MJA Material Wise Statement

You might also like

You are on page 1of 7

Scaffold M

RECEIVED AMOUNT
S.NO DESCRIPTION QTY RATE
DATE PER MONTH

06.04.2021 1 Cuplock ledger/horizontal pipe (1.5m) 100 22.50 2250.00


TOTAL 2250.00

1 Cuplock Vertical Pipes (6 cups) -3m 108 45.00 4860.00


2 Plain Scaffold Pipe -3m 90 45.00 4050.00
3 Plain Scaffold Pipe -2m 60 30.00 1800.00
10.04.2021 4 Walkway Planks - 2m 10 450.00 4500.00
5 Swivel Coupler/Round Clamp 125 13.00 1625.00
6 Beam Clamp 110 18.00 1980.00
7 Double Coupler ( Fix clamp ) 150 13.00 1950.00
TOTAL 20765.00

15.04.2021 1 Cuplock ledger/horizontal pipe (1.45m) 324 22.50 7290.00

TOTAL 7290.00

1 Cuplock Vertical Pipes (6 cups) -3m 96 45.00 4320.00


2 Cuplock ledger/horizontal pipe (1.5m) 288 22.50 6480.00
3 Plain Scaffold Pipe -3m 75 45.00 3375.00
4 Plain Scaffold Pipe -2m 50 30.00 1500.00
04.05.2021 5 Swivel Coupler/Round Clamp 100 13.50 1350.00
6 Beam Clamp 100 0 0.00
7 Double Coupler ( Fix clamp ) 125 13.50 1687.50
8 Base Jack 10 15.00 150.00
9 Joint pin 96 6.00 576.00
TOTAL 19438.50
Scaffold Material Sheet
IISM BILLING CYCLE
CONTRACTOR
1st Bill 2nd Bill 3rd Bill
COLOUR INDIA 06.04.2021 TO 30.04.2021 01.05.2021 TO 31.05.2021

COLOUR INDIA
COLOUR INDIA
COLOUR INDIA 10.04.2021 TO 30.04.2021
RA Bill - 001 01.05.2021 TO 31.05.2021
COLOUR INDIA
Revised on 11.06.2021 RA Bill - 003
COLOUR INDIA (Walkway Planks removed)
COLOUR INDIA
COLOUR INDIA

10.04.2021 TO 30.04.2021
RA Bill - 001 01.05.2021 TO 31.05.2021
Wintuss
Revised on 11.06.2021 RA Bill - 003
(Walkway Planks removed)

Wintuss
Wintuss
Wintuss
Wintuss 04.05.2021 TO 31.05.2021
26.04.2021 TO 30.04.2021
Wintuss RA Bill - 004
RA Bill - 002
Wintuss Revised on 11.06.2021
Wintuss
Wintuss
Wintuss
REMARKS
4th Bill

MJA 1st Work Order

MJA 1st Work Order

MJA 2nd Work Order


COLOUR INDIA to MJA
TOTAL
RATE RENT
S.NO DESCRIPTION START DATE END DATE QTY NUMBER OF
PER DAY AMOUNT
DAYS
1 Cuplock Vertical Pipes (6 cups) -3m 4/10/2021 9/24/2021 108 1.67 168 30240
2 Plain Scaffold Pipe -3m 4/10/2021 8/19/2021 90 1.67 132 19800
3 Plain Scaffold Pipe -2m - Total 60
3.1 Plain Scaffold Pipe -2m - 17 4/10/2021 8/19/2021 17 1.33 132 2992
3.2 Plain Scaffold Pipe -2m - 43 4/10/2021 9/24/2021 43 1.33 168 9632
4 Swivel Coupler/Round Clamp 4/10/2021 8/19/2021 125 0.67 132 11000
5 Beam Clamp - Total 110
5.1 Beam Clamp - 60 4/10/2021 8/19/2021 60 1 132 7920
5.2 Beam Clamp - 50 4/10/2021 11/9/2021 50 1 214 10700
6 Double Coupler ( Fix clamp ) 4/10/2021 9/24/2021 150 0.67 168 16800
TOTAL 109084
COLOUR INDIA to MJA

TOTAL
RATE RENT
S.NO DESCRIPTION START DATE END DATE QTY NUMBER OF
PER DAY AMOUNT
DAYS
1 Cuplock Vertical Pipes (6 cups) -3m 4/10/2021 9/24/2021 108 1.67 168 30240
2 Plain Scaffold Pipe -3m 4/10/2021 8/19/2021 90 1.67 132 19800
3 Plain Scaffold Pipe -2m - Total 60 60
3.1 Plain Scaffold Pipe -2m - 17 4/10/2021 8/19/2021 17 1.33 132 2992
3.2 Plain Scaffold Pipe -2m - 43 4/10/2021 9/24/2021 43 1.33 168 9632
4 Swivel Coupler/Round Clamp 4/10/2021 8/19/2021 125 0.67 132 11000
5 Beam Clamp - Total 110 110
5.1 Beam Clamp - 60 4/10/2021 8/19/2021 60 1 132 7920
5.2 Beam Clamp - 50 4/10/2021 11/9/2021 50 1 214 10700
6 Double Coupler ( Fix clamp ) 4/10/2021 9/24/2021 150 0.67 168 16800
TOTAL 109084
S.NO BILL NO. LOCATION
1 RA - 01 CDU / HPCL
2
3 RA - 02 CDU / HPCL
4 RA - 03 VDU / HPCL
5 RA - 04 CDU / HPCL
6 RA - 05 VDU / HPCL
7 RA - 06 CDU / HPCL
8 RA - 07 VDU / HPCL
9 RA - 08 CDU / HPCL
10 RA - 09 VDU / HPCL
11 RA - 10 CDU / HPCL
12 RA - 11 VDU / HPCL
13 RA - 12 CDU / HPCL
14 RA - 13 VDU / HPCL
16 Final Bill VDU / HPCL
TIME PERIOD INVOICE AMT.
25457.00
5571.00
37579.00
31200.00
36367.00
33429.00
37579.00
34543.00
33105.00
34543.00
22792.00
32721.00
13680.00
30885.00
33618.00
Total 443069