Professional Documents
Culture Documents
Standard Costing With Solutions
Standard Costing With Solutions
MCV = Rs.2,225(A)
(3) Material Usage Variance = (St. Qty –Actual Qty.) x St. Price
(4) Material Mix Variance = (Revised St. Qty –Actual Qty.) x St.
Price
Ques 2:
For making 10 kg. of yarn, the Quantity (kg.) Rate per kg. (Rs.)
standard material requirement is:
Material
White 8 6.00
Black 4 4.00
In March, 1,000 kg. of yarn was Quantity (kg.) Rate per kg. (Rs.)
produced. The actual consumption
of materials is as under: Material
White 750 7.00
Black 500 5.00
Calculate: (1) MCV (2) MPV (3) MUV
Solution:
Particular Standard for 1000 kgs. Actual for 1000 kgs.
Quantity Rate Amount Quantity Rate Amount
A 800 6 4,800 750 7 5,250
B 400 4 1,600 500 5 2,500
Total 1,200 6,400 1,250 7,750
(1) MCV: SC ‐ AC
= 6,400 ‐ 7,750 = Rs. 1,350 (A)
(2) MPV: (SP ‐ AP) x AQ
A = (6 ‐ 7) x 750 = Rs. 750 (A)
B = (4 ‐5) x 500 = Rs. 500 (A)
= 1,250(A)
(3) MUV: (SQ ‐ AQ) x SP
A = (800 ‐ 750) x 6 = Rs. 300 (F)
B = (400 ‐ 500) x 4 = Rs. 400 (A)
= Rs. 100 (A)
Question 3: A manufacturing concern which has adopted standard costing furnishes following
information:
Standard Material for 70 kg of Finished Products 100 kg
Price of Materials ` 1 per Kg
Actual: Output 2,10,000 Kg
Materials used 2,80,000 Kg
Cost of materials ` 2,52,000
Calculate (a) Material Usage Variance (b) Material Price Variance (c) Material Cost Variance.
Solution:
Data for Material Variance (2,10,000 kg)
Standard (Output 2,10,000 kg) Actual (Output 2,10,000 kg)
Qty. Rate Amount (`) Qty. Rate Amount (`)
3,00,000 kg 1 3,00,000 2,80,000 0.90 2,52,000
Statement of Variance
Sl. No. Particulars Basis Amount (`)
1. Material Usage Variance (Std.Qty. – A.Qty.) × S.P. 20,000 Favourable
(3,00,000 – 2,80,000) × 1
2. Material Price Variance (S.P. – A.P.) × A.S. 28,000 Favourable
(1 – 0.90) × 2,80,000
3. Material Cost Variance (Material Usage + Material Price 48,000 Favourable
Variance) i.e. SC–AC
Question 4: From the data given below, calculate the material price variance, the materials usage variance and
material cost variance.
Consumption per 100 Units of Product
Raw material Standard Actual
A 40 units @ ` 50 per unit 50 units @ ` 50 per unit
B 60 units @ ` 40 per unit 60 unit @ `45 per unit
-------------------------------------------------------------------------------------------------------------------------------------------------------
Question 6: Vinak Ltd. produces an article by blending two basic raw materials. It operates a standard costing
system and the following standards have been set for raw materials:
Material Standard Mix Standard Price per kg
A 40% `4.00
B 60%
` 3.00
The standard loss in processing is 15%. During April, 1980, the company produced 1,700 kg of finished output.
The position stock and purchases for the month of April, 1980 is as under:
Material Stock on 1.4.80 of kg Stock on 30.4.80 kg Purchased during April 1980
kg Cost (`)
A 35 5 800 3,400
B 40 50 1,200 3,000
Question 7: 1 kg of product ‘K’ requires two chemicals ‘A’ and ‘B’. The following were the details of product ‘K’
for the month of June 1987:
1. Standard mix Chemical ‘A’ 50% and Chemical ‘B’ 50%.
2. Standard price per kilogram of Chemical ‘A’ ` 12 and Chemical ‘B’ ` 15.
3. Actual input of Chemical ‘B’ 70 kilograms.
4. Actual price per kilogram of Chemical ‘A’ ` 15.
5. Standard normal loss 10% of total input.
6. Materials cost variance total ` 650 adverse.
7. Materials yield variance total `` 135 adverse.
Required: Calculate:
Material mix variance total
Material usage variance total
Material price variance total
Actual loss of actual input
Actual input of Chemical ‘A’
Actual price per kilogram of Chemical ‘B’
Solution:
Data for Material Variance
Standard Actual
Material Qty. Rate Amount Standard Qty. (kg) Rate Amount
(kg) (`/kg) Ratio for (`/kg)
(`) (`)
Actual Mix
A 50 12 600 55 40 15 600
B 50 15 750 55 70 20 1,400 (B.f.)
Statement of Requirement
1. Material Mix Variance= (Standard Ratio for Actual Mix – Actual Ratio for Actual Mix) ×
Standard Rate
= (55 – 40) × 12 + (55 – 70) × 15
= (15 × 12) + (–15 × 15)
= – 15 × 3 = – 45
= 45 (A)
2. Material Usage Variance= (S.Q. – A.Q.) × S.R.
= (50 – 40) × 12 + (50 – 70) × 15
= 180 (A)
3. Material Price Variance= (S.R. – A.R.) × A.Q.
=(12 – 15 ) X 40 + (15 – 20) X 70
= 470 (A)
4. Actual Loss = (110 – 90) = ` 20/kg
5. Actual Input of Chemical A = 110 – 70 = ` 40/kg
6. Actual Price per Kg of Chemical B = ` 1,400/70 = ` 20/ kg
Working Notes:
. M.C.V = S.C. – A.C.
- 650 = 1,350 – A.C.
Actual Cost = 1,350 + 650 = 2,000
2. Material Yield Variance = (Total Standard Quantity – Total Actual Quantity) × Standard Weighted
Avg. Rate
-135 = (100 – T.A.Q) X 1,350/100
- 13,500
1,350 = 100 – T.A.Q.
- 10 = 100 – T.A.Q.
Total Actual Quality = 100 + 10
= 110 kg
-------------------------------------------------------------------------------------------------------------------
Question 8: The following information is provided.
Standard Wages: Grade X: 90 Labourers at ` 2 per hour
Grade Y: 60 Labourers at ` 3 per hour
Actual Wages: Grade X: 80 Labourers at ` 2.50 per hour
Grade Y: 70 Labourers at ` 2.00 per hour
Budgeted Hours 1,000; Actual Hours 900; Budgeted Gross Production 5,000 units;
Standard loss 20%; Actual Loss 900 units.
Required: Calculate the labour variances from the above information.
Working Notes:
1. Calculation of Net Production
Budgeted (Units) Actual (Units)
Gross Production 5,000 5,000
(–) Loss (Normal) 1,000 9,00
(20% of 5,000)
Net Production 4,000 4,100
We should assume that Budgeted gross & actual gross production will be same.
2. Calculation of Revised Budgeted Hrs.
X: 4,000 F.G. = 90,000 Labour Hrs.
1 F.G 90,000 LAbour Hrs.
4,000
4100 F.G. = 90,000
4,000 X 4,100 Labour Hr.
= 92,250 Labour Hrs.
Y: 4,000 F.G. = 60,000 Labour Hrs.
1 F.G 60,000 LAbour Hrs.
4,000
4100 F.G = 60,000 X 4,100 Labour HRs.
4,000
= 61,500 Labour Hrs
-------------------------------------------------------------------------------------------------------------------------------------------------------
Question 9: A gang of workers usually consists of 10 men, 5 women and 5 boys in a factory. They are paid at
standard hourly rates of ` 1, ` 2 and ` 3, respectively. In a normal working week of 40 hours the gang is expected
to produce 1,000 units of output.
In a certain week, the gang consisted of 13 men, 4 women and 3 boys. Actual wages were paid at the rates of ` 3,
` 4 and ` 5, respectively. Two hours were lost due to abnormal idle time and 960 units of output were produced.
Calculate various labour variances.
Solution: Data for Labour Variance
Budgeted (1000) Revised Budgeted (960) Actual (960) Actual Working
Hours
Lab Hr. Rate Amount Lab Hr. Rate Amount Lab Hr. Rate Amount
(` ) (` ) (` )
Men 400 1 400 384 1 384 520 3 1,560 494
Women 200 2 400 192 2 384 160 4 640 152
600 576 600
Boys 200 3 1,400 192 3 1,344 120 5 2,800 114
-------------------------------------------------------------------------------------------------------------------------------------------------------
Question 10: The details regarding the composition and the weekly wage rates of labour force engaged on a
job scheduled to be completed in 30 weeks are as follows:
Standard Actual
Category or No. of Labourers Weekly wage rate No. of Weekly wage rate
Workers per Labourer (`) Labourers per Labourer (`)
Skilled 75 60 70 70
Semi-skilled 45 40 30 50
Unskilled 60 30 80 20
The work is actually completed in 32 weeks.
Required: Calculate the various labour variances.
4. Labour mix (S. Ratio for Actual Mix – Actual Ratio for Actual Mix) × S.R.
variance Skilled: (2,400 – 2,240) × 60 = 9,600 (F)
Semi-Skilled: (1,440 – 960) × 40 = 19,200 (F)
Unskilled: (1,920 – 2,560) × 30 = 19,200 (A) 9,600 (F)
5. Labour (Standard Ratio for Standard Quantity – Standard Ratio for Actual Quantity) × S.R.
yield Skilled: (2,250 – 2,400) × 60 = 9000(A)
variance Semi-Skilled: (1350 – 1440) × 40 = 3600(A) 16,200 (A)
Unskilled: (1800 – 1920) × 30 = 3600(A)
Ques 11:
Standard labour hours and rate Rate per Hour Total (Rs.)
for production of one unit of
Article P is given below: Per Unit
Hour
Solution:
Labour cost variance = (SH for actual production x SR) ‐‐‐ (AH x AR)
Skilled worker = (5,000 x 1.50) ‐‐‐ (4,500 x 2 )
= 7,500 – 9,000
= Rs. 1,500 (Adverse)
Unskilled worker = (8,000 x 0.50) ‐‐‐ (10,000 x 0.45)
= 4,000 ‐‐‐ 4,500
= Rs. 500 (Adverse)
Semi‐ skilled worker = (4,000 x 0.75) ‐‐‐ (4,200 x 0.75)
= 3,000 ‐‐‐ 3,150
= Rs. 150 (Adverse)
Total Labour cost variance = Rs. 2,150(Adverse)
Ques 12:
India Ltd. Manufactures a Hours Rate (Rs.) Amount (Rs.)
particular product, the standard
direct labour cost of which is Rs.
120 per unit whose
manufacture involves the
following: Type of workers
A 30 2 60
B 20 3 60
50 120
During a period, 100 units of the product were produced, the actual labour cost of
which was as follows:
Solution:
Type of Worker Standard for 100 units Actual for 100 units
Hours Rate Amount Hours Rate Amount
A 3,000 2 6,000 3,200 1.50 4,800
B 2,000 3 6,000 1,900 4.00 7,600
Total 5,000 12,000 5,100 12,400