Detail Quantity Estimate
SN Descriptions No Length(m) Breadth(m) Height(m) Quantity Unit Remarks
A Civil Woks
A.1 Earthwork Excavation Works
For Foundation
F1 12 1.63 1.63 1.5 47.82 2"projection
F2 19 1.93 1.93 1.5 106.16 2"projection
F3 9 2.2 2.2 1.5 65.34 2"projection
For Trench
grid A, B,G,H 4 13.61 0.5 1.5 40.83
grid-C,F 2 5.91 0.5 1.5 8.87
grid D,E 2 6.54 0.5 1.5 9.81
grid-1 1 7.36 0.5 1.5 5.52
grid-2 1 9.49 0.5 1.5 7.12
grid-3 1 14.81 0.5 1.5 11.11
grid-4,5,6 3 22.8 0.5 1.5 51.30
Total 353.87 cu.m
A.2 Earthwork Backfilling 20% of Excavation 70.77 cu.m

A.3 Sand Filling On Floor


Class Room 10 6.096 5.48 0.6 200.44
Corridor 1 area= 233.735 0.6 140.24
Toilet 2 5.38 3.61 0.6 23.31
Stair 1 6.096 3.65 0.6 13.35
Total 377.33 cu.m
A.4 Stone Soling Works
For Foundation
F1 12 1.63 1.63 0.15 4.78
F2 19 1.93 1.93 0.15 10.62
F3 9 2.2 2.2 0.15 6.53
For Trench
grid A, B,G,H 4 13.61 0.5 0.15 4.08
grid-C,F 2 5.91 0.5 0.15 0.89
grid D,E 2 6.54 0.5 0.15 0.98
grid-1 1 7.36 0.5 0.15 0.55
grid-2 1 9.49 0.5 0.15 0.71
grid-3 1 14.81 0.5 0.15 1.11
grid-4,5,6 3 22.8 0.5 0.15 5.13

Class Room 10 6.096 5.48 0.15 50.11


Corridor 1 area= 233.735 0.15 35.06
Toilet 2 5.38 3.61 0.15 5.83
Stair 1 6.096 3.65 0.15 3.34
Total 129.72 cu.m
A.5 PCC(1:3:6) Works
For Foundation
F1 12 1.63 1.63 0.08 2.55

Page 1 of 9
F2 19 1.93 1.93 0.08 5.66
F3 9 2.2 2.2 0.08 3.48
For Trench
grid A, B,G,H 4 13.61 0.5 0.08 2.18
grid-C,F 2 5.91 0.5 0.08 0.47
grid D,E 2 6.54 0.5 0.08 0.52
grid-1 1 7.36 0.5 0.08 0.29
grid-2 1 9.49 0.5 0.08 0.38
grid-3 1 14.81 0.5 0.08 0.59
grid-4,5,6 3 22.8 0.5 0.08 2.74

Class Room 10 6.096 5.48 0.08 26.72


Corridor 1 area= 233.735 0.08 18.70
Toilet 2 5.38 3.61 0.08 3.11
Stair 1 6.096 3.65 0.08 1.78
Total 69.184 cu.m

Page 2 of 9
A.6 PCC(1:1.5:3) Works
Foundation
F1 12 1.53 1.53 0.5 14.05
F2 19 1.83 1.83 0.5 31.81
F3 9 2.13 2.13 0.6 24.50

Trench Beam
grid A, B,G,H 4 19.72 0.23 0.3 5.44
grid-C,F 2 11.51 0.23 0.3 1.59
grid D,E 2 13.77 0.23 0.3 1.90
grid-1 1 11.32 0.23 0.3 0.78
grid-2 1 14.98 0.23 0.3 1.03
grid-3 1 24.3 0.23 0.3 1.68
grid-4,5,6 3 34.36 0.23 0.3 7.11

Plinth Beam
grid A, B,G,H 4 19.72 0.23 0.3 5.44
grid-C,F 2 11.51 0.23 0.3 1.59
grid D,E 2 13.77 0.23 0.3 1.90
grid-1 1 11.32 0.23 0.3 0.78
grid-2 1 14.98 0.23 0.3 1.03
grid-3 1 24.3 0.23 0.3 1.68
grid-4,5,6 3 34.36 0.23 0.3 7.11

Ground Floor Beam/1st Floor beam


grid A, B,G,H 8 19.72 0.3 0.3 14.20
grid-C,F 4 11.51 0.3 0.3 4.14
grid D,E 4 13.77 0.3 0.3 4.96
grid-1 2 11.32 0.3 0.3 2.04
grid-2 2 14.98 0.3 0.3 2.70
grid-3 2 24.3 0.3 0.3 4.37
grid-4,5,6 6 34.36 0.3 0.3 18.55
Cantilever Beam 16 1.22 0.3 0.3 1.76
Secondary beam
between grid AB&GH 4 21.23 0.23 0.23 4.49
between grid BCDEFG 8 12.52 0.23 0.23 5.30
between grid 1,2 4 6.88 0.23 0.23 1.46
between grid -5,6 4 16.58 0.23 0.23 3.51
stair beam 2 3.35 0.23 0.23 0.35
Column
Upto Plinth Level
C1 32 0.4 0.4 1.6 8.19
C2 6 0.355 0.355 1.6 1.21
C3 2 D= 0.355 1.6 0.32
Ground Floor/1st Floor/2nd Floor
C1 64 0.4 0.4 3.225 33.02
C2 12 0.355 0.355 3.225 4.88
C3 4 D= 0.355 3.225 1.28
3rd Floor
C1 4 0.4 0.4 2.305 1.48
Slab(ground,1st,2nd) 2 Area= 655.74 0.125 163.94
Stair Cover 1 Area= 38.706 0.125 4.84

Staircase
Waist Slab 6 2.97 1.68 0.15 4.49

Page 3 of 9
Steps 36 1.68 0.28 0.18 1.52
Sill Band 2 110.79 0.23 0.1 5.10
Lintel Band 2 121.87 0.23 0.1 5.61
Landing 2 3.71 1.65 0.15 1.84
Total 414.96 cu.m
A.7 BRICK MASONARY WORKS
Sub-Structure(Foundation upto plinth)
grid A, B,G,H 4 19.72 0.23 1.52 27.58
grid-C,F 2 11.51 0.23 1.52 8.05
grid D,E 2 13.77 0.23 1.52 9.63
grid-1 1 11.32 0.23 1.52 3.96
grid-2 1 14.98 0.23 1.52 5.24
grid-3 1 24.3 0.23 1.52 8.50
grid-4,5,6 3 34.36 0.23 1.52 36.04

Ground Floor
External Brick Wall(9"thk) 1 124.45 0.23 2.92 83.58
Partition Wall(5"thk) 1 68.6 0.115 2.92 23.04

1st Floor
External Brick Wall(9"thk) 1 180.27 0.23 2.92 121.07
Partition Wall(5"thk) 1 56.86 0.115 2.92 19.09

Page 4 of 9
Stair Cover 1 18.4 0.23 1.885 7.98
Parapet Wall(1st/2nd Floor) 2 47.8 0.115 0.7 7.70
Parapet Wall Roof 1 140.26 0.115 1 16.13
Deduct Openings
CG1 -2 1.52 0.23 2.13 -1.49
CG2 -2 2.44 0.23 2.44 -2.74
D1 -39 1 0.23 2.13 -19.11
D2 16 0.76 0.115 2.13 2.98
MD -1 1.52 0.23 2.13 -0.74
V1 -19 0.46 0.23 0.61 -1.23
V2 -2 1.22 0.23 1.53 -0.86
W1 -24 1.83 0.23 1.52 -15.35
W2 -32 1.52 0.23 1.52 -17.00
W3 -3 1.52 0.23 1.98 -2.08
Total 319.941 cu.m
A.8 Reinforcment Works 1.5% of conc Vol 48861.069 kg
A.9 Formworks
Foundation
F1 12 1.53 1.53 0.5 36.72
F2 19 1.83 1.83 0.5 69.54
F3 9 2.13 2.13 0.6 46.008

Trench Beam
grid A, B,G,H 4 19.72 0.23 0.3 65.47
grid-C,F 2 11.51 0.23 0.3 19.11
grid D,E 2 13.77 0.23 0.3 22.86
grid-1 1 11.32 0.23 0.3 9.40
grid-2 1 14.98 0.23 0.3 12.43
grid-3 1 24.3 0.23 0.3 20.17
grid-4,5,6 3 34.36 0.23 0.3 85.56

Plinth Beam
grid A, B,G,H 4 19.72 0.23 0.3 65.47
grid-C,F 2 11.51 0.23 0.3 19.11
grid D,E 2 13.77 0.23 0.3 22.86
grid-1 1 11.32 0.23 0.3 9.40
grid-2 1 14.98 0.23 0.3 12.43
grid-3 1 24.3 0.23 0.3 20.17
grid-4,5,6 3 34.36 0.23 0.3 85.56

Ground Floor Beam/1st Floor beam


grid A, B,G,H 8 19.72 0.3 0.3 141.98
grid-C,F 4 11.51 0.3 0.3 41.44
grid D,E 4 13.77 0.3 0.3 49.57
grid-1 2 11.32 0.3 0.3 20.38
grid-2 2 14.98 0.3 0.3 26.96
grid-3 2 24.3 0.3 0.3 43.74
grid-4,5,6 6 34.36 0.3 0.3 185.54
Cantilever Beam 16 1.22 0.3 0.3 17.57
Secondary beam
between grid AB&GH 4 21.23 0.23 0.23 58.59
between grid BCDEFG 8 12.52 0.23 0.23 69.11
between grid 1,2 4 6.88 0.23 0.23 18.99
between grid -5,6 4 16.58 0.23 0.23 45.76
stair beam 2 3.35 0.23 0.23 4.62

Page 5 of 9
Column
Upto Plinth Level
C1 32 0.4 0.4 1.6 81.92
C2 6 0.355 0.355 1.6 13.63
C3 2 D= 0.355 1.6 3.57
Ground Floor/1st Floor/2nd Floor
C1 64 0.4 0.4 3.225 330.24
C2 12 0.355 0.355 3.225 54.954
C3 4 D= 0.355 3.225 14.386
3rd Floor
C1 4 0.4 0.4 2.305 14.75
Slab(ground,1st,2nd) 2 Area= 655.74 0.125 1311.48
Stair Cover 1 Area= 38.706 0.125 38.71

Staircase
Waist Slab 6 2.97 1.68 0.15 29.94
Steps 36 1.68 0.28 0.18 10.89
Sill Band 2 110.79 0.23 0.1 44.32
Lintel Band 2 121.87 0.23 0.1 48.75
Landing 2 3.71 1.65 0.15 12.24
total 3356.28 sq.m

Page 6 of 9
A.10 Plastering on vertcal surface(inside,outside)
Wall Surface
Ground Floor
External Brick Wall(9"thk) 2 124.45 3.35 833.815
partition wall 2 68.6 3.35 459.62
1st Floor
External Brick Wall(9"thk) 2 180.27 3.35 1207.809
partition wall 2 56.86 3.35 380.962
Parapet Wall(1st,2nd floor) 2 47.8 0.75 71.7
Top floor 2 140.26 1 280.52

Column Surface(upto third floor)


C1 32 0.4 0.4 6.45 165.12
C2 6 0.35 0.35 6.45 27.09
C3 2 d= 0.35 6.45 14.18
Column surface (upto stair roof)
C1 4 0.4 0.4 2.31 7.39

Deduct for Openings


CG1 -4 1.52 2.13 -12.95
CG2 -4 2.44 2.44 -23.81
D1 -78 1 2.13 -166.14
D2 32 0.76 2.13 51.80
MD -2 1.52 2.13 -6.48
V1 -38 0.46 0.61 -10.66
V2 -4 1.22 1.53 -7.47
W1 -48 1.83 1.52 -133.52
W2 -64 1.52 1.52 -147.87
W3 -6 1.52 1.98 -18.06
Total 2973.06 sq.m
A.11 Plastering on Horizontal Surface
Plastering on Ceiling Surface including beam
Ground/1st/2nd Floor ceiling 2 Area= 655.75 1311.5
Stair Roof 1 Area= 34.01 34.01
Total 1345.51 sq.m
A.12 Painting on wall surface(inside,outside) 2973.06 sq.m
A.13 Weather Proof Painting on Ceiling 1345.51 sq.m
A.14 Marble on Floor
Ground Floor
Class Room 10 6.096 5.48 334.06
First Floor
Library Hall
Class Room 5 6.1 5.21 158.91
Principal Room 1 5.26 3.43 18.04
Staff Room 1 area= 53.38 53.38
on Staircase
Riser 54 1.73 0.18 16.82
Tread 54 1.73 0.28 26.16
Landing 3 1.73 3.71 19.25
Total 626.62 sq.m
A.15 Tiling on Toilet
Ground Floor/1st floor/2nd Floor 5 5.38 3.61 97.11
Vertical Surface 5 39.12 1.53 299.27
Deduct for Openings
D1 -1 1 2.1 -2.1

Page 7 of 9
D2 -4 0.75 2.1 -6.3
V1 -5 0.45 0.6 -1.35
Total 386.63 sq.m

Page 8 of 9
Sal-Wood Frame for Door & Window
A.16
Works
D1 39 5.26 0.08 0.1 1.64
D2 16 5.02 0.08 0.1 0.64
MD 1 5.78 0.08 0.1 0.05
V1 19 2.14 0.08 0.1 0.33
V2 2 3.98 0.08 0.1 0.06
W1 24 6.7 0.08 0.1 1.29
W2 32 6.08 0.08 0.1 1.56
W3 3 7 0.08 0.1 0.17
Total 5.73 cu.m
A.17 Sal-wood Shutter for Door & Window
D1 39 1 2.1 81.9
D2 16 0.76 2.1 25.54
MD 1 1.52 2.1 3.19
V1 19 0.76 0.45 6.50
V2 2 1.23 1.52 3.74
W1 24 1.83 1.52 66.76
W2 32 1.52 1.52 73.93
W3 3 1.52 1.98 9.03
Total 270.59 sq.m
A.18 Channel gate works
CG1 2 1.53 2.1 6.43
CG2 2 2.4 2.4 11.52
Total 17.95 sq.m
A.19 Stainless Steel railing works
staircase 2 6.21 12.42
1st floor 1 43.2 43.2
Total 55.62 RM

A.20 Punning Works


2nd Roof 1 Area= 655.74 655.74
Stair Roof 1 Area= 38.706 38.71
Ground floor Corridor 1 Area= 233.73 233.73
1st floor corridor 1 Area= 135.26 135.26
total 928.18 sq.m

Prepared By: Jansewa Engineering Consultancy, Krishnapur-2, Kanchanpur