AHSP
AHSP
Sat.
NO NAMA BARANG HARGA BAHAN
230 Lampu TL 2 x 18 Watt+ EBC Philips (Armatur Platinium RMI setara SAKA) Bh 750,000.00
231 Lampu TL 2 x 36 Watt+ EBC Philips (Armatur Platinium RMI setara SAKA) Bh 1,100,000.00
232 Lampu TL 2 x 18 Watt+ EBC Philips (Armatur V Shape setara SAKA) Bh 385,000.00
233 Lampu TL 2 x 36 Watt+ EBC Philips (Armatur V Shape setara SAKA) Bh 490,000.00
234 Lampu Down Light Recessed Halogen 35 Watt, Philips (Armatur setara SAKA ) dia 075 mm Bh 195,000.00
235 Lampu Down Light PLC 10 watt, Philips (Armatur 2 Kaki setara SAKA) dia 100 mm Bh 175,000.00
NO NAMA BAHAN/BARANG SATUAN HARGA BAHAN
236 Lampu Down Light PLC 18 watt, Philips (Armatur 2 Kaki setara SAKA) dia 125 mm Bh 185,000.00
237 Lampu Down Light PLC 26 watt, Philips (Armatur 2 Kaki setara SAKA) dia 150 mm Bh 190,000.00
238 Celling Exhaust Fan Type FV-11VQ5 setara Panasonic Unit 600,000.00
239 Ceiling Fan 4 Metal Blade 140 cm (56") setara Panasonic Unit 425,000.00
240 Sakral Tunggal setara Clipsal Bh 25,000.00
241 Saklar Double setara Clipsal Bh 30,000.00
242 Saklar Tukar/Hotel setara Clipsal Bh 50,000.00
243 Stop Kontak setara Clipsal Bh 30,000.00
244 Stop Kontak AC setara Clipsal Bh 50,000.00
245 AC 3/4 PK Inverter, Wall Mounted setara Daikin Unit 5,400,000.00
246 AC 1 PK Inverter, Wall Mounted setara Daikin Unit 4,000,000.00
247 AC 1,5 PK Inverter, Kapasitas 11,900 BTUH Wall Mounted setara Daikin 5,700,000.00
248 AC 2 PK Inverter, Wall Mounted setara Daikin Unit 7,800,000.00
249 AC 2,5 PK Inverter, Wall Mounted setara Daikin Unit 15,400,000.00
250 AC 3 PK Celling Casssete setara Daikin Unit 19,200,000.00
251 Pipa Refrigerant 3/4 PK M' 70,000.00
252 Pipa Refrigerant 1 PK M' 70,000.00
253 Pipa Refrigerant 2 PK M' 85,000.00
254 Pipa Refrigerant 2,5 PK M' 110,000.00
255 Pipa Refrigerant 3 PK M' 110,000.00
256 Pipa Drain 3/4 PK, PVC dia 20 mm + Insulation M' 12,500.00
257 Pipa Drain 1 PK, PVC dia 20 mm + Insulation M' 12,500.00
258 Pipa Drain 2 PK, PVC dia 20 mm + Insulation M' 18,000.00
259 Pipa Drain 2,5 PK, PVC dia 20 mm + Insulation M' 18,000.00
260 Pipa Drain 3 PK, PVC dia 20 mm + Insulation M' 25,000.00
261 LCD Proyektor XGA (1024x768) setara BENQ bh 5,200,000.00
262 LCD Proyektor XGA (1024x768) setara ACER bh 5,050,000.00
263 LCD Proyektor XGA (1024x768) setara SONY bh 9,275,000.00
264 Screen Motorize dia 70" bh 3,075,000.00
265 Braket bh 205,000.00
266 Pipa PVC TIPE AW Ø ½˝ ( Ø 15 mm ) M' 4,100.00
267 Pipa PVC TIPE AW Ø ¾˝ ( Ø 20 mm ) M' 6,200.00
268 Pipa PVC TIPE AW Ø 1˝ ( Ø 25 mm ) M' 8,500.00
269 Pipa PVC TIPE AW Ø 1,25˝ ( Ø 32 mm ) M' 12,100.00
270 Pipa PVC TIPE AW Ø 1.5˝ ( Ø 40 mm ) M' 14,000.00
271 Pipa PVC TIPE AW Ø 2˝ ( Ø 50 mm ) M' 18,700.00
272 Pipa PVC TIPE AW Ø 3˝ ( Ø 80 mm ) M' 38,500.00
273 Pipa PVC TIPE AW Ø 4˝ ( Ø 100 mm ) M' 63,400.00
274 Pipa PVC TIPE AW Ø 5˝ ( Ø 125 mm ) M' 105,500.00
NO NAMA BAHAN/BARANG SATUAN HARGA BAHAN
310 Single Lever shower Mixer Type TX 443 SE setara TOTO Unit 975,000.00
311 Floor Paper Holder Type YH 116 setara TOTO Unit 595,000.00
312 Bak mandi fibre glass 70x70x66 cm Unit 325,000.00
313 Kran Air setara Sanei Bh 131,000.00
314 Kran Air setara Honda Bh 38,000.00
315 Seal Tape Bh 2,500.00
316 Tangki Stainless Steel Kapasitas 2000 liter Bh 3,200,000.00
317 Paving Block 10 x 20 Tbl. 6 Cm m2 67,500.00
318 Paving Block 10 x 20 Tbl. 6 Cm m2 67,500.00
319 Paving Block 10 x 20 Tbl. 8 Cm m2 77,800.00
320 Paving Block 10 x 20 Tbl. 8 Cm m2 77,800.00
321 Paving Block 10 x 20 Tbl. 8 Cm m2 77,800.00
322 Paving Block 10 x 20 Tbl. 10 Cm m2 87,900.00
323 Paving Block 20 x 20 Tbl. 6 Cm m2 67,500.00
324 Paving Block 20 x 20 Tbl. 6 Cm m2 67,500.00
325 Paving Block 20 x 20 Tbl. 8 Cm m2 77,800.00
326 Paving Block 20 x 20 Tbl. 8 Cm m2 77,800.00
327 Paving Block 20 x 20 Tbl. 8 Cm m2 77,800.00
328 Paving Block 20 x 20 Tbl. 10 Cm m2 87,900.00
329 Paving Block 20 x 20 Tbl. 10 Cm m2 87,900.00
330 Paving Block 20 x 20 Tbl. 10 Cm m2 87,900.00
331 Paving Block Tiga Berlian Tbl. 6 Cm m2 72,000.00
332 Grass Blok Tbl. 10 cm m2 87,900.00
333 Koral sikat zak 55,000.00
334 Kanstein Bulat (P:50,T:30,La:10,Lb:16 cm K225) m' 67,800.00
335 1 M1 KANSTEIN JUMBO (P :50, L:15, T: 30 CM ,K225) m' 67,800.00
336 1 M1 KANSTEIN SEGI LIMA JUMBO (P: 50, L :15, T: 40 CM K. 225) m' 78,750.00
337 Buis beton 1/2 Diameter 30 cm m' 84,750.00
338 Kaca Tempered 12 mm m2 659,000.00
339 Kaca Tempered 10 mm m2 409,500.00
340 Kaca Bening 10 mm m2 209,000.00
341 Kaca Bening 8 mm m2 149,000.00
342 Kaca Bening 5 mm m2 97,000.00
343 Kaca Cermin 5 mm m2 135,000.00
344 Kaca Nako Bh 12,500.00
345 Kaca Nako teralis bening m2 765,000.00
346 Kaca Bevel 5mm Bh 225,000.00
347 Kaca Es 5mm Bh 165,000.00
HARGA SATUAN UPAH 2017
9 1 M3 URUGAN KEMBALI
Mengurug Kembali 1 m3 galian dihitung dari 1/3 kali dari indeks pekerjaan galian
19,994.26
11 1 M3 URUGAN PASIR
1.2000 m3 Pasir Urug 135,000.00 162,000.00
0.3000 oh Pekerja 76,643.70 22,993.11
0.0100 oh Mandor 100,000.00 1,000.00
Total : 23,993.11 162,000.00 185,993.11
16 1 M2 PASANGAN DINDING BATA RINGAN TEBAL 7,5 CM DGN MORTAR SIAP PAKAI
8.4000 m3 Bata Ringan tebal 7,5 cm 8,500.00 71,400.00
0.4730 kg Mortar siap pakai -
0.6700 oh pekerja 76,643.70 51,351.28
1.3000 oh Tukang Batu -
0.1300 oh Kepala Tukang Batu -
0.0030 oh Mandor -
Total : 51,351.28 71,400.00 122,751.28
16a 1 M2 PASANGAN DINDING BATA RINGAN TEBAL 12.5 CM DGN MORTAR SIAP PAKAI
0.1250 m3 Bata Ringan tebal 10 cm 800,000.00 100,000.00
0.0630 sak Mortar siap pakai 2,125.00 133.88
0.1300 oh pekerja 76,643.70 9,963.68
0.1300 oh Tukang Batu 80,000.00 10,400.00
0.1300 oh Kepala Tukang Batu 85,000.00 11,050.00
0.0030 oh Mandor 100,000.00 300.00
Total : 31,713.68 100,133.88 131,847.56
14 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS
4.3200 kg Semen Portland 1,120.00 4,838.40
0.0060 m3 Pasir Pasang 165,000.00 990.00
0.3000 oh Pekerja 76,643.70 22,993.11
0.1000 oh Tukang Batu 80,000.00 8,000.00
0.0100 oh Kepala Tukang 85,000.00 850.00
0.0150 oh Mandor 100,000.00 1,500.00
Total : 33,343.11 5,828.40 39,171.51
18 1 M2 PEKERJAAN ACIAN
3.2500 zak Semen Portland 50 Kg 1,120.00 3,640.00
0.2000 oh Pekerja 76,643.70 15,328.74
0.1000 oh Tukang Labur/Cat 80,000.00 8,000.00
0.0100 oh Kepala Tukang 85,000.00 850.00
0.0100 oh Mandor 100,000.00 1,000.00
Total : 25,178.74 3,640.00 28,818.74
5c MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL + KULIT JERUK KAYU KELAS I/II
0.0400 m3 Papan Kayu Kamper 7,000,000.00 280,000.00
0.5000 Kg Lem Kayu 12,000.00 6,000.00
1.0000 lbr Lapis Kulit jeruk -
1.0000 oh Pekerja 76,643.70 76,643.70
3.0000 oh Tukang Kayu 80,000.00 240,000.00
0.3000 oh Kepala Tukang 85,000.00 25,500.00
0.0500 oh Mandor 100,000.00 5,000.00
Total : 347,143.70 286,000.00 633,143.70
22a MEMASANG 1 M' LISPLANK UKURAN (3 X 15) CM, KAYU KELAS I/II
0.0055 m3 Papan Kayu Kamper 7,000,000.00 38,500.00
0.0500 Kg Paku 5 Cm dan 7 Cm 14,000.00 700.00
0.1000 oh Pekerja 76,643.70 7,664.37
0.2000 oh Tukang Kayu 80,000.00 16,000.00
0.0200 oh Kepala Tukang 85,000.00 1,700.00
0.0050 oh Mandor 100,000.00 500.00
Total : 25,864.37 39,200.00 65,064.37
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
22b MEMASANG 1 M' LISPLANK UKURAN (3 X 10) CM, KAYU KELAS I/II
0.0037 m3 Papan Kayu Kamper 7,000,000.00 25,666.67
0.0500 Kg Paku 5 Cm dan 7 Cm 14,000.00 700.00
0.1000 oh Pekerja 76,643.70 7,664.37
0.2000 oh Tukang Kayu 80,000.00 16,000.00
0.0200 oh Kepala Tukang 85,000.00 1,700.00
0.0050 oh Mandor 100,000.00 500.00
Total : 25,864.37 26,366.67 52,231.04
22c MEMASANG 1 M' LISPLANK UKURAN (3 X 10) CM, Conwood
1.1000 m Conwood Eave 2 in 1 53,333.33 58,666.67
0.1000 Kg Paku 5 Cm dan 7 Cm 14,000.00 1,400.00
0.1000 oh Pekerja 76,643.70 7,664.37
0.2000 oh Tukang Kayu 80,000.00 16,000.00
0.0200 oh Kepala Tukang 85,000.00 1,700.00
0.0050 oh Mandor 100,000.00 500.00
Total : 25,864.37 60,066.67 85,931.04
3 MEMBUAT 1 M³ BETON MUTU f'C= 12,2 Mpa (K150), Slump (12 ± 2)cm, w/c = 0,72
299.0000 kg Semen Portland 1,120.00 334,880.00
799.0000 kg Pasir Beton 110.71 88,460.71
1,017.0000 kg Koral Beton 181.48 184,566.67
215.0000 lt Air 25.00 5,375.00
1.6500 oh Pekerja 76,643.70 126,462.10
0.2750 oh Tukang Batu 80,000.00 22,000.00
0.0280 oh Kepala Tukang 85,000.00 2,380.00
0.0830 oh Mandor 100,000.00 8,300.00
Total : 159,142.10 613,282.38 772,424.49
4 MEMBUAT 1 M³ BETON MUTU f'C= 14,5 Mpa (K175), Slump (12 ± 2)cm, w/c = 0,66
326.0000 kg Semen Portland 1,120.00 365,120.00
760.0000 kg Pasir Beton 110.71 84,142.86
1,029.0000 kg Koral Beton 181.48 186,744.44
215.0000 lt Air 25.00 5,375.00
1.6500 oh Pekerja 76,643.70 126,462.10
0.2750 oh Tukang Batu 80,000.00 22,000.00
0.0280 oh Kepala Tukang 85,000.00 2,380.00
0.0830 oh Mandor 100,000.00 8,300.00
Total : 159,142.10 641,382.30 800,524.41
5 MEMBUAT 1 M³ BETON MUTU f'C= 16,9 Mpa (K200), Slump (12 ± 2)cm, w/c = 0,61
352.0000 kg Semen Portland 1,120.00 394,240.00
731.0000 kg Pasir Beton 110.71 80,932.14
1,031.0000 kg Koral Beton 181.48 187,107.41
215.0000 lt Air -
1.6500 oh Pekerja 76,643.70 126,462.10
0.2750 oh Tukang Batu 80,000.00 22,000.00
0.0280 oh Kepala Tukang 85,000.00 2,380.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.0830 oh Mandor 100,000.00 8,300.00
Total : 159,142.10 662,279.55 821,421.66
6 MEMBUAT 1 M³ BETON MUTU f'C= 19,3 Mpa (K225), Slump (12 ± 2)cm, w/c = 0,58
371.0000 kg Semen Portland 1,120.00 415,520.00
698.0000 kg Pasir Beton 110.71 77,278.57
1,047.0000 kg Koral Beton 181.48 190,011.11
215.0000 lt Air -
1.6500 oh Pekerja 76,643.70 126,462.10
0.2750 oh Tukang Batu 80,000.00 22,000.00
0.0280 oh Kepala Tukang 85,000.00 2,380.00
0.0830 oh Mandor 100,000.00 8,300.00
Total : 159,142.10 682,809.68 841,951.79
7 MEMBUAT 1 M³ BETON MUTU f'C= 21,7 Mpa (K250), Slump (12 ± 2)cm, w/c =0,56
384.0000 kg Semen Portland 1,120.00 430,080.00
692.0000 kg Pasir Beton 110.71 76,614.29
1,039.0000 kg Koral Beton 181.48 188,559.26
215.0000 lt Air 25.00 5,375.00
1.6500 oh Pekerja 76,643.70 126,462.10
0.2750 oh Tukang Batu 80,000.00 22,000.00
0.0280 oh Kepala Tukang 85,000.00 2,380.00
0.0830 oh Mandor 100,000.00 8,300.00
Total : 159,142.10 700,628.54 859,770.65
8 MEMBUAT 1 M³ BETON MUTU f'C= 24,0 Mpa (K275), Slump (12 ± 2)cm, w/c =0,53
406.0000 kg Semen Portland 1,120.00 454,720.00
684.0000 kg Pasir Beton 110.71 75,728.57
1,026.0000 kg Koral Beton 181.48 186,200.00
215.0000 lt Air 25.00 5,375.00
1.6500 oh Pekerja 76,643.70 126,462.10
0.2750 oh Tukang Batu 80,000.00 22,000.00
0.0280 oh Kepala Tukang 85,000.00 2,380.00
0.0830 oh Mandor 100,000.00 8,300.00
Total : 159,142.10 722,023.57 881,165.68
9 MEMBUAT 1 M³ BETON MUTU f'C= 26,4 Mpa (K300), Slump (12 ± 2)cm, w/c =0,52
413.0000 kg Semen Portland 1,120.00 462,560.00
681.0000 kg Pasir Beton 110.71 75,396.43
1,021.0000 kg Koral Beton 181.48 185,292.59
215.0000 lt Air 25.00 5,375.00
1.6500 oh Pekerja 76,643.70 126,462.10
0.2750 oh Tukang Batu 80,000.00 22,000.00
0.0280 oh Kepala Tukang 85,000.00 2,380.00
0.0830 oh Mandor 100,000.00 8,300.00
Total : 159,142.10 728,624.02 887,766.13
10 MEMBUAT 1 M³ BETON MUTU f'C= 28,8 Mpa (K325), Slump (12 ± 2)cm, w/c =0,49
439.0000 kg Semen Portland 1,120.00 491,680.00
670.0000 kg Pasir Beton 110.71 74,178.57
1,006.0000 kg Koral Beton 181.48 182,570.37
215.0000 lt Air -
1.6500 oh Pekerja 76,643.70 126,462.10
0.2750 oh Tukang Batu 80,000.00 22,000.00
0.0280 oh Kepala Tukang 85,000.00 2,380.00
0.0830 oh Mandor 100,000.00 8,300.00
Total : 159,142.10 748,428.94 907,571.05
11 MEMBUAT 1 M³ BETON MUTU f'C= 31,2 Mpa (K350), Slump (12 ± 2)cm, w/c =0,48
448.0000 kg Semen Portland 1,120.00 501,760.00
667.0000 kg Pasir Beton 110.71 73,846.43
1,000.0000 kg Koral Beton 181.48 181,481.48
215.0000 lt Air -
1.6500 oh Pekerja 76,643.70 126,462.10
0.2750 oh Tukang Batu 80,000.00 22,000.00
0.0280 oh Kepala Tukang 85,000.00 2,380.00
0.0830 oh Mandor 100,000.00 8,300.00
Total : 159,142.10 757,087.91 916,230.02
13b Pembesian 100 kg jaring kawat (wiremesh) untuk pelat atau dinding
102.0000 Kg Wire mesh 13,500.00 1,377,000.00
0.5000 Kg Kawat ikat 13,500.00 6,750.00
0.2500 Oh. Pekerja 76,643.70 19,160.93
0.2500 Oh. Tukang besi 80,000.00 20,000.00
0.0250 Oh. Kepala Tukang 85,000.00 2,125.00
0.0250 Oh. Mandor 100,000.00 2,500.00
Total 43,785.93 1,383,750.00 1,427,535.93
untuk 1 kg 437.86 13,837.50 14,275.36
8 1 M2 PEKERJAAN WATERPROFING
1.0000 Kg Masterseal 440 65,000.00 65,000.00
0.0400 oh Pekerja 76,643.70 3,065.75
0.0400 oh Tukang cat 80,000.00 3,200.00
0.0040 oh Mandor 100,000.00 400.00
222,815,746.37
637,632.00
1,020,211.20
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
5,687,677.44
3,946,942.08
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
25 1 M2 PENGECATAN KANSTEIN
0.2840 kg Cat 55,000.00 15,620.00
0.0710 kg Thiner 24,500.00 1,739.50
0.0300 oh Tukang Cat 80,000.00 2,400.00
0.0030 oh Kep. Tukang 85,000.00 255.00
0.1500 oh Pekerja 76,643.70 11,496.55
0.0150 oh Mandor 100,000.00 1,500.00
Total : 15,651.55 17,359.50 33,011.05
26 1 M2 RUMPUT MUTIARA
1.0000 m2 Rumput Mutiara -
0.0300 m3 Tanah Subur 70,000.00 2,100.00
0.0030 oh Kep. Tukang 85,000.00 255.00
0.1500 oh Pekerja 76,643.70 11,496.55
0.0150 oh Mandor 100,000.00 1,500.00
Total : 13,251.55 2,100.00 15,351.55
27 1 M1 TANAMAN CROCOT
11.0000 m1 Tanaman Crocot -
0.0300 m3 Tanah Subur 70,000.00 2,100.00
0.0030 oh Kep. Tukang 85,000.00 255.00
0.1500 oh Pekerja 76,643.70 11,496.55
0.0150 oh Mandor 100,000.00 1,500.00
Total : 13,251.55 2,100.00 15,351.55
28 1 BH TANAMAN SOKA
1.0000 bh Tanaman Soka -
0.0300 m3 Tanah Subur 70,000.00 2,100.00
0.0030 oh Kep. Tukang 85,000.00 255.00
0.1500 oh Pekerja 76,643.70 11,496.55
0.0150 oh Mandor 100,000.00 1,500.00
Total : 13,251.55 2,100.00 15,351.55
29 1 M2 RUMPUT MUTIARA
1.0000 bh Tanaman Soka -
0.0300 m3 Tanah Subur 70,000.00 2,100.00
0.0030 oh Kep. Tukang 85,000.00 255.00
0.1500 oh Pekerja 76,643.70 11,496.55
0.0150 oh Mandor 100,000.00 1,500.00
Total : 13,251.55 2,100.00 15,351.55
1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN
8.0000 m1 Kabel NYM 3 x 2.5 mm ex. Supreme 13,000.00 104,000.00
3.0000 bt Pipa Clipsal 20 mm hitam 10,000.00 30,000.00
2.0000 bh Tee dos clipsal 20 mm hitam 5,000.00 10,000.00
15.0000 bj Klem clipsal 20 mm hitam 500.00 7,500.00
3.0000 bj Sock clipsal 20 mm hitam 1,500.00 4,500.00
1.0000 bj Inbow dos plastik clipsal E 157 P 6,000.00 6,000.00
1.0000 ttk Biaya pasang 30,000.00
Total : 30,000.00 162,000.00 192,000.00
a 1 Bh. Pasang Saklar/ Stop Kontak
1.0000 bh Saklar tunggal [1 way 1 gang] setara clipsall 25,000.00 25,000.00
1.0000 bh Saklar double [1 way 2 gang] setara clipsall 30,000.00 30,000.00
1.0000 bh Stop kontak setara clipsall 30,000.00 30,000.00
1.0000 bh bok MK
Saklar tunggal [1 way 1 gang] setara clipsall - 25,000.00 25,000.00
b Saklar double [1 way 2 gang] setara clipsall - 30,000.00 30,000.00
c Stop kontak setara clipsall - 30,000.00 30,000.00
1 Bh. Pasang Lampu
1.0000 bh Lampu TL 2x18 Watt + kap lampu setara saka 750,000.00 750,000.00
1.0000 bh Lampu down light 14 Watt philip 80,000.00 80,000.00
1.0000 bh Material Bantu 25,000.00 25,000.00
d Lampu TL 2x18 Watt + kap lampu setara saka Total : 25,000.00 750,000.00 775,000.00
e Lampu down light 14 Watt philip Total : 25,000.00 80,000.00 105,000.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
2 1 TITIK INSTALASI AC
10.0000 m1 Kabel NYM 3 x 2.5 mm ex. Supreme 13,000.00 130,000.00
3.0000 bt Pipa Clipsal 20 mm hitam 10,000.00 30,000.00
1.0000 bh Tee dos clipsal 20 mm hitam 5,000.00 5,000.00
15.0000 bj Klem clipsal 20 mm hitam 500.00 7,500.00
4.0000 bj Sock clipsal 20 mm hitam 1,500.00 6,000.00
1.0000 bj Inbow dos plastik clipsal E 157 P 6,000.00 6,000.00
1.0000 m1 Pipa flexible clipsal 20 mm hitam 10,000.00 10,000.00
1.0000 ttk Biaya pasang - - -
Total : - 194,500.00 194,500.00
2b PEKERJAAN PIPA REFRIGERANT, DRAIN AC dan POWER LISTRIK
1.0000 ls Pipa Refrigerant (1/4" X 1/2" ) -
1.0000 ls Kabel Control (3X2.5mm ) / Remote -
Instalasi Kabel Power (3X2.5mm )
16.0000 m - Kabel NYM 3x4 mm² -
5.0000 m - Conduit PVC dia 20 mm² 10,000.00 50,000.00
1.0000 bh - Tee doos 5,000.00 5,000.00
1.0000 bh - Inbow Dus 6,000.00 6,000.00
5.0000 bh - Sock 1,500.00 7,500.00
9.0000 bh - Klem conduit 500.00 4,500.00
1.0000 bh Instalasi Stop Kontak AC -
10.0000 m Pipa Pembuangan Air PVC AW 3/4" 6,200.00 62,000.00
2.0000 oh Pekerja 76,643.70 153,287.40
1.0000 oh Tukang AC 80,000.00 80,000.00
0.7500 oh Kepala Tukang 85,000.00 63,750.00
0.5000 oh Mandor 100,000.00 50,000.00
Total : 347,037.40 135,000.00 482,037.40
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SAT NO ANALISA SATUAN HARGA
( Rp ) ( Rp )
1 2 3 4 5 6 7