MOP - Enable SNMP To Kubernates Reg 3 v1.0
MOP - Enable SNMP To Kubernates Reg 3 v1.0
Confidentiality
This document contains confidential and proprietary information of NTT Limited (‘NTT’). PT Telekomunikasi
Selular (‘PT Telekomunikasi Selular’) may not disclose the confidential information contained herein to any
third party without the written consent of NTT, save that PT Telekomunikasi Selular may disclose the contents
of this document to those of its agents, principals, representatives, consultants or employees who need to
know its contents for the purpose of PT Telekomunikasi Selular’s evaluation of the document. PT
Telekomunikasi Selular agrees to inform such persons of the confidential nature of this document and to obtain
their agreement to preserve its confidentiality to the same extent as PT Telekomunikasi Selular. As a condition
of receiving this document, PT Telekomunikasi Selular agrees to treat the confidential information contained
herein with at least the same level of care as it takes with respect to its own confidential information, but in no
event with less than reasonable care. This confidentiality statement shall be binding on the parties for a period
of five (5) years from the issue date stated on the front cover unless superseded by confidentiality provisions
detailed in a subsequent agreement.
Document Identification
File Name MOP - Enable SNMP to Kubernates Reg 3 v1.0.docx
Version Version 0.01
Sensitivity Classification Company Confidential - Client / Vendor Information
Preparation
Action Name Role / Function Date
Release
Date Released Change Notice Remarks
Table of Contents
1. Executive Summary.............................................................................................. 5
1 .1 A ct iv ity Summa ry ............................................................................................... 5
1 .2 S ite & No de ........................................................................................................ 5
1 .3 Con ta ct Pe rson .................................................................................................. 5
1 .4 Im pa ct Se rv ic e – Node ...................................................................................... 5
List of Figures
Figure 2-1Existing Topology ............................................................................................... 6
List of Tables
Table 1-1Description of activity summary ............................................................................ 5
Table 1-2Site and Node of implementation activity ............................................................... 5
Table 1-3Contact Person of Activity..................................................................................... 5
Table 4-1Service Status before Migration ............................................................................ 8
Table 4-2Checklist before implementation and Migration ...................................................... 8
Table 5-1Detailed step by step of implementation and execution time .................................. 10
Table 6-1Post activity Service test ..................................................................................... 11
Table 7-1Condition of Fall back Plan and Initiation Time...................................................... 12
Table 7-2Detail fall back activity......................................................................................... 12
1. Executive Summary
This document is a step-by-step sequence for performing an operation and
migration. It tells the implementors, field engineers, operation team and inform client
about how to execute the actions in order to perform an operation and migration and
impact of activity to existing network services.
A brief summary and service impact of activity can be explained in section below.
Prerequisites
Table 1-1Description of activity summary
FW-GI-TBS TBD
FW-GI-BRN TBD
Forti-Analyzer-TBS TBD
FAZ-BigData-TBS-1 TBD
Forti-Analyzer-BRN TBD
Table 1-2Site and Node of implementation activity
Parameter
4. Pre-activity Checklist
These sections will describe state of service before migration and implementation
activity begin. These will be used as a baseline and reference point for activity checking
when implementation and migration is completed .
FW-GI-TBS
FW-GI-BRN
FAZ TBS
FAZ BD
FAZ BRN
Execution Service
No Task Description PIC
Time Impact
6. Post-activity Checklist
These Section will describe about activity checking after changes and all step of
implementations are completed. These will help PT. Telekomunikasi Selular to check
service sanity status and help making decision whether everything is normal or fall-back
plan need to be executed to avoid unnecessary downtime.
7. Fallback Plan
This section will describe fallback plan that will be executed (if necessary) under
coordination PT. Telekomunikasi Selular should these implementation or service
migration declared as failed since application and service is heavily disrupted for too
long.
Item Remark
Condition for Fallback plan or abort If traffic or service status is degraded or not running at
04:00 AM
Notes:
Signature Signature
Date Date
PT Telekomunikasi Selular should send this signed Acceptance Sheet to +62 -21-8356423
(fax) or email to kurniadi.angriawan@global.ntt