PROJECT
METAL - HA
ZED Towers PROJECT - PHASE 02
SHEIKH ZAYED CITY - EGYPT
Employer
CONSTRUCTION SUPERVISION
ZED Towers PROJECT - PHASE 02
SHEIKH ZAYED CITY - EGYPT
METHOD STATEMENT
FOR METAL MESH WORKS Date : 25/1/2023 Page : 2 of 11
Method Statement
Metal Mesh Works
SCOPE:
The aim of this method statement is to provide and maintain an effective quality control to execute the work in
compliance to standard and good practices at all This General method statement describes the methodology to be
employed in the safe (Pouring Precast Staircase Works).
This method statement covers all sequence of the work to be carried out for (Pouring of Precast
Staircase Works).
SPECIFICATION REFERENCES:
- Egyptian code of practice for design and construction reinforced concrete ECP 203-
2017.
- Egyptian code of practice for design and construction steel ECP ASD.
- Project specification volume III, division 3, section 033000
- Contract /IFC drawings.
- Manufacture’s recommendation according to approved Material Submittals.
- Project HSE Plan and Procedures.
RESPONSIBILITIES
The direct personnel responsible for the works are Section Engineers; the section engineer is responsible
for compliance by his subordinates with the contents of this method statement, for ensuring that all
parties involved in supervision of the works are in receipt of all relevant information.
The section engineer will ensure the required degree of safety to personnel and protection to property
is maintained at all times.
Surveyor: -
o Make exact measurements and determine property boundaries. Provide data relevant to the shape, contour, gravitation,
location, elevation, or dimension of land or land features on or near the earth's surface for engineering, construction, and
other purposes.
MATERIALS STORAGE:
In the event that any materials for use in this chapter deteriorate and become unusable due to
inadequate and poor storage they shall be removed from site as instructed by the Engineer.
ZED Towers PROJECT - PHASE 02
SHEIKH ZAYED CITY - EGYPT
METHOD STATEMENT
FOR METAL MESH WORKS Date : 25/1/2023 Page : 5 of 11
Products:
1- Metal mesh according to approved material submittal.
2- Metal mesh according to approved shop drawing.
3- Painting material according to approved material submittal.
4- Approved Release agent according to approved material submittal.
5- Nails.
EQUIPMENT
Depending on the size of the area, site conditions and accessibility, some / all of
the following equipment shall be used as applicable for:
- Hand Tools
- Air Compressor
- Metal work cutting power machine
- Electrical welding machine
- Mobile crane
Electric Lifting Hoist
MANPOWER
Manpower allocated to this job will be as follows:
• Site Engineers
• Superintendent, General Foreman, Supervisor and Charge
Hands.
• HSE Officer
• Labors
• QC Inspectors
Safety:
All safety and health regulations shall be strictly followed and any case disregarding the safety
procedures to be immediately reported to safety office and construction manager.
Risk assessment will be submitted separately.
MANPOWER
Manpower allocated to this job will be as follows:
• Site Engineers
• Superintendent, General Foreman, Supervisor and Charge
Hands.
• HSE Officer
• Operators, drivers and Riggers
• Labors
• Flagman
• QC Inspectors
ZED Towers PROJECT - PHASE 02
SHEIKH ZAYED CITY - EGYPT
METHOD STATEMENT
FOR METAL MESH WORKS Date : 25/1/2023 Page : 7 of 11
Procedure for installing the metal mesh: -
Installing the Electric Lifting Hoist and Lifting the metal mesh to the required level.
ZED Towers PROJECT - PHASE 02
SHEIKH ZAYED CITY - EGYPT
METHOD STATEMENT
FOR METAL MESH WORKS Date : 25/1/2023 Page : 10 of 11
Installing the metal mesh using AKMON screws and installing door handles.