ID Task Task Name Duration Start Finish Predecessors January 2024 February 2024

Mode 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24
1 Recovery Plan Pertashop BLP 37 days Tue 02/01/24 Wed 21/02/24
2 Penyelesaian Permasalahan BLP 13 days Tue 02/01/24 Thu 18/01/24
3 Pengaturan jadwal pertemuan Direksi 9 days Tue 02/01/24 Fri 12/01/24
Indopelita dan Direktur Utama BLP
4 Pertemuan Direksi Indopelita dan 1 day Mon 15/01/24 Mon 15/01/24 3
Direktur Utama BLP
5 Penyusunan Berita Acara Penyelesaian 1 day Tue 16/01/24 Tue 16/01/24 4
Kontrak
6 Penandatanganan Berita Acara 2 days Wed 17/01/24 Thu 18/01/24 5
Penyelesaian Kontrak
7 Penerbitan Berita Acara Penyelesaian 0 days Thu 18/01/24 Thu 18/01/24 6 18/01
Kontrak
8 Pemindahan Pertashop dari Worshop BLP 21 days Tue 02/01/24 Tue 30/01/24
ke Indopelita area Balikpapan
9 Persiapan Pekerjaan 16 days Tue 02/01/24 Tue 23/01/24
10 Survey lokasi Warehouse Indopelita 1 day Tue 02/01/24 Tue 02/01/24
11 Perizinan demobilisasi pertashop 1 day Fri 19/01/24 Fri 19/01/24 7
12 Rekrut Helper 1 day Mon 22/01/24 Mon 22/01/24 11
13 Sewa Forklift & Trailer 2 days Mon 22/01/24 Tue 23/01/24 11
14 Demobilisasi Pertashop 5 days Wed 24/01/24 Tue 30/01/24
15 Loading Pertashop 4 days Wed 24/01/24 Mon 29/01/24 12;11;13
16 Mobilisasi Pertashop 4 days Thu 25/01/24 Tue 30/01/24 15SS+1 day
17 Unloading Pertashop 4 days Thu 25/01/24 Tue 30/01/24 16SS

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Pemindahan Pertashop
Summary Manual Summary Rollup Progress
Date: Fri 29/12/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors January 2024 February 2024
Mode 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24
18 Serah Terima Pertashop BLP ke 1 day Tue 30/01/24 Tue 30/01/24 17FF
Indopelita
19 Penerbitan Berita Acara Serah Terima 0 days Tue 30/01/24 Tue 30/01/24 18 30/01
Pertashop dari BLP ke Indopelita
20 Penjualan Pertashop 37 days Tue 02/01/24 Wed 21/02/24
21 Penjualan Pertashop ke Subholding C&T 37 days Tue 02/01/24 Wed 21/02/24
22 Pengaturan Pertemuan Indopelita, 5 days Tue 02/01/24 Mon 08/01/24
SPPU, dan Subholding C&T
23 Pertemuan Awal Indopelita, SPPU, dan 1 day Tue 09/01/24 Tue 09/01/24 22
Subholding C&T
24 Pertemuan Lanjutan Indopelita, SPPU, 1 day Wed 10/01/24 Wed 10/01/24 23
dan Subholding C&T
25 Pembentukan kerjasama penjualan 15 days Thu 11/01/24 Wed 31/01/24 24
Pertashop dengan Subholding C&T
26 Penerbitan Kontrak Kerjasama 0 days Wed 31/01/24 Wed 31/01/24 25 31/01
Penjualan Pertashop ke Subholding
27 C&T
Penyempurnaan konstruksi Pertashop 10 days Thu 01/02/24 Wed 14/02/24 26
28 Pengiriman Pertashop dari Indopelita 5 days Thu 15/02/24 Wed 21/02/24 27
ke Subholding C&T
29 Serah Terima Pertashop dari 0 days Wed 21/02/24 Wed 21/02/24 28 21/02
Indopelita ke Subholding C&T
30 Likuidasi Project melalui Penjualan 20 days Tue 16/01/24 Mon 12/02/24
Material Pertashop (Jika Plan A gagal)
31 Menyusun rencana dan kontrak 10 days Tue 16/01/24 Mon 29/01/24 21SS+10 days
penjualan material Pertashop
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Pemindahan Pertashop
Summary Manual Summary Rollup Progress
Date: Fri 29/12/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Predecessors January 2024 February 2024
Mode 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24
32 Penyusunan SK Likuidasi Project untuk 10 days Tue 16/01/24 Mon 29/01/24 31SS
penjualan Pertashop
33 Penerbitan SK Likuidasi Project untuk 0 days Mon 29/01/24 Mon 29/01/24 32;31 29/01
penjualan Pertashop
34 Lelang Terbuka material Pertashop 5 days Tue 30/01/24 Mon 05/02/24 33
35 Penerbitan kontrak jual beli material 0 days Mon 05/02/24 Mon 05/02/24 34 05/02
Pertashop
36 Pengambilan pertashop dari workshop 5 days Tue 06/02/24 Mon 12/02/24 35
Indopelita oleh Buyer
37 Serah Terima Pertashop dari 0 days Mon 12/02/24 Mon 12/02/24 36 12/02
Indopelita ke Buyer

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Pemindahan Pertashop
Summary Manual Summary Rollup Progress
Date: Fri 29/12/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only