Professional Documents
Culture Documents
7th Sem Final Report 1-1
7th Sem Final Report 1-1
Submitted by
Nirmali Chakravarty 200810001030
Saurabh Jyoti Kashyap 200810001049
Kausik Pathak 200810001022
Bhaswat Kashyap 200810001007
Submitted to
Submitted by
Submitted to
Department of Civil Engineering
Jorhat Institute of Science &Technology
Jorhat-10
Certificate from Supervisor
The undersigned certify that the project report entitled “PARTIAL
REPLACEMENT OF CEMENT WITH BANANA PEEL ASH”
submitted by,
The results contained in this report have not been submitted in part or
full to any other Institute or University for award of any degree or
diploma.
……………………………..
Date:
(Miss. Deepika Taye)
Place:
Supervisor
Assistant Professor, Civil Engineering
Jorhat Institute of Science & Technology
I
Certificate of Approval from Department of Civil Engineering,
Jorhat Institute of Science & Technology
submitted by—
Nirmali Chakravarty
Sourabh Jyoti Kashyap
Kausik Pathak
Bhaswat Kashyap
……………………
……
Miss. Deepika Taye
Assistant Professor
Department of Civil Engineering
Jorhat Institute of Science and Technology
Jorhat-10, Assam
………………………
……
Dr. Sudarshan Patowary
Head, Department of Civil Engineering
Jorhat Institute of Science and Technology,
Jorhat – 10
II
Certificate of Approval from
Committee on Final examination for Evaluation of the Project
Report
Submitted by—
Nirmali Chakravarty
Sourabh Jyoti Kashyap
Kausik Pathak
Bhaswat Kashyap
………………………
……
Dr. Sudarshan Patowary
Head, Department of Civil Engineering
Jorhat Institute of Science and Technology,
Jorhat – 10
III
ACKNOWLEDGEMENT
It gives us immense pleasure to express our deepest sense of gratitude and
sincere thanks to our highly respected and esteemed guide, Miss. Deepika Taye
Assistant Professor, for her valuable guidance, encouragement and help for
completing this work. Her useful suggestions for this whole work and co-operative
behavior are sincerely acknowledged.
We would like to express our sincere thanks to Dr. Atanu Kumar Dutta,
Principal & professor for giving us this opportunity to undertake this project. We
would also like to thank Dr. Sudarshan Patowary, Head of Civil Engineering
Department for whole hearted support.
We are also grateful to our teachers for their constant support and guidance.
At the end we would like to express our sincere thanks to all our friends and
others who helped us directly or indirectly during this project work.
i
ABSTRACT
Concrete is widely used in civil infrastructure development works all over the
world. Researchers have explored that incorporating the waste and by-products
as partial replacement of cement can improve its workability and compressive
strength. In this paper,Banana peel ash is used as an alternative material to partially
replace the cement. A comparative study on compressive strength of conventional
concrete along with four varying percentage of banana peel ash 0.8%,1%,2%,3%
for M25 grade of concrete is carried out. The result indicates that compressive
strength is increased at 2% replacement of Banana peel ash with a very minimal
impact on workability
ii
CONTENTS
Title Page No.
Acknowledgement i
Abstract ii
List of symbols x
Abbreviations xi
CHAPTER-1 .............................................................................................................1-4
1.1 INTRODUCTION ........................................................................ 1
1.1.1 BANANA PEEL ASH .......................................................... 2
1.2 OBJECTIVES ............................................................................... 3
1.3 ORGANIZATION OF THE REPORT ......................................... 4
CHAPTER-2 .................................................................................................. 5-8
LITERATURE REVIEW.................................................................. 5-8
CHAPTER-3 ................................................................................................ 9-54
METHODOLOGY ............................................................................... 9
iii
3.1.2.2 PortlandPozzolanaCement(PPC)………………..13
3.1.2.3 Use of PPC…………..………………………….13
3.1.3 Concrete ............................................................................... 14
3.1.3.1 Characteristics of good concrete ..……...………14
3.1.4 Aggregate ............................................................................ 14
3.1.4.1 Requirement of a good aggregate….……...……15
3.1.4.2 Classification of aggregate……………..………15
3.1.5 Water………………………………...………………16
3.2 FLOW CHART………………………..…………………..17
3.3 PRELIMINARY TEST ............................................................... 18
3.3.1 Sieve Analysis ..................................................................... 18
3.3.1.1 Sieve Analysis for Fine Aggregate…………….18
3.3.1.2 Sieve Analysis for Coarse Aggregate………….19
3.3.2 Determination of Specific Gravity ...................................... 19
3.3.2.1 Specific Gravity of Coarse aggregate……..……20
3.3.2.2 Specific Gravity of Fine aggregate……………..22
3.3.3 Impact value test .................................................................. 24
3.3.4 Aggregate crushing test ....................................................... 26
3.3.5 Water absorption test on aggregate ..................................... 27
3.3.6 Normal Consistency Test………………………...………….28
3.3.7 Test for initial and final setting time…………………...…….29
3.3.8 Test for fineness of cement………………..…………...…….31
3.4 MIX DESIGN CALCULATION ................................................ 33
3.5 EXPERIMENTAL WORK......................................................... 49
3.5.1 Slump Test ........................................................................... 49
3.5.2 Casting…………………………………………………...51
3.5.3 Curing…………………………………………………....52
3.5.4 Compression Test…………………………………..…….53
CHAPTER 4…………………………………………………….…………...55-74
TEST RESULTS ................................................................................ 50
4.1 DETERMINATION OF GRADING OF COARSE
AGGREGATE
iv
AND ZONE OF FINE AGGREGATE………………………....55
4.2 RESULTS FOR SPECIFIC GRAVITY TEST ........................... 57
4.3 RESULTS FOR IMPACT VAUE TEST.................................... 60
4.4 RESULTS FOR AGGREGATE CRUSHING TEST ................. 61
4.5 RESULT FOR CEMENT TESTING ......................................... 62
4.6 FOR AMOUNT OF W/C, FA, CA, BANANA PEEL ASHES
AND WATER……………………………………………….…64
4.7 COMPRESSIVE STRENGTH ................................................... 65
4.7.1 Replacement of cement with BPA ...................................... 65
4.7.2 Comparison of strength at 0% replacement….……………….67
4.7.3 Comparison of strength at 0.8% replacement …………….....68
4.7.4 Comparison of strength at 1% replacement .…………………69
4.7.5 Comparison of strength at 2% replacement ………………….70
4.7.6 Comparison of strength at 3% replacement ………………….71
4.7.7 Analysis of compressive strength of concrete at the end of day 7
& 28…………………………………………………………72
4.8 SAVING OF CEMENT .............................................................. 74
CHAPTER-5………………………………………………...…….…....75-76
5.1 CONCLUSION ........................................................................... 75
5.2 SCOPE OF FUTURE STUDY………………...…………….…..75
REFERENCE
v
LIST OF FIGURES
vi
Figure Number Name of the Figure Page
No.
4.1 Graph between compressive strength at 7 days………..65
With respect to the percentage of replacement
Of cement by banana peel ash
4.2 Graph between compressive strength at 28 days……….66
With respect to the percentage of replacement
Of cement by banana peel ash
4.3 Compressive strength vs. Age (days)………………….67
at 0% replacement
4.4 Compressive strength vs. Age (days)…………………68
at 0.8% replacement
4.5 Compressive strength vs. Age (days)………………...69
at 1% replacement
4.6 Compressive strength vs. Age (days)……………......70
at 2% replacement
4.7 Compressive strength vs. Age (days)…………….….71
at 3% replacement
4.8 Variation of compressive strength in 7days……....…72
and 28 days
4.9 Variation of compressive strength in 7days……......…72
and 28 days
4.10 Percentage of increment of compressive ……....…....73
at the end of 7 and 28 days
4.11 Amount of cement saved…..………………..………74
vii
LIST OF TABLES
Table Number Table Description Page No.
viii
Table Number Table Description Page No.
ix
LIST OF SYMBOLS
SYMBOLS REPRESENTATION
x
ABBREVIATIONS
ABBREVIATIONS REPRESENTATION
FA Fine aggregate
CA Coarse aggregate
BPA Banana Peel Ash
RDA Recommended dietary allowance
IS Indian Standard
W/C water cement ratio
xi
CHAPTER-1
1.1 INTRODUCTION
Concrete is commonly used in construction due to globalization.
Concrete is used because it has several benefits including durability,
energy-efficiency, low maintenance, affordability and fire- resistance.
Moreover,it is known for its versatility.
Concrete is a crucial part of modern society's infrastructure. It plays a
vital role in the growth and survival of human societies. Concrete is used
as a foundation and building material for durable and dependable
infrastructure. It offers an outstanding performance in social, economic,
and environmental aspects.
However,the high demand of concrete has led to a shortage of traditional
materials and an increase in cement costs.The increasing need for
sustainable construction materials has led to the use of waste from
agricultural and industrial processes. This waste is now being utilized to
create environmental friendly final products, resulting in a reduction in
carbon emissions. In the construction industry, these waste materials are
added as admixtures or partial replacement to produce sustainable
concrete. Engineers, material scientists, and chemists have studied and
applied these materials to effectively control various properties of
concrete, such as workability, water/cement ratio, setting time, durability,
fire resistance, and compressive strength.
Banana peel ash, a byproduct of the combustion of dried banana peels,
can be used as a partial replacement for cement in construction. This
material, rich in potassium and natural fiber, can be used as a
supplementary cementitious material in concrete production. This not
only reduces the environmental impact of disposing of banana peels but
also offers benefits such as improved compressive strength and reduced
costs. Additionally, banana peel ash contains minerals like silica, which
contribute to the strength and performance of concrete. Banana peels, rich
in potassium, are used as a partial replacement to improve the
1
compressive strength of concrete.
.
1.1.1 BANANA PEEL ASH (BPA)
Banana Peel ash is also known as kol Khar. Kol Khar is the alkaline
extract from the ashes of burnt dried banana peels. The banana variety
commonly used is Musa balbisiana, locally known as
the Bhimkol or Athiyakol.
This unique banana plant is described to have seeds of the size of black
pepper, and the tree is known to be taller than most varieties. To make
the Kol Khar the peels of the mature fruit or the bark of the banana tree
is first sun dried and then burnt to an ash.
Banana peel ash is the powdery residue that remains after burning or
incinerating banana peels. Banana peel is rich in fiber content, out of
which 30-35% of total mass of fiber is carbohydrates. Mineral content in
banana generally consists of potassium (78.10mg/g) and manganese
(76.2mg/g) which are essential for plants and can be used as a fertilizer
.Although banana peel has these meritorious uses, these are considered
as vegetable waste. As 145million tones of Banana is consumed in
worldwide hence amount of banana peel will be approximately 40million
tones with 10million tones of Banana peel ash. Thus these ash can be
used as a partial replacement for cement in concrete mixtures. When used
in concrete, it serves as a supplementary cementitious material .
2
Environmental benefits of BPA:
1.2 OBJECTIVES
3
1.3 ORGANIZATION OF THE REPORT
The entire work has been divided into several phases and it is presented in different
chapters as given below:
In chapter 2, a brief review of the past works done on the effect of compressive
strength of concrete by Banana peel ash , effect on workability and Compressive
strength of concrete is discussed. Therefore, in this chapter, a brief literature review
of the different works is presented.
Chapter 3, mainly focuses on various materials used, the preliminary tests, mix
design and the various experimental works that have been carried out throughout
the project.
Chapter 4, includes all the results obtained in the course of completion of the
project in the form of tables and graphs.
Chapter 5, contains all the conclusion we have drawn from the study and also the
future scope of this project
4
CHAPTER-2
Yang et al. (2016), conducted valuable insights into the fresh and hardened
properties of concrete containing banana peel ash. The study explores
factors such as setting time, consistency, and ultimate strength. Published in
Construction and Building Technology.
5
due to exothermal reaction plays an important role and to be reduced in
construction
Smith, J., et al. (2019), They conducted the study delves into the pozzolanic
characteristics of banana peel powder, revealing compelling insights into its
capacity to enhance both compressive strength and durability in concrete
structures1. The findings from this research underscore the promising
potential of utilizing this agricultural waste by product as a valuable and
sustainable component in concrete formulations, offering a viable solution
to enhance the mechanical properties of the material.
6
ecological impact of traditional concrete formulations. This literature
provides a nuanced perspective on how banana peel derivatives align with
the global shift towards environmentally conscious building materials and
methodologies.
Zhang et al. (2020), focus on the influence of banana peel ash on concrete
microstructure. Their work delves into the nanoscale changes, providing a
comprehensive understanding of the material's impact on the composition
and arrangement of concrete components. Published in Journal of Advanced
Concrete Technology.
7
Huang et al. (2022), conducted a study to explore the rheological properties
of concrete with banana peel ash. The study provides a nuanced
understanding of how the material influences concrete workability and
viscosity. Published in Construction Materials Journal.
Mohamad et al. (2022) confirmed that banana skin powder has excellent
potential for concrete flexural strength increment up to 1.0% inclusion of
banana peel ash compared with control.
8
CHAPTER-3
METHODOLOGY
3.1 MATERIAL USED
Banana peel is rich in crude fibre, carbohydrates, crude protein and ash
and can serve as basal materials or components of animal feed. It is also
high in calcium, phosphorus, magnesium and iron, and can be good
source of these minerals. This study underscores the nutritional relevance
and mineral potentials of banana peel ash.Thus usage of this banana peel
ash will lead to the benefit of wastes management (waste reduction)
strategy, as the wastes would have constitute nuisance to the
environment.
NUTRIENTS % COMPOSITION
9
Table 3.2 Mineral Composition of Banana Peel (mg/100g)
10
Table-3.3: Physical properties of Banana Peel Ash
Particulars Properties
Colour Grey
Shape Texture Irregular
Particle Size <4.75mm
Specific gravity 2.1
Parameter Composition(%)
Fig 3.1 Dry Banana Peel Fig 3.2 Burning of Banana Peels
11
Fig 3.3 Dry Banana Peel Ash
3.1.2 Cement
Cement is a binder, a chemical substance used for construction that sets, hardens,
and adheres to other materials to bind them together. Cement is seldom used on its
own, but rather to bind sand and gravel (aggregate) together. Cement mixed with
fine aggregate produces mortar for masonry, or with sand and gravel, produces
concrete.
The properties of cement are in compliance with the Indian standard organization.
The specific gravity of the cement used is 3.15. PPC is the most widely used
Portland cement.
12
3.1.2.2 Portland Pozzolana cement (PPC)
PPC is made by blending OPC with pozzolanic materials such as fly ash,
volcanic ash, or silica fumes. It offers improved workability, durability,
and reduced heat of hydration. PPC is commonly used in hydraulic
structures, marine construction, and mass concrete works.
13
3.1.3 Concrete
Concrete is construction material composed mainly of water, aggregate and
cement. In addition to this reinforcement and additives are often included in
mixture to achieve the desired physical properties of the finished material
Concrete forms a fluid mass when fresh that can be easily moulded in shape The
cement forms a hard matrix over time which binds the rest of the ingredients into
a durable stone line material with many uses. Here we used the M25 grade of
concrete.
3.1.3.1 Characteristics of a good concrete
They are:
1. Workable
2. Free from segregation
3. Free from bleeding
4. Proper strength
5. Durability
6. Appearance
3.1.4 Aggregate
14
3.1.4.1 Requirement of a good aggregate
The requirements are:
1. It should be sufficiently strong
2. It should be hard
3. It should be durable
4. It should have a rough surface
5. It should be spherical or cubical in shape
The aggregates which pass through 75mm IS Sieve and retain on 4.75mm IS Sieve
are known as coarse aggregates. Coarse aggregates refer to irregular and granular
materials such as sand, gravel, or crushed stone, and are used for making concrete.
In most cases, Coarse is naturally occurring and can be obtained by blasting quarries
or crushing them by hand or crushers. It is imperative to wash them before using
them for producing concrete. Their angularity and strength affect the concrete in
numerous ways. Needless to say, the selection of these aggregates is a very
important process.
15
2. Fine aggregates
The aggregates which pass through 4.75mm IS Sieve and retain on 75micron
IS Sieve are known as Fine aggregates.Fine aggregate, which may be granular
material or crushed stone, is a fundamental component of concrete. The quality of
the fine aggregate and the density of the fine aggregate both have a significant
impact on the hardened qualities of the concrete. If the fine aggregate is chosen for
its grading zone, particle geometry and surface characteristics, wear and skid
resistance, soaking and surface moisture, then the concrete mixture will last longer,
become sturdier, and cost less.
3.1.5 Water
16
3.2 FLOW CHART
17
3.3 PRELIMINARY TEST
3.3.1 Sieve Analysis
Purpose: This test is performed to determine the percentage of different grain sizes
obtained within a sample. The distribution of different grain sizes affects the
engineering properties of concrete.
3.3.1.1 Sieve Analysis for Fine Aggregates
Apparatus used: Balance, Set of sieves (4.75mm, 2.36mm, 1.18mm, 600μm,
300μm, 150μm, 75μm), Pan, Sieve shaker, Timing device.
Test Procedures:
1) The test sample is dried to a constant weight at a temperature of 110+5 degree
centigrade and weighted.
2) The sample is sieved by using a set of IS Sieves.
3) On completion of sieving, the material on sieve is weighted.
4) Cumulative weight passing through each sieve is calculated as a % of total sample
weight.
5) Fineness modulus is obtained by adding cumulative percentage of aggregate
retained on each sieve and dividing the sum by 100.
18
3.3.1.2 Sieve Analysis for Coarse Aggregates
Fig 3.10 sieve shaker machine with IS sieve for coarse aggregates
19
3.3.2.1 Specific gravity of Coarse Aggregates
Following apparatus are used to conduct the specific gravity test and water
absorption test of aggregates:
1. Balance: A balance or scale of about 3 kg capacity to weigh accurately up to 0.5
g, and of such a type and shape, so as to permit within the basket containing the
aggregates when suspended in water.
2. Oven: A well-ventilated oven, which can be controlled thermostatically and it
maintains a temperature of 100 to 110 ˚C.
3. Wire Basket (Density Basket): A wire basket or density basket of not more than
6.3 mm mesh or a perforated container of convenient size with wire hangers for
suspending it from the
4. Water tight Container: A stout watertight container in which the basket can be
freely suspended.
5. Dry Clothes: Two dry, soft, and good quality absorbent clothes of size 75 x 45
cm. 6. Shallow Tray: A shallow tray of the area not less than 650 cm2 .
Test Procedure:
1) Taking a sample of 2 kg of aggregates. Wash the sample thoroughly to remove
finer particles and dust from it.
2) After washing, we place aggregates in the wire basket and immersing it in
distilled water at a temperature between 22°C and 32°C with a cover of at least 5
cm of water above the top of the basket.
3) Immediately, after immersion, we remove the entrapped air from the sample by
lifting the basket containing aggregates 25 mm above from the base of the tank and
allowing it to drop again. Continue this process at least 25 times at the rate of about
one drop per second. The basket and aggregates shall remain completely immersed
during this process as well as for a period of 24 ± ½ hours afterwards.
4) Then the basket and the sample are jolted and weighed in the water at a
temperature of 22 to 32°C. If it is necessary for them to be transferred to a different
tank for weighing, they are jolted 25 times as described above in the new tank before
weighing. Note down this weight of aggregates and basket in water as A1.
5) After that, we remove the basket and the aggregates from the water and allowing
to drain for a few minutes. After that, empty the aggregates from the basket on the
20
dry clothes and returning the empty basket to the water, jolting it 25 times and weigh
in water. The weight of basket suspended in water as A2 is noted.
6) Gently drying those aggregates with the dry cloth. We transfer aggregates to the
second dry cloth if the first one cannot remove optimum moisture residue from
them. After that spread out them in one layer for at least 10 minutes for surface to
get dry completely and avoid direct sunlight on them. Then the weight of these dry
aggregates are taken which are saturated and noted as B.
7) Next, placing the aggregates in the oven on the shallow tray at a temperature of
100 to 110°C and maintain this temperature for next 24 ± 1/2 hours. Then removing
aggregates from the oven and cool in an airtight container. After that, we measure
the weight of the aggregates and the weight of oven-dry aggregates as C is noted.
Fig 3.11 Wireness bucket in water Fig 3.12 Wireness bucket in water
Fig 3.13 Wireness bucket Fig 3.14 Setup of specific gravity test
21
3.3.2.2 Specific Gravity of Fine Aggregates
Apparatus Required
Apparatus required to determine the specific gravity of solids using density bottle
method are:
• Density bottle of 50 ml capacity
• Digital balance of accuracy 0.001g
• vacuum desiccator
• Vacuum pump
• Oven
• Constant temperature water bath (27 0C)
• Spatula
Test Procedure:
Test Procedure to determine the specific gravity of solids using density bottle
consists following steps:
1) Firstly, the density bottle is cleaned and we put it in an oven at a temperature of
105 0C to 100 0C for drying. After drying, putting it in the desiccators to cool down.
2) Now the density bottle along with stopper is weighed using balance to an
accuracy of 0.001 gm and the is reading is noted as “W1”
3) Taking 5 to 10 g of oven dried sample in the density bottle and the weight of the
bottle along with stopper and dry sample is taken and the reading is noted as “W2”.
4) Now adding de-aired distilled water to the soil in the density bottle up to the soil
level and shaking gently to mix soil and water.
5) Now removing the stopper of density bottle and placing it in vacuum desiccators
and the vacuum pump is connected.
22
7) Removing the bottle from the desiccators and add more distilled water until the
bottle is full. Inserting the stopper.
8) To attain the constant temperature through the bottle, it is immersed into the
water bath for one hour.
9) Taking out the bottle from water bath after attaining constant temperature and
cleaning and drying the outside using smooth cloth.
10) Now the bottle is weighed which is the total mass of bottle, soil and water and
is noted down as “W3”.
11) In the final step, the bottle is emptied and washed and refilling it with only
distilled water. Now also placing it in water bath for one hour to maintain same
temperature during experiment.
12) Now taking weight of the bottle with full of distilled water along with stopper
which is “W4”.
13) Now the same procedure is repeated for three times and the average reading of
three observations is taken as final result.
23
𝑊2 − 𝑊1
𝐺=
(𝑊2 − 𝑊1) − (𝑊3 − 𝑊4)
Where W1 = mass of empty bottle, W2 = mass of the bottle and dry soil, W3 = mass
of bottle, soil and water, W4 = mass of bottle filled with water only
Apparatus:
1. Impact value machine (The machine consists of a metal base.
Cylindrical steel cup which dia 10.2 cm and depth 5 cm. A metal
hammer of weight 13.5 to14 kg, 10 cm dia and 5 cm long).
2. Weight balance.
3. A Cylindrical cup having 7.5 cm dia and 5 cm depth)
4. A steel rod (1cm dia and 23 cm long)
5. Sieves – the IS Sieves of 12.5 mm, 10mm, and 2.36 mm.
24
Preparation of the test sample:
1. The test sample shall consist of aggregate the whole of which passes
a 12.5- mm IS Sieve and is retained on a 1O-mm IS Sieve. The
aggregate comprising the test sample shall be dried in an oven for a
period of four hours at a temperature of 100 to 110°C and cooled.
2. The measure shall be filled about one-third full with the aggregate
and tamped with 25 strokes of the rounded end of the tamping rod.
Further similar quantity of aggregate shall be added and a further
tamping of 25 strokes given. The measure shall finally be filled to
overflowing, tamped 25 times and the surplus aggregate struck off,
using the tamping rod as a straight-edge. The net weight of
aggregate in the measure shall be determined to the nearest gram
(Weight A) and this weight of aggregate shall be used for the
duplicate test on the same material.
Test Procedure:
1. We take some aggregate passing through 12.5 mm IS sieve and
retained on 10 mm IS sieve.
2. We now fill the cylinder with aggregate in three approximately equal
layers by tamping 25 times each layer by tamping rod.
3. The excess material from the top layer is removed by tamping rod or
straight edge.
4. The weight of test sample is now measured.
5. The test sample from cylinder is transferred to the cup of impact
machine which is firmly fixed on the base of the impact machine, and
the testing sample is compacted by tamping 25 strokes.
6. The hammer is raised above the upper surface of the aggregate in the
cup, and allowed to fall freely on to the aggregate.
7. The test sample is subjected to a total of 15 such blows.
8. The crushed aggregate is then removed from the cup and whole of it
sieved on the 2.36 mm IS Sieve until no further significant amount
passes.
25
Fig 3.18 Tamping of Coarse Aggregate Fig 3.19 Impact Testing
Apparatus:
1. A 15 cm diameter open-ended steel cylinder, with plunger and base-
plate.
2. A straight metal tamping rod of circular cross-section 16 mm in
diameter and 45 to 60 cm long, rounded at one end.
3. Sieves – the IS Sieves of 12.5 mm, 10mm, and 2.36 mm.
4. Oven.
5. Weight balance.
6. A compression testing machine capable of applying a load of 46
tonnes.
7. A cylindrical cup for measuring the sample.
26
Test Procedure:
1. We take some aggregate passing through 12.5 mm IS sieve and
retained on 10 mm IS sieve.
2. The cylinder is filled with aggregate in three approximately equal
layers by tamping 25 times each layer by tamping rod.
3. The excess material is removed from the top layer by tamping rod
or straight edge.
4. The weight of the test sample (Weight A) is measured and the
plunger is placed on the top of the cylinder.
5. The cylinder on the compression testing machine is placed.
6. Applying the load at a uniform rate of 4 tonnes per minute until the
load reaches to 40 tonnes.
7. The load is released and the whole of the material is removed from
the cylinder and sieved on a 2.36 mm IS Sieve for the standard test.
8. The fraction passing the sieve is weighed (Weight B).
27
Apparatus:
1. Wire mesh bucket
2. Setup of water absorption test
Procedure:
1. About 2 kg of aggregate sample is taken, washed to remove fines
and then placed in the wire basket. The wire basket is then immersed
in water, which is at a temperature of 220C to 320C.
2. Immediately after immersion the entrapped air is removed from the
sample by lifting the basket 25 mm above the base of the tank and
allowing it to drop, 25 times at a rate of about one drop per second.
3. The basket, with aggregate are kept completely immersed in water
for a period of 24 ± 0.5 hour.
4. The basket and aggregate are weighed while suspended in water,
which is at a temperature of 220C to 320C.
5. The basket and aggregates are removed from water and dried with
dry absorbent cloth.
6. The surface dried aggregates are also weighed.
7. The aggregate is placed in a shallow tray and heated to 100 to 1100C
in the oven for 24 ± 0.5 hours. Later, it is cooled in an airtight
container and weighed.
Apparatus:
1. Vicat apparatus
2 .Weight balance
3. Gauging trowel
5. Enamel tray
28
Theory:
The standard consistency of cement is defined as the consistency which will permit
a vicat plunger having 10 mm diameter and 50 mm length to penetrate to a depth of
33-35 mm from the top of the mould. The apparatus is called as vicat apparatus.
This apparatus is used to find out the % of water required to produce a cement paste
of standard consistency The standard consistency of the cement paste is some time
called as normal consistency.
Test procedure:
2. The paste is prepared in standard manner and filled into the vicat mould within
3-5 minutes.
3. After completely filling the mould, the mould is shaken to expel the air.
6. Similarly second trial (say 30% of water) is conducted and the depth of
penetration of plunger is measured. Similarly trials are conducted with higher and
higher water cement ratios till such time the plunger penetrates for a depth of 5 to 7
mm from the bottom of the vicat mould that means cement is of normal consistency.
Apparatus:
1. Vicat apparatus
2. Weight balance
3. Gauging trowel
29
4. Plastic measuring jar
5. Enamel tray
Theory:
It is defined as the time elapsed from the moment when the water is added to the
cement and to the time that the paste starts losing its plasticity.
It is the time elapsed from the moment when the water is added to the cement and
when the paste has completely lost its plasticity and has attained sufficient firmness
to resist certain definite pressure.
Test procedure:-
1. At first cement paste is prepared by gauging the cement with 0.85 times the water
required to give a paste of standard consistency.
3. The paste is gauged and filled in to the vicat mould in specified manner within
3-5 minutes.
1. The test block is placed confined in the mould and resting on the non-porous
plate, under the rod bearing initial setting needle (diameter -1 mm). The needle is
gently until it comes in contact with the surface of the test block and quickly
released, allowing it to penetrate into the test block.
2. In the beginning, the needle will completely penetrate the test block.
30
3. This procedure is repeated until the needle, when brought in contact with the test
block and released as described above fails to pierce the block beyond 5 mm
measured from the bottom of the mould.
4. The period elapsing between the time when water is added to the cement and the
time at which the needle fails to pierce the test block to a point 5 mm measured
from the bottom of the mould shall be the initial setting time.
1 The needle of the Vicat apparatus is replaced by the needle with an annular
attachment.
2. The cement is considered as finally set when, upon applying the needle gently to
the surface of the test block, the needle makes an impression thereon, while the
attachment fails to do so.
3. The period elapsing between the time when water is added to the cement and the
time at which the needle makes an impression on the surface of test block while the
attachment fails to do so shall be the final setting time.
Range: Initial setting time should be not less than 30 minutes. Final setting time
should not be more than 10 hours.
Apparatus:
2. Cement sample.
3. Weight balance.
Theory:
The fineness of cement has an important bearing on the rate of hydration and hence
on the rate of gain of strength and also on the rate of evolution of heat. Finer cement
offers a greater surface area for hydration and hence the faster and greater
development of strength. Increase in fineness of cement is also found to increase
31
the drying shrinkage of concrete. Fineness of cement is tested either by sieving or
by determining the specific surface by the air permeability apparatus. Specific
surface is the total surface area of all the particles in one gram of cement.
Test Procedure:
1. By sieving
2. By determination of specific surface by air permeability apparatus.
Generally Blaine Air permeability apparatus is used. Expressed as cm²/gm or
m²/kg
By sieving method:
32
3.4 MIX DESIGN CALCULATION
Mix design is defined as the process of selecting suitable materials of concrete and
determining their relative proportions with the object of producing concrete of
certain minimum strength and durability as economically as possible. The design
of concrete mix requires the knowledge of material properties and properties of
concrete in plastic and hardened condition and also the experience of concreting.
In the hardened state, it should achieve the required strength, adequate durability
and minimal shrinkage to maintain dimensional stability.
The mix proportioning for a concrete of M25 grade is as follows (As per IS:
10262-2009)
Design of concrete Mix
33
Value for fine aggregate
34
Stipulation for Proportioning
Grade Designation M25
Types of cement Dalmia Cement (PPC)
Maximum
nominal
size of
aggregate 20mm
250 kg/m3 (from
Minimum Cement table 5 IS 456 2000)
content
Maximum water
cement
ratio(I.S.456:2000) 0.5
Medium (slump=75mm)
workability as per I.S.456:2000
Exposure
Condition Severe
Degree of
supervision: good
Crushed angular aggregate
Type of aggregate
Method of
concrete placing Hand
Maximum cement 450 kg/m3 (Cl 8.2.4.2 IS456
content 2000)
water absorption
of coarse aggregate 0.9% (Part 3, IS 2386:1983)
water absorption
of fine aggregate 1.55 % (Part 3, IS 2386:1983)
Seive Analysis
Coarse aggregate conforming to table 7; IS 383:2016
Fine aggregate conforming to grading Zone 3 of table 9; IS 383:2016
35
PROCEDURE FOR CONCRETE MIX DESIGN:
Target strength for mix proportioning:
f′ck = fck + 1.65×s
= 25 + 1.65×4 (s= standard deviation from table 2: IS
10262:2019)
= 31.6 N/mm2
Or f′ck = fck + X
= 25+5.5
= 30.5 N/mm2 (for X, table 2: IS 10262:2019)
The higher value is to be adopted. Therefore, the target strength will be 31.6
N/mm2
Trial:-1
36
cement ratio of 0.50 = 0.64
So the water-cement ration is less by 0.5-0.48=0.02
In the present case water-cement ratio is 0.48. So, it is increased by 0.02. For
decreased by 0.02, volume to be increased = (0.01÷ 0.05) × 0.02= 0.004
Therefore, the corrected proportion of the volume of coarse aggregate for the
water-cement ratio of 0.48= 0.64+0.004 = 0.644.
Volume of fine aggregate content = 1- 0.644= 0.356
Mix calculations:
The mix calculations per unit volume of concrete shall be as follows:
1) Total volume = 1 m3
2) Volume of entrapped air in wet concrete = 0.01 m3 [ IS 10262-2019 Table
3]
3) Volume of cement = (399.125 /3.15) × (1/1000) = 0.126m3
4) Volume of water = (191.58 /1) × (1/1000) = 0.191 m3
5) Volume of all in aggregate = 1- (0.126 + 0.191 + 0.01) = 0.673 m3
6) Mass of coarse aggregate = 0.673 × 0.644× 2.79 × 1000 = 1209.219 kg
7) Mass of fine aggregate = 0.673 × 0.356 × 2.62×1000 = 627.72kg
Table 3.6 Mix proportions of 0.48 w/c ratio
Volume of ingredients:
1. No. of cubes to cast = 2
2. Volume of 1 cube = 0.150 m× 0.150 m× 0.150 m = 0.003375 m3
3. Volume of 2 cubes = 0.003375×2 = 0.00675 m3
4. Adding 15% extra volume for losses
Total volume of 2 cubes =0.00675× 1.15 = 0.00776 m3
37
Weight of ingredients:
1) Amount of ingredients for the 2 cubes are,
2) Cement =0.00776×399.12 = 3.09 kg
3) Coarse aggregate =0.00776×1209.219 = 9.38 kg
4) Fine aggregate (sand) =0.00776×627.72 = 4.80.48 kg
5) Water = 0.48×399.125x0.00776 = 1.48 litre
Trial 2:
Selection of water-cement ratio:
38
decreased by 0.04, volume to be increased = (0.01÷ 0.05) × 0.04= 0.008
Therefore, the corrected proportion of the volume of coarse aggregate for the
water-cement ratio of 0.46= 0.64+0.008 = 0.648.
Volume of fine aggregate content = 1- 0.648= 0.352
Mix calculations:
The mix calculations per unit volume of concrete shall be as follows:
1) Total volume = 1 m3
2) Volume of entrapped air in wet concrete = 0.01 m3 [ IS 10262-2019
Table3]
3) Volume of cement = (416.47 /3.15) × (1/1000) = 0.132m3
4) Volume of water = (191.58 /1) × (1/1000) = 0.191 m3
5) Volume of all in aggregate = 1- (0.132 + 0.191 + 0.01) = 0.667 m3
6) Mass of coarse aggregate = 0.667 × 0.648× 2.79 × 1000 = 1205.882 kg
7) Mass of fine aggregate = 0.667 × 0.352 × 2.62×1000 = 615.13kg
Table 3.7 Mix proportions 0.46
Cement 416.47 kg/m3
Water 191.58 kg/m3
Coarse aggregate 1205.882 kg/m3
Fine aggregate 615.13kg/m3
Water-cement ratio 0.46
Proportion obtained 1:1.47:2.89:0.46
(cement: fine aggregate: coarse aggregate: water))
Volume of ingredients:
39
Weight of ingredients:
Amount of ingredients for the 2 cubes are,
1) Cement =0.00776×416.47 = 3.23 kg
2) Coarse aggregate =0.00776×1205.882 = 9.35 kg
3) Fine aggregate (sand) =0.00776×615.13 = 4.77 kg
4) Water = 0.46×416.47x0.00776 = 1.46 litre
Trial 3:
40
water-cement ratio of 0.47= 0.64+0.006 = 0.646.
Volume of fine aggregate content = 1- 0.646= 0.354
Mix calculations:
1) Total volume = 1 m3
2) Volume of entrapped air in wet concrete = 0.01 m3 [ IS 10262-2019 Table
3]
3) Volume of cement = (407.61/3.15) × (1/1000) = 0.129 m3
4) Volume of water = (191.58 /1) × (1/1000) = 0.191 m3
5) Volume of all in aggregate = 1- (0.129 + 0.191 + 0.01) = 0.670 m3
6) Mass of coarse aggregate = 0.670 × 0.646× 2.79 × 1000 = 1207.5678 kg
7) Mass of fine aggregate = 0.670× 0.354 × 2.62×1000 = 621.411 kg
Table 3.8 Mix proportions 0.47
Cement 407.61kg/m3
Water 191.58 kg/m3
Coarse aggregate 1207.5678 kg/m3
Fine aggregate 621.411 kg/m3
Water-cement ratio 0.47
Proportion obtained 1:1.525:2.93:0.47
(cement: fine aggregate: coarse aggregate: water))
Volume of ingredients:
1) No. of cubes to cast = 2
2) Volume of 1 cube = 0.150 m× 0.150 m× 0.150 m = 0.003375 m3
3) Volume of 2 cubes = 0.003375×2 = 0.00675 m3
4) Adding 15% extra volume for losses
Total volume of 2 cubes =0.00675 × 1.15 = 0.00776 m3
Weight of ingredients:
Amount of ingredients for the 2 cubes are,
1) Cement =0.00776×407.61 = 3.16 kg
2) Coarse aggregate =0.00776×1207.5678.219 = 9.37 kg
3) Fine aggregate (sand) =0.00776×621.411 = 4.822 kg
4) Water = 0.47×407.61x0.00776 = 1.45 litre
41
Table 3.9: Compressive strength for different water/cement ratio
After testing the samples of the above-mentioned W/Cs for compressive strength
at 7 days and 28 days, it has been found that the concrete blocks with W/C= 0.46
have passed the compressive strength test successfully. So, for further
experimental works, we have considered the W/C= 0.46
42
TRIAL 1 :
FOR 0.8% REPLACEMENT OF CEMENT WITH BANANA PEEL ASH
Mix calculations:
The mix calculations per unit volume of concrete shall be as follows:
1) Total volume = 1 m3
2) Volume of entrapped air in wet concrete = 0.01 m3 [ IS 10262-2019 Table 3]
Volume of ingredients:
1) No. of cubes to cast = 2
2) Volume of 1 cube = 0.150 m× 0.150 m× 0.150 m = 0.003375 m3
3) Volume of 2 cubes = 0.003375×2 = 0.00675 m3
4) Adding 15% extra volume for losses
5) Total volume of 2 cubes =0.00675 × 1.15 = 0.00776 m3
Weight of ingredients:
Amount of ingredients for the 2 cubes are,
1) Cement =0.00776×404.35 = 3.21 kg
43
2) Banana Peel Ash=0.00776x3.33= 0.026 kg
3) Coarse aggregate =0.00776×1204.07 = 9.34 kg
4) Fine aggregate (sand) =0.00776×617.701 = 4.766 kg
5) Water = 0.46×404.35.61x0.00776 = 1.45 litre
TRIAL 2 :
FOR 1% REPLACEMENT OF CEMENT WITH BANANA PEEL ASH
Mix calculations:
The mix calculations per unit volume of concrete shall be as follows:
1) Total volume = 1 m3
2) Volume of entrapped air in wet concrete = 0.01 m3 [ IS 10262-2019 Table 3]
44
Volume of ingredients:
1) No. of cubes to cast = 2
2) Volume of 1 cube = 0.150 m× 0.150 m× 0.150 m = 0.003375 m3
3) Volume of 2 cubes = 0.003375×2 = 0.00675 m3
4) Adding 15% extra volume for losses
5) Total volume of 2 cubes =0.00675 × 1.15 = 0.00776 m3
Weight of ingredients:
Amount of ingredients for the 2 cubes are,
1) Cement =0.00776×412.3 = 3.19 kg
2) Banana Peel Ash=0.00776 x 4.16= 0.0322 kg
3) Coarse aggregate =0.00776×1202.2678 = 9.33 kg
4) Fine aggregate (sand) =0.00776×613.289= 4.822 kg
5) Water = 0.46 × 412.3 x 0.00776 = 1.47 litre
TRIAL 3 :
FOR 2% REPLACEMENT OF CEMENT WITH BANANA PEEL ASH
Mix calculations:
The mix calculations per unit volume of concrete shall be as follows:
1) Total volume = 1 m3
2) Volume of entrapped air in wet concrete = 0.01 m3 [ IS 10262-2019 Table
3]
3) Volume of cement = (408.1406/3.15) × (1/1000) = 0.1295 m3
4) Volume of Banana Peel Ash =(8.3294/1.95) × (1/1000) = 0.00427 m3
5) Volume of water = (191.58 /1) × (1/1000) = 0.191 m3
6) Volume of all in aggregate = 1- (0.129 + 0.191 +0.00427+ 0.01) = 0.6657
m3
7) Mass of coarse aggregate = 0.6657 × 0.648× 2.79 × 1000 = 1203.5378 kg
8) Mass of fine aggregate = 0.6657× 0.352 × 2.62×1000 = 613.811 kg
45
Table 3.8 (c) Mix proportions 0.46 with 2% replacement
Cement 408.1406 kg/m3
Banana peel Ash 8.3294 kg/m3
Water 191.58 kg/m3
Coarse aggregate 1203.5378 kg/m3
Fine aggregate 613.935 kg/m3
Water-cement ratio 0.46
Proportion obtained 1:0.0228:1.504:2.95
(cement:Banana peel ash: fine aggregate: coarse
aggregate)
Volume of ingredients:
1) No. of cubes to cast = 2
2) Volume of 1 cube = 0.150 m× 0.150 m× 0.150 m = 0.003375 m3
3) Volume of 2 cubes = 0.003375×2 = 0.00675 m3
4) Adding 15% extra volume for losses
5) Total volume of 2 cubes =0.00675 × 1.15 = 0.00776 m3
Weight of ingredients:
Amount of ingredients for the 2 cubes are,
1) Cement =0.00776×408.1406 = 3.167 kg
2) Banana Peel Ash=0.00776x8.3294 = 0.0646 kg
3) Coarse aggregate =0.00776×1203.5378 = 9.33 kg
4) Fine aggregate (sand) =0.00776×613.935 = 4.76 kg
5) Water = 0.46×408.1406x0.00776 = 1.456 litre
TRIAL 4 :
FOR 3% REPLACEMENT OF CEMENT WITH BANANA PEEL ASH
Mix calculations:
The mix calculations per unit volume of concrete shall be as follows:
9) Total volume = 1 m3
10) Volume of entrapped air in wet concrete = 0.01 m3 [ IS 10262-2019 Table 3]
46
14) Volume of all in aggregate = 1- (0.128 + 0.191 +0.006405+ 0.01) = 0.6645
m3
15) Mass of coarse aggregate = 0.6645 × 0.648× 2.79 × 1000 = 1201.3628 kg
16) Mass of fine aggregate = 0.6645× 0.352 × 2.62×1000 = 612.82 kg
Volume of ingredients:
1) No. of cubes to cast = 2
2) Volume of 1 cube = 0.150 m× 0.150 m× 0.150 m = 0.003375 m3
3) Volume of 2 cubes = 0.003375×2 = 0.00675 m3
4) Adding 15% extra volume for losses
5) Total volume of 2 cubes =0.00675 × 1.15 = 0.00776 m3
Weight of ingredients:
Amount of ingredients for the 2 cubes are,
1) Cement =0.00776×403.98 = 3.07 kg
2) Banana Peel Ash=0.00776x12.49= 0.095 kg
3) Coarse aggregate =0.00776×1201.3628 = 9.13 kg
4) Fine aggregate (sand) =0.00776×621.411 = 4.722 kg
5) Water = 0.47×407.61x0.00776 =1.442
47
Table 3.10 Concrete Mix Proportion Weightage
PARTICULARS AMOUNT
(Partially only Cement is Replacement % amount (Kg)
replaced by BPA, rest are 0% 0.8% 1% 2% 3%
same)
48
3.5 EXPERIMENTAL WORK
3.5.1 Slump Test
Procedure to determine workability of fresh concrete by slump test
1) The internal surface of the mould was cleaned and oil was applied.
2) Placed the mould on a smooth horizontal non- porous base plate.
3) Filled the mould with the prepared concrete mix in 4 approximately equal
layers.
4) Tamped each layer with 25 strokes of the rounded end of the tamping rod
in a uniform manner over the cross section of the mould. For the
subsequent layers, the tamping should penetrate into the underlying
layer.
5) Removed the excess concrete and level the surface with a trowel.
6) Cleaned away the mortar or water leaked out between the
mould and the base plate.
7) Raised the mould from the concrete immediately and slowly in vertical
direction.
49
Fig 3.22: Slump Test
50
3.5.2 Casting
1) The mould was cleaned and oil was applied.
2) The mould was filled with concrete in 3 layers.
3) Compacting each layer with not less than 35 strokes per layer
using a tamping rod (steel bar 16mm diameter and 60cm long,
bullet pointed at lower end)
5) After 24 hours the specimen was removed from the mould and
submerged it into fresh and clean water until time of testing.
51
3.5.3 Curing
As all over the world concrete is accessed by its compressive strength so curing of
concrete cube in a proper manner having great importance. Concrete cube can be
cured in a following manner:
1) Leave the test specimens in the mould for at least 16 h, but not longer than
three days, from the time of addition of water to the dry ingredients. Protect
the specimens from shock, vibration and water evaporation. Store the
specimens at a temperature of 27 ± 3 o c.
2) After removal from the mould, submerge the test specimens in clean, fresh
water immediately. Store the test specimens in water at a temperature of
27±20C and take it out just prior to testing. Alternately, store the test
specimens in a chamber at a temperature of 27 ± 20 C and a relative
humidity of at least 95 percent until just before testing.
3) If the test specimens are to be sent to a test laboratory, cover the test
specimens with wet cloth or wet sand/ sawdust or other suitable material
or seal the test specimens in plastic bags containing water to ensure that
the test specimens are delivered to the test laboratory in damp condition not
less than 24 h before the time of testing. At the test laboratory, store the test
specimens in water at a temperature of 27 ± 20C until taking it out just prior
to testing.
52
3.5.4 Compression Test
53
Fig 3.24: Compression testing machine
54
CHAPTER 4
TEST RESULTS
4.1 DETERMINATION OF
(A) Gradation of Coarse Aggregate
[As per IS 383-2016]
40 0 0 0 100 100
PAN 0.063 5
55
(B) Zone of fine aggregate
Table 4.2 Zoning Of Fine aggregate
[ As Per IS 383:1970]
56
4.2 RESULT OF SPECIFIC GRAVITY
(A) For Coarse Aggregates
Table 4.3: Specific gravity of Coarse Aggregates
[As per IS:2386(Part-3):1963]
57
(B) For fine aggregate (sand)
Table 4.4: Specific Gravity of Fine Aggregates
[As per IS:2386(Part-3):1963]
58
(C) For Banana Peel Ashes
Table 4.5: Specific Gravity of Banana Peel Ash
[As per IS:2386(Part-3):1963]
59
4.3 RESULTS FOR IMPACT VAUE TEST
FOR COARSE AGGREGATE:
[As per IS 2386 (Part 4) – 1963
Table No.: 4.6 impact value coarse aggregate
1 Total weight of 1 2
aggregate sample filling
the cylinder measure = 326 317
A gm
2 Weight of 49 55
aggregate passing
through 2.36 mm is sieve
after the test
= B gm
60
4.4 RESULTS FOR AGGREGATE CRUSHING TEST
FOR COARSE AGGREGATE
[As Per IS : 2386 ( Part IV) – 1963, IS: 383-1970]
Table No.: 4.7 Crushing value of coarse aggregate
Result : As Per IS : 2386 ( Part IV) – 1963, IS: 383-1970 Crushing strength of
aggregate is 18.53%.
61
4.5 RESULT FOR CEMENT TESTING
(A) FINENSS TEST OF CEMENT
(As per IS: 4031 (Part 1) – 1988)
Table no. 4.8 fineness of cement value
7.95+8.25
Average fineness of cement = 2
= 8.1%
Result:- The standard value of the fineness of cement should have a fineness of
less than 10 % or fineness of cement should not be more than 10% as per IS
Recommendations.
62
(B) CONSISTENCY OF CEMENT
[As per IS: 4031 (Part 4) - 1988, IS: 5513-1976]
Table no. 4.9 Normal consistency of cement value
Result: -
1. Initial setting time of cement is for the given sample is found to be 45 min
2. Final setting time of cement is for the given sample is found to be 5 hour
45 min
63
4.6 FOR AMOUNT OF W/C, FA, CA, BANANA PEEL ASHES
AND WATER
Table 4.11
64
4.7 COMPRESSIVE STRENGTH
4.7.1 Replacement of cement with Banana Peel Ashes
23 22.83
22.67
22.5 22.3
22
21.77
21.5
21
0% 0.80% 1% 2% 3%
65
Table 4.13: Compressive strength values at 28 days
% of Days Area(mm Weight Compre Compressive
2)
replaceme ssive
(kg) Strength(N/mm
nt load(K 2
)
N)
0 28 150x150 8.227 687.7 30.55
33 32.51
32.5 32.17
32 31.46
31.5
31 30.55
30.5
30
29.5
29
0% 0.80% 1% 2% 3%
percentage of replacement of cement with Banana peel ashes
66
4.7.2 COMPARISON OF COMPRESSIVE STRENGTH AT 0%
REPLACEMENT (STANDARD M25 CONCRETE)
The Compressive Strength for the standard M25 Graded concrete mix at 0%
replacement is found to be 21.77 N/mm2 at 7 days, 30.55 N/mm2 at 28 days.
Hence it can be said that the strength of the specimen has increased significantly
over time. From the above graphical representation, it is possible to observe that
the amount of strength gained by the standard concrete mix in 7th and 28th day
after casting.
30
25
21.77
20
15
10
0
7 days 28 days
Age (days)
67
4.7.3 COMPARISON OF COMPRESSIVE STRENGTH AT 0.8%
REPLACEMENT OF CEMENT WITH BPA
(STANDARD M25 CONCRETE)
The Compressive Strength for the standard M25 Graded concrete mix at 0.8%
replacement is found to be 22.33 N/mm-2 at 7 days, 31.46 N/mm2 at 28 days. Hence
it can be said that the strength of the specimen has increased significantly over time.
From the above graphical representation, it is possible to observe that the amount
of strength gained by the standard concrete mix in 7th and 28th day after casting.
Table 4.15 Compressive Strength of M25 Grade Standard Concrete with 0.8%
BPA
30
25 22.33
20
15
10
5
0
7 days 28 days
Age (days)
68
4.7.4 COMPARISON OF COMPRESSIVE STRENGTH AT 1%
REPLACEMENT OF CEMENT WITH BPA
(STANDARD M25 CONCRETE)
The Compressive Strength for the standard M25 Graded concrete mix at 1 %
replacement is found to be 22.67 N/mm-2 at 7 days, 32.17 N/mm2 at 28 days. Hence
it can be said that the strength of the specimen has increased significantly over time.
From the above graphical representation, it is possible to observe that the amount
of strength gained by the standard concrete mix in 7th and 28th day after casting.
Table 4.16 Compressive Strength of M25 Grade Standard Concrete with 1%
BPA
30
25 22.67
20
15
10
0
7 days 28 days
Age (days)
69
4.7.5 COMPARISON OF COMPRESSIVE STRENGTH AT 2%
REPLACEMENT OF CEMENT WITH BPA
(STANDARD M25 CONCRETE)
The Compressive Strength for the standard M25 Graded concrete mix at 2%
replacement is found to be 23.2 N/mm-2 at 7 days, 33.67 N/mm2 at 28 days. Hence
it can be said that the strength of the specimen has increased significantly over time.
From the above graphical representation, it is possible to observe that the amount
of strength gained by the standard concrete mix in 7th and 28th day after casting.
25 23.2
20
15
10
0
7 days 28 days
Age (days)
70
4.7.6 COMPARISON OF COMPRESSIVE STRENGTH AT 3%
REPLACEMENT OF CEMENT WITH BPA
(STANDARD M25 CONCRETE)
The Compressive Strength for the standard M25 Graded concrete mix at 3%
replacement is found to be 22.83 N/mm-2 at 7 days, 32.51 N/mm2 at 28 days. Hence
it can be said that the strength of the specimen has increased significantly over time.
From the above graphical representation, it is possible to observe that the amount
of strength gained by the standard concrete mix in 7th and 28th day after casting.
30
compressive strength (N/mm2)
25 22.83
20
15
10
0
7 days 28 days
Age (days)
71
4.7.7 ANALYSIS OF COMPRESSIVE STRENGTH OF CONCRETE AT
THE END OF DAY 7 and 28:
By plotting the compressive strength of 28 days aged cube with various
replacement percentages, we got the following graphical representation graph.
35
30 21.7 22.33 22.67 23.2 22.83
25
20
15
10
5
0
0% 0.80% 1% 2% 3%
7days 21.7 22.33 22.67 23.2 22.83
28 days 30.55 31.46 32.17 33.67 32.51
Percentage of cement replace with banana peel ash
7days 28 days
23.2
21.7
7days 28days
0% BPA 21.7 30.55
0.80% BPA 22.33 31.46
1% BPA 22.67 32.17
2% BPA 23.2 33.67
3% BPA 22.83 32.51
TIME (DAYS)
72
percentage of compressive strength
percentage of compressive strength increment
12% 10.21%
10%
8% 6.42%
5.30% 6.90%
6%
5.20%
4% 2.90% 4.47%
2.70%
2%
0%
0% 0%
0% 0.80% 1% 2% 3%
Compressive strength 28
0% 2.90% 5.30% 10.21% 6.42%
days
Compressive strength at 7
0% 2.70% 4.47% 6.90% 5.20%
days
percentage of replaced cement with BPA
The compression test results are shown in above fig. From the following graphical
representation, it is observed that the maximum result or maximum compressive
strength is obtained at 2% of Banana peel Ash replacement in concrete. The 28
days compressive strength for conventional M25 grade concrete is found 30.55
N/mm2 and that for 2% Banana Peel ash concrete is 33.67 N/mm2 . It shows the
10.21% improvement from conventional concrete. Thus, optimum use of Banana
Peel ash is 2%. Again, it is also observed from the graphical representation that at
1% banana peel ash replacement the strength improvement is 5.30% and at 3%
banana peel ash replacement the compressive strength changes it falls down from
10.21% to 6.42%.
73
4.8 SAVING OF CEMENT
Table 4.19
0 0
0.8 3.33
1 4.16
2 8.323
3 12.494
12
Amount of cement Saved
10
8.323
8
6
4.16
4 3.33
2
0
0
0% 0.80% 1% 2% 3%
percentage of replacement of cement with banana peel ashes
74
CHAPTER-5
CONCLUSION
5.1 CONCLUSION
The partial replacement of cement with banana peel ash represents an innovative
and sustainable approach in the construction industry, addressing both
environmental concerns and resource utilization. Banana peel ash, derived from the
combustion of banana peels, is an eco-friendly alternative that minimizes waste by
re-purposing a readily available organic material. In this comprehensive study on
cement replacement in concrete, we systematically explored various substitution of
varying percentages 0%,0.8%,1%,2%,3%. The primary objective was to assess the
impact of these replacements on the compressive strength and workability of the
resulting concrete mix. The compressive strength tests were carried out for 7 and
28 days on blocks with conventional mix design and varying replacement
percentages (0.8%, 1%, 2%, 3%). The results indicated a noticeable increase in
compressive strength with very minimal impact on workability.Interestingly, our
research uncovered that a 2% substitution of cement yielded the highest
compressive strength among all examined compositions. There was a slight
decrease in compressive strength when incorporating a 3% replacement of cement
with banana peel ash.
In this study, the effect of partial replacement of cement by Banana peel Ash has
been studied at a smaller scale. However, with some modifications, it may become
applicable for large scale construction work. As we have seen in this study that the
compressive strength increases at 2% replacement of cement by Banana Peel Ash
further researches can also be done .
Further research can focus on determining the different percentages of
banana peel ash in concrete to achieve the desired results for workability,
and cost-effectiveness
Extensive testing and analysis can be conducted to explore the effects of
75
different Banana peel ash percentages on various concrete properties and
performance.
Further research can focus on the practical application and field studies of
Banana Peel Ash based concrete in real construction projects.
76
REFERENCE
[1] IS 2386 (Part 3) – 1963 “Methods of Test for Aggregates for Concrete,
Part 3: Specific Gravity, Density, Voids, Absorption and Bulking.”
[2] 383-1970 “Indian Standard Specification for Coarse and Fine aggregate
from natural sources for concrete. “
[3] IS 4031 (Part 1) – 1988 “Indian Standard: Methods of physical tests for
hydraulic cement, Part 1: Determination of fineness by dry sieving.”
[4] IS 456-2000, “Plain and Reinforced concrete code of practice”, Bureau of
Indian Standards, New Delhi.
[4] B. Lothenbach, F. Winnefeld / Cement and Concrete Research 36 (2006)
209 – 226.
[5] IS 10262-2009, “Concrete mix proportioning guidelines “, Bureau of
Indian Standards, New Delhi.
[6] “Strength performance of banana fiber ash as cementitious material with
different temperature” Report by Nur Aqilah Bt. Abd Karim (2014)
[7] IS 383-2016, “Coarse and Fine aggregate for concrete-specification”,
Bureau of Indian Standards, New Delhi.
[8] Gadgihalli et. al., Vol 5;Nov 2017 “Analysis of properties of concrete
using dried banana peel powder as admixture”
[9] “Exploring the Potentials of Banana (Musa Sapietum) Peels in Feed
Formulation”International Journal of Advanced Research in Chemical Science
(IJARCS).Volume 5, Issue 5, 2018)
[10] R. S. Ranjani, et al. (2018). “Performance Evaluation of Banana Peel
Ash Blended Cement Concrete.” Materials Today: Proceedings, 5(1), 2392-
2397.
[11] Research Journal of Chemistry and Environment,Vol. 22(Special Issue
II) August (2018)Res. J. Chem. Environ.
[12] Anand & N. Tharunkumar / International Research Journal of
Multidisciplinary Technovation /2019, 1(6), 526-531
[13] S. S. Abideen et al. (2019). “Banana Peel Ash as a Supplementary
Cementitious Material in Concrete.” Construction and Building Materials,
204, 537-548.
[14] A. K. Jain et al. (2020). “Utilization of Banana Peel Ash as a Partial
Replacement of Cement in Concrete.” Journal of Cleaner Production, 266,
121980.
[15] Nura Muhammad Apr. (2022)”The effect of banana peel ash on the
properties of concrete”.INTERNATIONAL JOURNAL OF INNOVATIONS
IN ENGINEERING RESEARCH AND TECHNOLOGY,[IJIERT] ISSN:
2394-3696,ijiert.org VOLUME 9, ISSUE 4
[16] Kilani, A., Olubambi, A., Ikotun, B., Adeleke, O., & Adetayo, O. (2022).
Structural performance of concrete reinforced with banana and orange peel
fibers - a review. J Sustain Const Mater Technol, 7(4), 339–357
[17] Hassan Pyar et al.(2018). “Chemical Compositions of Banana Peels Fruits
cultivated in Malaysia using proximate analysis”. Research Journal of
Chemistry and Environment, Vol. 22(Special Issue II).
[18] A. B., Hassan, H. F. , Ibrahim, O. A. and Tabe, U. F. , Usher, , N. N.
(2018). “Exploring the Potentials of Banana Peels in Feed Formulation”.
International Journal of Advanced Research in Chemical Science (IJARCS)
Volume 5, Issue 5, 2018, PP 10-14.