Professional Documents
Culture Documents
Particular Conditions (Yellow Book)
Particular Conditions (Yellow Book)
For the Conditions of Contract for Design & Construction of the Woodbrook
Presbyterian Primary School.
1.0 DEFINITIONS
1.1.1.1 "Contract"
Delete this definition and replace with the following:
"Contract" means the Contract Agreement, the Letter of Acceptance,
the Letter of Tender, the Letter of Invitation to Tender, the Conditions
of Contract, the Bills of Quantities and all amendments thereto via
addenda, the Drawings, the Specifications, and any other documents, if
any, which are listed in the Contract Agreement or the Letter of
Acceptance".
1.1.1.9 Delete this sub sub-clause and replace with the following: "Appendix
to Tender" means the completed pages entitled Appendix to Form of
Contract appended to the Conditions of Contract in the Bills of
Quantities and also annexed to the Particular Conditions."
Page 1 of 25
1.8 Care and Supply of Documents:
Insert the following after the last paragraph of this sub-clause
"The contractor shall at all times maintain accurate records in a form
acceptable to the Engineer. Such records shall identify the depth and
location of footings and foundations, the position and routing of all
services internally and externally, whether or not same was executed
by the Contractor's personnel or others, all variations to the original
design and shall deliver in duplicate fully detailed "as-built” drawings
to the Engineer no later than seven (7) days after the completion of the
section of the work or of the particular installation."
Page 2 of 25
1.15 Details to be Confidential
Add the following Sub-Clause immediately after Sub-Clause 1.14.
"1.15 Details to be Confidential.
The Contractor shall treat the details of the Contract as private and
confidential except to the extent necessary to carry out obligations
under it or to comply with applicable Laws."
2.0 EMPLOYER
2.2 Permits, Licences and Approvals
Delete the first sentence of this Sub-Clause and replace with the
following:
"The Employer shall (where it is in a position to do so) provide
reasonable assistance to the Contractor at the request and cost of the
Contractor."
3.0 ENGINEER
3.1 Engineer's Duty and Authority
Delete the last sentence of the third paragraph of Sub-Clause 3.1 and
replace with the following:
"The Employer reserves the right to vary the Engineer's authority at
any time Provided that any such variation shall be made in writing and
shall not take effect until a copy thereof has been received by the
Contractor."
Insert the following at the end of the last paragraph of this sub- clause:
"The Engineer shall obtain the specific approval of the Employer in
writing before taking any of the following actions:
Page 3 of 25
(i) an emergency situation, as reasonably determined by the
Engineer.
Page 4 of 25
4.0 CONTRACTOR
4.2 Performance Security
(a) Delete the second paragraph of Sub-Clause 4.2 and replace with the
following:
"The Contractor shall deliver the Performance Security to the
Employer within fourteen (14) days after receiving the Letter of
Acceptance and shall send a copy to the Engineer. The Performance
Security shall be issued by a bank, insurance company or a financial
institution:
(i) located in;
(ii) registered and licensed to do business in the country; and
(iii) approved by the Employer.
(b) Add the following at the end of the second paragraph of Sub-Clause
4.2:
"Whenever the amount of the Performance Security becomes less than
that stated in the Appendix to Tender (where applicable) due to
additions to the Contract Price (as determined by the Engineer)
resulting from changes in cost and/or the Laws or a Variation which, in
the aggregate, exceeds 15% of the Accepted Contract Amount or the
Contract Price the Contractor shall at the written instructions of the
Engineer increase the value of the Performance Security in the same
ratio as the increase in the Contract Price."
4.4 Sub-Contractors
(a) Insert the following immediately after the first paragraph of Sub-
Clause 4.4:
"Upon the written consent of the Engineer, the Contractor will be
permitted to sub-contract parts of the Works, but must as far as
possible utilize a minimum of eighty percent (80%) of unskilled and
Page 5 of 25
twenty-five percent (25%) of semi-skilled and skilled labour from
residents within close proximity to or former residents of the Site."
4.6 Co-operation
(a) Delete the third paragraph of Sub-Clause 4.6 and replace with the
following:
"The Contractor shall be responsible for his construction activities on
the Site and shall co-ordinate his own activities with those of
sub-contractors, Employer's Personnel or personnel of any
legally constituted public authority on the Site as may be required by
the Employer."
Page 6 of 25
"The Contractor shall comply fully with all environmental protection
and safety laws governing carrying out the Works. The Contractor
shall comply with all Specification Clauses concerning the protection
of the environment"
Page 7 of 25
Progress Report and shall meet with the Contractor within seven (7)
days after receipt of the Contractors' Progress Report to discuss any
problems the Contractor has highlighted therein.
Delete the second and third paragraph of this sub-clause and replace
with the following:
“During the execution of the Works, the Contractor shall keep the Site
free from all necessary obstruction, and shall store and dispose of any
Contractor's equipment or surplus materials in the area so designated
by the Engineer. The Contractor shall be responsible for and shall upon
the request of the Engineer clear away and remove from the Site all
wreckage, rubbish and temporary Works. The Contractor shall leave
Page 8 of 25
that part of the Site and the works in a clean and safe condition.
However, the Contractor may retain on Site, during the Defects
Notification Period, such goods as required for the Contractor to fulfil
obligations under the Contract.”
4.24 Fossils
The first paragraph of Sub-Clause 4.24 is deleted and replaced with the
following:
“As between the parties, all fossils, coins, articles of value or antiquity
and structures and other remains or items of archaeological interest
found on the Site shall belong to the Employer. The Contractor shall
take reasonable precautions to prevent Contractor‟s Personnel or other
persons from removing or damaging any of these findings."
Page 9 of 25
of work performed by workmen in and about the execution of the
Contract, and the Contractor or his sub-contractors shall be bound
whenever required, to produce such wage and time books and/or work
sheets for the inspection of any person authorized by the Government
of Trinidad and Tobago."
6.13 Sub-Contractors
(a) The Contractor shall be responsible (so far as may be applicable for the
observance of the provisions of this Contract by any permitted Sub-
contractor.
Page 10 of 25
8.0 COMECEMENT. DELAYS AND SUSPENSION
8.3 Programme
(a) Delete the first sentence of Sub-Clause 8.3 and replace with the
following:
"The Contractor shall submit, within fourteen (14) days after the notice
under Sub-Clause 8.1 [Commencement of Works], six (6) digital
copies of the detailed programme of the Works identifying a critical
path and showing all the components of the Contract, their duration,
relationship and all other necessary data to the approval of the
Engineer including the work of all specialist Sub-Contractors and a
proposed cash drawdown schedule."
(b) Delete the second paragraph of Sub-Clause 8.3 and replace with the
following:
“Unless the Engineer within fourteen (14) days after receiving a
programme gives notice to the Contractor stating the extent
to which it does not comply with the Contract, the Contractor shall
proceed in accordance with the programme subject to his other
obligations under the Contract. The Employer‟s Personnel shall be
entitled to rely upon the programme when planning their activities.”
(c) Insert the following after the last paragraph of Sub-clause 8.3: “When
requested by the Engineer to submit a revised work programme due to
inconsistencies between the work programme and the actual progress
of the Works and or the Contractor‟s obligations, the Contractor shall
submit the revised work programme containing the items mentioned in
(a), (b), (c) and (d) of this sub-clause [Programme] no later than
fourteen (14) days after the date of the Engineer‟s request."
Page 11 of 25
8.8 Suspension of the Works
Add the following at the end of Sub-Clause 8.8:
“The Contractor shall not suspend the Works (unless so ordered in
writing by the Engineer) pending the Engineer‟s decision on any
question under this Contract."
13.6 Daywork
This Sub-Clause shall not apply.
Page 12 of 25
of the instalments, and the applicable currencies and proportions, shall
be as stated in the Appendix to Tender.
Page 13 of 25
(i) to the Employer, where they are stored on the premises of the
Contractor, and in any other case the person to whose order
they are held; and
(ii) their destination at the works.
(4) Where the Materials were ordered from a supplier by the Contractor or
by any Sub-contractor, the contract for their sub- contract is in writing
and expressly provides that the property therein shall pass
unconditionally to the Contractor or the Sub-contractor (as the case
may be) not later than the happening of the events set out in (h) (2) and
(h) {3) of this Sub-Clause.
(5) Where the Materials were ordered from a supplier by any Sub-
contractor and the relevant sub-contract between the Contractor and
the Sub-Contractor is in writing and expressly provides that the
property in the materials passing to the Sub- Contractor the same shall
immediately thereon pass to the Contractor.
(8) The Contractor provides the Engineer with reasonable proof that the
property in the materials is in him and that the appropriate conditions
set out in (h) (1) to (h) (7) of this Sub- Clause have been fulfilled.
(9) The Contractor provides the Engineer with reasonable proof that the
materials are insured against loss or damage for their full value plus
ten (10) percent under a policy of insurance protecting the interest of
the Employer and the Contractor in respect of loss or damage sustained
as in Sub-Clause 18.2 during the period commencing with the transfer
Page 14 of 25
of property in the materials to the Contractor until they are delivered
to, or adjacent to the Works.
14.7 Payment
Delete the last paragraph of this sub-clause
Page 15 of 25
15.6 Suspension or Termination of the Contract due to an Order
of the Court
Add a new Sub-Clause 15.6 immediately after Sub-Clause 15.5 as
follows:
“15.6 Suspension or Termination of the Contract due to an Order of the
Court
Without prejudice to any other entitlement of the Employer to
terminate the Contract, if the performance of the Work is stopped
temporarily or otherwise by an order of the Court, whether or not such
order is made in consequence of any act or default of the Employer,
the Employer shall be entitled to terminate the Contract by giving
notice of termination to the Contractor. The termination shall take
effect fourteen (14) days after the later of the dates on which the
Contractor receives this notice or the Employer returns the
Performance Security.
After this termination, the Contractor shall proceed in accordance with
Sub-Clause 16.3 [Cessation of Work and Removal of Contractor's
Equipment] and shall be paid in accordance with Sub- Clause 19.6
[Optional Termination, Payment and Release]”.
Page 16 of 25
17.0 RISK AND RESPONSIBILITY
17.1 Indemnities
(a) Delete the period (“.”) at the end of sub-paragraph (ii) of sub-
paragraph (b) of Sub-Clause 17.1 and replace with the following
(b) Add the following sub-paragraphs (c) and (d) immediately after sub-
paragraph (b) of the first paragraph of Sub-Clause 17.1:
“(c) any and all claims of infringements of patents, trademarks,
industrial designs, copyrights or other intellectual property
rights affecting the designs and any of the Contractor's
Documents.
(d) any breach by the Contractor, his employees, agents or servants
of the covenants and conditions affecting the Site as specified
in the title relating thereto.”
Page 17 of 25
accordance with this Sub-Clause 20.4 acting fairly, impartially and the
cost shall be shared equally between the Employer and the Contractor.
20.6 Arbitration
(a) Delete the words “Rules of Arbitration of the International Chamber of
Commerce" as they appear in sub-paragraph (a) of the first paragraph
of Sub-Clause 20.6 and replace with the following: “Rules of
Arbitration UNCITRAL in accordance with the Arbitration Laws of
Trinidad and Tobago."
(b) Delete sub-paragraph (b) of the first paragraph of Sub-Clause
20.6 and substitute with the following;
“the dispute shall be settled by the number of arbitrators specified in
the Appendix to Tender.”
Page 18 of 25
22.0 UTILITIES
The Contractor shall take all precautions against damage to existing
public utilities on or near the Site. Should any cable, pipeline,
manhole, or otherwise. be damaged by the Contractor in any manner,
then the Contractor shall notify and co-operate with the appropriate
authority and bear all expenses involved in reconstruction of the
damaged utilities
Page 19 of 25
25.0 SUPERINTENDENT TO SPEAK ENGLISH
The Contractor or any agent or representative thereof appointed in
accordance with Clause 4 of the Conditions of Contract shall unless
otherwise specified have sufficient knowledge of English to receive
written and verbal instructions from the Engineer and to make such
written and verbal reports as the Engineer may from time to time
require.
Page 20 of 25
governmental, statutory or public authorities, public bodies and
private parties whatsoever concerned or affected or likely to be
concerned or affected by blasting operations.
- shall not use or bring on to the Site any explosives of any kind
without the prior consent of the Engineer in writing. Explosives
shall be stored in an approved building that shall be sited in a
position approved by the Engineer. Detonators shall be stored
separately. Permission to use explosives given in accordance
with this Clause shall not absolve the Contractor from any
liability in respect of damage to public or private property.
Page 21 of 25
28.0 RESTORATION OF CONDITIONS
All rubbish or refuse and all unused materials and tools shall be
removed promptly from the Site and as the Works progress, and it shall
be carefully cleaned and kept clear of such rubbish and refuse. Before
the Works will be considered as having been completed, the Site and
places affected by the Works shall be thoroughly cleared and left
clean, free from debris and in a condition satisfactory to the Engineer.
Page 22 of 25
reason of his work whenever the accumulation is sufficient to cause
dust or the formation of mud that may interfere with drainage or create
a traffic hazard or a disturbance to adjoining properties. Whenever the
Works cause traffic or the Contractor‟s Equipment to create dusty
conditions, the Contractor shall take steps, including applying water,
furnishing and spreading calcium chloride or using other adequate
methods to relieve and prevent such conditions. The steps to be taken
shall be approved by the Engineer.
Page 23 of 25
The Contractor shall satisfy himself as to the exact locations of utility
lines. He shall protect and support in a suitable manner all utilities
encountered in his excavating and trenching operations. The
Contractor shall make good any damage to these lines caused by his
operations. If the nature of the damage is such as to endanger the
satisfactory operations of utilities and the necessary repairs are not
made immediately by the Contractor under the direction and
supervision of the respective utility authorities, the work may be done
by the respective owners or agents and the cost-thereof charged against
the Contractor.
The Contractor shall conduct his work and cooperate with such parties
so as to cause as little interference as possible with such other work as
may be progressing at the same time.
Page 24 of 25
35.0 PROPERTY IN EXCAVATED MATERIALS
All materials, soil and things of any kind obtained from excavation or
found on or under the Site or under any additional site which the
Contractor may be allowed to occupy shall remain the property of the
Employer and shall not be used in the Works or sold or otherwise
disposed of without the written authority of the Engineer.
Page 25 of 25