Damage Report of PMGSY roads executed under Phase 1 & Pha

S.No. Name of road Block Package weather Year of whether


Number construct complet falls
ed under etion under
PMGSY DLP
Phase 1 period
or 2 (Yes/No
)

1 Khudla Seras Samloun Gopalpur HP-08-325 Phase 2 2021 YES


Road

2 Paunta to Dhalwan Road Gopalpur HP-08-436 Phase 2 2020 YES

3 Dhalwan Masyani Bahnu Gopalpur HP-08-492 Phase 2 2022 YES


Road
3 Dhalwan Masyani Bahnu Gopalpur HP-08-492 Phase 2 2022 YES
Road

4 Amblagalu Chowk Gopalpur HP-08-491 Phase 2 2022 YES


Andhrada Road

5 Kalkhar to Bhambla Gopalpur HP-08-491 Phase 2 2022 YES


Road

6 Upper Bhambla Kared Gopalpur HP-08-319 Phase 2 2021 YES


Dhadwan Road
7 Baldwara Math Khalyana Gopalpur HP-08-483 Phase 2 2022 YES
Road

8 Smaila Tikkari Nargi Gopalpur HP-08-322 Phase 2 2020 YES


Road

9 Ukhala Baras Marhi Gopalpur HP-08-321B Phase 2 2020 YES


PAtwana Road
10 Baturda to Dhanalag Gopalpur HP-08-320 Phase 2 2022 YES
Road

11 Khudla Baswater Trandol Gopalpur HP-08-335 Phase 2 2022 YES


Road

12 Leda Balhra Alsogi Road Gopalpur HP-08-482 Phase 2 2022 YES

13 Plasssi Larha Road Gopalpur HP-08-510 Phase 2 2021 YES


13 Plasssi Larha Road Gopalpur HP-08-510 Phase 2 2021 YES

14 Rehri thanachowki Road Gopalpur HP-08-318 Phase 2 2022 YES


ed under Phase 1 & Phase 2 for Sub Division Baldwara Division Sarkaghat Distt. Mandi HP

Stipulated Detail of damage to PMGSY roads


Date of
completio Type of Chainage Length Date of Amount
n of DLP damage (Metres) damage required
for
restoratio
n
From To (In Lacs)

2026 R/Walls
collapsed/Da
mged

Road Crust
Damaged
Heavy Slips
Wearing
surface
washed

Breast wall
dmaged/coll
apsed

2025 R/Walls
collapsed/Da
mged

Road Crust
Damaged
Heavy Slips
Wearing
surface
washed

Breast wall
dmaged/coll
apsed

2027 R/Walls
collapsed/Da
mged
2027

Road Crust
Damaged
Heavy Slips
Wearing
surface
washed

Breast wall
dmaged/coll
apsed

2027 R/Walls
collapsed/Da
mged

Road Crust
Damaged
Heavy Slips
Wearing
surface
washed

Breast wall
dmaged/coll
apsed

2027 R/Walls
collapsed/Da
mged

Road Crust
Damaged
Heavy Slips
Wearing
surface
washed

Breast wall
dmaged/coll
apsed

2026 R/Walls
collapsed/Da
mged

Road Crust
Damaged
Heavy Slips
Wearing
surface
washed

Breast wall
dmaged/coll
apsed

2027 R/Walls
collapsed/Da
mged

Road Crust
Damaged
Heavy Slips
Wearing
surface
washed

Breast wall
dmaged/coll
apsed

2025 R/Walls
collapsed/Da
mged

Road Crust
Damaged
Heavy Slips
Wearing
surface
washed

Breast wall
dmaged/coll
apsed

2025 R/Walls
collapsed/Da
mged

Road Crust
Damaged
Heavy Slips
Wearing
surface
washed
Breast wall
dmaged/coll
apsed

2027 R/Walls
collapsed/Da
mged

Road Crust
Damaged
Heavy Slips
Wearing
surface
washed

Breast wall
dmaged/coll
apsed

2027 R/Walls 1/600 to 1/615, 2/260 to 75 mtrs 12.08.2023 30.00


collapsed/Da 2/280, 2/315 to 2/335, to
mged 2/580 to 2/590 14.08.2023

Road Crust In various chainages 12.08.2023 1.75


Damaged/po to
t holes 14.08.2024

Heavy Slips 4/845, 2/030, 2/360, 12.08.2023 25.00


2/420, 2/580, 2/620, to
2/710, 2/920, 2/970, 14.08.2025
3/070, 3/250

CD 1/850 & 2/270 2 Nos 12.08.2023 5.00


Damaged to
14.08.2027

2027 Heavy Slips 2/275 to 2/300,1/500 to 50.00 mtrs. 12.08.2023 0.750


1/515 & 1/625 to 1/635 to
14.08.2023

Road Crust 0/00 to 3/350 In patches 12.08.2023 1.500


Damaged to
14.08.2024

2026 Road Crust 0/00 to 3/350 In patches 12.08.2023 1.500


Damaged/po to
tholes 14.08.2024
2026

Heavy Slips 2/275 to 2/300,1/500 to 50.00 mtrs. 12.08.2023 0.750


1/515 & 1/625 to 1/635 to
14.08.2023

2027 R/Walls
collapsed/Da
mged

Road Crust
Damaged
Heavy Slips
Wearing
surface
washed

Breast wall
dmaged/coll
apsed
rkaghat Distt. Mandi HP

Remarks

The road was closed for traffic for all kind of


vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 15.08.203 lead to hevy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will be made
open for Light motor vehicles mvement on dated
17.08.2023. This road can be opened for HTV
only after providing protection works at various
mentioned required Rds & after restoring the
road surface.

The road was closed for traffic for all kind of


vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 15.08.203 lead to hevy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will bw
made open for Light motor vehicles mvement on
dated 17.08.2023. THe road is washed out at rd

The road was closed for traffic for all kind of


vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 15.08.203 lead to hevy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will bw
made open for Light motor vehicles mvement on
dated 17.08.2023. THe road is washed out at rd
The road was closed for traffic for all kind of
vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 15.08.203 lead to hevy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will bw
made open for Light motor vehicles mvement on
dated 17.08.2023. THe road is washed out at rd

The road was closed for traffic for all kind of


vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 15.08.203 lead to hevy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will bw
made open for Light motor vehicles mvement on
dated 17.08.2023. THe road is washed out at rd

The road was closed for traffic for all kind of


vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 15.08.203 lead to hevy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will bw
made open for Light motor vehicles mvement on
dated 17.08.2023. THe road is washed out at rd

The road was closed for traffic for all kind of


vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 15.08.203 lead to hevy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will bw
made open for Light motor vehicles mvement on
dated 17.08.2023. THe road is washed out at rd
10.08.2023 to 15.08.203 lead to hevy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will bw
made open for Light motor vehicles mvement on
dated 17.08.2023. THe road is washed out at rd

The road was closed for traffic for all kind of


vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 15.08.203 lead to hevy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will bw
made open for Light motor vehicles mvement on
dated 17.08.2023. THe road is washed out at rd

The road was closed for traffic for all kind of


vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 15.08.203 lead to hevy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will bw
made open for Light motor vehicles mvement on
dated 17.08.2023. THe road is washed out at rd

The road was closed for traffic for all kind of


vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 15.08.203 lead to hevy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will bw
made open for Light motor vehicles mvement on
dated 17.08.2023. THe road is washed out at rd
dated 17.08.2023. THe road is washed out at rd

The road was closed for traffic for all kind of


vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 15.08.203 lead to hevy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will bw
made open for Light motor vehicles mvement on
dated 17.08.2023. THe road is washed out at rd

The road was closed for traffic for all kind of


vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 15.08.203 lead to hevy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will bw
made open for Light motor vehicles mvement on
dated 17.08.2023. THe road is washed out at rd

The road was closed for traffic for all kind of


vehicular traffic and even for pedestrain
movement due to continous heavy rain from
12.08.2023 to 15.08.2023 lead to hevy slips, road
crust damage, failure/damage to protection
works, road side & cross drains and was opened
for vehicular traffic on 16.08.2023

The road was closed for traffic for all kind of


vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 13.08.203 lead to heavy slips, road
crust damage, damage to protection works, road
side & cross drains and was opened to all kind of
vehicular traffic by 15.08.2023
The road was closed for traffic for all kind of
vehicular traffic and even for pedestrain
movement due to continous heavy rain from
10.08.2023 to 13.08.203 lead to heavy slips, road
crust damage, damage to protection works, road
side & cross drains and was opened to all kind of
vehicular traffic by 15.08.2023
The road was closed for traffic for all kind of
vehicular traffic and even for pedestrain
movement due to continous heavy rain from
3.08.2023 to 15.08.203 lead to heavy slips, road
crust damage, failure/damage to protecgion
works, road side & cross drains and will bw
made open for Light motor vehicles mvement on
dated 17.08.2023. THe road is washed out at rd
7/850 to 7/900