM
800Raw water pre-pressure min. 3.0 bar
Raw water pre-pressure max. 6.0
barWater temperature min. 5.0°C
Water temperature max.
30.0°CImplementation:
Insulation:
- with mineral wool mats and protective cladding of structurated aluminium
Equipment boiler:
1 pressure safeguard, feed water shut-off valve,
feed water non-return device, drain shut-off valve,
automatic blow down device, feed water pump control
Documentation:
operating
manual,
operation log,
acceptance documentation
cerfiticate acc. to EN 10204 per valve.
Pos. 2.5.20
Pipeline
Corrosion protection:
stainless steel parts are pickled and passivated.
Pos.
2.60
Control
Pos. 2.6.10
1 Controller
Implementation:
Pos.
2.70
Packing, Assembly, Start-up
Pos. 2.7.10
Type: Verpackung
Pos. 2.7.20
1 Assembly
Pos. 2.7.30
1 Start-up the line
Type: Inbetriebnahme
Function: Bring the machines gradually to full load. Training the
coworkerof the client.
Two supervisors are locally for the start-up of the line.
The maximally time estimated for this amounts to 1
week,work time of 8 hours per day, with 5 days per
week.
Belt conveyor
Corrosion protection:
stainless steel parts are pickled and
passivated.Drive components 1 basic, 1 top
coat with synthetic enamel, RAL 5002,
ultramarine blue
Pos. 2.8.20
Steam Peeler
Monsun
Type: DS 05-16 Monsun
Product: washed potatoes
Capacity: approx. 6,7 t/h, peeling time 30 sec., details*
Material: stainless steel, mat. 304 (1.4301)
Implementation:
*details capacity:
65 % filling, filling per cycle 158 kg.
The performance depends on the quality of the product,
it may vary.
Advantage:
Accessory:
Certificates:
Corrosion protection:
stainless steel parts are pickled and
passivated.Drive components 1 basic, 1 top
coat with synthetic enamel, RAL 5002,
ultramarine blue.
Pos. 2.8.30
Omega-trough screw conveyor
Corrosion protection:
stainless steel parts are pickled and
passivated.Drive components 1 basic, 1 top
coat with synthetic enamel, RAL 5002,
ultramarine blue
Corrosion protection:
stainless steel parts are pickled and
passivated.Drive components 1 basic, 1 top
coat with synthetic enamel, RAL 5002,
ultramarine blue
Pos. 2.8.50
Peelings pump
Type: SP 2
Product: potato peelings
Capacity: 2 t/h
Material: gray cast iron
Function: grabbing of peelings and pumping in the case
Energy: Engine Power/ current: approx. 3,0 kW
Pos. 2.8.60
Water circulation pump with pipe fittings
Type: Kreiswasserpumpe
Product: water
Material: Hydro steel
Conveyor output: 90 m3/h
Energy: Engine Power/ current: approx. 3,0
kW Water: approx. 1,0
m³/h
Implementation:
Commercial Conditions:
Facing the price fluctuations this time of the stainless steel (V2A)
prices, will the called prices of this offer will be new calculated at
thedate of the application.
The payment is made through funds transfer to the account of the vendor
to the above mentioned bank: Landessparkasse zu Oldenburg.
The payments from the letter of credit (L/C) are made in 2 steps against
document
presentation:
a) 30% of the contract price
b) 30% of the contract price.
For all offers and agreements for the delivery products made by us and/or for services
for delivery and adjustment of the mechanical, electrical and attached electronically
productscount the ORGALIME abstracted bonds (November 2016).
Yours faithfully
EIMA Engineering
GmbHKai Brandt
Unless other terms or conditions have been agreed upon in writing, solely the following terms
andconditions are valid for all present and future deliveries and services (subsequently jointly
referred to as "deliveries"). The customer's terms and conditions are valid only to the extent that
we agree to them in writing.
1. Offer
s1.1
Offers are not binding. Contracts come into being only through our confirmation of the order in
writing or by delivery. In particular, our employees must confirm in writing oral collateral
agreements or promises going beyond the contents of the written contract or changing these
General Terms of Delivery and Payment to our disadvantage.
1.2
Unless they are explicitly referred to as binding, those illustrations, drawings, and details
concerning colour, weight, or size included in the offer are only approximations.
2. Price
s2.1
Our prices are ex works without packaging or the applicable value added tax.
2.2
Should the delivery period exceed 2 months, and there be significant changes in wage, salary,
material, or raw material expenses after conclusion of the contract, and we not be responsible for
these changes, we have the right to increase or decrease the agreed-upon prices
correspondingly. Should a price increase exceed 5%, the customer has the right to withdraw from
the contract within 2 weeks after notification of the price increase.
3. Paymen
t3.1
Payments must be made to our designated account without deductions or fees within 10 days of
the invoice date. Payments are valid only to the extent that we can freely dispose them at our
bank. We accept checks and bills of exchange only on account. The customer bears banking
charges. Banking charges are due at once.
3.2
Should payment be delayed, we will charge interest on the overdue amount of 8 per cent or of
10%, whichever is greater.
3.3
Withholding payment or offsetting claims is allowed only to the extent that the counterclaim is
undisputed or legally binding.
4.2
We have the right to make reasonable partial deliveries.
5. Delivery
Period5.1
The delivery period begins with the dispatch of the order confirmation, but not before
clarificationof all details of the execution of the order and of all technical questions, and before
receipt of anyagreed-upon partial payment. The delivery deadline has been met when the goods
have left the factory before the deadline or, when shipment has been delayed for reasons that
are not our fault, when the customer has been notified that the goods are ready to ship.
5.2
Customer's modification requests extend the period of delivery until we have evaluated their
feasibility and for the period of time necessary to implement the new manufacturing instructions.
Should the implementation of the modification request interrupt an ongoing production, we may
give priority to and finish other orders. We are not required to reserve production capacity during
the delay.
5.3
Should delivery be delayed, our liability is limited in cases of ordinary negligence to a lump sum
compensation of 0,5% of the invoice value of the delayed goods for every full week of delay and
to a maximum 5% of the invoice value of the delayed goods. Claims for damages instead of
performance according to Clause 11.1 are not affected by this clause. The customer must inform
us no later than at the time the contract is concluded about his liability concerning contractual
penalties to his customers.
5.4
Should shipment be delayed for reasons that are not our fault, we may charge at least 0,5% of
the invoiced value of the stored goods per month for storage at our plant.
7. Force
majeure7.1
Events that are unforeseen, unavoidable or beyond our control (e.g., force majeure; strikes and
lockouts; stoppages; difficulties in obtaining materials or energy; transportation delays; labor,
7.2
Should the difficulty not only be temporary, both parties to the contract have the right to withdraw
from the contract. Claims for damages are excluded in those cases listed in Clause
7.1
8. Packaging
We accept returned transport packaging at our place of business during our usual opening
hours.The customer bears the disposal expenses. The packaging must be returned clean, free of
foreign substances, and sorted according to type.
9. Retention of
Title9.1
We retain title on the delivered goods until all payments due under the business relationship with
the customer have been received and all checks and bills of exchange have been irrevocably
credited to our account. Should an open account relationship with the customer exist, retention of
title applies to the acknowledged balance.
9.2
The customer must maintain the conditional goods and handle them with care. In particular,
hemust insure them at his own expense against loss and damage for their replacement value.
Hemust show us the insurance policy as well as proof of payment of the insurance premiums
on request. He cedes any claims arising from the insurance policies to us in advance.
9.3
Treatment and processing of the conditional goods are carried out by the customer on our behalf
without creating any liability on our part. Should the conditional goods be mixed with or
incorporated into other goods, we acquire title to the new goods in the proportion of the invoiced
value of the conditional goods to the invoiced value of the other materials.
9.4
The customer has the right to sell the conditional goods in the course of normal business
transactions. However, the customer assigns us in full and in advance all claims against a
customer or against a third party that result from further sales or use on a customer's behalf.
9.5
As long as he meets his payment obligations to us from these proceeds, the customer has the
right to himself collect the claims assigned to us.
9.6
Should the customer no longer meet his payment obligations to us, we may revoke our
permission to further sell or use the conditional goods and demand that the customer informs us
about his assignment of claims and the corresponding debtors, give us all information
necessaryfor the collection of our claims, surrender the documents belonging to these claims,
and inform his debtors about the assignment of claims. Repossession of the conditional goods
does not
9.7
The customer must notify us without delay of third-party actions against the conditional goods. To
the extent that the customer cannot recover the expenses resulting from such an action from a
third party, he must bear them himself.
9.8
Should the value of collateral exceed our claims by more than 10%, and should the customer so
request, we will release collateral of our choice to this extent.
Defects10.1
Defects must be reported to us in writing without delay, in any case within one week after receipt
of the goods; hidden defects, within 3 days after discovery. Should these deadlines be exceeded,
all claims and rights arising from liability for defects expire. Unless we have violated our
responsibilities grossly, or deliberately or fraudulently concealed the defect, the period of
limitations is 12 months after delivery.
10.2
Violation of third party intellectual property rights is a defect only when these rights are valid
inthe Federal Republic of Germany.
10.3
Should there be legitimate complaints, we have the choice between delivering replacement
goods or repairing the goods. Should a replacement delivery also be defective or the repair be
unsuccessful, or refused or delayed without good reason, the customer may, after a reasonable
additional extension period has expired without remedy, demand a reduction in price or, by not
insignificant defects, withdraw from the contract and demand damages instead of performance
according to Clause 1.1. We assume no supplementary performance expenses arising because
the purchased item has been moved to a location other than the customer's place of business.
10.4
To the extent that the defect has been caused by a significant non-EIMA product, we have the
right to restrict our liability at first to the surrender of our claims for and rights of liability for defects
against the supplier of the non-EIMA product. Should the settlement from the surrendered claims
or rights come to nothing or for other reasons not be able to be enforced, the customer is entitled
to the rights in Clause 10.3.
11. General
Liability11.1
11.2
With the exception of claims arising from liability for material defects, claims arising from product
liability law, and claims due to death, bodily injury, or damages to health, claims for damages
expire one year after the customer learns about the damage and our liability for damages or,
should, without gross negligence, have learned about the damage or liability.
12. Place of Fulfilment, Place of Jurisdiction, Choice of
Law12.1
The place of fulfilment for all services resulting from the delivery contracts is our place of
business.
12.2
The place of jurisdiction for all disputes arising from the delivery contract is our place of business.
However, we also have the right to sue at the customer's place of business.
12.3
German law applies.