Professional Documents
Culture Documents
Project Management - Cheat Sheet
Project Management - Cheat Sheet
Project Management - Cheat Sheet
2. Core Team: Keep small and functional. Consider what skills will contribute to the success of the project and
who will benefit.
3. Extended Team: Part-time involvement or involved for specific tasks or phases. Includes Subject Matter
Experts (SMEs)
4. Other Stakeholders: Management, Sponsor, etc. A Project Sponsor authorizes project, appoints PM,
authorizes team, mentors and supports team, approves plan. Never deliver news good/bad to the whole group
before reviewing with the sponsor first.
- Success Criteria: what do the sponsors and key stakeholders think we’ll have at the end of the project?
2. Success Criteria
Defines successful project completion per the stakeholders and the sponsor. What does it include and what
does it not include.
Is Is Not
2.4 Define The Project Infrastructure - How the Team will operate.
Infrastructure: Written guidelines and procedures that will define how the project core team will plan, manage,
track and report on the project
Team Logistics:
Facilities Hardware
Office equipment Software
Communication equipment and infrastructure Intranet
Furniture Networks
Website
Planning Methodologies:
Phase Planning: As below. There is a risk of delay if any phase doesn’t complete on time.
Concurrent Planning - AKA Rapid Application & Design: Begin work tasks while planning continues. Ensure that
work doesn’t start to drive planning or that unnecessary work gets done
Rigor: How rigorous will you be as a project manager everything in the project, are you going to delay step 2
until step 1 is complete, or will you be more flexible
Top-Down vs Botton-Up
Top-Down:
Have the team:
1. Identify 4 - 7 major components of work (how you will manage work)
2. Identify Level 2 (+) tasks for each grouping
● with one owner (may be multiple doers),
● Clear deliverable,
● 2 - 20 days duration,
● Credible estimate of duration,
● Ability to be tracked
4. Use Verb-Noun: action statements including who/what
Bottom-Up:
Have the team:
1. Brainstorm all tasks
2. Organize tasks into 4 -7 major groupings reflecting how the project will be managed
Task Ownership
● One owner/task, responsible for planning and managing task
● Owner may or may not be “doer”
● Plan and manage the work
● Identify requisite skill sets
● Estimate task duration
● Act as point-of-contact until resources are assigned
● Ensure work is to specifications and within schedule
Logic
Dependency Diagram: Flow/sequence of work form start to finish:
Annotation Dont’s
Avoid Loops.
2. Consider the number of people: Adding people to a task cuts down on the time it takes to complete the task.
Be sure to consider communication lines when adding bodies to a task to speed up an estimate.
3. Consider productivity: Average 4.6 productive hours in a productive day.
No padding - use Management Reserve:
No fractional days
No task duration greater than 10% of project phase
Managers: Don’t arbitrarily alter estimates
Estimators: Don’t just give in to pressure
Use multi-approaches - compare results
Perform peer reviews
Watch for overly optimistic/pessimistic estimates
Apply more intensity for critical path tasks
4. Assure equal probability that actual duration will be longer or shorter than estimate
5. Document assumptions
Rigors of Estimating
Low Rigor:
● Just use the last estimate
● Add an “allowable” slip to the previous estimate
● What does the boss want to hear?
● Subtract the past slip from the new estimate
Medium Rigor:
● Apply historical data
● Apply rules of thumb
● Gather expert input
● Break large tasks into smaller ones
● Complete a portion, then extrapolate
Identifying Resources
● Task owner identifies the resource needs - Functional Manager provides the resources
● Dependent on rigor
○ May only have titles or organizations later in the plan
● Occurs from the proposal phase through Track & Manage
○ Document assumptions that affect resources
○ Document/manage issues
○ Update/communicate Team Roster when necessary
2. Propose modifications to the project objectives if the POS is still not met
Modifications could be significant
*Prepare three options and a recommendation
Provide “what-if” analysis
Present to the sponsor for approval (using below template)
2. Assess Risks
Risk Assessment Matrix
Ask these four questions of each risk and rate each risk High, Medium, Low. Do not average first three to get
fourth.
1. Potential Impact
2. Likelihood of Occurrence
3. Difficulty of Timely Detection: The higher the surprise of the risk occurring the higher the rating. If you
can see the risk coming then you give it a lower rating.
4. Overall threat = do we need an impact plan for this risk? High=Yes, Low=No, Med=Time dependent
Project Baseline
Snapshot of approved plan
Establishes a target
Provides something to measure progress against
Makes project goals visible
Once the Project is baselined, use Change Management for any changes to the Project Plan
Change Management:
● Review proposed changes
● Log all changes
● Validate if outside POS
● Announce changes
4. Track & Manage The Project
Tracking:
● Provides clear indication of progress
● Keeps everyone informed
● Encourages the addressing of problems
● Provides credible completion estimates
● Provides data for Organizational Mastery
Tracking Continuum:
Trac
king Tactics
Hard - Quantitative: What is happening?
1. If started, on what date did the task start?
2. If not started, on what date will the task start?
3. If finished, on what date did the task finish?
4. If not finished, on what date will the task finish?
Soft - Qualitative: Why is it happening?
● Listen
● Ask why
○ “Tell me more …”
○ “Help me understand …”
● Be alert to:
○ Requirements changes
○ Customer requests
○ Organizational issues, changes
Variance Analysis
Many standard reports show variance
Backtrack slippage
Variance tells “what” (hard data)
More detective work for “why” (soft data)
Adaptive Action
If significant variance is identified, take Adaptive Action (like Optimization)
● Redefine Logic
● Use Flexibility Matrix
● Re-deploy resources
Might trigger contingency plans
May require revalidation (3 options and 1 recommendation)
Managing Issues:
Issue: A problem that is currently impeding the project. Today’s issue is yesterdays risk!
● From status data
● From meetings, discussions
Identifying Issues:
Issue Log
Responding To Issues
Manage the issues log
Issues resolution meetings
Hold issues owners accountable
May affect scope, schedule, or resources
May need to update the plan
May need to escalate to the sponsor
Communicate appropriately
Addressing Change
Change: A modification in the scope, schedule or resources of a project
● In requirements, scope
● In schedule targets
● In resources
Change could be: An opportunity for new business/An opportunity for organizational learning
Addressing Change
1. Document the need/request for change
Internal
External
2. Follow the Change Management process
Change Request Form
Analysis
3. Proceed to the appropriate step in theProject Management Model, if necessary
Dashboard - Example: