13/08/2023

Construction of Masdar Big Square -Roads, Utilities and Public Ream Packages 1A & 1B
Hardscape Work Progress 01-Aug-23 to 10-Aug-23

01-Aug-23

02-Aug-23

03-Aug-23

04-Aug-23

05-Aug-23

06-Aug-23

07-Aug-23

08-Aug-23

09-Aug-23

10-Aug-23
Total Cummulative Remaining Avg. Daily
List of Activities Unit
Scope Actual Quantity Productivity

Hardscape Work

Laying of Kerbstones LM 31,720 9,633 21,877 97 130 0 20 65 100 20 360 60 210

Laying of Paving Tiles SM 92,013 12,957 78,836 64 20 0 0 150 80 0 140 30 220

Cycle Track

Laying of Kerbstones LM 5,591 5,591 0 0 0 0 0 0 0 0 0 0

Z:\11-PLANNING\Big Square,LRT & Street Scape\Project Control Files\Management Req\PM Files\PLC Progress.xlsx 1