Alcantarilla
Alcantarilla
Progresiva 0+ 10
L cuneta
A1 26,35m
A2
3,65m
Alcantarilla
1
Q= ∗A∗R 2/ 3
H ∗S
1/ 2
n
( )
3/ 8
Q∗n
D=
0 , 1558∗S1 /2
n= 0.013
S= 1.00 %
En zanja:
B=1 , 5∗D+0 , 3
Tubería de Hormigon simple Clase 1
W =C∗γ∗B2
C= 2.44
H/B = 3 (Tabla)
H adm = 2.588 m
ALCANTARILLA Nº 2
Progresiva 0+ 210
L cuneta
A1 26,35m
A2
3,65m
Alcantarilla
1
Q= ∗A∗R 2/ 3
H ∗S
1/ 2
n
( )
3/ 8
Q∗n
D=
0 , 1558∗S1 /2
n= 0.013
S= 1.00 %
En zanja:
B=1 , 5∗D+0 , 3
Tubería de Hormigon simple Clase 1
W =C∗γ∗B2
W =C∗γ∗B2
C= 2.94
H/B = 4.35 (Tabla)
H adm = 3.262 m
ALCANTARILLA Nº 3
Progresiva 0+ 410
A1 26,35m
cuneta
A2
3,65m
Alcantarilla
1
Q= ∗A∗R 2/ 3
H ∗S
1/ 2
n
( )
3/ 8
Q∗n
D=
0 , 1558∗S1 /2
n= 0.013
S= 1.00 %
En zanja:
B=1 , 5∗D+0 , 3
Tubería de Hormigon simple Clase 1
2
W =C∗γ∗B
C= 2.94
H/B = 4.35 (Tabla)
H adm = 3.262 m
ALCANTARILLA Nº 4
Progresiva 0+ 560
A1 26,35m
cuneta
A2
3,65m
Alcantarilla
1
Q= ∗A∗R 2/ 3
H ∗S
1/ 2
n
( )
3/ 8
Q∗n
D=
0 , 1558∗S1 /2
n= 0.013
S= 1.00 %
En zanja:
B=1 , 5∗D+0 , 3
Tubería de Hormigon simple Clase 1
Wadm = 2650 Kg/m
γ= 1600 Kg/m3
B= 0.750 m
W =C∗γ∗B2
C= 2.94
H/B = 4.35 (Tabla)
H adm = 3.262 m
ALCANTARILLA Nº 5
Progresiva 0+ 734.53
L1 L2
A1 a1
cuneta 26.35 m
A2 a2
3.65 m
Alcantarilla
ESCORRENTIA:
Prog. Inicio 0+ 675
Prog. Final 0+ 815
ac = 3.65 m
der. Via = 30 m
C2(asfalto)= 0.75
C1(terreno)= 0.4
i= 10.8 cm/hr
Qd=27 , 52∗Cp∗i∗A
A= 0.420 Has
Qd1= 55.248 lt/s
1
Q * A * R 2 /3
H * S 1/ 2
3/8
Q*n
D 1/ 2
0 ,1558 * S
n= 0.013
S= 1.00 %
W C * * B2
C= 7.94
H/B = 4.9 (Tabla)
H adm = 2.573 m
ALCANTARILLA Nº6
Progresiva 1+ 55
A1 26,35m
A1
cuneta
A2
3,65m
Alcantarilla
1
Q * A * R 2 /3
H * S 1/ 2
3/8
Q*n
D 1/ 2
0 ,1558 * S
n= 0.013
S= 1.00 %
En zanja:
B=1 , 5∗D+0 , 3
Tubería de Hormigon simple Clase 1
W C * * B2
C= 2.94
H/B = 4.35 (Tabla)
H adm = 3.262 m
ALCANTARILLA Nº 7
Progresiva 1+ 177.908
L cuneta
A1 26,35m
A2
3,65m
Alcantarilla
ESCORRENTIA:
Prog. Inicio 1+ 55
Prog. Final 1+ 230
ac = 3.65 m
der. Via = 30 m
C2(asfalto)= 0.75
C1(terreno)= 0.4
i= 10.8 cm/hr
Qd=27 , 52∗Cp∗i∗A
A= 0.525 Has
Qd1= 69.060 lt/s
1
Q * A * R 2 /3
H * S 1/ 2
3/8
Q*n
D 1/ 2
0 ,1558 * S
n= 0.013
S= 1.00 %
W C * * B2
C= 9.88
H/B = 6 (Tabla)
H adm = 2.700 m
ALCANTARILLA Nº 8
Progresiva 1+ 790
A1 26,35m
cuneta
A2
3,65m
Alcantarilla
TRAMOS DE APORTE: Nº 12
3/8
Q*n
D 1/ 2
0 ,1558 * S
n= 0.013
S= 1.00 %
En zanja:
B=1 , 5∗D+0 , 3
Tubería de Hormigon simple Clase 1
W C * * B2
C= 2.44
H/B = 3 (Tabla)
H adm = 2.588 m
ALCANTARILLA Nº 9
Progresiva 1+ 975.16
A1 26,35m
cuneta
A2
3,65m
Alcantarilla
TRAMOS DE APORTE: Nº 13
Qd total= #REF! m3/seg
1
Q * A * R 2 /3
H * S 1/ 2
3/8
Q*n
D 1/ 2
0 ,1558 * S
n= 0.013
S= 1.00 %
En zanja:
B=1 , 5∗D+0 , 3
Tubería de Hormigon simple Clase 1
W C * * B2
C= 2.44
H/B = 3 (Tabla)
H adm = 2.588 m